JPH0216818B2 - - Google Patents

Info

Publication number
JPH0216818B2
JPH0216818B2 JP565184A JP565184A JPH0216818B2 JP H0216818 B2 JPH0216818 B2 JP H0216818B2 JP 565184 A JP565184 A JP 565184A JP 565184 A JP565184 A JP 565184A JP H0216818 B2 JPH0216818 B2 JP H0216818B2
Authority
JP
Japan
Prior art keywords
hole
excavator
drilling
screw
auger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP565184A
Other languages
Japanese (ja)
Other versions
JPS60152725A (en
Inventor
Fumio Hata
Seiji Fujishima
Koichi Michiura
Kunyoshi Morimoto
Hisao Kuroda
Yoshio Kyo
Mitsuhiro Kunito
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Seiko Kogyo Co Ltd
Keihan Electric Railway Co Ltd
Original Assignee
Kajima Corp
Seiko Kogyo Co Ltd
Keihan Electric Railway Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Seiko Kogyo Co Ltd, Keihan Electric Railway Co Ltd filed Critical Kajima Corp
Priority to JP565184A priority Critical patent/JPS60152725A/en
Publication of JPS60152725A publication Critical patent/JPS60152725A/en
Publication of JPH0216818B2 publication Critical patent/JPH0216818B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/13Foundation slots or slits; Implements for making these slots or slits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 本発明は、アースオーガ掘削機による削孔方法
およびその方法を実施するためのアースオーガ掘
削機に関し、特に路面覆工下あるいは橋梁下等作
業位置が低い所あるいは狭隘な場所での杭打ち、
連続壁等を施工するのに好適なアースオーガ掘削
機による削孔方法およびその方法を実施するため
のアースオーガ掘削機に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for drilling holes using an earth auger excavator, and an earth auger excavator for carrying out the method, particularly in places where the working position is low or narrow, such as under a road surface lining or under a bridge. Staking at the location,
The present invention relates to a hole drilling method using an earth auger excavator suitable for constructing continuous walls, etc., and an earth auger excavator for carrying out the method.

従来、アースオーガ掘削機を使用しての単独
杭、連続杭等の施工は、施工高5m以内の場所に
おいては施工不可能とされていた。しかし都市土
木工事においては、土留、止水用の杭施工は最近
特にアセスメント等の問題から路下での施工が多
くなり施工高5m以内での施工方法および該方法
を実施するための掘削機が要望されている。
Conventionally, it has been considered impossible to construct single piles, continuous piles, etc. using an earth auger excavator in locations where the construction height is less than 5 m. However, in urban civil engineering work, pile construction for earth retaining and water-stopping has recently been carried out under roads, especially due to issues such as assessment. It is requested.

本発明は、この要望に応えるべくなされたもの
で、高さ制限のない路上工事と同様の施工能率と
安全施工でもつて単独杭、連続杭、等を施工でき
るアースオーガ掘削機による削孔方法および該方
法を実施するためのアースオーガ掘削機を提供す
ることを目的としてなされたものである。
The present invention was made in response to this demand, and includes a hole drilling method using an earth auger excavator that can construct single piles, continuous piles, etc. with construction efficiency and safety similar to road construction without height restrictions. The object of this invention is to provide an earth auger excavator for carrying out the method.

本発明の方法によれば、アースオーガ掘削機に
よる削孔方法において、スクリユウヘツドを少く
とも2セツト使用し、そのスクリユウヘツドを第
1の削孔の位置と該第1の削孔の位置から所定の
間隔をへだてて第2の削孔の位置に据え付け、掘
削機を第1の削孔の位置に据え付けし、オーガモ
ータをスクリユウヘツドに接続して第1の削孔を
スクリユウヘツドで掘削し、スクリユウヘツドを
ガイドウオール等に仮受けし、オーガモータと切
り離して掘削機を横移動させる。掘削機の作業ア
ームのチエンブロツクで中間スクリユウを吊り込
みスクリユウヘツドに接続し、掘削機を再び第1
の削孔の位置に据え付けし、オーガモータを中間
スクリユウに接続して第1の削孔を中間スクリユ
ウの一節分掘削し、上記の横移動ないし一節分掘
削の各作業を所要回数繰り返して第1の削孔の掘
削を完了し、この際スクリユウは第1の削孔に入
つたままになつており、次いで掘削機を移動させ
て第2の削孔の掘削作業を行うようになつてい
る。
According to the method of the present invention, in the drilling method using an earth auger drilling machine, at least two sets of screw heads are used, and the screw heads are located at the first drilling position and at the first drilling position. The excavator is installed at the position of the second hole at a predetermined distance from the hole, the excavator is installed at the position of the first hole, the auger motor is connected to the screw head, and the first hole is drilled with the screw head. Excavate, temporarily support the screw head on a guide wall, etc., disconnect from the auger motor, and move the excavator laterally. The intermediate screw is suspended by the chain block on the working arm of the excavator and connected to the screw head, and the excavator is returned to the first position.
, connect the auger motor to the intermediate screw, drill the first hole by one section of the intermediate screw, and repeat the above-mentioned horizontal movement or one section drilling operation as many times as required to drill the first hole. The drilling of the hole is completed, with the screw remaining in the first hole, and then the excavator is moved to begin drilling the second hole.

また本発明の掘削機によれば、走行車輪、無限
軌条帯等の走行手段を備えた台車上に所定の間隔
をへだてて2本で組をなすリーダが立設されてお
り、そのリーダはスライドジヤツキにより前後に
移動されるようになつていると共にステージヤツ
キにより前後の傾きを調整できるようにされてお
り、またリーダ間にはリーダに設けたリフトジヤ
ツキによりリーダにガイドされて上下動するシー
ブが設けられていて、そのシーブには一端がオー
ガモータと連結されたワイヤロープが掛け渡され
ており、そのワイヤロープの他端はリーダに設け
たリフト補助ジヤツキに連結されており、さらに
リーダの先端には作業アームが回動可能にして取
り付けられている。
Further, according to the excavator of the present invention, a set of two leaders is installed at a predetermined interval on a truck equipped with running means such as running wheels and endless track strips, and the leader slides. The sheave is moved back and forth by a jack, and the inclination can be adjusted by a stage jack, and between the leaders there is a sheave that moves up and down guided by the leader by a lift jack installed on the leader. A wire rope with one end connected to the auger motor is strung around the sheave, and the other end of the wire rope is connected to a lift assist jack provided on the leader, and the wire rope is connected to a lift assisting jack provided on the leader. is attached with a rotatable working arm.

そこで、まず本発明の方法を実施するためのア
ースオーガ掘削機の一例を第1図ないし第5図を
参照し説明する。
First, an example of an earth auger excavator for implementing the method of the present invention will be described with reference to FIGS. 1 to 5.

例えば連続壁を造成する施工個所に沿い走行レ
ール1,1を敷設し、そのレール1,1上を全体
をAで示すアースオーガ掘削機が走行するように
なつている。掘削機Aは台車2,2A,2Bを備
えており、中央部の台車2に対して前部および後
部の台車2A,2Bは切り離すことができるよう
にされている。隣接構造物に接触する連続壁を造
成する場合には後部台車2Bを切り離して施工す
るようにする。中央部の台車2には比較的径の大
きい車輪3が、また前部および後部の台車2A,
2Bには比較的径の小さい車輪3A,3Bが取り
付けられており、さらに前部および後部の台車2
A,2Bには走行レール1,1に沿つて設けたT
字状レール4,4と係合する浮上防止装置5が設
けられている。台車2には走行モータ6が設けら
れていて掘削機Aは電動走行で横移動する。
For example, traveling rails 1, 1 are laid along the construction site where a continuous wall is to be constructed, and an earth auger excavator, generally designated by A, runs on the rails 1, 1. The excavator A is equipped with trucks 2, 2A, and 2B, and the front and rear trucks 2A, 2B can be separated from the central truck 2. When constructing a continuous wall that contacts an adjacent structure, the rear truck 2B should be separated and constructed. The central truck 2 has relatively large diameter wheels 3, and the front and rear trucks 2A,
Wheels 3A and 3B with a relatively small diameter are attached to 2B, and the front and rear bogies 2
A, 2B has T provided along running rails 1, 1.
An anti-floating device 5 is provided which engages the character-shaped rails 4,4. The trolley 2 is provided with a travel motor 6, and the excavator A moves horizontally by electric travel.

台車2の両側にガイド部材7,7が溶接等によ
り固着されており、そのガイド部材7,7にガイ
ドされて台車2の前後方向に摺動するスライド部
材8が設けられており、そのスライド部材8に2
本で1組をなすリーダ9,9の基端が軸連結され
ている。リーダ9,9を前後方向に移動させる油
圧作動のスライドジヤツキ10が台車2とスライ
ド部材8との間に設けられており、またリーダ
9,9の前後の傾きを調整する油圧作動のステー
ジヤツキ11,11が台車2とリーダ9,9の上
部との間に設けられている。
Guide members 7, 7 are fixed to both sides of the truck 2 by welding or the like, and a slide member 8 is provided which slides in the front and back direction of the truck 2 while being guided by the guide members 7, 7. 8 to 2
The proximal ends of the readers 9, 9, which form a pair of books, are axially connected. A hydraulically operated slide jack 10 for moving the leaders 9, 9 in the front-back direction is provided between the cart 2 and the slide member 8, and a hydraulically operated stage jack for adjusting the longitudinal inclination of the leaders 9, 9. 11, 11 are provided between the cart 2 and the upper part of the leaders 9, 9.

左右のリーダ9,9にガイドされて上下動する
2個のシーブ12,12が設けられており、その
支軸13の両端にはガイド部材14,14が設け
られていて、ガイド部材14,14はリーダ9,
9と係合してシーブ12,12をリーダ9,9に
沿つてガイドする。またリーダ9,9の基端とシ
ーブ12,12との間には油圧作動のリフトジヤ
ツキ15が設けられていて、このリフトジヤツキ
15によりシーブ12,12は上下動される。
Two sheaves 12, 12 are provided which move up and down guided by left and right leaders 9, 9, and guide members 14, 14 are provided at both ends of the support shaft 13. is leader 9,
9 to guide the sheaves 12, 12 along the leaders 9, 9. Further, a hydraulically operated lift jack 15 is provided between the base ends of the leaders 9, 9 and the sheaves 12, 12, and the sheaves 12, 12 are moved up and down by this lift jack 15.

全体を16で示すものはオーガモータでモータ
および減速装置を備えており、このオーガモータ
16によりオーガスクリユウ17が回転駆動され
る。オーガモータ16にはワイヤロープ18,1
8の一端が連結されており、そのワイヤロープ1
8,18は前記シーブ12,12に掛け渡され、
その他端はリーダ9,9の基端に連結された油圧
作動のリフト補助ジヤツキ19に連結されてい
る。したがつて前記リフトジヤツキ15を作動さ
せることにより前記シーブ12,12が上下動
し、それに伴いワイヤロープ18,18を介して
オーガモータ16が上下動される。またリフト補
助ジヤツキ19を作動することによりワイヤロー
プ18,18を介してオーガモータ16が上下動
する。オーガモータ16はガイドギブ20を備え
ており、このガイドギブ20がリーダ9,9に沿
つて一体に設けたガイド軸21と係合しオーガモ
ータ16を円滑に上下動させるようになつてい
る。
The auger motor indicated by 16 as a whole is equipped with a motor and a speed reduction device, and the auger screw 17 is rotationally driven by this auger motor 16. The auger motor 16 has a wire rope 18,1
One end of 8 is connected, and the wire rope 1
8 and 18 are stretched over the sheaves 12 and 12,
The other end is connected to a hydraulically operated lift assist jack 19 connected to the base ends of the leaders 9,9. Therefore, by operating the lift jack 15, the sheaves 12, 12 are moved up and down, and accordingly, the auger motor 16 is moved up and down via the wire ropes 18, 18. Furthermore, by operating the lift assisting jack 19, the auger motor 16 is moved up and down via the wire ropes 18,18. The auger motor 16 is equipped with a guide gib 20, which engages with a guide shaft 21 provided integrally along the leaders 9, 9 to smoothly move the auger motor 16 up and down.

リーダ9,9の先端には作業アーム22が軸連
結されており、例えばターンバツクル23により
その取付け角度が調整できるようにされている。
この作業アーム22によりオーガモータ16のキ
ヤブタイヤケーブルや注水ホースを吊り下げ、ま
たチエンブロツクを取付けてオーガスクリユウ1
7の吊り下げ作業などを行う。台車2にはカウン
タウエイト24が設けられており、また台車2A
には油圧ユニツト25が載置されている。前述の
ように作業アーム22を軸連結して中折れ式にす
ることによりアースオーガ掘削機の高さ寸法を低
くすることができ、例えば全長5mで上部1mに
て中折れ式とする。またオーガスクリユウ17も
従来のものに比べて短い例えば2.5mのものを使
用する。
A working arm 22 is axially connected to the ends of the leaders 9, 9, and the mounting angle thereof can be adjusted by, for example, a turnbuckle 23.
The work arm 22 hangs the cab tire cable and water injection hose of the auger motor 16, and also attaches a chain block to the auger screw 1.
Perform the hanging work, etc. in step 7. The cart 2 is provided with a counterweight 24, and the cart 2A is provided with a counterweight 24.
A hydraulic unit 25 is mounted on. As mentioned above, the height of the earth auger excavator can be reduced by connecting the working arm 22 with the shaft and making it foldable in the middle.For example, the total length is 5 m and the upper part is foldable in the middle. Also, the auger crayon 17 is shorter than the conventional one, for example, 2.5 m.

前述のアースオーガ掘削機Aにおいて走行モー
タ6を作動させて掘削機Aを横移動させて削孔位
置に順次動かし、またスライドジヤツキ10を作
動させてリーダ9,9を前後移動させ、ステージ
ヤツキ11を作動させてリーダ9,9の前後の傾
きを調整することができる。またリフトジヤツキ
15およびリフト補助ジヤツキ19を作動させて
オーガモータ16を上下動させ、オーガスクリユ
ウ17の継ぎ足し等を行う。
In the above-mentioned earth auger excavator A, the traveling motor 6 is operated to move the excavator A laterally and sequentially to the drilling position, and the slide jack 10 is operated to move the leaders 9 back and forth to move the stage jack. 11 can be operated to adjust the longitudinal inclination of the leaders 9,9. In addition, the lift jack 15 and the lift assist jack 19 are operated to move the auger motor 16 up and down, thereby adding the auger screw 17 and the like.

第6図ないし第9図に他の例のアースオーガ掘
削機を示し、第1図ないし第5図に示すものは1
軸オーガであつたが、第6図ないし第9図に示す
ものは3軸オーガであり、第1図ないし第5図に
示すものと同一部分には同一符号を付すが、この
例では3本のオーガスクリユウ17,17,17
により同時に3本の削孔を行うことができる。
Figures 6 to 9 show other examples of earth auger excavators, and those shown in Figures 1 to 5 are 1
The one shown in Figures 6 to 9 is a three-shaft auger, and the same parts as those shown in Figures 1 to 5 are given the same reference numerals, but in this example there are three augers. August 17th, 17th, 17th
This allows three holes to be drilled at the same time.

第8図および第9図にオーガモータ16の詳細
を示し、フレーム26にはモータ27、高速減速
装置28、低速減速装置29が設けられていて、
モータ27の出力軸の回転は高速減速装置28で
減速され、さらに低速減速装置29で減速されて
カツプリング30に伝達され、フランジ31に接
続されたオーガスクリユウ17,17,17を回
転駆動する。低速減速装置29としては遊星歯車
式の減速装置が使用されており、該変速装置29
はモータ27の出力軸線上に設けずそれと偏寄し
て設けられている。これにより掘削機Aの高さ寸
法を小さくしている。またフレーム26の両側に
はシーブ32,32が設けられており、また吊り
ドラム33、注水装置34が設けられている。さ
らにフレーム26には3個のガイドギブ20,2
0,20が設けられており、このガイドギブ2
0,20,20はリーダ9,9にそつてそれと一
体に設けられたガイド軸21,21と係合し、オ
ーガモータ16を円滑に上下動させる。
Details of the auger motor 16 are shown in FIGS. 8 and 9, and the frame 26 is provided with a motor 27, a high speed reduction device 28, and a low speed reduction device 29.
The rotation of the output shaft of the motor 27 is decelerated by a high speed reduction device 28, further decelerated by a low speed reduction device 29, and transmitted to a coupling 30, which rotationally drives auger screws 17, 17, 17 connected to a flange 31. A planetary gear type reduction gear is used as the low speed reduction gear 29.
is not provided on the output axis of the motor 27 but offset therefrom. This reduces the height of the excavator A. Further, sheaves 32, 32 are provided on both sides of the frame 26, and a hanging drum 33 and a water injection device 34 are also provided. Furthermore, the frame 26 has three guide gibs 20, 2.
0,20 is provided, and this guide give 2
0, 20, 20 engage with guide shafts 21, 21 provided integrally with the leaders 9, 9 to smoothly move the auger motor 16 up and down.

次に第1図ないし第5図に示すアースオーガ掘
削機を用いて連続壁を造成するため削孔を掘削す
る方法を第10図を参照し説明する。
Next, a method of excavating a hole to create a continuous wall using the earth auger excavator shown in FIGS. 1 to 5 will be described with reference to FIG. 10.

(イ) スクリユウヘツド(スクリユウヘツドを、中
間スクリユウは図示せず)を2セツト使用し、
そのスクリユウヘツドを第1の削孔の位置と
第1の削孔の位置から所定の間隔をへだてた
第2の削孔の位置に据え付ける。
(a) Using two sets of screw heads (intermediate screw heads are not shown),
The screw head is installed at a first drilling position and a second drilling position separated from the first drilling position by a predetermined distance.

(ロ) 掘削機Aを削孔の位置に据え付けし、オー
ガモータ16をスクリユウヘツドに接続して削
孔をスクリユウヘツドで掘削する。
(b) Install the excavator A at the location where the hole is to be drilled, connect the auger motor 16 to the screw head, and use the screw head to drill the hole.

(ハ) スクリユウヘツドをガイドウオール等に仮受
けし、オーガモータ16と切り離して掘削機A
を横移動させる。
(c) Temporarily support the screw head on a guide wall, etc., and disconnect it from the auger motor 16 and remove it from the excavator A.
move laterally.

(ニ) 掘削機Aの作業アーム22のチエンブロツク
で中間スクリユウを吊り込みスクリユウヘツド
に接続する。
(d) Suspend the intermediate screw using the chain block of the working arm 22 of excavator A and connect it to the screw head.

(ホ) 掘削機Aを再び削孔の位置に据え付けし、
オーガモータ16を中間スクリユウに接続して
削孔を中間スクリユウの一節分掘削する。
(e) Install excavator A again at the drilling position,
The auger motor 16 is connected to the intermediate screw and a hole is drilled by one section of the intermediate screw.

(ヘ) (ハ)ないし(ホ)の各作業を所要回数繰り返して削
孔の掘削を完了する。この時スクリユウは削
孔に入れたままになつている。
(F) Repeat each operation from (C) to (E) the required number of times to complete the drilling of the hole. At this time, the screw remained in the hole.

(ト) 掘削機Aを削孔の位置に移動させ、オーガ
モータ16を(イ)の行程で削孔の位置に据え付
けたもう1組のスクリユウヘツドに接続し、削
孔をスクリユウヘツドで掘削する。
(g) Move the excavator A to the drilling position, connect the auger motor 16 to the other set of screw heads installed at the drilling position in step (a), and drill the hole with the screw head. do.

(チ) 削孔をスクリユウヘツドで掘削したらスク
リユウヘツドをガイドウオール等に仮受けし、
オーガモータ16をスクリユウヘツドと切り離
して掘削機Aを削孔の位置に戻す。
(h) After drilling the hole with the screw head, temporarily support the screw head on a guide wall, etc.
The auger motor 16 is separated from the screw head and the excavator A is returned to the drilling position.

(リ) 削孔の中間スクリユウにオーガモータ16
を接続し中間スクリユウの1節を抜き上げガイ
ドウオール等に仮受けし、オーガモータ16と
中間スクリユウの1節を接続した状態で掘削機
Aを削孔2の位置に移動する。
(l) Auger motor 16 is installed in the intermediate screw of hole drilling.
is connected, one section of the intermediate screw is pulled up and temporarily supported on a guide wall, etc., and the excavator A is moved to the position of the drilling hole 2 with the auger motor 16 and one section of the intermediate screw connected.

(ヌ) 削孔のスクリユウヘツドと中間スクリユウ
を接続し中間スクリユウの1節分掘削する。
(J) Connect the screw head of the drilling hole and the intermediate screw and drill one section of the intermediate screw.

(ル) (チ)ないし(ヌ)の各作業を所要回数繰り返して
削孔の掘削を完了する。
(l) Repeat each operation from (ch) to (n) the required number of times to complete the drilling of the hole.

(オ) 掘削機Aを再び削孔の位置に戻し、削孔1
のスクリユウヘツドをオーガモータ16に接続
して掘削機Aを削孔と所定の間隔をへだてた
第3の削孔の位置に移動させ、スクリユウヘ
ツドで削孔を掘削する。
(E) Return excavator A to the drilling position again and drill hole 1.
The screw head is connected to the auger motor 16, and the excavator A is moved to a third drilling position separated by a predetermined distance from the drilled hole, and the drilled hole is drilled with the screw head.

(ワ) (チ)ないし(ヌ)の作業を削孔と削孔の間で
やりとりと削孔の掘削を完了させる。
(W) Complete the work of (C) through (N) between drilling and drilling of the holes.

(カ) 第4の削孔、第5の削孔…も同様に掘削
して完了させる。
(f) Drill the fourth hole, fifth hole, etc. in the same manner and complete.

H形鋼の建て込みは、(a)については削孔のス
クリユウヘツドを削孔に移動した時点で行う。
また(b)、(c)については削孔のスクリユウヘツド
を削孔に移動した後とする。
For (a), the H-section steel is installed when the screw head of the drilled hole is moved to the drilled hole.
In addition, (b) and (c) are assumed to be after the screw head of the drilled hole has been moved to the drilled hole.

前記の行程において掘削機Aの移動は走行モー
タ6を作動して行い、またオーガスクリユウとオ
ーガモータ16との接続の際などにおけるオーガ
モータ16の上下動はリフトジヤツキ15および
リフト補助ジヤツキ19を作動して行う。
In the above-mentioned process, the excavator A is moved by operating the travel motor 6, and the vertical movement of the auger motor 16 when connecting the auger screw and the auger motor 16 is carried out by operating the lift jack 15 and the lift auxiliary jack 19. conduct.

以上説明したように本発明によれば、ヘツドス
クリユウを2セツト使用し、第1の削孔の位置に
据え付けたヘツドスクリユウに順次中間スクリユ
ウを接続して第1の削孔を所定の深度掘削し、第
1の削孔の掘削を完了したら第2の削孔の位置に
据え付けたヘツドスクリユウに第1の削孔の掘削
に使用した中間スクリユウを1節ずつ抜き上げて
接続して第2の削孔を掘削し、第2の削孔を所定
の深度掘削したら第1の削孔の掘削に使用したヘ
ツドスクリユウを第3の削孔の位置に据え付け、
また第2の削孔の掘削に使用した中間スクリユウ
を1節ずつ抜き上げて接続して第3の削孔を掘削
し、以後同様の作業を行つて第4の削孔、第5の
削孔、…と順次掘削していくものであるので、き
わめて能率よくアースオーガ掘削機により削孔す
ることができる。そしてアースオーガ掘削機とし
て例えば全長5mで上部1mを中折れとし、かつ
オーガモータとしてモータの出力軸の軸線上に減
速装置を配置することなく減速装置をモータの出
力軸の軸線から偏寄させて可及的全長を短くした
ものを使用することにより、路面覆工下あるいは
橋梁下等の施工高さ5m以内で従来、アースオー
ガ掘削機を使用しての杭打ち、連続壁等の施工は
不能とされていた場所でも、高さ制限のない路上
工事と同様の施工能率と安全施工でもつて杭打
ち、連続壁等の施工が可能となるものである。
As explained above, according to the present invention, two sets of head screws are used, and the intermediate screws are successively connected to the head screw installed at the position of the first hole to drill the first hole to a predetermined depth. After drilling the first hole, the intermediate screw used for drilling the first hole is pulled out one section at a time and connected to the head screw installed at the second hole location. After drilling the second hole and drilling the second hole to a predetermined depth, install the head screw used for drilling the first hole at the position of the third hole,
In addition, the intermediate screw used to drill the second hole was pulled out one section at a time and connected to drill the third hole, and the same operation was performed thereafter to drill the fourth and fifth holes. , . . . , and so on, the hole can be drilled with an extremely efficient earth auger excavator. As an earth auger excavator, for example, the total length is 5 m and the top 1 m is bent in the middle, and as an auger motor, the deceleration device can be offset from the axis of the motor's output shaft without placing the deceleration device on the axis of the motor's output shaft. By using a product with a shorter overall length, it is no longer possible to drive piles or construct continuous walls using an earth auger excavator at a construction height of 5 m or less, such as under road surface coverings or under bridges. This makes it possible to construct piles, continuous walls, etc., with the same efficiency and safety as on-road construction without height restrictions, even in areas where the construction has previously been carried out.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第5図はアースオーガ掘削機の第
1実施例を示し、第1図は側面図、第2図は正面
図、第3図は平面図、第4図はリーダとシーブと
の関係を示す詳細断面図、第5図は浮上防止装置
の詳細正面図である。第6図ないし第9図はアー
スオーガ掘削機の第2実施例を示し、第6図は側
面図、第7図は正面図、第8図はオーガモータの
詳細正面図、第9図は同平面図、第10図は作業
行程を示す説明図である。 1…レール、2,2A,2B…台車、9…リー
ダ、10…スライドジヤツキ、11…ステージヤ
ツキ、12…シーブ、15…リフトジヤツキ、1
6…オーガモータ、17…オーガスクリユウ、1
8…ワイヤロープ、19…リフト補助ジヤツキ、
22…作業アーム、27…モータ、28…高速減
速装置、29…低速減速装置、30…カツプリン
グ。
Figures 1 to 5 show a first embodiment of the earth auger excavator, with Figure 1 being a side view, Figure 2 being a front view, Figure 3 being a plan view, and Figure 4 showing the structure of the leader and sheave. A detailed sectional view showing the relationship, and FIG. 5 is a detailed front view of the floating prevention device. Figures 6 to 9 show a second embodiment of the earth auger excavator, with Figure 6 being a side view, Figure 7 being a front view, Figure 8 being a detailed front view of the auger motor, and Figure 9 being the same plane. 10 are explanatory diagrams showing the work process. 1...Rail, 2, 2A, 2B...Dolly, 9...Leader, 10...Slide jack, 11...Stage jack, 12...Sheave, 15...Lift jack, 1
6... Auger motor, 17... Auger screw, 1
8...wire rope, 19...lift assist jack,
22... Working arm, 27... Motor, 28... High speed reduction device, 29... Low speed reduction device, 30... Coupling.

Claims (1)

【特許請求の範囲】 1 アースオーガ掘削機による削孔方法におい
て、スクリユウヘツドを少くとも2セツト使用
し、そのスクリユウヘツドを第1の削孔の位置と
該第1の削孔の位置から所定の間隔をへだてて第
2の削孔の位置に据え付け、掘削機を第1の削孔
の位置に据え付けし、オーガモータをスクリユウ
ヘツドに接続して第1の削孔をスクリユウヘツド
で掘削し、スクリユウヘツドをガイドウオール等
に仮受けし、オーガモータと切り離して掘削機を
横移動させる。掘削機の作業アームのチエンブロ
ツクで中間スクリユウを吊り込みスクリユウヘツ
ドに接続し、掘削機を再び第1の削孔の位置に据
え付けし、オーガモータを中間スクリユウに接続
して第1の削孔を中間スクリユウの一節分掘削
し、上記の横移動ないし一節分掘削の各作業を所
要回数繰り返して第1の削孔の掘削を完了し、こ
の際スクリユウは第1の削孔に入つたままになつ
ており、次いで掘削機を移動させて第2の削孔の
掘削作業を行うことを特徴とする削孔方法。 2 走行車輪、無限軌条帯等の走行手段を備えた
台車上に所定の間隔をへだてて2本で組をなすリ
ーダが立設されており、そのリーダはスライドジ
ヤツキにより前後に移動されるようになつている
と共にステージヤツキにより前後の傾きを調整で
きるようにされており、またリーダ間にはリーダ
に設けたリフトジヤツキによりリーダにガイドさ
れて上下動するシーブが設けられていて、そのシ
ーブには一端がオーガモータと連結されたワイヤ
ロープが掛け渡されており、そのワイヤロープの
他端はリーダに設けたリフト補助ジヤツキに連結
されており、さらにリーダの先端には作業アーム
が回動可能にして取り付けられていることを特徴
とするアースオーガ掘削機。 3 オーガモータはモータおよび減速装置を備え
ており、減速装置はモータの出力軸の軸線と偏寄
させて設けられていることを特徴とする特許請求
の範囲第2項記載のアースオーガ掘削機。
[Claims] 1. A method for drilling a hole using an earth auger excavator, in which at least two sets of screw heads are used, and the screw head is connected to the position of the first hole and from the position of the first hole. The drill is installed at the position of the second hole at a predetermined distance, the excavator is installed at the position of the first hole, the auger motor is connected to the screw head, and the first hole is drilled with the screw head. Then, temporarily support the screw head on a guide wall, etc., disconnect it from the auger motor, and move the excavator laterally. The intermediate screw is suspended by the chain block of the working arm of the excavator and connected to the screw head, the excavator is installed again in the position for drilling the first hole, the auger motor is connected to the intermediate screw and the first hole is drilled. Drill one section of the intermediate screw, and repeat the above-mentioned horizontal movement or one section excavation operation as many times as necessary to complete the drilling of the first hole, and at this time, the screw remains in the first hole. A drilling method characterized in that the drilling machine is moved and a second drilling operation is performed by moving the excavator. 2. A pair of leaders are set up at a predetermined distance on a cart equipped with running means such as running wheels or endless track strips, and the leaders are moved back and forth by a slide jack. It is possible to adjust the front and rear inclination with a stage jack, and between the leaders there is a sheave that moves up and down guided by the leader with a lift jack installed on the leader. A wire rope is connected to the auger motor at one end, and the other end of the wire rope is connected to a lift assisting jack provided on the leader, and a work arm is rotatably attached to the tip of the leader. An earth auger excavator characterized by being attached. 3. The earth auger excavator according to claim 2, wherein the auger motor includes a motor and a speed reduction device, and the speed reduction device is provided offset from the axis of the output shaft of the motor.
JP565184A 1984-01-18 1984-01-18 Method of excavating hole by earth auger and earth auger excavator Granted JPS60152725A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP565184A JPS60152725A (en) 1984-01-18 1984-01-18 Method of excavating hole by earth auger and earth auger excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP565184A JPS60152725A (en) 1984-01-18 1984-01-18 Method of excavating hole by earth auger and earth auger excavator

Publications (2)

Publication Number Publication Date
JPS60152725A JPS60152725A (en) 1985-08-12
JPH0216818B2 true JPH0216818B2 (en) 1990-04-18

Family

ID=11617028

Family Applications (1)

Application Number Title Priority Date Filing Date
JP565184A Granted JPS60152725A (en) 1984-01-18 1984-01-18 Method of excavating hole by earth auger and earth auger excavator

Country Status (1)

Country Link
JP (1) JPS60152725A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0439865Y2 (en) * 1990-02-28 1992-09-18

Also Published As

Publication number Publication date
JPS60152725A (en) 1985-08-12

Similar Documents

Publication Publication Date Title
CN109372529B (en) In-tunnel dismantling device and method for hard rock heading machine
CN105626088B (en) T-shaped bored tunnel shield machine is gone into the well shift method
JPS63530A (en) Drilling machine
KR101919920B1 (en) Diaphragm wall device and method for producing trenches in the ground
CN1076982A (en) The excavator of building diaphragm wall and the building method of diaphragm wall
CN108442948B (en) Double-lane inverted arch trestle and construction method
JP3725605B2 (en) Movable temporary road surface structure and its installation / removal method
EP1013834B1 (en) Machine for digging into the lower layers of the ground
CN205387937U (en) T -shaped undercut tunnel shield constructs supporting platform truck in machine back translation system of going into well
JP2539151B2 (en) Excavation method for bottom floor in tunnel
CN119593766A (en) A method for quickly assembling a split starter in a narrow space of a shield machine
JPH11247430A (en) Transferable scaffold device
CN219343349U (en) TRD construction equipment for forming wall in middle
CN205477629U (en) T -shaped undercut tunnel shield constructs owner's machine translation system that goes into well
JP2913630B2 (en) Pile driver
JPS60152725A (en) Method of excavating hole by earth auger and earth auger excavator
CN116122370A (en) TRD construction equipment for forming wall in middle
JP7643735B2 (en) Tunnel invert installation device and installation method
SU756021A1 (en) SELF-PROPELLED MINE CRANE 1
CN221503304U (en) Sliding platform trolley adapting to large-gradient tunnel with variable size
CN221373590U (en) Sliding platform trolley suitable for large-gradient tunnel
JPH061628Y2 (en) Working machine for long objects
JPH0416596B2 (en)
CN212272017U (en) Double-drill-rod full-sleeve type long spiral drilling pile machine
JPH08177396A (en) Tunnel invert construction method and scaffold board device for tunnel invert construction

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term