JPH0256450B2 - - Google Patents

Info

Publication number
JPH0256450B2
JPH0256450B2 JP17570283A JP17570283A JPH0256450B2 JP H0256450 B2 JPH0256450 B2 JP H0256450B2 JP 17570283 A JP17570283 A JP 17570283A JP 17570283 A JP17570283 A JP 17570283A JP H0256450 B2 JPH0256450 B2 JP H0256450B2
Authority
JP
Japan
Prior art keywords
formwork
slab
column
floor
dolly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP17570283A
Other languages
Japanese (ja)
Other versions
JPS6065843A (en
Inventor
Hisanobu Kobayashi
Shunichi Kobayashi
Yasuyuki Myoshi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Metal Products Co Ltd
Original Assignee
Nippon Steel Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Metal Products Co Ltd filed Critical Nippon Steel Metal Products Co Ltd
Priority to JP17570283A priority Critical patent/JPS6065843A/en
Publication of JPS6065843A publication Critical patent/JPS6065843A/en
Publication of JPH0256450B2 publication Critical patent/JPH0256450B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は、大組型枠による建築工法の改良に係
り、詳しくは大組型枠の脱型、移動、組立を容易
にし、且つ1階分の躯体コンクリートを打設して
順次上階に建築物の躯体構造物を築造していく建
築工法に関する。
[Detailed Description of the Invention] The present invention relates to an improvement in a construction method using a large-scale formwork, and more specifically, it facilitates the removal, movement, and assembly of a large-scale formwork, and also facilitates the pouring of one-story concrete structure. It relates to a construction method in which the building frame structure is built on the upper floors one after another.

従来、中層建築物等の躯体構造物を作るには、
一般にメタルフオーム工法が行われてきたが、こ
のメタルフオーム工法は組立、解体が手作業で行
われる為、工期が長期化していた。このようなこ
とから近時、大組型枠を用いる種々の工法が普及
しているが、これらの工法は、いずれも壁、柱
と、梁、スラブのコンクリートが2回に分けて打
設されるので、壁、柱の大組型枠のセツト、脱
型、移動と、梁、スラブの大組型枠のセツト、脱
型、移動とを交互に行うことになり、施工が繁雑
となつて、施工能率が期待した程向上しないのが
実情である。
Traditionally, to make frame structures such as medium-rise buildings,
Generally, the metal form construction method has been used, but since assembly and disassembly are done by hand, this metal form construction method takes a long time. For this reason, various construction methods using large formwork have become popular in recent years, but in all of these construction methods, the concrete for walls, columns, beams, and slabs is poured in two steps. As a result, the construction work became complicated because the large formwork for walls and columns had to be set, removed, and moved, and the large formwork for beams and slabs had to be set, removed, and moved alternately. The reality is that construction efficiency has not improved as much as expected.

一方、海外では建築のトンネル工法として、ス
ラブと壁のコンクリート打設を1回で済ませる方
法があるが、この工法は躯体構造物の形状が単純
なものにしか適用できない。またスラブコンクリ
ートの養生期間が長く、壁、柱コンクリートの養
生期間が短いので、型枠の脱型を2回に分けて行
うことが必要であるが、トンネル工法の場合これ
が不可能である。
On the other hand, overseas, there is an architectural tunnel construction method that requires only one step of pouring concrete for the slab and walls, but this method can only be applied to structures with simple shapes. Furthermore, since the curing period for slab concrete is long and the curing period for wall and column concrete is short, it is necessary to demold the formwork in two steps, but this is not possible with the tunnel construction method.

通常、躯体構造物の躯体コンクリートを1回で
打設する場合、型枠を大組型枠にすると、スラ
ブ、梁のコンクリートがある為、上階へ移動が困
難である。
Normally, when concrete is poured for a frame structure in one go, if the formwork is made into a large assembly formwork, it is difficult to move it to the upper floors because of the concrete slabs and beams.

本発明は斯かる諸事情に鑑みなされたものであ
り、大組柱型枠と大組スラブ・梁型枠を組合せセ
ツトしたその内側に躯体コンクリートを打設し、
養生後、大組の各型枠を脱型し、躯体構造物の開
口部に走行移動し、これより上階の所定位置に吊
り上げ移動して組合せセツトの上、躯体コンクリ
ートを打設することを順次繰り返していく大組型
枠による建築工法を提供せんとするものである。
The present invention was developed in view of the above circumstances, and consists of a combination of a large column formwork and a large slab/beam formwork, and the concrete is poured inside the set.
After curing, each formwork in the large assembly is removed, moved to the opening of the frame structure, lifted from there to a predetermined position on the upper floor, assembled, and then concrete for the frame is poured. The aim is to provide a construction method using large-scale formwork that can be repeated in sequence.

以下本発明による大組型枠による建築工法の詳
細について説明する。
The details of the construction method using the large assembled formwork according to the present invention will be explained below.

先ず本発明の建築工法を実施する為の大組型枠
及びそれにまつわる補助の型枠等を図によつて説
明する。
First, the large-scale formwork and related auxiliary formwork for carrying out the construction method of the present invention will be explained using figures.

第1図a,bに示すものは、壁柱と言われる柱
を築造する大組柱型枠1で、この大組柱型枠1
は、複数枚の鋼製型枠2をUクリツプにて結合の
上、上、中、下3段に角パイプ2丁合せの端太材
3を連結して補強した広幅の型枠パネル4を相対
向させ、各型枠パネル4の互いに反対側の側端に
細幅の型枠パネル5を回動可能に支持せしめたも
のである。即ち、型枠パネル5の両側端に前記広
幅の型枠パネル4の側端に当接するアングル材5
aが設けられ、一側端のアングル材5aにヒンヂ
プレート6が上、中、下3段に固設され、この各
ヒンヂプレート6のボルト穴と広幅の型枠パネル
4に於ける端太材3の端部に穿設された長孔7に
ヒンヂボルト8が挿通され締付けられ、細幅の型
枠パネルが広幅の型枠パネル4の側端に回動可能
に支持されている。尚長孔7は端太材3の端部に
設ける代りにヒンヂプレート6に設け、ヒンヂプ
レート6のボルト穴を端太材3の端部に設けるよ
うにしても良いものである。従つて柱の二側面の
型枠パネル5が開閉可能となつている。この型枠
パネル5を回動して閉じたその外側で相対向する
端太材3の端部間にはタイボルト9が締付張架さ
れて、相対向する広幅の型枠パネル4間がコンク
リートの打設により拡がらないようにしてある。
各広幅の型枠パネル4の上部の端太材3の外面に
は左右にハンガー取付金具10が設けられ、その
下方位置で型枠パネル4には後述するリフテイン
グフレームで吊り上げる為の吊り金具11が着脱
可能に水平に取付けられている。
What is shown in Fig. 1 a and b is a large column formwork 1 for constructing pillars called wall pillars.
A wide formwork panel 4 is constructed by connecting multiple steel formworks 2 with U-clips, and then reinforcing them by connecting thick pieces 3 of two square pipes at the top, middle, and bottom three stages. A narrow formwork panel 5 is rotatably supported at opposite side ends of each formwork panel 4 so as to face each other. That is, angle members 5 are placed on both sides of the formwork panel 5 to abut against the side ends of the wide formwork panel 4.
a, and hinge plates 6 are fixed to the angle member 5a at one side end in three stages: upper, middle, and lower. A hinge bolt 8 is inserted into a long hole 7 drilled at the end and tightened, and the narrow formwork panel is rotatably supported at the side end of the wide formwork panel 4. Note that the elongated holes 7 may be provided in the hinge plate 6 instead of being provided at the ends of the end pieces 3, and the bolt holes of the hinge plates 6 may be provided at the ends of the end pieces 3. Therefore, the formwork panels 5 on the two sides of the column can be opened and closed. After the formwork panel 5 is rotated and closed, tie bolts 9 are tightened and tensioned between the ends of the thick timbers 3 that face each other on the outside, and the space between the wide formwork panels 4 that face each other is made of concrete. The concrete is placed in place to prevent it from spreading.
Hanger mounting fittings 10 are provided on the left and right sides of the outer surface of the thick timber 3 at the top of each wide formwork panel 4, and below these hanger fittings 10 are attached to the formwork panel 4 for lifting with a lifting frame to be described later. is removably mounted horizontally.

尚、型枠パネル5は、型枠パネル4よりも上端
を低くしてあつて、所定位置にセツトした際、こ
の部分に後述する梁底型枠の端部のL形鋼製型枠
が配されようになつている。
The upper end of the formwork panel 5 is lower than that of the formwork panel 4, and when it is set in a predetermined position, the L-shaped steel formwork at the end of the beam bottom formwork, which will be described later, is placed in this part. It is becoming more and more like that.

第2図は大組スラブ・梁型枠13を示すもの
で、この大組スラブ・梁型枠13は、テーブル1
4上に支持したスラブ型枠15の左右両側端の調
整型枠16の下側に梁側型枠17を進退可能に支
持したものである。即ち、テーブル14の上面の
大引14aの下側で、左右両側方に伸縮自在な伸
縮管18が複数本一定間隔を存してスラブ型枠1
5に取付けられ、この伸縮管18の両端のコネク
タ22に梁側型枠17の外面に取付けられた伸縮
管受金具がピン結合されて、梁側型枠17がスラ
ブ型枠15の左右両側端の調整型枠16の下側に
沿つて進退可能に支持されている。この梁側型枠
17を摺動させる駆動源としては油圧ジヤツキが
使用され、この油圧ジヤツキは手押し車に搭載さ
れ、使用時伸縮管18の中央部一側面に設けられ
たブラケツトと梁型枠17の外面に取付けたジヤ
ツキ受金具の係合ピンに張架するものである。ス
ラブ型枠15の左右両側端の梁側型枠17を前進
させた際には調整型枠16の下側に適宜な寸法の
間隔保持型枠が配され、この間隔保持型枠34が
梁側型枠17とUクリツプ(図示省略)て結合さ
れ、調整型枠16及びスラブ型枠15とUクリツ
プ付クランプピン(図示省略)にて結合されるも
のである。前記梁側型枠17の外側下端にハンガ
ーレール吊り金具(図示省略)を介してハンガー
レール37が水平に取付けられ、このハンガーレ
ール37に伸縮可能なハンガー38がその上端の
ローラ39にて走行可能に取付けられている。
Figure 2 shows the large slab/beam formwork 13.
A beam side formwork 17 is supported under adjustment formworks 16 at both left and right ends of a slab formwork 15 supported on the slab formwork 15 so as to be movable forward and backward. That is, below the main drawer 14a on the upper surface of the table 14, there are a plurality of telescopic tubes 18 which are extendable and retractable on both the left and right sides at regular intervals, and are connected to the slab formwork 1.
5, and the expandable tube holder attached to the outer surface of the beam side formwork 17 is connected with pins to the connectors 22 at both ends of this expandable tube 18, so that the beam side formwork 17 connects to both left and right ends of the slab formwork 15. It is supported along the lower side of the adjustment formwork 16 so as to be movable forward and backward. A hydraulic jack is used as a driving source for sliding this beam side formwork 17, and this hydraulic jack is mounted on a handcart, and when in use, it connects a bracket provided on one side of the central part of the telescoping pipe 18 and the beam formwork 17. It is suspended from the engaging pin of the jack holder attached to the outer surface of the holder. When the beam-side formwork 17 at both left and right ends of the slab formwork 15 is advanced, a spacing-maintaining formwork of appropriate dimensions is arranged below the adjustment formwork 16, and this spacing-maintaining formwork 34 is placed on the beam side. It is connected to the formwork 17 with a U clip (not shown), and is connected to the adjustment formwork 16 and the slab formwork 15 with a clamp pin with a U clip (not shown). A hanger rail 37 is horizontally attached to the outer lower end of the beam side formwork 17 via a hanger rail hanging fitting (not shown), and an extendable hanger 38 can run on the hanger rail 37 using rollers 39 at its upper end. installed on.

第3図に示すものは、梁底型枠40で、この梁
底型枠40は、平坦な鋼製型枠41aと前記大組
柱型枠1の両側面の型枠パネル5の上端と結合さ
れるL形鋼製型枠41bとより成り、これらは
個々に組合せセツトするものである。
What is shown in FIG. 3 is a beam bottom formwork 40, which is connected to a flat steel formwork 41a and the upper ends of the formwork panels 5 on both sides of the large column column formwork 1. The L-shaped steel formwork 41b is assembled and set individually.

第4図に示すものは前記大組スラブ・梁型枠1
3の前後方向端の梁型枠42で、この梁型枠42
はスラブ型枠15の前端又は後端に結合するL形
の梁側鋼製型枠42aと、これに対する梁側型枠
42bと両梁側鋼製型枠42a,42b間の下端
に配される平坦な梁底鋼製型枠42cとより成
り、これらは個々に組合せセツトするものであ
る。尚42a′は脱型用のテーパー付梁側鋼製型枠
である。
What is shown in Figure 4 is the large slab/beam formwork 1.
The beam formwork 42 at the front and back ends of No. 3
is arranged at the lower end between the L-shaped beam side steel formwork 42a connected to the front end or rear end of the slab formwork 15, the beam side formwork 42b for this, and both beam side steel formworks 42a, 42b. It consists of a flat beam-bottomed steel formwork 42c, which are assembled and set individually. Note that 42a' is a tapered beam side steel formwork for demolding.

第5図に示すものは建築物の外面に配される外
面梁側型枠パネル43で、これには大組柱型枠1
の外面の型枠パネル4を走行可能に吊垂するハン
ガーレール37及びハンガー38が設けられてい
て、大組スラブ・梁型枠13の梁側型枠17にタ
イボルトにて結合され且つセツトされた大組柱型
枠1の外面の型枠パネル4に結合支持されるよう
になつている。
What is shown in FIG.
A hanger rail 37 and a hanger 38 are provided for movably suspending the form panel 4 on the outer surface of the block, and are connected to the beam side formwork 17 of the large slab/beam formwork 13 with tie bolts and set. It is designed to be connected and supported by a formwork panel 4 on the outer surface of the large column formwork 1.

次に上記の大組柱型枠1、大組スラブ・梁型枠
13、梁底型枠40、梁型枠42、外面梁側型枠
パネル43等を用いて中層建築物の躯体構造物を
築造する建築工法の工程を説明する。
Next, use the above-mentioned large column formwork 1, large slab/beam formwork 13, beam bottom formwork 40, beam formwork 42, external beam side formwork panel 43, etc. to construct the frame structure of a medium-rise building. Explain the process of construction method.

予め前記各型枠が組合せセツトされた状態で、
1階の躯体コンクリートが打設され、養生期間が
経過したならば、先ず第6図aに示す如く各大組
スラブ・梁型枠13の両側端の梁側型枠17の下
端部のハンガーレール37にハンガー38を介し
て走行可能に吊垂され、且つ梁側型枠17の下端
に結合された大組柱型枠1の下端を受けている枕
45を第6図bに示す如く外し、大組柱型枠1と
梁側型枠17との結合を解き、次に細幅の型枠パ
ネル5の外側で相対向する端太材3の端部間に張
架されたタイボルト9を外し、各型枠パネル5を
ヒンヂボルト8を介して、端太材3の長孔7に沿
つて外側方に引き、ヒンヂボルト8を中心に回動
して直角に開く。次いで、梁底型枠40の端部の
L形鋼製型枠41bと広幅の型枠パネル4の上部
両側面を結合しているコーナーアングル46を取
外す。次に大組柱型枠1を脱型し、該大組柱型枠
1をハンガー38のローラ39を介してハンガー
レール37内を走行させて躯体構造物の開口部側
に移動する。同様に各大組柱型枠1を前記の手順
を経て順次躯体構口部側に移動する。この時外柱
外面に位置する広幅の型枠パネル4は、外面梁側
型枠パネル43の下端部に取付けられたハンガー
レール37内(第5図参照)を走行して移動す
る。
With each formwork set in advance,
After the concrete for the first floor frame has been poured and the curing period has passed, first, as shown in Figure 6a, hanger rails are installed at the lower ends of the beam side formwork 17 at both ends of each large slab/beam formwork 13. Remove the pillow 45, which is movably suspended from the pillar 37 via the hanger 38 and which receives the lower end of the large column formwork 1 connected to the lower end of the beam side formwork 17, as shown in FIG. 6b. The large column formwork 1 and the beam side formwork 17 are uncoupled, and then the tie bolts 9 stretched between the ends of the thick timbers 3 facing each other on the outside of the narrow formwork panel 5 are removed. , each formwork panel 5 is pulled outward along the long hole 7 of the end piece 3 via the hinge bolt 8, and rotated around the hinge bolt 8 to open at right angles. Next, the corner angles 46 connecting the L-shaped steel formwork 41b at the end of the beam bottom formwork 40 and both upper sides of the wide formwork panel 4 are removed. Next, the large-assembly column form 1 is demolded, and the large-assembly column form 1 is moved within the hanger rail 37 via the rollers 39 of the hanger 38 to the opening side of the frame structure. Similarly, each large-assembly column formwork 1 is sequentially moved to the frame opening side through the above-described procedure. At this time, the wide formwork panel 4 located on the outer surface of the outer column travels within the hanger rail 37 (see FIG. 5) attached to the lower end of the outer beam side formwork panel 43.

次に第6図cの如く躯体構造物Bの開口部まで
移動した大組柱型枠1の吊り金具11にリフテイ
ングフレームFの吊り索Wを掛合し、ハンガー取
付金具10よりハンガー38を外して、リフテイ
ングフレームFにて大組柱型枠1をその一側が一
点鎖線に示す如く躯体構造物Bの外方にはみ出る
まで移動し、その一側面の開かれた型枠パネル5
を閉じ、相対向する型枠パネル4を連結した後、
リフテイングフレームFにて大組柱型枠1全体を
躯体構造物Bの外方に引き出して実線の如く吊り
上げる。そして2階の柱鉄筋47が配筋され、キ
ツカー48が躯体構造物Bと一体に築造された所
定位置に第6図dに示す如く柱鉄筋47を内包す
るように吊り降ろし、予めキツカー48の外面に
配置した枕45上に載せ、他側面の開かれた型枠
パネル5を閉じ、その両外側で相対向する端太材
3の端部間にタイボルト9を締付張架してセツト
を終える。同様の各大組柱型枠1を上階の所定位
置に吊り上げ移動してセツトする。
Next, as shown in FIG. 6c, hook the hanging cable W of the lifting frame F to the hanging fitting 11 of the large column formwork 1 that has been moved to the opening of the frame structure B, and remove the hanger 38 from the hanger fitting 10. Then, using the lifting frame F, move the large column formwork 1 until one side of it protrudes outside the frame structure B as shown by the dashed line, and open the formwork panel 5 on one side.
After closing and connecting the opposing formwork panels 4,
The entire large column formwork 1 is pulled out to the outside of the frame structure B by the lifting frame F and lifted up as shown by the solid line. Then, the column reinforcing bars 47 on the second floor are arranged, and the kicker 48 is suspended at a predetermined position built integrally with the frame structure B so as to enclose the column reinforcing bars 47 as shown in FIG. 6d. Place it on a pillow 45 placed on the outside, close the formwork panel 5 that is open on the other side, and tighten and tension the tie bolts 9 between the ends of the end pieces 3 facing each other on both outside sides to complete the set. Finish. Each similar large column formwork 1 is lifted up and moved to a predetermined position on the upper floor and set.

次いで大組柱型枠1の走行方向の各大組柱型枠
1間の梁底型枠40の第6図bに示されるサポー
ト49を外し、平坦な鋼製型枠41aの両側のコ
ーナーアングル50を外して鋼製型枠41a及び
L形鋼製型枠41bを大組スラブ・梁型枠13の
梁側型枠17との結合を解いてから脱型し、これ
を2階に移動し、第6図eに示す如く先にセツト
した大組柱型枠1間にサポート49を用いてセツ
トする。
Next, the supports 49 shown in FIG. 6b of the beam bottom formwork 40 between each large-assembly column formwork 1 in the running direction of the large-assembly column formwork 1 are removed, and the corner angles on both sides of the flat steel formwork 41a are removed. 50, the steel formwork 41a and the L-shaped steel formwork 41b are uncoupled from the beam side formwork 17 of the large slab/beam formwork 13, and then demolded and moved to the second floor. As shown in FIG. 6e, the support 49 is used to set between the large column formwork 1 set previously.

また第6図fに示される大組スラブ・梁型枠1
3の前後方向端の梁型枠42の梁側鋼製型枠42
a′,42a,42bを脱型し、下端の梁底鋼製型
枠42c(第4図参照)をサポートを外して脱型
し、これらを2階に移動して第6図fと同様に梁
型枠42を組立てる。
Also, large slab/beam formwork 1 shown in Figure 6 f
Beam-side steel formwork 42 of the beam formwork 42 at the front-back direction end of No. 3
a', 42a, and 42b are demolded, and the lower end beam bottom steel formwork 42c (see Figure 4) is demolded by removing the support, and these are moved to the second floor and processed in the same manner as in Figure 6f. Assemble the beam formwork 42.

次に、大組スラブ・梁型枠13の左右両側端の
梁側型枠17に於ける端部の脱型用テーパ付梁側
型枠51(第6図f参照)を取外し、且つ調製型
枠16の下側の間隔保持型枠34を取外した後、
手押し車30に搭載された油圧ジヤツキを伸縮管
18の一側面のブラケツトと梁側型枠17のジヤ
ツキ受金具(図示省略)との間に張架し、該油圧
ジヤツキを短縮して、第6図gに示す如く伸縮管
18の先端に結合支持された梁側型枠17を後退
させて脱型する。脱型後油圧ジヤツキを取外し、
手押し車30を除去した後テーブル14の下側に
ドーリ52を配し、第6図hに示す如くテーブル
14の下部支柱14bを引上げた後該ドーリ52
により大組スラブ・梁型枠13全体を下降させて
スラブ型枠15を脱型すると共に梁下をくぐれる
ようにし、ドーリ52を走行させて第6図iに示
す如く大組スラブ・梁型枠13を躯体構造物Bの
開口部に移動する。
Next, remove the tapered beam side formwork 51 (see Fig. 6 f) for demolding at the end of the beam side formwork 17 at both left and right ends of the large assembled slab/beam formwork 13, and remove the After removing the spacing formwork 34 on the lower side of the frame 16,
A hydraulic jack mounted on the handcart 30 is stretched between a bracket on one side of the telescoping pipe 18 and a jack receiving fitting (not shown) on the beam side formwork 17, and the hydraulic jack is shortened. As shown in FIG. g, the beam-side formwork 17 connected and supported at the tip of the telescopic tube 18 is moved back and removed from the mold. After demolding, remove the hydraulic jack,
After removing the wheelbarrow 30, a dolly 52 is placed below the table 14, and after pulling up the lower support 14b of the table 14 as shown in FIG.
The entire large slab/beam formwork 13 is lowered to remove the slab formwork 15 and pass under the beam, and the dolly 52 is run to lower the large slab/beam formwork 13 as shown in Figure 6i. 13 to the opening of the frame structure B.

次いで躯体構造物Bの開口部に移動した大組ス
ラブ・梁型枠13をテーブル14と一緒にリフテ
イングフレームF′にて吊り上げて第6図jに示す
如く2階の所定位置に移動し、ドーリ52は次の
大組スラブ・梁型枠13の脱型の為に走行移動
し、前記と同様に大組スラブ・梁型枠13を脱型
し、躯体構造物Bの開口部に移動し、この大組ス
ラブ・梁型枠13をリフテイングフレームF′にて
吊り上げて2階の所定位置に移動する。このよう
にして全ての大組スラブ・梁型枠13が2階の所
定位置に移動し終えれならば、ドーリ52もリフ
テイングフレームF′にて2階に吊り上げ移動す
る。そして第6図kに示す如くドーリ52にて大
組スラブ・梁型枠13を上昇させ、該大組スラ
ブ・梁型枠13のスラブ型枠15と梁側型枠17
との間に前述の如く油圧ジヤツキを張架し、該油
圧ジヤツキを伸長して、伸縮管18の先端に結合
支持された梁側型枠17を調製型枠16の下側に
沿つて前進させ、大組柱型枠1の型枠パネル4の
上側に位置させる。次にドーリ52にて第6図l
に示す如くテーブル14を下降し、大組スラブ・
梁型枠13全体を所定の高さにセツトして、梁側
型枠17を既にセツトした大組柱型枠1の型枠パ
ネル4及び梁底型枠40に結合する。またスラブ
型枠15の前後方向端を既に組立てた梁型枠42
を結合する。この時大組スラブ・梁型枠13の梁
側型枠17の端部に脱型用テーパ付梁側型枠51
(第6図f参照)を取付ける。次に梁側型枠17
とスラブ型枠15との間の調製型枠16内に間隔
保持型枠34を取付ける。
Next, the large slab/beam formwork 13 moved to the opening of the frame structure B is lifted together with the table 14 by the lifting frame F' and moved to a predetermined position on the second floor as shown in Fig. 6j. The dolly 52 moves to demold the next large slab/beam formwork 13, demolds the large slab/beam formwork 13 in the same manner as above, and moves to the opening of the frame structure B. This large slab/beam formwork 13 is lifted up by a lifting frame F' and moved to a predetermined position on the second floor. When all the large slab/beam forms 13 have not been moved to the predetermined positions on the second floor in this manner, the dolly 52 is also lifted and moved to the second floor by the lifting frame F'. Then, as shown in FIG. 6k, the large slab/beam formwork 13 is raised using a dolly 52, and the slab formwork 15 and beam side formwork 17 of the large slab/beam formwork 13 are raised.
As described above, a hydraulic jack is stretched between the two and the hydraulic jack is extended, and the beam side formwork 17 connected and supported at the tip of the telescopic tube 18 is advanced along the lower side of the preparation formwork 16. , located above the formwork panel 4 of the large column formwork 1. Next, at Dori 52, Figure 6
As shown in the figure, the table 14 is lowered, and the large slab
The entire beam formwork 13 is set at a predetermined height, and the beam side formwork 17 is connected to the formwork panel 4 and beam bottom formwork 40 of the large column formwork 1 that has already been set. In addition, the beam formwork 42 has already been assembled at the front and rear ends of the slab formwork 15.
combine. At this time, a tapered beam side formwork 51 for demolding is attached to the end of the beam side formwork 17 of the large slab/beam formwork 13.
(See Figure 6 f). Next, the beam side formwork 17
A spacing formwork 34 is installed within the preparation formwork 16 between the slab formwork 15 and the slab formwork 15 .

次いでスラブ型枠15の上方及び各梁型枠の内
方にスラブ鉄筋及び梁鉄筋を配筋し、1階の外面
梁側型枠パネル43(第6図f参照)を取外して
2階に運搬し、これを第6図lに示す如く既にセ
ツトした大組スラブ・梁型枠13の梁側型枠17
にタイボルト53にて結合し且つ大組柱型枠1の
建築物外面に位置する広幅の型枠パネル4に結合
支持する。そしてこの外面梁側型枠パネル43の
下端のハンガーレール37に走行可能に取付けら
れているハンガー38を大組柱型枠1の建築物外
面に位置する広幅の型枠パネル4のハンガー取付
金具10に結合する。また大組スラブ・梁型枠1
3のテーブル14の下側のドーリ52を適当な位
置に移動しておく。然る後各大組柱型枠1及び各
梁型枠の内側と各スラブ型枠15の上側に、2階
の躯体コンクリートを1回で打設し、養生する。
Next, slab reinforcing bars and beam reinforcing bars are placed above the slab formwork 15 and inside each beam formwork, and the first floor external beam side formwork panel 43 (see Figure 6 f) is removed and transported to the second floor. Then, as shown in Fig. 6l, the beam side formwork 17 of the already set large slab/beam formwork
It is connected with tie bolts 53 and is connected and supported to a wide formwork panel 4 located on the outer surface of the building of the large column formwork 1. The hanger 38 movably attached to the hanger rail 37 at the lower end of the external beam side formwork panel 43 is attached to the hanger mounting bracket 10 of the wide formwork panel 4 located on the outside of the building of the large column formwork 1. join to. Also large slab/beam formwork 1
The dolly 52 under the table 14 of No. 3 is moved to an appropriate position. Thereafter, concrete for the second floor frame is poured in one step on the inside of each large column formwork 1 and each beam formwork, and on the upper side of each slab formwork 15, and is cured.

以後前記工程を繰り返し行つて、所要階数の躯
体構造物を築造する。
Thereafter, the above steps are repeated to construct a frame structure with the required number of floors.

以上の説明で判るように本発明の大組型枠によ
る建築工法は、大組型枠を大組柱型枠と大組スラ
ブ・梁型枠とで構成し、大組柱型枠は大組スラ
ブ・梁型枠に取付けたハンガーレールに沿つて躯
体構造物の開口部まで走行移動せしめ、また大組
スラブ・梁型枠は両側端の梁側型枠を進退可能に
支持すると共に全体をテーブル上に支持してドー
リにより上下動且つ躯体構造物の開口部まで走行
移動せしめるので、これら各大組型枠はリフテイ
ングフレームにて上階の所定位置に容易に吊り上
げ移動して、組合せセツトでき、あとは大組柱型
枠の走行方向の梁底型枠、大組スラブ・梁型枠の
前後方向端の梁型枠、外面梁側型枠パネル等の小
ばらし型枠を移動し、組合せ結合するだけで、1
階分の柱、梁、スラブ等の躯体コンクリートを1
回で打設できる。従つて施工が極めて簡素化され
て、施工能率が著しく向上し、工期を大幅に短縮
でき、しかも養生期間に応じて大組柱型枠を先に
脱型移動し、その後大組スラブ・梁型枠を脱型移
動できるという優れた効果がある。
As can be seen from the above explanation, the construction method using the large assembled formwork of the present invention consists of the large assembled formwork consisting of the large assembled column formwork and the large assembled slab/beam formwork, and the large assembled column formwork is composed of the large assembled column formwork and the large assembled column formwork. The slab/beam formwork is moved along the hanger rail attached to the slab/beam formwork to the opening of the frame structure, and the large slab/beam formwork supports the beam side formwork at both ends so that it can move forward and backward, and the entire slab/beam formwork is turned into a table. These large formworks can be easily lifted and moved to a predetermined position on the upper floor using a lifting frame, and then assembled and set. Then, move and assemble the small formwork such as the beam bottom formwork in the running direction of the large column column formwork, the beam formwork at the longitudinal end of the large slab/beam formwork, and the external beam side formwork panels. Just by combining, 1
Concrete building blocks such as columns, beams, slabs, etc. for each floor are 1
Can be cast in one turn. Therefore, construction is extremely simplified, construction efficiency is significantly improved, and the construction period can be significantly shortened. Moreover, depending on the curing period, the large column column formwork is removed first, and then the large group slab/beam form is removed. It has the excellent effect of allowing the frame to be removed from the mold and moved.

また本発明の大組型枠による建築工法は、両側
端に梁側型枠を摺動自在に支持した大組スラブ・
梁型枠を用いるので、各階で築造するスラブの面
積が変化した場合、両側端の梁側型枠を適宜に進
退させることにより、また前後方向端のスラブ型
枠の長さを変えることにより、即ち前後方向端で
鋼製型枠を適宜に組合せ結合する枚数を増減する
ことにより、容易に所要面積のスラブを築造する
ことができる。
In addition, the construction method using the large assembled formwork of the present invention is based on the large assembled slab structure with the beam side formwork slidably supported at both ends.
Since beam formwork is used, if the area of the slab to be constructed on each floor changes, by moving the beam side formwork at both ends as appropriate, and by changing the length of the slab formwork at the front and rear ends. That is, by appropriately increasing or decreasing the number of steel formworks to be combined and joined at the front and rear ends, a slab of the required area can be easily constructed.

さらに本発明の大組型枠による建築工法は、大
組スラブ・梁型枠の両側端のハンガーレールに沿
つて走行する二側面を開閉可能にした大組柱型枠
を用いるので、打設した柱コンクリートがあつて
もまた大組スラブ・梁型枠を支持したテーブルが
あつても隣り合うテーブル間の狭い間隔の部分を
打設した柱コンクリートを避けて躯体構造物の開
口部までスムースに走行移動できて、脱型移動が
極めて容易である。しかも上階にリフテイングフ
レームで吊り上げて所定位置に大組柱型枠を移動
した際、予め配筋された鉄筋を囲んで据付けるこ
とができるので、極めて作業性が良く、最も手間
のかかる柱コンクリート打設の為の段取作業が著
しく簡素化される。
Furthermore, the construction method using large assembled formwork of the present invention uses large assembled column formwork that can be opened and closed on two sides that run along the hanger rails at both ends of the large slab/beam formwork. Even if there is column concrete or tables supporting large slabs or beam formwork, the column can run smoothly to the opening of the frame structure, avoiding the column concrete poured in the narrow space between adjacent tables. It can be moved and demolding is extremely easy. What's more, when the large column formwork is lifted to the upper floor using a lifting frame and moved to the specified position, it can be installed surrounding the reinforcing bars that have been arranged in advance, making it extremely easy to work with, and the most labor-intensive column. The setup work for concrete pouring is significantly simplified.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は大組柱型枠を示すもので、aは斜視
図、bは平面図、第2図は大組スラブ・梁型枠を
示す一部破断斜視図、第3図は大組柱型枠の走行
方向に於ける梁底型枠を示す仰面斜視図、第4図
は大組スラブ・梁型枠の前後方向端の梁型枠を示
す仰面斜視図、第5図は建築物外面に位置する外
面梁側型枠パネルの斜視図、第6図a乃至lは本
発面の大組型枠による建築工法の工程を示す図で
ある。 1……大組柱型枠、2……鋼製型枠、3……端
太材、4……広幅の型枠パネル、5……細幅の型
枠パネル、5a……アングル材、6……ヒンヂプ
レート、7……長孔、8……ヒンヂ用ボルト、9
……タイボルト、10……ハンガー取付金具、1
1……吊り金具、13……大組スラブ・梁型枠、
14……テーブル、14a……大引き、15……
スラブ型枠、16……調製型枠、17……梁側型
枠、18……伸縮管、22……コネクタ、30…
…手押し車、34……間隔保持型枠、37……ハ
ンガーレール、38……ハンガー、39……ロー
ラ、40……梁底型枠、41a……鋼製型枠、4
1b……L形の鋼製型枠、42……梁型枠、42
a……L形の梁側鋼製型枠、42a′……脱型用テ
ーパ付梁側鋼製型枠、42b……梁側鋼製型枠、
42c……梁底鋼製型枠、43……外面梁側型枠
パネル、45……枕、46……コーナーアング
ル、47……柱鉄筋、48……キツカー、49…
…サポート、50……コーナーアングル、51…
…脱型用テーパ付梁側型枠、52……ドーリ、B
……躯体構造物、F,F′……リフテイングフレー
ム、W……吊り索。
Figure 1 shows the large assembled column formwork, a is a perspective view, b is a plan view, Figure 2 is a partially cutaway perspective view showing the large assembled slab/beam formwork, and Figure 3 is the large assembled column formwork. Figure 4 is a top perspective view showing the beam bottom formwork in the running direction of the formwork, Figure 4 is a top perspective view showing the beam formwork at the front and rear ends of the large slab/beam formwork, and Figure 5 is the outside of the building. FIGS. 6a to 6l are perspective views of the external beam-side formwork panel located at , and are diagrams showing the steps of the construction method using the large-scale formwork of the present invention. 1... Large column formwork, 2... Steel formwork, 3... Thick timber, 4... Wide formwork panel, 5... Narrow formwork panel, 5a... Angle material, 6 ... Hinge plate, 7 ... Long hole, 8 ... Hinge bolt, 9
...Tie bolt, 10...Hanger mounting bracket, 1
1... Hanging fittings, 13... Large slab/beam formwork,
14...Table, 14a...Big draw, 15...
Slab formwork, 16... Preparation formwork, 17... Beam side formwork, 18... Expansion pipe, 22... Connector, 30...
...Handcart, 34... Spacing formwork, 37... Hanger rail, 38... Hanger, 39... Roller, 40... Beam bottom formwork, 41a... Steel formwork, 4
1b... L-shaped steel formwork, 42... Beam formwork, 42
a...L-shaped beam side steel formwork, 42a'...beam side steel formwork with taper for demolding, 42b...beam side steel formwork,
42c... Beam bottom steel formwork, 43... External beam side formwork panel, 45... Pillow, 46... Corner angle, 47... Column reinforcing bar, 48... Kitsuka, 49...
...Support, 50...Corner angle, 51...
...Tapered beam side formwork for demolding, 52...Dolly, B
...Main structure, F, F'...Lifting frame, W...Hanging cable.

Claims (1)

【特許請求の範囲】 1 テーブル上に支持したスラブ型枠の左右両端
の調整型枠の下側に梁側型枠を進退可能に支持し
た大組スラブ・梁型枠と、前記梁側型枠の下端部
外側のハンガーレールに走行可能に吊垂され走行
方向の両側面の型枠パネルを開閉可能になした大
組柱型枠と、大組柱型枠の走行方向の梁底型枠
と、大組スラブ・梁型枠の前後方向端の梁型枠
と、建築物外面梁側型枠との組合せにより1階の
躯体コンクリートを打設し養生した後、各大組柱
型枠を脱型し、走行方向の型枠パネルを開き、ハ
ンガーレール上を順次建築物の開口部に移動する
工程と、前記の移動した各大組柱型枠の一側を建
築物の外方までさらに移動し、その一側面の開か
れた型枠パネルを閉じた後リフテイングフレーム
にて大組柱型枠を吊り上げ、2階の鉄筋の配筋さ
れた所定位置に吊り降ろして、他側面の開かれた
型枠パネルを閉じてセツトする工程と、 1階の大組柱型枠間にあつた梁底型枠を脱型し
これを2階に移動し、大組柱型枠間にセツトし、
且つ大組スラブ・梁型枠の前後方向端の梁型枠を
脱型、解体し、これを2階に移動し組立セツトす
る工程と、 大組スラブ・梁型枠の両側端の梁側型枠を後退
させて脱型し、テーブルの下側にドーリを配しド
ーリによりテーブル毎大組スラブ・梁型枠全体を
下降させてスラブ型枠を脱型すると共に前後方向
端の梁下をくぐれるようにした後、ドーリを走行
させて順次建築物の開口部に移動する工程と、 建築物の開口部に移動した大組スラブ・梁型枠
を順次テーブルと一緒にリフテイングフレームに
て吊り上げ、2階の所定位置に吊り降ろし、大組
スラブ・梁型枠の両側端の梁側型枠を所定量前進
させた上、テーブルの下側にドーリを配し、該ド
ーリによりテーブルを下降してスラブ型枠を所定
の高さにセツトし、梁側型枠を既にセツトした大
組柱型枠及び梁底型枠に結合すると共にスラブ型
枠の前後方向端を前記の組立セツトした梁型枠に
結合し、さらに1階の外面梁側型枠を脱型し2階
の所定位置にセツトする工程と、 スラブ型枠の上方及び梁型枠の内方に鉄筋を配
筋した後、大組柱型枠及び梁型枠の内側とスラブ
型枠の上側に2階の躯体コンクリートを打設し養
生する工程と、 の諸工程を繰り返し行つて、所要階数の躯体構造
物を築造することを特徴とする大組型枠による建
築工法。
[Scope of Claims] 1. A large slab/beam formwork in which a beam side formwork is supported under adjustment formworks at both left and right ends of the slab formwork supported on a table so that it can move forward and backward, and the beam side formwork. A large column column formwork that is suspended from a hanger rail on the outside of the lower end and has formwork panels on both sides in the running direction that can be opened and closed, and a beam bottom formwork in the running direction of the large column column formwork. After pouring and curing concrete for the first floor frame by combining the beam formwork at the front and back ends of the large slab/beam formwork and the formwork on the external beam side of the building, each large column column formwork is removed. The process of molding, opening the formwork panel in the running direction, and moving it sequentially to the opening of the building on the hanger rail, and further moving one side of each large column formwork that has been moved above to the outside of the building. After closing the open formwork panel on one side, the large column formwork is lifted up using a lifting frame, and lowered to the specified position where the reinforcing bars are arranged on the second floor, and the open formwork panel on the other side is closed. The process involved closing and setting the formed formwork panels, removing the beam bottom formwork between the large column formworks on the first floor, moving it to the second floor, and setting it between the large column formworks.
In addition, the process of demolding and dismantling the beam formwork at the front and rear ends of the large slab/beam formwork, moving it to the second floor and assembling it, and the process of removing the beam side molds at both ends of the large slab/beam formwork. The frame is moved back and demolded, a dolly is placed under the table, and the entire slab/beam formwork for each table is lowered by the dolly, the slab formwork is demolded, and it can pass under the beam at the end in the front and back direction. After that, the process of moving the dolly to the opening of the building one by one, and lifting the large slab and beam formwork moved to the opening of the building one by one with the lifting frame together with the table, It was lowered to a predetermined position on the second floor, the beam side formwork at both ends of the large slab/beam formwork was advanced by a predetermined amount, and a dolly was placed below the table, and the table was lowered by the dolly. The slab formwork is set at a predetermined height, the beam side formwork is connected to the already set large column formwork and the beam bottom formwork, and the longitudinal ends of the slab formwork are attached to the assembled beam formwork. After that, the first floor external beam side formwork was demolished and set in the specified position on the second floor, and after reinforcing bars were placed above the slab formwork and inside the beam formwork, large-scale assembly was carried out. The process of pouring and curing the second-story frame concrete inside the column formwork and beam formwork and above the slab formwork, and repeating the following steps to construct a frame structure with the required number of floors. A construction method using large formwork.
JP17570283A 1983-09-22 1983-09-22 Building method by large mold frame Granted JPS6065843A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17570283A JPS6065843A (en) 1983-09-22 1983-09-22 Building method by large mold frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17570283A JPS6065843A (en) 1983-09-22 1983-09-22 Building method by large mold frame

Publications (2)

Publication Number Publication Date
JPS6065843A JPS6065843A (en) 1985-04-15
JPH0256450B2 true JPH0256450B2 (en) 1990-11-30

Family

ID=16000747

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17570283A Granted JPS6065843A (en) 1983-09-22 1983-09-22 Building method by large mold frame

Country Status (1)

Country Link
JP (1) JPS6065843A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61246470A (en) * 1985-04-22 1986-11-01 鹿島建設株式会社 Building method
JPS6424253U (en) * 1987-07-28 1989-02-09
MY167504A (en) * 2007-02-16 2018-09-04 Hang Seng Tang A formwork system

Also Published As

Publication number Publication date
JPS6065843A (en) 1985-04-15

Similar Documents

Publication Publication Date Title
EP0123264A2 (en) Building system and components thereof
CN102383590B (en) Split building template combined system
US3274306A (en) Method for casting concrete structures
US4272050A (en) Method and apparatus for pre-casting steel reinforced concrete box-like modules
JPH0256450B2 (en)
CN106285721A (en) A kind of railway culvert method of construction based on sliding mode system
CN222525639U (en) Assembled composite floor slab
CN104797762A (en) Building and construction method thereof
JPH0143086B2 (en)
CN218092007U (en) An underground waterproof shear wall post-pouring reinforcement structure with formwork
KR100361047B1 (en) Construction mold
WO2020134239A1 (en) Side mold fixing method for production of prefabricated component
CN117721777A (en) Assembled composite floor slab and construction method thereof
JP2620687B2 (en) Construction method of culvert by movable formwork
US3451108A (en) Movable concrete form with a pair of endless flexible mats
US2713190A (en) Building construction form
JP2992882B2 (en) Beam formwork device
JPH03103569A (en) Formwork device for column construction
CN113089897A (en) Construction method for integrally hoisting disassembly-free cement formwork
JPS6358993B2 (en)
CN211007661U (en) Beam and slab post-cast with formwork support system
JPS6358992B2 (en)
JPH04309664A (en) Channel constructing mold
NL8201173A (en) Building construction method - using movable formworks removed for pouring next unit after pouring and hardening
JP2005048416A (en) Steel panels for beams and walls, and beam and wall construction methods using the same