JPH025202B2 - - Google Patents
Info
- Publication number
- JPH025202B2 JPH025202B2 JP59120939A JP12093984A JPH025202B2 JP H025202 B2 JPH025202 B2 JP H025202B2 JP 59120939 A JP59120939 A JP 59120939A JP 12093984 A JP12093984 A JP 12093984A JP H025202 B2 JPH025202 B2 JP H025202B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- underground
- continuous wall
- hollow part
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、土止めならびに止水用として地下外
壁の外周に構築する地下連続壁に関する。DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to an underground continuous wall constructed around the outer periphery of an underground outer wall for use as earth retaining and water stopping purposes.
従来の地下外壁構造は、第6図で示すように、
空隙を有さない状態でコンクリートを打設して構
築された地下連続壁2に対して地下外壁1を密着
状態で構築し、この地下外壁1の地下室側に、各
階の浸透水を下層階及び最下層に位置する床スラ
ブ7の下方に流下案内する排水路50を形成する
とともに、前記の上下排水路50,50間の水の
自由落下空間Sを閉塞するコンクリートブロツク
壁10を構築している。
The conventional underground external wall structure is as shown in Figure 6.
The underground outer wall 1 is constructed in close contact with the underground continuous wall 2, which is constructed by pouring concrete without voids, and the seepage water from each floor is drained from the lower floors and the basement side of the underground outer wall 1. A concrete block wall 10 is constructed to form a drainage channel 50 that guides the flow downward of the floor slab 7 located at the lowest level, and to close off the free fall space S of water between the upper and lower drainage channels 50, 50. .
このような従来の地下外壁構造による場合は、
(イ) 地下連続壁2を構築するためのコンクリート
打設量が多く、それに伴うコンクリート打設作
業時間の増大によつて工期が長くなる。
In the case of such a conventional underground external wall structure, (a) the amount of concrete placed to construct the underground continuous wall 2 is large, and the construction period becomes longer due to the accompanying increase in concrete placing work time.
(ロ) 地下外壁1の各階の地下室側に夫々コンクリ
ートブロツク壁10を構築するため、地下室の
有効面積が小さくなるばかりでなく、工期の増
大とコストアツプを招来し易い問題があつた。(b) Concrete block walls 10 are constructed on the basement side of each floor of the basement exterior wall 1, which not only reduces the effective area of the basement, but also tends to increase construction time and costs.
本発明の第1目的は、地下連続壁自体の合理的
な改造をもつて該地下連続壁の構築工期の短縮化
を図る点にあり、第2目的は、第1目的を達成す
るための構造を有効利用した簡単な改造をもつて
浸透水処理に纒る従来の問題点を改善する点にあ
る。 The first objective of the present invention is to shorten the construction period of an underground continuous wall by rationally modifying the underground continuous wall itself, and the second objective is to develop a structure for achieving the first objective. The aim is to improve the conventional problems associated with permeate water treatment by making effective use of simple modifications.
本発明による地下連続壁の特徴構成は、前記地
下外壁の下端部あるいはそれに近い箇所よりも上
方において、連続壁体の厚み内に浸透水集収用の
中空部を備えさせるとともに、前記中空部を挟ん
だ厚み方向両側壁部を、前記連続壁体の長手方向
に継続して剛性連結し、かつ、前記中空部から前
記地下外壁の内部にわたつて排水路を設けた点に
ある。
The characteristic structure of the underground continuous wall according to the present invention is that a hollow part for collecting seepage water is provided within the thickness of the continuous wall above the lower end of the underground outer wall or a place near it, and the hollow part is sandwiched between the walls. The wall portions on both sides in the thickness direction are continuously and rigidly connected in the longitudinal direction of the continuous wall body, and a drainage channel is provided from the hollow portion to the inside of the underground outer wall.
上記特徴構成による作用効果は次の通りであ
る。 The effects of the above characteristic configuration are as follows.
つまり、連続壁体の厚み内に中空部を形成する
ことによつて、この連続壁体を構築するためのコ
ンクリート打設量を極力少なくでき、しかも、前
記中空部を挟んだ厚み方向両側壁部が連続壁体の
長手方向に断続して剛性連結することによつて、
地下連続壁を土圧等の各種応力に十分抗するだけ
の強度構造に構成することができながら、連続壁
体内を浸透してくる水を、工期の短縮化を目的と
して連続壁体に形成される中空部及びこれらに連
通形成された排水路を通して地下外壁内側の所要
箇所に排出することができるから、前記中空部形
成箇所に相当する地下外壁の地下室側には、従来
のような浸透水排出のための特別なコンクリート
ブロツク壁の構築を不要にできる。
In other words, by forming a hollow part within the thickness of the continuous wall, the amount of concrete poured to construct the continuous wall can be minimized, and furthermore, both walls in the thickness direction sandwiching the hollow part can be By connecting rigidly intermittently in the longitudinal direction of the continuous wall,
While it is possible to configure underground continuous walls with a structure strong enough to withstand various stresses such as earth pressure, it is possible to prevent water from penetrating into the continuous wall by forming it into a continuous wall for the purpose of shortening the construction period. Because the water can be discharged to the required location inside the underground outer wall through the hollow part and the drainage channel formed in communication with these, seepage water can be discharged to the basement side of the underground outer wall corresponding to the hollow part formation point as in the conventional method. This eliminates the need to construct special concrete block walls.
従つて、地下連続壁として要求される機械的強
度を充分確保し、しかも、コンクリート打設に要
する時間を極力少なくして工期の短縮化を図るこ
とができながら、第1目的を達成するために形成
される連続壁体の中空部を有効利用して、この中
空部に前述のような排水路を連通形成するだけの
簡単な改造をもつて、浸透水処理工事の工期短縮
化とコストダウンを図ることができるとともに、
地下室の有効床面積も大きくできるに至つた。
Therefore, in order to achieve the first objective, it is possible to secure sufficient mechanical strength required for an underground continuous wall, and to shorten the construction period by minimizing the time required for concrete pouring. By making effective use of the hollow part of the continuous wall that is formed, and by simply modifying the hollow part to form a drainage channel as described above, it is possible to shorten the construction period and reduce the cost of seepage water treatment work. In addition to being able to
The effective floor area of the basement has also been increased.
第1図で示すように、地下構造物の地下外壁1
の外周に構築される地下連続壁2を構成するに、
連続壁体の厚み内の中心部に、中空部の一例で、
地上GL近くから地下2階の床スラブ3形成相当
位置にまで及ぶ長さを有する中空部としての有底
筒状孔4を備えさせるとともに、前記有底筒状孔
4を連続壁体の厚み方向に挟んだ両側壁部2a,
2aを前記連続壁体の長手方向に断続して一体的
に形成し、更に、前記有底筒状孔4の下端から前
記地下外壁1の内部に亘つて排水路6を設けてい
る。
As shown in Figure 1, the underground outer wall 1 of the underground structure
To configure the underground continuous wall 2 constructed around the outer periphery of
This is an example of a hollow part in the center of the thickness of the continuous wall.
A bottomed cylindrical hole 4 is provided as a hollow portion having a length extending from near the ground level GL to a position corresponding to the formation of the floor slab 3 on the second basement floor, and the bottomed cylindrical hole 4 is inserted in the thickness direction of the continuous wall body. Both side wall portions 2a sandwiched between
2a are integrally formed intermittently in the longitudinal direction of the continuous wall body, and furthermore, a drainage channel 6 is provided extending from the lower end of the bottomed cylindrical hole 4 to the inside of the underground outer wall 1.
また、前記地下外壁2の、地下3階の上下両側
に位置する壁部分1a,1bには、前記排水路6
からの水を下層階及び最下層階でもある地下3階
の床スラブ7の下方に排出案内する排水路8,9
を形成するとともに、これら両排水路8,9間の
水の自由落下空間Sを閉塞するコンクリートブロ
ツク壁10を構築している。 In addition, the drainage channels 6 are provided in the wall portions 1a and 1b of the underground outer wall 2 located on both upper and lower sides of the third basement floor.
Drain channels 8 and 9 that drain and guide water from the lower floors and below the floor slab 7 on the third basement floor, which is also the lowest floor.
At the same time, a concrete block wall 10 is constructed to close off the free fall space S of water between these drainage channels 8 and 9.
尚、図中11は地下2階の床スラブ3に形成さ
れた堰である。 In addition, numeral 11 in the figure is a weir formed on the floor slab 3 on the second basement floor.
次に、上述の如く構成された地下連続壁2の構
築方法の一例を説明する。 Next, an example of a method of constructing the underground continuous wall 2 configured as described above will be explained.
(イ) 第2図で示すように、連続壁体構築予定箇所
を掘削し、鉄筋かご12に中空部形成用鋼管1
3に対する円弧状ガイド14,14を取付けて
前記掘削孔a内に建込む。(b) As shown in Figure 2, excavate the area where the continuous wall is planned to be constructed, and place steel pipes 1 for forming hollow parts in the reinforcing bar cage 12.
The arc-shaped guides 14, 14 for 3 are attached and built into the excavated hole a.
(ロ) 先端を密閉処理した前記鋼管13に引き抜き
を容易にするための合成樹脂発泡シート(商品
名セキスイT−フオム等)などを巻きつけたの
ち、前記円弧状ガイド14,14に沿つて挿入
してコンクリートを打設する。(b) After wrapping a synthetic resin foam sheet (trade name: Sekisui T-Foom, etc.) to make it easier to pull out the steel pipe 13, the tip of which has been sealed, the tube is inserted along the arcuate guides 14, 14. and pour concrete.
(ハ) コンクリート打設後、第3図で示すように前
記鋼管13に挟持固定されたチヤツク15及び
ジヤツキ16を介して鋼管13を引き抜き、転
用する。(c) After concrete is poured, the steel pipe 13 is pulled out through the chuck 15 and jack 16 which are clamped and fixed to the steel pipe 13, as shown in FIG. 3, and is used for other purposes.
尚、上述実施例では地下構造物として地下3階
の場合を例にとつて説明したが、この階数は各種
条件に応じて自由に変更できるものである。 In the above-described embodiment, the underground structure has three floors underground, but the number of floors can be freely changed depending on various conditions.
(イ) 第4図で示すように、地下連続壁2の有底筒
状孔4を、連続壁体の厚み方向中心位置よりも
外方に変位させた状態で形成する。この実施例
の場合は、浸透水排出空間を形成するための有
底筒状孔4に向かつてひび割れを積極的に誘導
することができるから、例えば、前記有底筒状
孔4を連続壁体の厚み方向中心位置よりも内方
に変位させる場合に比して、この有底筒状孔4
以外の箇所にひび割れが発生することに起因す
る漏水を抑制することができる利点がある。
(a) As shown in FIG. 4, the bottomed cylindrical hole 4 of the underground continuous wall 2 is formed in a state displaced outward from the center position in the thickness direction of the continuous wall. In the case of this embodiment, since it is possible to actively induce cracks toward the bottomed cylindrical hole 4 for forming the seepage water discharge space, for example, the bottomed cylindrical hole 4 can be connected to a continuous wall. Compared to the case where the bottomed cylindrical hole 4 is displaced inward from the center position in the thickness direction
There is an advantage that water leakage caused by cracks occurring in other locations can be suppressed.
(ロ) 第5図で示すように、掘削孔a内に所定のピ
ツチで鉄骨17……を建込むとともに、これら
隣接鉄骨17,17……間に中空部形成用ウレ
タン18……を充填したのち、コンクリート打
設する。(b) As shown in Fig. 5, steel frames 17... were erected at a predetermined pitch in the excavated hole a, and urethane 18 for forming hollow portions was filled between these adjacent steel frames 17, 17... Afterwards, concrete will be poured.
コンクリート打設後にウレタン18……を抜
き出す。言換えれば、連続壁体の、中空部4を
挟んだ厚み方向両側壁部2a,2aを鉄骨17
……にて剛性連結する。 After concrete is poured, urethane 18... is extracted. In other words, both wall portions 2a, 2a in the thickness direction sandwiching the hollow portion 4 of the continuous wall body are connected to the steel frame 17.
Rigidly connect at...
第1図乃至第3図は本発明に係る地下連続壁の
実施例を示し、第1図は縦断正面図、第2図、第
3図は構築工法の一例を示す平面図と縦断正面図
である。第4図、第5図は夫々別の実施例を示す
要部の横断平面図であり、第6図は従来の地下連
続壁を示す縦縦断正面図である。
1……地下外壁、2a……両側壁部、4……中
空部、有底筒状孔、6……排水路。
Figures 1 to 3 show examples of underground continuous walls according to the present invention, with Figure 1 being a vertical front view, and Figures 2 and 3 being a plan view and a vertical front view showing an example of the construction method. be. 4 and 5 are cross-sectional plan views of main parts showing different embodiments, respectively, and FIG. 6 is a longitudinal cross-sectional front view showing a conventional underground continuous wall. DESCRIPTION OF SYMBOLS 1... Basement outer wall, 2a... Both side wall parts, 4... Hollow part, bottomed cylindrical hole, 6... Drainage channel.
Claims (1)
つて、前記地下外壁1の下端部あるいはそれに近
い箇所よりも上方において、連続壁体の厚み内に
浸透水集収用の中空部4を備えるとともに、前記
中空部4を挟んだ厚み方向両側壁部2a,2a
を、前記連続壁体の長手方向に断続して剛性連結
し、かつ、前記中空部4から前記地下外壁1の内
部にわたつて排水路6を設けてある地下連続壁。1 An underground continuous wall constructed around the outer periphery of the underground outer wall 1, which is provided with a hollow part 4 for collecting seepage water within the thickness of the continuous wall above the lower end of the underground outer wall 1 or a place near it. , both side wall portions 2a, 2a in the thickness direction sandwiching the hollow portion 4
are rigidly connected intermittently in the longitudinal direction of the continuous wall body, and a drainage channel 6 is provided extending from the hollow part 4 to the inside of the underground outer wall 1.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12093984A JPS611720A (en) | 1984-06-12 | 1984-06-12 | Underground continuous wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12093984A JPS611720A (en) | 1984-06-12 | 1984-06-12 | Underground continuous wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS611720A JPS611720A (en) | 1986-01-07 |
| JPH025202B2 true JPH025202B2 (en) | 1990-02-01 |
Family
ID=14798705
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12093984A Granted JPS611720A (en) | 1984-06-12 | 1984-06-12 | Underground continuous wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS611720A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112281810A (en) * | 2020-10-21 | 2021-01-29 | 江苏旭辰交通科技发展有限公司 | Construction method of underground diaphragm wall with water-rich fine sand layer |
| CN116122264B (en) * | 2023-03-21 | 2025-09-02 | 上海市机械施工集团有限公司 | A method for constructing underground continuous walls in existing underground structures |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4898617A (en) * | 1972-03-29 | 1973-12-14 | ||
| JPS5936058B2 (en) * | 1981-10-20 | 1984-09-01 | 鹿島建設株式会社 | How to construct a structure using underground continuous walls |
-
1984
- 1984-06-12 JP JP12093984A patent/JPS611720A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS611720A (en) | 1986-01-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH039277B2 (en) | ||
| US3656268A (en) | Drainage wall system and method of erecting same | |
| JP3645773B2 (en) | Wastewater treatment method for underground wall and underground wall constructed by this method | |
| JPH025202B2 (en) | ||
| US4465403A (en) | Method of constructing poured-concrete wall panels and wall thus obtained | |
| EP1116829A2 (en) | Foundation raft | |
| CN218060417U (en) | Concrete pouring and tamping structure for vertical structure of underground structure constructed by reverse construction method | |
| JPS5829922A (en) | Constructing method for underground outer wall | |
| KR200242253Y1 (en) | Drain pipe of tunnel | |
| CN213682162U (en) | Wall body template bearing structure of column plate wall slope protection structure | |
| EP1310601A2 (en) | Foundation raft | |
| JPH084033A (en) | Construction method of the pressure barrier against the outer perimeter of the building | |
| CN220079984U (en) | Precast concrete drainage pile | |
| CN112211204A (en) | A wall formwork support structure of a column-slab wall slope protection structure and its construction method | |
| KR20060115303A (en) | Tunnel drainage method | |
| CN209990501U (en) | Drainage blind pipe device suitable for collapsible loess tunnel | |
| JPH10195866A (en) | Underground diaphragm wall | |
| CN222362472U (en) | Basement enclosure strengthening structure | |
| JP3991480B2 (en) | Construction method for the junction of the sinking box | |
| JPH07894B2 (en) | Construction method for underground wall | |
| JPS637416A (en) | Construction of hollow concrete structure under ground | |
| JPS6335998A (en) | Tunnel lining method | |
| JP2000234332A (en) | Connection structure and connection method of underground continuous wall and guide wall | |
| JPH0128172Y2 (en) | ||
| JPH0730628B2 (en) | Steel pipe concrete pillar construction method |