JPH02236770A - System for supporting control of plant construction process - Google Patents

System for supporting control of plant construction process

Info

Publication number
JPH02236770A
JPH02236770A JP1059410A JP5941089A JPH02236770A JP H02236770 A JPH02236770 A JP H02236770A JP 1059410 A JP1059410 A JP 1059410A JP 5941089 A JP5941089 A JP 5941089A JP H02236770 A JPH02236770 A JP H02236770A
Authority
JP
Japan
Prior art keywords
construction
data
plant
advancing
setting function
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1059410A
Other languages
Japanese (ja)
Other versions
JP2721231B2 (en
Inventor
Nobuhide Sato
信秀 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP5941089A priority Critical patent/JP2721231B2/en
Publication of JPH02236770A publication Critical patent/JPH02236770A/en
Application granted granted Critical
Publication of JP2721231B2 publication Critical patent/JP2721231B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To confirm the actual condition of construction advancement by extracting a plant constituting element where the construction sequence is set from a data base with the designation of attribute data, setting the construction advancing condition and executing display based on the time attribute and sequence provided on the plant constituting element. CONSTITUTION:Based on a data base DB 1 storing the data of the plant constituting element provided on a CAD system, a system for supporting the control of a plant construction process is mainly constituted of a construction sequence setting function 2, a display function 3 and a construction advancing condition setting function 4. The advancing condition setting function 4 extracts the data from the CAD-DB in correspondence to the request of a user and displays the data on a display device such as a CRT. Afterwards, the advancing condition is registered to the element successively selected on a screen by an element selecting means such as a mouse. When the connecting relation of the respective constituting elements is defined by the CAD system, the construction advancing condition can be easily set by selecting the mouse, etc., such as the selection from the element A to the element B by following the connecting relation. Thus, the advancing degree of the construction process can be practically recognized.

Description

【発明の詳細な説明】 [発明の目的] (産業上の利用分野) 本発明は、各建設作業のスケジュール管理を長期にわた
って必要とするプラント等の大規模なな建造物の建設工
程管理を支援するシステムに関(従来の技術) これまでに多くの工程管理用のシステム(プログラム等
)が存在し、これらはスケジュールの入力、確認、調整
をサポートしている。基本的にここで得られる情報は、
作業ごとのスケジュール、いいかえれば線引きのデータ
であり、本来作ろうとしている物との対応は、その作業
名称を通して得られるイメージだけである。
[Detailed Description of the Invention] [Objective of the Invention] (Industrial Application Field) The present invention supports construction process management of large-scale buildings such as plants, which requires schedule management of each construction work over a long period of time. Related to systems (prior art) Many process management systems (programs, etc.) have existed to date, and these support input, confirmation, and adjustment of schedules. Basically, the information you can get here is
It is a schedule for each task, or in other words, data for delineating the lines, and the only correspondence to what is originally intended to be made is the image obtained through the name of the task.

一方、計算機利用技術の進展により、計算機を用いた設
計システム( C A D : Computer  
A1dcdDesign)が盛んに利用されるようにな
ってきた。
On the other hand, with the advancement of computer technology, computer-based design systems (CAD: Computer
A1dcdDesign) has become widely used.

このようなCADシステムでは、その個々の構成要素に
関する情報、例えばその物の名前、位置、形状等がそこ
での設計に必要な範囲で設定されている。ここで得られ
る主な情報は、その構造物はどのような構造、形態を有
しているかといった視覚情報であり、ある意味では出来
上がりはこうなりますといった情報である。
In such a CAD system, information regarding each component, such as the name, position, shape, etc. of the component, is set to the extent necessary for the design. The main information obtained here is visual information such as what kind of structure and form the structure has, and in a sense, it is information such as what the finished product will look like.

工事期間中はこれらのシステムをもとに実際の工事状況
をフォローしている。
During the construction period, we are following up on the actual construction status based on these systems.

(発明が解決しようとする課題) プラントなどの大規模な建造物では、例えば、まず壁、
床等の概略の大工程の設定、次のレベルとしては主要な
コンポーネントの設置、さらに次のレベルとしては各区
画の配管等の設置などといった手順で分割して工程を設
定する。主要なコンポーネントの設置では、例えば、そ
の搬入経路が確保されていることの確認、そのコンポー
ネントがその時点で確保されていことの確認、その下の
レベルでは、具体的な作業手順を考慮しての作業日数の
算出、その時点での作業スペースの確認、平行して行わ
れる作業間の干渉の確認等の作業を机上で検討する必要
がある。工事遅れに伴うスケジュール再調整においても
同様な検討が必要であり、実際にはかなりの業務負荷と
なる。一般にこのような大規模な建設工事では多くの資
源が投入され、その資源のロスの回避、実際の工事進歩
状況の具体的な把握の難しさ等から、工程管理システム
が工程再調整機能を持っていても、実質的には当初のス
ケジュールを厳守するとして対応するのが一般的である
。しかしながら、このようなスケジュール厳守の対応を
とるにしても、より具体的に工事進歩度を把握すること
は管理上重要である。
(Problem to be solved by the invention) In large-scale buildings such as plants, for example, walls,
The process is divided into steps such as setting a rough outline of the major process such as the floor, installing the main components at the next level, and installing piping, etc. for each section at the next level. In the installation of major components, for example, it is necessary to confirm that the delivery route is secured, that the component is secured at that time, and at a lower level, it is necessary to take into account specific work procedures. It is necessary to consider tasks such as calculating the number of working days, checking the work space at that point, and checking for interference between parallel tasks. Similar consideration is required when rescheduling due to construction delays, which actually results in a considerable workload. In general, large-scale construction works like this require a large amount of resources, and it is difficult to avoid the loss of resources and to grasp the actual progress of the construction work, so it is important that the process management system has a process readjustment function. However, it is common to respond by strictly adhering to the original schedule. However, even if such measures are taken to strictly adhere to the schedule, it is important for management to understand the progress of the construction work in a more concrete manner.

本発明はかかる点に対処してなされたもので、実際の工
事進歩状況を設定し確認することができるプラント建設
工程管理支援システムを提供することを目的とする。
The present invention has been made in response to this problem, and it is an object of the present invention to provide a plant construction process management support system that can set and confirm the actual construction progress status.

[発明の構成] (課題を解決するための手段) 本発明のプラント建設工程管理支援システムは、プラン
ト構成要素のデータを格納したデータベースと、前記プ
ラント構成要素にそれぞれ工事シーケンスを設定する工
事シーケンス設定機能と、前記プラント構成要素の有す
る時間属性およびシーケンスに基づいて時間軸に沿った
表示を行う表示機能と、工事シーケンスを設定された前
記プラント構成要素をその属性データの指定により前記
データベースから抽出し工事進歩状況を設定する工事進
歩状況設定機能とを有することを特徴とする。
[Structure of the Invention] (Means for Solving the Problems) The plant construction process management support system of the present invention includes a database that stores data on plant components, and a construction sequence setting that sets construction sequences for each of the plant components. a display function that displays along a time axis based on the time attribute and sequence that the plant component has; and a display function that extracts the plant component to which a construction sequence is set from the database by specifying its attribute data. It is characterized by having a construction progress status setting function for setting the construction progress status.

すなわち、本発明のプラント建設工程管理支援システム
では、たとえば以下に示すデータベース(DB)を利用
する。
That is, the plant construction process management support system of the present invention uses, for example, the following database (DB).

CAD−DB   :構成要素名、位置、形状、・・・
属性DB:構成要素の属性、例えば名前、工事予定日、
完成予定日、進歩状況(朱、工事中、完了日等)・・・ 標準工期DB:構成要素名、標準工期、工事制約条件、
・・・ シーケンスDB:工程名、要素−1、要素−1の作業ス
ケジュール(口時等)、要素−2、要素−2の作業スケ
ジュール、・・・ こ1れらのDBへのアクセス手段はDBMS(Data
  Base  Management  Syste
m)として一般化されている。そして、これらのDBを
もとにしてたとえば次のような手段を利用する。
CAD-DB: Component name, position, shape,...
Attribute DB: Attributes of component elements, such as name, scheduled construction date,
Scheduled completion date, progress status (red, under construction, completion date, etc.)... Standard construction period DB: Component name, standard construction period, construction constraints,
... Sequence DB: Process name, element-1, work schedule of element-1 (time etc.), element-2, work schedule of element-2, ... The means to access these DBs is DBMS (Data
Base Management System
It has been generalized as m). Then, based on these DBs, for example, the following means are used.

(イ)空間的領域、シーケンス、システム名/構成要素
名、日時、進歩状況等の属性値を指定することによりC
AD−DBより構成要素を抽出し表示する手段。
(b) By specifying attribute values such as spatial area, sequence, system name/component name, date and time, progress status, etc.
Means for extracting and displaying constituent elements from AD-DB.

(口)表示画面からマウス等のボインティングディバイ
スを用いて構成要素を選択する手段。
(mouth) A means of selecting a component from a display screen using a pointing device such as a mouse.

(ハ)選択された構成要素にデータ(日時等)を設定す
る手段。
(c) A means for setting data (date and time, etc.) in the selected component.

(二)各々の構成要素の有する時間属性、シーケンスに
基づいて時間軸に沿った表示を行う手段。
(2) Means for displaying along the time axis based on the time attributes and sequences of each component.

以上の手段もCAD技術の進展、ワークステーション等
の計算機技術の進展により一般化されている。
The above-mentioned means have also become popular due to advances in CAD technology and computer technology such as workstations.

(作 用) 本発明のプラント建設工程管理支援装置における進歩状
況設定機能は、ユーザーの要求に応じてCAD−DBよ
りデータを抽出しCRT等の表示装置に表示した後、マ
ウス等の要素選択手段により順次画面上で選択された要
素に進歩状況を登録する。工事が予定通り進んでおり、
がっ当日の工事予定が設定されているものであれば、極
めて容昌にそのイメージを視覚的に確認しながら個々の
要素に進歩状況を設定することができる。工程遅れのも
のに対しては、「完成予定日を過ぎているのに完成して
いないもので」といった簡単な条件で抽出し、同様な手
順で設定することができ、かつ工程遅れの確認も同時に
行うことができる。
(Function) The progress status setting function in the plant construction process management support device of the present invention extracts data from the CAD-DB according to the user's request, displays it on a display device such as a CRT, and then extracts data from the CAD-DB and displays it on a display device such as a CRT. The progress status is registered in the elements sequentially selected on the screen. Construction is progressing as planned.
If the construction schedule for the day is set, it is possible to visually check the image and set the progress status of each element in an extremely easy way. Items with process delays can be extracted using simple conditions such as ``Items have not been completed even though the scheduled completion date has passed'' and can be set using the same procedure. Can be done at the same time.

CADシステムのデータを用いているので、そこで個々
の構成要素の接続関係が定義されていれば、その接続関
係をたどることにより、要素人から要素Bといったマウ
ス等の選択により容易に工事進歩状況を設定することが
できる。
Since data from the CAD system is used, if the connection relationships of individual components are defined there, by tracing the connection relationships, you can easily check the construction progress status by selecting elements such as element B from element B using the mouse. Can be set.

(実施例) 以下、本発明の一実施例について説明する。(Example) An embodiment of the present invention will be described below.

第1図は本発明のプラント建設工程管理支援システムの
概略の機能構成を示すもので、CADシステムの有する
プラント構成要素のデータを収納したデータベース1を
もとに、主として工事シーケンス設定機能2、表示機能
3および工事進歩状況設定機能4によって構成される。
Fig. 1 shows the general functional configuration of the plant construction process management support system of the present invention, which mainly uses the construction sequence setting function 2, the display function, and the It is composed of a function 3 and a construction progress status setting function 4.

データベース1は、工事シーケンス設定機能2によって
設定された各構成要素の工事予定、標準工期、工事制約
条件、作業スケジュール等のデータをプラント構成要素
の属性値として順次蓄槓する。表示機能3はデータベー
ス1からデータを要求に応じて抽出しCRT等の表示装
置に表示するもので、各゛々の時間属性およびシーケン
スに基づいて時間軸に沿って表示することができる。工
事進歩状況設定機能4は、属性値を指定することにより
データベース1より抽出し画面上に表示したプラント構
成要素に当日の工事進歩状況を設定し、データベース1
に登録する機能であり、基本的なユーザーの操作は、常
に画面上に映し出されたその形状を見ながら「これは終
わった」、「これは工事にかかった」というようなデー
タを設定していけばよい。
The database 1 sequentially stores data such as the construction schedule, standard construction period, construction constraints, and work schedule for each component set by the construction sequence setting function 2 as attribute values of the plant components. The display function 3 extracts data from the database 1 in response to a request and displays it on a display device such as a CRT, and can display data along the time axis based on each time attribute and sequence. The construction progress status setting function 4 sets the current construction progress status for the plant components extracted from the database 1 and displayed on the screen by specifying attribute values, and
The basic user operation is to constantly look at the shape displayed on the screen and set data such as ``This is finished'' or ``This will require construction.'' Just go.

この間のインタラクションはワークステーション環境で
頻繁に利用されるウィンドーシステム、メニュー選択等
の手法を用いて実現することができる。
Interaction during this time can be realized using techniques such as window systems and menu selections that are frequently used in workstation environments.

工事進歩状況の設定は、例えば第2図に示すような手順
で行われる。まず、工事区画、対象系統等の選択をもっ
て空間的範囲を定める(5)。次に、設定された範囲の
構成要素に対する工事予定、進歩状況の属性データをデ
ータベース1から抽出し(6)、指定された時間範囲に
おいて完成すべき、着工すべきあるいは工事中であるべ
きといった工事状況の属性から構成要素を絞り込み(7
)、その範囲にある構成要素の形状データをデータベー
ス1から抽出する(8)。すでに工事完了したもの、予
定日を過ぎているが未完成のもの等を判別可能なように
所定の色等で表示して(9)、マウス等による要素選択
に対応してその進歩状況を設定し、データベース1に保
存する(10)。以上の操作を必要に応じて繰返す。
The construction progress status is set, for example, by the procedure shown in FIG. First, the spatial scope is determined by selecting the construction area, target system, etc. (5). Next, attribute data on the construction schedule and progress status for the components in the set range are extracted from the database 1 (6), and the construction work that should be completed, started, or under construction within the specified time range is extracted. Narrow down the components from the attributes of the situation (7
), the shape data of the constituent elements within that range is extracted from the database 1 (8). Items that have already been completed, items that are unfinished beyond the scheduled date, etc. are displayed in a predetermined color so that they can be distinguished (9), and the progress status is set in response to element selection using a mouse, etc. and save it in database 1 (10). Repeat the above operations as necessary.

以上説明したように、マウス等のボインティングディバ
イスを用いて、工事工程およびそこでの作業イメージ、
工事対象物のイメージを見ながら実際の工事進歩状況を
容易に設定することができる。
As explained above, using a pointing device such as a mouse, you can visualize the construction process and the work involved.
The actual construction progress status can be easily set while looking at the image of the construction object.

゛[発明の効果] 以上の説明からも明らかなように、本発明のプラント建
設工程管理支援システムは、工事工程の進歩度を具体的
に把握することができ、工程設定から実際の工事完了ま
でのスケジュール管理をグラフィカルに支援することが
できる。
゛ [Effects of the Invention] As is clear from the above explanation, the plant construction process management support system of the present invention can concretely grasp the progress of the construction process, and can be used from process setting to actual completion of construction. can graphically support schedule management.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明のプラント建設工程管理支援システムの
概略構成を示すブロック図、第2図は本発明のプラント
建設工程管理支援システムにおける工事進歩状況設定手
順の一例を示すフロー図である。 1・・・・・・・・・・・・データベース2・・・・・
・・・・・・・工事シ〜ケンス設定機能3・・・・・・
・・・・・・表示機能 4・・・・・・・・・・・・工事進歩状況設定機能出願
人     日本原子カ事業株式会社出願人     
株式会社 東 芝
FIG. 1 is a block diagram showing a schematic configuration of a plant construction process management support system of the present invention, and FIG. 2 is a flow diagram showing an example of a construction progress status setting procedure in the plant construction process management support system of the present invention. 1・・・・・・・・・・・・Database 2・・・・・・
......Construction sequence setting function 3...
・・・・・・Display function 4・・・・・・・・・Construction progress status setting function Applicant: Japan Atomic Energy Corporation Applicant:
Toshiba Corporation

Claims (1)

【特許請求の範囲】[Claims] (1)プラント構成要素のデータを格納したデータベー
スと、前記プラント構成要素にそれぞれ工事シーケンス
を設定する工事シーケンス設定機能と、前記プラント構
成要素の有する時間属性およびシーケンスに基づいて時
間軸に沿った表示を行う表示機能と、工事シーケンスを
設定された前記プラント構成要素をその属性データの指
定により前記データベースから抽出し工事進歩状況を設
定する工事進歩状況設定機能とを有することを特徴とす
るプラント建設工程管理支援システム。
(1) A database that stores data on plant components, a construction sequence setting function that sets construction sequences for each of the plant components, and display along the time axis based on the time attributes and sequences of the plant components. and a construction progress status setting function that extracts the plant components for which construction sequences have been set from the database by specifying their attribute data and sets the construction progress status. Management support system.
JP5941089A 1989-03-10 1989-03-10 Plant construction process management support system Expired - Lifetime JP2721231B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5941089A JP2721231B2 (en) 1989-03-10 1989-03-10 Plant construction process management support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5941089A JP2721231B2 (en) 1989-03-10 1989-03-10 Plant construction process management support system

Publications (2)

Publication Number Publication Date
JPH02236770A true JPH02236770A (en) 1990-09-19
JP2721231B2 JP2721231B2 (en) 1998-03-04

Family

ID=13112480

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5941089A Expired - Lifetime JP2721231B2 (en) 1989-03-10 1989-03-10 Plant construction process management support system

Country Status (1)

Country Link
JP (1) JP2721231B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06231137A (en) * 1993-01-28 1994-08-19 Amada Metrecs Co Ltd Computer supported work analyzer using video equipment
EP1331580A4 (en) * 2000-10-27 2008-03-26 Mitsubishi Electric Corp INSTALLATION PLAN SUPPORT METHOD, INSTALLATION PLAN SUPPORT SYSTEM SERVER COMPUTER, AND INSTALLATION PLAN SYSTEM CLIENT COMPUTER
JP2009076104A (en) * 2008-12-22 2009-04-09 Jgc Corp Construction work management device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6132165A (en) * 1984-07-24 1986-02-14 Mitsubishi Heavy Ind Ltd Device for computing progressing state of work at site
JPS62255053A (en) * 1986-04-30 1987-11-06 Toshiba Corp Process controller
JPS6397443U (en) * 1986-12-17 1988-06-23
JPS63211070A (en) * 1987-02-27 1988-09-01 Hitachi Ltd Display device for structure analysis and calculation result
JPS63280442A (en) * 1987-05-12 1988-11-17 Fujitsu Ltd Manufacture of semiconductor device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6132165A (en) * 1984-07-24 1986-02-14 Mitsubishi Heavy Ind Ltd Device for computing progressing state of work at site
JPS62255053A (en) * 1986-04-30 1987-11-06 Toshiba Corp Process controller
JPS6397443U (en) * 1986-12-17 1988-06-23
JPS63211070A (en) * 1987-02-27 1988-09-01 Hitachi Ltd Display device for structure analysis and calculation result
JPS63280442A (en) * 1987-05-12 1988-11-17 Fujitsu Ltd Manufacture of semiconductor device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06231137A (en) * 1993-01-28 1994-08-19 Amada Metrecs Co Ltd Computer supported work analyzer using video equipment
EP1331580A4 (en) * 2000-10-27 2008-03-26 Mitsubishi Electric Corp INSTALLATION PLAN SUPPORT METHOD, INSTALLATION PLAN SUPPORT SYSTEM SERVER COMPUTER, AND INSTALLATION PLAN SYSTEM CLIENT COMPUTER
JP2009076104A (en) * 2008-12-22 2009-04-09 Jgc Corp Construction work management device

Also Published As

Publication number Publication date
JP2721231B2 (en) 1998-03-04

Similar Documents

Publication Publication Date Title
US20050171790A1 (en) Construction project management system and method
US5835898A (en) Visual schedule management system for a manufacturing facility
US7042468B2 (en) Text overlay for multi-dimensional construction project models
US7720703B1 (en) System and method for tracking and managing construction projects
EP3454268A1 (en) A graphical project management tool technical field
US8412550B2 (en) One view integrated project management system
US20060167736A1 (en) Schedule chart for project management
US20100325582A1 (en) System and Method for Assigning and Scheduling Activities
US7428724B2 (en) Interactive interface for engineering standard work
US20040205519A1 (en) Method and system for automatically generating construction documents
Adelsberger et al. The leitstand-a new tool for computer-integrated manufacturing
JPH09512377A (en) Method and apparatus for process and project management computer systems
CN103034920B (en) System and method for controlling operations of manufacturing facility
CN105956742A (en) Command task management information and progress monitoring integrated display method
TWI784311B (en) Management device, management system, and management program
Retik et al. The use of computer graphics as a scheduling tool
JPH02236770A (en) System for supporting control of plant construction process
US20090048882A1 (en) Apparatus and methods for strategic planning
JPH02127773A (en) Plant construction process control support system
JP2000317779A (en) Simulation system for discrete phenomena
JPH0373257A (en) Production scheduling device
JPH07141421A (en) Process control system utilizing computer wherein general-purpose-process forming block is used
JPH01121155A (en) Production scheduling system
JP2000194755A (en) Inter-workplace worker accommodation system
JPH07296062A (en) Staffing decision support method