JPH0266024A - Bucket conveyance system - Google Patents

Bucket conveyance system

Info

Publication number
JPH0266024A
JPH0266024A JP21758988A JP21758988A JPH0266024A JP H0266024 A JPH0266024 A JP H0266024A JP 21758988 A JP21758988 A JP 21758988A JP 21758988 A JP21758988 A JP 21758988A JP H0266024 A JPH0266024 A JP H0266024A
Authority
JP
Japan
Prior art keywords
bucket
floor
air
vertical pipe
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21758988A
Other languages
Japanese (ja)
Other versions
JP2645865B2 (en
Inventor
Ippei Watanabe
一平 渡辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shinmaywa Industries Ltd
Original Assignee
Shin Meiva Industry Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shin Meiva Industry Ltd filed Critical Shin Meiva Industry Ltd
Priority to JP21758988A priority Critical patent/JP2645865B2/en
Publication of JPH0266024A publication Critical patent/JPH0266024A/en
Application granted granted Critical
Publication of JP2645865B2 publication Critical patent/JP2645865B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Refuse Collection And Transfer (AREA)

Abstract

PURPOSE:To improve the operation efficiency by reciprocatively carrying floor dust collectors between each floor and a dust collection floor via a bucket which is carried by the air flow in a vertical pipe installed throughout the floors. CONSTITUTION:A vertical pipes 10 is installed from the first to the top dust collection floor and a bucket C is carried in the pipe. The bucket C is lifted up and down under the control of the quantity of air supplied by an air supply means 20. When a dust collector 13 in which dust has been collected is detected on the specified floor, the bucket C is carried thereto and mounted on an arbitrarily exposing and retracting support device 14 and after a gate 12 is opened, the dust collector 13 is put in the bucket C. The gate 12 is closed and the support device 14 is retracted so that the bucket C is lowered against the air flow to the first dust collection floor where dust is collected. The collector 13 which collects dust on each floor is reciprocatively carried between each floor via the bucket C, whereby improving the operation efficiency.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明はバケット搬送システムに関するものである。[Detailed description of the invention] (Industrial application field) TECHNICAL FIELD The present invention relates to a bucket transport system.

(従来の技術) 従来、ホテル、事務所ビルなどの高層建築物において発
生する塵芥は、作業者によって収集コレクタに回収され
、その収集コレクタを収集階までエレベータを用いて輸
送し、適宜塵芥貯留搬出手段に排出するものである。
(Prior Art) Conventionally, the garbage generated in high-rise buildings such as hotels and office buildings is collected by workers into a collection collector, and the collector is transported to the collection floor using an elevator, and the garbage is stored and carried out as appropriate. It is something that is discharged into a means.

また、高層住宅における塵芥の収集方式として、建物の
最下階から各階に亘って配設されたシュートに塵芥を収
容したカプセルを建物の各階から投下して最下階まで搬
送するカプセル搬送方式(特公昭60−286号公報参
照)が提案されている。
In addition, as a garbage collection method in high-rise residential buildings, a capsule transport method (capsule transport method) is used in which capsules containing garbage are dropped from each floor of the building into chutes arranged from the bottom floor of the building to the bottom floor. (See Japanese Patent Publication No. 60-286) has been proposed.

(発明が解決しようとする課題) しかしながら、上記従来の収集方式には次のような問題
があった。
(Problems to be Solved by the Invention) However, the above conventional collection method has the following problems.

事務所ピルなどにおける収集コレクタによる収集は、エ
レベータを一時的に専用することになることから、人や
貨物の輸送に支障を来すと同時に、腐敗臭の残留によっ
て不快感を与えるなどの問題がある。
Collection by collectors at office buildings, etc. requires the temporary use of elevators, which poses problems such as hindering the transportation of people and cargo and causing discomfort due to residual putrid odors. be.

また、カプセル搬送方式においては ■ シュートを落下するカプセルの落下速度を該カプセ
ルの巾mに応じて制御する機能がないため、カプセル内
に収容された塵芥の重;iによりシュート内を落下する
カプセルの落ド速度が異なり、このため、高層建物にお
いては、カプセルが軽いと落下に時間がかかり過ぎて実
用上問題があるとともに、逆に重いと落下速度が速くな
り着地時にカプセルに作用する衝撃力が増大してカプセ
ルが損傷する恐れがある。
In addition, in the capsule conveyance method, ■ Since there is no function to control the falling speed of the capsule falling down the chute according to the width m of the capsule, the weight of the garbage contained in the capsule; For this reason, in high-rise buildings, if the capsule is light, it will take too long to fall, which poses a practical problem.On the other hand, if it is heavy, the falling speed will be faster, and the impact force that will act on the capsule when it lands will be a problem. may increase and damage the capsule.

■ −反落下させたカプセルを再利用するためにはいち
いちエレベータ等の他の手段により元の場所に回収しな
ければならず回収作業に手間がかかる。
- In order to reuse dropped capsules, they must be recovered to their original locations by other means such as an elevator, which takes time and effort.

本発明は上記の点に鑑みてなされたもので、特に事務所
ビルなどの高層建築物から発生する塵芥の収集に好適な
バケット搬送システムを提供するものである。
The present invention has been made in view of the above-mentioned points, and provides a bucket conveyance system particularly suitable for collecting garbage generated from high-rise buildings such as office buildings.

(課題を解決するための手段) 本発明は、建物の所要階に亘って配設されるとともに、
開閉可能な搬出入口が適宜形成され、内部をバケットが
搬送可能な縦管と、前記搬出入口に設けられ、該搬出入
口に臨む縦管内でバケットを支持可能なバケット支持装
置と、前記縦管外より吸引された空気を塵芥収集階のバ
ケット支持装置の下方の縦管内に供給するとともに、そ
の空気量を調整可能な空気供給手段と、前記収集階のバ
ケット支持装置の上方近傍の縦管内より空気を排気し、
その排気量が調整可能な排気量制御手段と、前記収集階
を除くその上方階の搬出入口にそれぞれ設けられ、1r
j記空気供給手段により縦管内に口(給される空気を排
気する排気1lIl+御手段と、前記バケットの重量を
直接的にもしくは間接的に計測するlff1測定手段と
を備え、前記バケットは搬出入1]に対応して一側壁が
開口されて収集コレクタを収容可能に構成してなり、前
記収集コレクタを収容したバケットの’rI mを重量
測定手段を介して計測し、その測定結果に基づいて排気
lrt制御手段により排気量を1tII制御することで
バケットを予め設定された速度で降下させ、収集階のバ
ケット支持装置上に着地したバケットより収集コレクタ
を引き出して適宜塵芥を排出した後、収集コレクタをバ
ケットに収容して空気供給手段によりバケットを−L、
昇させ、排気制御手段で所定階に停+hさせて支持装置
」二に支持し、収集コレクタを回収するように構成した
ものである。
(Means for Solving the Problems) The present invention is arranged over required floors of a building, and
a vertical pipe in which an openable and closable loading/unloading port is appropriately formed and a bucket can be transported therein; a bucket support device provided at the loading/unloading port and capable of supporting the bucket within the vertical tube facing the loading/unloading port; and a bucket support device provided outside the vertical tube. An air supply means capable of supplying the sucked air into the vertical pipe below the bucket support device on the garbage collection floor and adjusting the amount of air; exhaust,
An exhaust volume control means whose exhaust volume can be adjusted, and a 1r.
The vertical pipe is provided with an exhaust control means for exhausting the air supplied by the air supply means, and an lff1 measurement means for directly or indirectly measuring the weight of the bucket, and the bucket is loaded and unloaded. 1], one side wall is opened to accommodate the collection collector, the 'rI m of the bucket containing the collection collector is measured via a weight measuring means, and based on the measurement result, The bucket is lowered at a preset speed by controlling the exhaust volume by 1tII by the exhaust lrt control means, the collection collector is pulled out from the bucket that has landed on the bucket support device on the collection floor, and the garbage is discharged as appropriate. is stored in the bucket and the bucket is moved to -L by the air supply means.
The collector is raised, stopped at a predetermined floor using exhaust control means, supported by a support device, and collected.

(作用) 各階で塵芥を回収してきた収集コレクタが搬出入口を介
して縦管内で支持されているバケット内に供給されると
、そのバケットは縦管内を降下することによって収集階
に搬送される。
(Operation) When the collection collector that has collected garbage on each floor is supplied through the carry-in/out port into a bucket supported within the vertical pipe, the bucket is conveyed to the collection floor by descending within the vertical pipe.

バケットが降下すると、バケット重量に基づいて排気量
制御手段で縦管内から排気する空気量を制御し、この結
果、バケットを予め設定された速度で降下させる。
When the bucket descends, the amount of air exhausted from the vertical pipe is controlled by the exhaust amount control means based on the weight of the bucket, and as a result, the bucket is lowered at a preset speed.

バケットが収集階の支持装置上に着地すると、その搬出
入口を経て収集コレクタを引き出し、塵芥貯留搬出手段
に収集コレクタ内の塵芥を排出した後、再び収集階の支
持装置上に支持されているバケット内に収集コレクタを
供給する。
When the bucket lands on the support device on the collection floor, the collection collector is pulled out through the loading/unloading entrance, and after the garbage in the collector is discharged to the garbage storage/export means, the bucket is again supported on the support device on the collection floor. Supply the collection collector within.

空の収集コレクタを収容したバケットは空気供給手段に
よって縦管内に供給される空気を介して設定速度で上昇
される。そして、バケットは排気制御手段によって所定
階のバケット支持装置上に支持され、搬出入口を介して
収集コレクタが引き出される。
The bucket containing the empty collection collector is raised at a set speed via air supplied into the vertical tube by the air supply means. The bucket is then supported by the exhaust control means on a bucket support device on a predetermined floor, and the collection collector is pulled out through the loading/unloading entrance.

(実施例) 以下、本発明の一実施例を図面を参照して説明する。(Example) Hereinafter, one embodiment of the present invention will be described with reference to the drawings.

図は本発明に係るバケット搬送システムの概略構成を示
している。
The figure shows a schematic configuration of a bucket transport system according to the present invention.

図において、10は建物の所要階に亘って配設された縦
管であり、本例では塵芥収集階になされた地」二階から
例えば最上階に亘って配設されたものを例示している。
In the figure, 10 is a vertical pipe arranged over the required floors of the building, and in this example, the pipe is arranged from the second floor to the top floor, for example, on the garbage collection floor. .

この縦管10は、横断面形状が例えば矩形に形成される
とともに、全長にわたって一定の大きさで延設されてお
り、この縦管10内を通ってバケットCが搬送される。
The vertical tube 10 has a rectangular cross-sectional shape, for example, and extends with a constant size over its entire length, and the bucket C is conveyed through the vertical tube 10.

バケットCは後述するように収集コレクタ13を収容す
る容器であり、その横断面形状は前記縦管lOの横断面
形状と略同様矩形に形成されている他、収集コレクタ1
3の出入口となるようにその側壁は開口されるとともに
、収集コレクタ13を動かないように保持する図示しな
い係合装置を備えている。このバケットCは、縦管lO
内を極めて容易に落下できるとともに、後述する空気供
給手段により縦管10内を容易に上昇できるように、縦
管lOに対する横断面形状及び大きさが設定されている
。すなわち、後述する空気供給手段により縦管10内に
供給する空気でバケットCを上昇させるには、縦管10
とバケットCとの間隙を空気が通過する時に発生ずる圧
力とバケットCの受圧面積及び重量を適切に設定する必
要がある。
The bucket C is a container that accommodates the collection collector 13, as will be described later, and its cross-sectional shape is rectangular, approximately the same as the cross-sectional shape of the vertical pipe 1O.
Its side wall is opened to serve as an entrance and exit for the collection collector 13, and is provided with an engagement device (not shown) for holding the collection collector 13 stationary. This bucket C is a vertical pipe lO
The cross-sectional shape and size of the vertical tube 10 are set so that the vertical tube 10 can be easily dropped into the vertical tube 10 and can be easily raised inside the vertical tube 10 by means of an air supply means to be described later. That is, in order to raise the bucket C with air supplied into the vertical pipe 10 by the air supply means described later, the vertical pipe 10
It is necessary to appropriately set the pressure generated when air passes through the gap between the bucket C and the bucket C, as well as the pressure-receiving area and weight of the bucket C.

また、縦管10の各階及び最下階には搬出人口11が形
成されている。搬出人口11は必ずしも各階に設ける必
要はなく、塵芥収集が必要な適宜階に設ければよい。こ
れら搬出入口11にはそれぞれゲート12がゲートシリ
ンダ12aにより開閉自在に設けられており、各ゲート
12を閉鎖することで縦管lO内が密閉状態になるよう
に構成されている。
Furthermore, an outgoing port 11 is formed on each floor and the lowest floor of the vertical pipe 10. The carry-out port 11 does not necessarily need to be provided on each floor, but may be provided on an appropriate floor where garbage collection is required. A gate 12 is provided in each of these carry-in/out entrances 11 so as to be openable and closable by a gate cylinder 12a, and by closing each gate 12, the inside of the vertical pipe 10 is sealed.

以下説明の便宜上、最下階を除く各階に設けられた搬出
人口IIを投入口11aと称し、最下階に設けられた搬
出入口11を排出口11bと称する。
For convenience of explanation, the carry-out port II provided on each floor except the bottom floor will be referred to as an input port 11a, and the carry-out port 11 provided on the bottom floor will be called a discharge port 11b.

なお、本実施例では、収集コレクタ13は作業者にて直
接バケットC内に供給されるものを示している・が、収
集コレクタ13を投入口11aを介してバケットCとの
間で搬送する図示しないコレクタ搬出入装置を設けるこ
ともでき、また、排出口11b側にも排出口11b近傍
に設置された塵芥貯留排出手段とバケットCとの間で収
集コレクタ13を搬送するコレクタ搬出入装置を設ける
こともできる。このようなコレクタ搬出入装置を設けた
場合、収集コレクタ!3を所定の場所に配置すれば回収
された塵芥を自動的に排出させることが可能となる。
In this embodiment, the collection collector 13 is directly supplied into the bucket C by an operator. Alternatively, a collector carrying-in/out device may be provided on the discharge port 11b side to transport the collection collector 13 between the garbage storage/discharge means installed near the discharge port 11b and the bucket C. You can also do that. If such a collector loading/unloading device is installed, the collector! 3 at a predetermined location, it becomes possible to automatically discharge the collected garbage.

一方、縦管10の下端部には縦管!0内の排出口11b
に臨む位置でバケットCを支持する第1パケツト支持装
置15が設けられている。この第1パケツト支持装置1
5は、例えば複数のローラ15aから構成されており、
縦管10内を降下するバケットCが着地する着地部にな
されている。
On the other hand, there is a vertical tube at the lower end of the vertical tube 10! Outlet 11b inside 0
A first packet support device 15 is provided to support the bucket C at a position facing the bucket. This first packet support device 1
5 is composed of, for example, a plurality of rollers 15a,
A landing section is provided on which a bucket C descending within the vertical pipe 10 lands.

また、縦管10内の各階部には第2パケツト支持装置1
4が設けられている。第2パケツト支持装置14は各投
入口11a・・・に臨むよう縦管10内でバケットを支
持する位置とバケットの降下を許容する位置とを作動す
るように構成されており、バケット支持位置においてバ
ケットCの底部を支持し、バケットCを縦管lO内の各
階部で安定的に保持する。
In addition, a second packet support device 1 is installed at each floor within the vertical pipe 10.
4 is provided. The second packet support device 14 is configured to operate between a position where it supports the bucket in the vertical pipe 10 and a position where it allows the bucket to be lowered so as to face each input port 11a. The bottom of the bucket C is supported and the bucket C is stably held at each floor within the vertical pipe IO.

さらに、縦管IOの各階部には、排気口16が設けられ
ており、排気口16には排気バルブ18を有する配管1
7が連通されており、これにより後述する空気供給手段
20により縦管10内に供給される空気を排気する排気
制御手段19が構成されている。この排気制御手段19
は、バケットCと排気口+6で形成される実排気口にお
ける排気抵抗に応じてバケットが受ける上昇力とバケッ
トCの重量が平衡状態になり、バケットCは縦管lO内
で停止状態(浮遊)になるという原理な利用してバケッ
トCを所望の目標階で停止トさせるように構成されてい
る。
Further, each floor of the vertical pipe IO is provided with an exhaust port 16, and the exhaust port 16 has a pipe 1 having an exhaust valve 18.
7 are in communication with each other, thereby forming an exhaust control means 19 for exhausting air supplied into the vertical pipe 10 by an air supply means 20, which will be described later. This exhaust control means 19
In this case, the lifting force applied to the bucket according to the exhaust resistance at the actual exhaust port formed by the bucket C and the exhaust port +6 and the weight of the bucket C are in equilibrium, and the bucket C is stopped (floating) in the vertical pipe IO. The bucket C is configured to stop at a desired target floor by utilizing the principle that

縦管10の各階部には例えば光電センサ70等の位置検
出器が設けられており、この位置検出器によりバケット
Cが縦管lO内における投入口11aに臨む位置にある
ことを感知する。
A position detector such as a photoelectric sensor 70 is provided at each floor of the vertical pipe 10, and this position detector detects that the bucket C is at a position facing the input port 11a in the vertical pipe 10.

縦管lOの前記第1パケツト支持装置15よりも下方に
は空気吹出口21が設けられている。空気吹出口21は
バルブ25を有する配管23によってブロワ−22の空
気吐出口22aに連通されており、一方その空気取入口
22bにはバルブ27を有する配管26の一端が接続さ
れている。
An air outlet 21 is provided below the first packet support device 15 of the vertical pipe IO. The air outlet 21 is connected to an air outlet 22a of the blower 22 by a pipe 23 having a valve 25, and one end of a pipe 26 having a valve 27 is connected to the air intake port 22b.

この配管26の他端26aは空気を縦管lO外から吸入
する吸入口になされている。さらに、縦管10の下部に
おける前記第1パケツト支持装置15よりも上方には空
気取入口32が設けられており、この空気取入口32は
前記配管26におけるバルブ27よりもブロワ−22側
から分岐された配管36にバルブ37を介して接続され
ている。また、配管23におけるバルブ25とブロワ−
22との間にはバルブ29を有する配管28の一端が接
続されており、この配管28の他端28aがブロワ−2
2から供給される空気を縦管10外に排出する排出口に
なされている。このように5これら空気吹出口21.空
気取入口32、ブロワ−22、各配管23.26.28
.36及び各バルブ25.27.29.37によって空
気供給手段20が構成されており、各バルブを開閉制御
することで空気を配管26の他端26aもしくは空気取
入口32から選択的に吸引し、配管28の他端28aも
しくは空気吹出[」21に選択的に供給できるようにな
されている。
The other end 26a of this pipe 26 is made into an inlet for sucking air from outside the vertical pipe 1O. Furthermore, an air intake port 32 is provided above the first packet support device 15 in the lower part of the vertical pipe 10, and this air intake port 32 is branched from the blower 22 side of the pipe 26 beyond the valve 27. The valve 37 is connected to the pipe 36 which is connected to the pipe 36 via a valve 37. In addition, the valve 25 in the pipe 23 and the blower
One end of a pipe 28 having a valve 29 is connected to the blower 22, and the other end 28a of the pipe 28 is connected to the blower 22.
The vertical pipe 10 is provided with an exhaust port for discharging the air supplied from the vertical pipe 10 to the outside of the vertical pipe 10. In this way, there are 5 air outlets 21. Air intake port 32, blower 22, each piping 23.26.28
.. 36 and each valve 25, 27, 29, 37 constitute the air supply means 20, and by controlling the opening and closing of each valve, air is selectively sucked from the other end 26a of the piping 26 or the air intake port 32, The air can be selectively supplied to the other end 28a of the piping 28 or to the air outlet 21.

この空気供給手段20は、■バルブ29.37を開にし
て縦管lO内の空気を空気取入口32から吸い込み、配
管36、配管26、ブロワ−22、配管23、配管28
を経て外部に排出することで縦管10内を換気する換気
状態、■バルブ37.25を開にして縦管10内の空気
を空気取入口32から吸い込み、配管36、配管26、
ブロワ−22、配管23を経て空気吹出口21から縦管
10内に供給し、再び空気取入口32から吸い込むこと
で循環させ、縦管10内の空気吹出口21と空気取入口
32との間に上昇気流を発生させる着地速度制御状態、
■バルブ27.29を開にして空気を配管26の他端2
6aから吸い込み、ブロワ−22、配管23、配管28
を経て配管28の他端28aから排出するいわゆるニュ
ートラル状態、■バルブ25.27を開にして空気を配
管26の他端26aから配管26、ブロワ−22、配管
23、空気吹出口21に送り、該空気吹出口21から縦
管10内に供給し、縦管10内でバケットCを上昇させ
るバケット上昇搬送状態の4つの状態を選択的に取るこ
とができる。
This air supply means 20 opens the valve 29.37 and sucks the air in the vertical pipe 10 from the air intake port 32, pipe 36, pipe 26, blower 22, pipe 23, pipe 28.
Ventilation state in which the inside of the vertical pipe 10 is ventilated by exhausting it to the outside through
The air is supplied into the vertical pipe 10 from the air outlet 21 via the blower 22 and piping 23, and is sucked in again from the air intake 32 to circulate the air between the air outlet 21 and the air intake 32 in the vertical tube 10. A landing speed control state that generates an updraft,
■Open the valve 27.29 and supply air to the other end 2 of the pipe 26.
Suction from 6a, blower 22, piping 23, piping 28
A so-called neutral state in which air is discharged from the other end 28a of the piping 28 through the valve 25.27 is opened and air is sent from the other end 26a of the piping 26 to the piping 26, the blower 22, the piping 23, and the air outlet 21; It is possible to selectively take four states including a bucket raising transport state in which air is supplied from the air outlet 21 into the vertical pipe 10 and the bucket C is raised within the vertical pipe 10.

また、前記配管36におけるバルブ37よりも空気取入
口32寄りには、バルブ39を有する配管38の一端が
接続されており、空気成人1コ32、配管36、配管3
8、バルブ39により排気量制御手段40が構成されて
いる。この排気量制御手段40は、バケット降下時にこ
のバケットCにより縦管10内で圧縮される空気の排気
量を制御し、バケットCの降下速度を制御するものであ
る。なお、この排気量制御手段40は上述のように空気
取入口32と配管36の一部を併用しているが、これに
限らず別個に設けてもよい。
Further, one end of a pipe 38 having a valve 39 is connected to the pipe 36 closer to the air intake port 32 than the valve 37, and the air intake 32, the pipe 36, the pipe 3
8. The valve 39 constitutes a displacement control means 40. This displacement control means 40 controls the displacement amount of the air compressed in the vertical pipe 10 by the bucket C when the bucket is lowered, and controls the lowering speed of the bucket C. In addition, although this exhaust amount control means 40 uses the air intake port 32 and a part of the piping 36 together as described above, it is not limited thereto and may be provided separately.

上記各バルブ25.27.29.37.39はコンピュ
ータ等の制御装置によって開閉制御されることで前述の
空気供給手段20による空気の供給経路と供給量及び排
気量制御手段40を使い分けることができる。各バルブ
のうちバルブ25及びバルブ39は制御装置により流量
が調整可能な可変流量制御弁が用いられており、これら
バルブ25.39のシール性を高め、縦管lO内の気密
性を確保するためには可変流量制御弁とシール性の高い
開閉弁とを併用するのが好ましい。
Each of the above-mentioned valves 25, 27, 29, 37, 39 is controlled to open and close by a control device such as a computer, so that the air supply path and the supply amount and exhaust amount control means 40 by the air supply means 20 described above can be used properly. . Among the valves, valve 25 and valve 39 are variable flow control valves whose flow rate can be adjusted by a control device, and in order to improve the sealing performance of these valves 25 and 39 and ensure airtightness in the vertical pipe IO. It is preferable to use a variable flow rate control valve and an on-off valve with high sealing performance in combination.

さらに、縦管lOの下端部には重量測定手段としての圧
力測定器Pが設けられている。この圧力測定器Pは、縦
管lO内でバケットCが投下された所定時間後に密閉さ
れた状態でのバケットCにより圧縮される縦管10内の
圧力を検出するもので、この圧力測定器Pによって測定
された圧力は前記制御装置に出力される。
Further, a pressure measuring device P as a weight measuring means is provided at the lower end of the vertical pipe IO. This pressure measuring device P detects the pressure inside the vertical pipe 10 compressed by the bucket C in a sealed state after a predetermined time after the bucket C is dropped into the vertical pipe IO. The pressure measured by is output to the control device.

建物の最下階の排出口11b近傍に設けられた塵芥貯留
搬出手段は、反転投入装置50と塵芥貯留排出装置60
とを備えている1反転投入装置50は各階から搬送され
てきた収集コレクタ13を反転させ、その収集コレクタ
13内に収容されている塵芥を塵芥貯留排出装置60に
投入するものである。また、塵芥貯留排出装置60は、
反転投入装置50によって投入された塵芥を貯留した後
、この塵芥を排出口から排出して塵芥収集車80に積み
替えるように構成されたものである。
The garbage storage/unloading means provided near the discharge port 11b on the lowest floor of the building includes a reversing/feeding device 50 and a garbage storage/discharge device 60.
The 1-inversion loading device 50, which is equipped with the following, inverts the collection collector 13 conveyed from each floor and inputs the garbage contained in the collection collector 13 into the garbage storage and discharge device 60. Further, the garbage storage and discharge device 60 is
After storing the garbage input by the reversing input device 50, the garbage is discharged from the discharge port and transferred to the garbage collection vehicle 80.

次に、以上にように構成されたバケットCの搬送システ
ムの動作について説明する。
Next, the operation of the bucket C transport system configured as described above will be explained.

ここで、ブロワ−22は駆動を開始してから平常運転に
達するまでの立ち上がりに時間がかかるため通常は常時
駆動させており、縦管10内fパケツトCを搬送しない
時は、バルブ29.37のみを開にして縦管lO内の空
気を空気取入口32から吸い込み、配管36.配管26
、ブロワ−22、配管23、配管28を経て外部に排出
することで縦管lO内を換気しており、また、バケット
Cが縦管lO内を降下している時は、バルブ37.25
を開にして縦管IO内の空気を空気取入口32から吸い
込み、配管36、配管26、ブロワ−22、配管23を
経て空気吹出口21から縦管IO内に排出し、再び空気
取入口32から吸い込むことで循環させ、縦管lO内の
空気吹田口21と空気取入口32との間に上昇気流を発
生させるようになされている。
Here, since the blower 22 takes time to start up from the start of operation until it reaches normal operation, it is normally operated all the time. The air in the vertical pipe 1O is sucked in from the air intake port 32 by opening the pipe 36. Piping 26
, the inside of the vertical pipe 10 is ventilated by discharging it to the outside through the blower 22, piping 23, and piping 28, and when the bucket C is descending inside the vertical pipe 10, the valve 37.25
When the air is opened, air in the vertical pipe IO is sucked in from the air intake port 32, passed through the pipe 36, pipe 26, blower 22, and pipe 23, and discharged from the air outlet 21 into the vertical pipe IO. The air is circulated by being sucked in from the vertical pipe 10, and an upward air current is generated between the air suita port 21 and the air intake port 32 in the vertical pipe IO.

先ず、バケットCを各階から最下階に降下させる場合に
ついて説明する。
First, a case will be described in which the bucket C is lowered from each floor to the lowest floor.

所望階の第2バケット支持装置14−LにバケットCは
支持されており、この階のゲート12を開いて投入口1
1aを開放し、収集コレクタ13をバケットC内に搬入
する。この後、ゲート12を閉じて縦管10内を気密状
態にし、前記第2パケツト支持装置14を降下許容位置
に作動させて縦管10内から没すると、バケットCは縦
管lO内を降下し始める。この時、空気供給手段20は
、上述の換気状態から制御装置によりバルブ27.29
のみを開にして空気を配管26の他端26aから吸い込
み、ブロワ−22,配管23、配管28を経て配管28
の他端28aから排出する、いわゆるニュートラル状態
になされている。
The bucket C is supported by the second bucket support device 14-L on the desired floor, and the gate 12 on this floor is opened to access the input port 1.
1a is opened and the collection collector 13 is carried into the bucket C. After that, the gate 12 is closed to make the inside of the vertical pipe 10 airtight, and the second packet support device 14 is operated to the lowering permission position to sink from inside the vertical pipe 10, so that the bucket C descends inside the vertical pipe IO. start. At this time, the air supply means 20 is operated by the valves 27 and 29 from the above-mentioned ventilation state by the control device.
The air is sucked in from the other end 26a of the piping 26 by opening only the piping 26, and passes through the blower 22, piping 23, and piping 28 to the piping 28.
It is in a so-called neutral state where it is discharged from the other end 28a.

そして、縦管lO内を降下するバケットCは、該バケッ
トCにより圧縮される縦管10内の空気をバケットCと
縦管lOとの間隙から徐々に逃すことで徐々に降下する
Then, the bucket C descending inside the vertical pipe 1O gradually descends by letting the air in the vertical pipe 10 compressed by the bucket C gradually escape from the gap between the bucket C and the vertical pipe 1O.

ここで、バケットCの定常落下速度Vcは、m :バケ
ット質量 ρ :空気比重量 Cd:空気抵抗係数 SP:縦管段面積 Sc:バケット受圧面積 で表すことができ、この時、バケットCにより圧縮され
る縦管10内の空気の圧力Pslは、Sc で求めることができる。よって、圧力測定器Pで縦管1
0内の圧力P31を検出することで(2)式からmgを
求めることができ、このmgを(+)式に代入すること
によって定常落下速度■。を求めることができる。
Here, the steady-state falling velocity Vc of the bucket C can be expressed as: m: bucket mass ρ: air specific weight Cd: air resistance coefficient SP: vertical pipe stage area Sc: bucket pressure receiving area; The pressure Psl of the air inside the vertical pipe 10 can be determined by Sc. Therefore, with pressure measuring device P, vertical pipe 1
By detecting the pressure P31 within 0, mg can be obtained from equation (2), and by substituting this mg into equation (+), the steady falling velocity ■. can be found.

したがって、バケットCの降下時において、圧力測定器
PではバケットCが降下し始めてから所定時間後にこの
縦管10内の圧力を測定し、制御装置では圧力測定器P
で測定された圧力P、1に基いてバケットCの定常落下
速度Vcを−L式(1)。
Therefore, when the bucket C is lowered, the pressure measuring device P measures the pressure inside the vertical pipe 10 a predetermined time after the bucket C starts to descend, and the control device measures the pressure inside the vertical pipe 10.
Based on the pressure P, 1 measured at -L, the steady-state falling velocity Vc of the bucket C is expressed by equation (1).

(2)から演算する。この結果、制御装置ではバルブ3
9を開放制御して排気量制御手段40を作動させ、測定
速度が設定速度に近似するようバルブ39を開閉制御し
て排気量を制御するとともに、バルブ37.25を開に
して空気供給手段20をニュートラル状態から着地速度
制御状態にする。
Calculate from (2). As a result, the control device
9 is opened to operate the displacement control means 40, the valve 39 is opened and closed to control the displacement so that the measured speed approximates the set speed, and the valve 37.25 is opened to operate the air supply means 20. from the neutral state to the landing speed control state.

つまり、バケットCの降下時において、制御袋[nでは
バルブ39を開閉制御して排気m制御手段40を作動さ
せ、縦管10内の空気を空気取入口32から配管36、
配管38を介して外部に排出し、その空気の排気量を制
御することでバケットCの降下速度を設定速度に近似す
るように制御する。詳しくは、測定された圧力より導ひ
かれた降下速度が設定速度との間に差が生じている場合
には、バケット降下速度を設定速度に接近するようバル
ブ39の開度を調整し、排気量を制御する。
That is, when the bucket C is lowered, the control bag [n controls the opening and closing of the valve 39 to operate the exhaust m control means 40, and the air in the vertical pipe 10 is transferred from the air intake port 32 to the pipe 36,
The air is discharged to the outside through the pipe 38, and by controlling the amount of air discharged, the descending speed of the bucket C is controlled to approximate the set speed. Specifically, if there is a difference between the bucket descent speed derived from the measured pressure and the set speed, the opening degree of the valve 39 is adjusted so that the bucket descent speed approaches the set speed, and the displacement is adjusted. control.

このようなバケットCの降下速度の制御は、投入・階か
ら空気取入口32を通過する(着地手前)まで行われる
Such control of the descending speed of the bucket C is performed from the input floor until it passes through the air intake port 32 (just before landing).

また、この時、空気供給手段20は着地速度制御状態に
なされているので、これによって、空気取入口32から
吸い込まれた空気は、前記排気量制御手段40により配
管38の他端38aから排出されるとともに、配管36
、配管26、ブロワ−22、配管23を経て空気吹出口
21から供給されて111び空気取入口32から吸い込
まれて循環し、縦管10内の空気吹田口21と空気取入
口32との間で上昇気流を発生させている。そして、バ
ケットCが空気取入口32を通過した後、つまり、この
通過後から着地するまでの着地区域において、バケット
Cは、空気吹出口21と空気取入口32との間に発生し
た上昇気流により降下速度がさらに遅くなるよう制御さ
れて第1パケツト支持装置15にゆっくりと着地する。
Also, at this time, the air supply means 20 is in the landing speed control state, so that the air sucked in from the air intake port 32 is discharged from the other end 38a of the pipe 38 by the displacement control means 40. At the same time, the piping 36
, the air is supplied from the air outlet 21 via the piping 26, the blower 22, and the piping 23, is sucked in from the air intake 111 and the air intake 32, and circulates between the air outlet 21 and the air intake 32 in the vertical pipe 10. This creates an updraft. After the bucket C passes through the air intake port 32, that is, in the landing area from after this passing until it lands, the bucket C is moved by the updraft generated between the air outlet 21 and the air intake port 32. The descending speed is controlled to further slow down, and the packet slowly lands on the first packet support device 15.

この場合における空気吹田口21からの吐出量はバルブ
25により調整され、この吐出量は降下速度を遅くする
ための上昇気流を発生ずる分だけでよく、バケットCを
上昇させる時の吐出量に比べれば僅かである。
In this case, the discharge amount from the air suita port 21 is adjusted by the valve 25, and this discharge amount only needs to generate an upward airflow to slow down the descending speed, and is compared to the discharge amount when raising the bucket C. There are only a few.

なお、バルブ25による空気の吐出量の応答性を高める
ために、このバルブ25に微調整可能な補助バルブを併
設してもよい。
Note that in order to improve the responsiveness of the amount of air discharged by the valve 25, an auxiliary valve that can be finely adjusted may be provided alongside the valve 25.

この後、空気供給手段20では、バルブ29.37のみ
を開にして縦管10内の空気を配管36、配管26、ブ
ロワ−22、配管23、配管28を経て外部に排出する
ことで換気状態になる。そして、最下階のゲート12を
開いてバケットCより収集コレクタ13を排出口11b
から弓き出し、反転投入装置50で収集コレクタ13内
に収容された塵芥を塵芥貯留排出装置60に投入する。
After this, the air supply means 20 opens only the valve 29.37 to discharge the air in the vertical pipe 10 to the outside via the pipe 36, pipe 26, blower 22, pipe 23, and pipe 28, thereby creating a ventilation state. become. Then, open the gate 12 on the bottom floor and remove the collection collector 13 from the bucket C through the discharge port 11b.
The garbage stored in the collection collector 13 is thrown into the garbage storage and discharge device 60 using the reversing and feeding device 50.

次に、バケットCを最下階から所望階まで上昇させる場
合について説明する。
Next, a case will be described in which the bucket C is raised from the lowest floor to a desired floor.

反転投入装置50によって塵芥を塵芥貯留排出装置60
に投入した空の収集コレクタ13は、縦管lO内におい
て第1パケツト支持装置?ff115に支持されている
バケットCに再び搬入される。この後、ゲート12を閉
じ、制御装置によりバケットCを搬送しようとする所望
階の排気制御手段19の排気バルブ18を開にするとと
もに、この制御装置によりバルブ25.27のみを開く
ことで空気供給手段20をバケット上昇搬送状態にする
The garbage is transferred to the garbage storage and discharge device 60 by the reversing feeding device 50.
The empty collection collector 13 loaded into the first packet support device ? It is carried back into bucket C supported by ff115. After that, the gate 12 is closed, and the control device opens the exhaust valve 18 of the exhaust control means 19 of the desired floor to which the bucket C is to be transported, and the control device opens only the valves 25 and 27 to supply air. The means 20 is placed in the bucket-up conveying state.

これにより、空気は配管26の他端26aから配管26
、ブロワ−22、配管23、空気吹田口21に送られ、
この空気吹出口21から縦管10内に供給される。この
ように空気を空気吹出口21から供給することでバケッ
トCは縦管!0内を上昇する。ここで、ブロワ−22は
バケットCを上昇させるだけの十分な出力を有するもの
が用いられる。
As a result, air flows from the other end 26a of the pipe 26 to the pipe 26.
, blower 22, piping 23, air is sent to Suita outlet 21,
Air is supplied into the vertical pipe 10 from this air outlet 21 . By supplying air from the air outlet 21 in this way, the bucket C becomes a vertical pipe! Rise within 0. Here, a blower 22 having sufficient output to lift the bucket C is used.

そして、排気バルブ18が開になされている所望階にバ
ケットCが達すると、(3)式に示すようにバケットC
を上昇させるために供給された空気が排気口16より排
気される際に発生する圧力PsmとバケットCの受圧面
積Scの積と、バケットCの重量Wが釣り合い、この位
置でバケットCは停止することになる。
When the bucket C reaches the desired floor where the exhaust valve 18 is opened, the bucket C
The product of the pressure Psm generated when the air supplied to raise the air is exhausted from the exhaust port 16 and the pressure receiving area Sc of the bucket C is balanced with the weight W of the bucket C, and the bucket C stops at this position. It turns out.

w = s c −p sx        −(3)
したがって、排気バルブ18が開状態になされている排
気口16に達すると、バケットCはその受圧部でその位
置を維持するだけの風量を受け、上昇に寄与していた風
量の一部が排気口16より排出される形となり、結果的
にそのバケットCと釣り合う上昇力が得られることにな
る。これにより、バケットCは停止(浮遊)状態になる
w = s c - p sx - (3)
Therefore, when the bucket C reaches the exhaust port 16 where the exhaust valve 18 is in the open state, the bucket C receives an air volume sufficient to maintain its position in its pressure receiving part, and part of the air volume that was contributing to the rise is transferred to the exhaust port 16. 16, and as a result, a lifting force that balances the bucket C is obtained. As a result, bucket C becomes stopped (floating).

また、ブロワ−22の回転数もしくはバルブ25の開閉
を制御することにより、バケット上昇搬送状態になされ
た空気供給手段20を介して縦管10内に供給する空気
の風量を調整することができ、これによってバケットC
の上y?、に寄与する風量を制御してバケットCを所望
の目標階に適宜減速させながら停止させることも可能で
ある。
Furthermore, by controlling the rotation speed of the blower 22 or the opening/closing of the valve 25, it is possible to adjust the volume of air supplied into the vertical pipe 10 via the air supply means 20 which is in the bucket upward conveyance state. This allows bucket C
Above y? It is also possible to stop the bucket C at a desired target floor while appropriately decelerating it by controlling the amount of air that contributes to .

このように所望階に停止したバケットCは、光電センサ
70によってその存在が確認され、これによってその所
望階の第2パケツト支持装置??I4がバケット支持位
置に作動し、バケットCを支持する。この後、この階の
ゲート+2が開かれ、バケットCより収集コレクタ13
は縦管IO内から所望階に搬出される。
The existence of the bucket C that has stopped at the desired floor is confirmed by the photoelectric sensor 70, and the second packet support device on the desired floor is thereby detected. ? I4 is activated to the bucket support position and supports bucket C. After this, gate +2 on this floor will be opened and collector 13 will be collected from bucket C.
is carried out from inside the vertical pipe IO to the desired floor.

そして、縦管IO内でバケットCの搬送を行わない場合
は、バルブ29.37を開にして空気供給手段20を換
気状態にする。
When the bucket C is not transported within the vertical pipe IO, the valves 29 and 37 are opened to bring the air supply means 20 into a ventilation state.

このように、各階と最下階との間でバケットCを往復搬
送することができる。
In this way, the bucket C can be transported back and forth between each floor and the lowest floor.

また、重量検出手段として圧力測定器を用いたが、この
ような間接的な検出のほか、バケット支持装置に作用す
る負荷を直接計測してもよい。
Further, although a pressure measuring device is used as the weight detecting means, in addition to such indirect detection, the load acting on the bucket support device may be directly measured.

さらに、ブロワ−からの吐出量は吸入側のバルブ27を
制御することでも可能である。
Furthermore, the discharge amount from the blower can also be controlled by controlling the valve 27 on the suction side.

(発明の効果) 以上のように本発明は、各階で収集された塵芥を収容す
る収集コレクタをバケットを介して各階と収集術との間
で往復搬送することができることから、エレベータによ
る人や貨物の輸送を阻害することがなく、また腐敗臭を
残すこともない。
(Effects of the Invention) As described above, the present invention enables the collection collector that stores the garbage collected on each floor to be transported back and forth between each floor and the collection site via the bucket, so that people and cargo can be transported by elevator. It does not obstruct the transportation of food and does not leave a putrid odor.

さらには、バケットの搬送速度は任意に調整できること
から、高層ビルに適用した場合、短時間に昇降搬送する
ことができ、全体としての作業時間を短縮することが可
能となり、作業効率を向上させることができる。
Furthermore, since the transport speed of the bucket can be adjusted arbitrarily, when applied to high-rise buildings, it is possible to transport the bucket up and down in a short time, reducing overall working time and improving work efficiency. Can be done.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の実施例を例示するもので、第1図はバケ
ット搬送システムの概略構成及び動作を示す側面図、第
2図はバケットと収集コレクタとの関係を示す斜視図で
ある。
The drawings illustrate an embodiment of the present invention, and FIG. 1 is a side view showing the schematic structure and operation of a bucket conveying system, and FIG. 2 is a perspective view showing the relationship between buckets and collection collectors.

Claims (1)

【特許請求の範囲】[Claims] (1)建物の所要階に亘って配設されるとともに、開閉
可能な搬出入口が適宜形成され、内部をバケットが搬送
可能な縦管と、 前記搬出入口に設けられ、該搬出入口に臨む縦管内でバ
ケットを支持可能なバケット支持装置と、 前記縦管外より吸引された空気を塵芥収集階のバケット
支持装置の下方の縦管内に供給するとともに、その空気
量を調整可能な空気供給手段と、前記収集階のバケット
支持装置の上方近傍の縦管内より空気を排気し、その排
気量が調整可能な排気量制御手段と、 前記収集階を除くその上方階の搬出入口にそれぞれ設け
られ、前記空気供給手段により縦管内に供給される空気
を排気する排気制御手段と、前記バケットの重量を直接
的にもしくは間接的に計測する重量測定手段と、 を備え、前記バケットは搬出入口に対応して一側壁が開
口されて収集コレクタを収容可能に構成してなり、前記
収集コレクタを収容したバケットの重量を重量測定手段
を介して計測し、その測定結果に基づいて排気量制御手
段により排気量を制御することでバケットを予め設定さ
れた速度で降下させ、収集階のバケット支持装置上に着
地したバケットより収集コレクタを引き出して適宜塵芥
を排出した後、収集コレクタをバケットに収容して空気
供給手段によりバケットを上昇させ、排気制御手段で所
定階に停止させて支持装置上に支持し、収集コレクタを
回収するように構成したことを特徴とする、バケット搬
送システム。
(1) A vertical pipe that is arranged over the required floors of the building, has an openable and closable loading/unloading entrance formed as appropriate, and that allows buckets to be transported inside; a bucket support device capable of supporting a bucket within the pipe; and an air supply means capable of supplying air sucked from outside the vertical pipe into the vertical pipe below the bucket support device on the garbage collection floor and adjusting the amount of air. , an exhaust amount control means for evacuating air from a vertical pipe near the upper part of the bucket support device on the collection floor and adjusting the amount of the exhaust; an exhaust control means for exhausting the air supplied into the vertical pipe by the air supply means; and a weight measurement means for directly or indirectly measuring the weight of the bucket, the bucket being arranged in a manner corresponding to the loading/unloading entrance. One side wall is opened to accommodate the collection collector, and the weight of the bucket containing the collection collector is measured via a weight measuring means, and the displacement is controlled by the displacement control means based on the measurement result. The bucket is lowered at a preset speed by controlling the bucket, and the collection collector is pulled out from the bucket that has landed on the bucket support device on the collection floor, and the garbage is discharged as appropriate.Then, the collection collector is housed in the bucket and the air supply means 1. A bucket conveyance system, characterized in that the bucket is raised by a pump, stopped at a predetermined floor by an exhaust control means, supported on a support device, and collected by a collector.
JP21758988A 1988-08-31 1988-08-31 Bucket transport system Expired - Fee Related JP2645865B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21758988A JP2645865B2 (en) 1988-08-31 1988-08-31 Bucket transport system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21758988A JP2645865B2 (en) 1988-08-31 1988-08-31 Bucket transport system

Publications (2)

Publication Number Publication Date
JPH0266024A true JPH0266024A (en) 1990-03-06
JP2645865B2 JP2645865B2 (en) 1997-08-25

Family

ID=16706659

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21758988A Expired - Fee Related JP2645865B2 (en) 1988-08-31 1988-08-31 Bucket transport system

Country Status (1)

Country Link
JP (1) JP2645865B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0425540U (en) * 1990-06-25 1992-02-28

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0425540U (en) * 1990-06-25 1992-02-28

Also Published As

Publication number Publication date
JP2645865B2 (en) 1997-08-25

Similar Documents

Publication Publication Date Title
JP2614088B2 (en) Garbage collection method using bucket transport system
JP2645865B2 (en) Bucket transport system
JP4383153B2 (en) Waste container transport device
JP2708781B2 (en) Bucket feeder in bucket transport system
JP2702506B2 (en) Landing control device in bucket transport system
JP2635101B2 (en) Dust collection control device in bucket reciprocating transport system
JP2635100B2 (en) Bucket reciprocating transfer system
JP2635999B2 (en) Waste collection method in bucket reciprocating transport system
JP2636018B2 (en) Bucket transport system
JPH0636007Y2 (en) Bucket for transport in bucket transport system
JPH028102A (en) Bucket conveyance system and its garbage collection method
JP2635102B2 (en) Transfer control device to target floor in bucket transfer system
JP2636019B2 (en) Bucket transport system
JP2703782B2 (en) Operation safety device in bucket transport system
JP2638128B2 (en) Bucket landing device in bucket transport system
JPH0289702A (en) Transport bucket in bucket transport system
JP2708788B2 (en) Transfer bucket in bucket transfer system
EP0714364B1 (en) Hopper for dusty materials
JP2546170Y2 (en) Transfer stop device of bucket transfer device
JP2662620B2 (en) Input device for waste collection device
JPH03115002A (en) Dust disposal system
JPH09153437A (en) Portable airtight container gas supply and exhaust system
JP2504960Y2 (en) Garbage container carrier
JPS6125872Y2 (en)
JP4294795B2 (en) Method and apparatus for transferring soil amendment

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees