JPH026886B2 - - Google Patents

Info

Publication number
JPH026886B2
JPH026886B2 JP59241796A JP24179684A JPH026886B2 JP H026886 B2 JPH026886 B2 JP H026886B2 JP 59241796 A JP59241796 A JP 59241796A JP 24179684 A JP24179684 A JP 24179684A JP H026886 B2 JPH026886 B2 JP H026886B2
Authority
JP
Japan
Prior art keywords
concrete
pile
pipe
crushing agent
static crushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59241796A
Other languages
Japanese (ja)
Other versions
JPS61122322A (en
Inventor
Hachiro Kubota
Junichiro Uda
Akiiku Sasada
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taiheiyo Cement Corp
Original Assignee
Onoda Cement Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Onoda Cement Co Ltd filed Critical Onoda Cement Co Ltd
Priority to JP24179684A priority Critical patent/JPS61122322A/en
Publication of JPS61122322A publication Critical patent/JPS61122322A/en
Publication of JPH026886B2 publication Critical patent/JPH026886B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/005Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Aftertreatments Of Artificial And Natural Stones (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は、場所打コンクリート杭の杭頭余盛
コンクリート部に計画的にクラツクを発生させ
て、破壊が容易に行なうことができる杭頭破壊方
法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention provides a method for destroying pile heads that can be easily destroyed by systematically generating cracks in the concrete portion of the pile head of cast-in-place concrete piles. It is about the method.

[従来の技術] 従来、場所打コンクリート杭の杭頭余盛コンク
リートを破壊する方法として、ピツクなどを使用
して行なう人力による方法が主体であり、又、ハ
ンドハンマーで穿設した孔中或いはパイプを予め
切断予定の箇所に埋設し、この中に膨張性破砕剤
のスラリーを充填して破壊する方法(特開昭58−
204216号公報、特開昭59−91214号公報)などが
ある。
[Prior art] Traditionally, the main method for destroying pile head reinforcement concrete of cast-in-place concrete piles has been manual methods using picks, etc. A method of destroying the material by burying it in advance at the location where it is planned to be cut and filling it with a slurry of an expandable crushing agent
204216, Japanese Patent Application Laid-open No. 59-91214), etc.

[発明が解決しようとする問題点] これらの方法のうち、ピツクなどを使用して人
力で行なう方法は、騒音、粉塵の発生が著しく、
市街地などでは公害の原因となり、又、作業者の
安全衛生上の問題がある。
[Problems to be Solved by the Invention] Among these methods, the manual method using a pick etc. generates significant noise and dust.
In urban areas, it causes pollution and also poses safety and health problems for workers.

膨張性破砕剤のスラリーを充填する方法は、騒
音、粉塵の発生を抑制できるが、操作の上でスラ
リーの流動性を一定に保つ必要があり、このため
水量の管理や、混練り作業管理を充分に行なう必
要があるなど作業が煩雑である。
The method of filling a slurry of expandable crushing agent can suppress the generation of noise and dust, but it is necessary to maintain the fluidity of the slurry constant during operation, which makes it difficult to control the amount of water and kneading work. The work is complicated as it needs to be done thoroughly.

従つて、膨張性破砕剤の使用による場所打コン
クリートの杭頭破砕方法において、水量の管理や
破砕剤の混練り作業管理面での煩雑さを伴わない
方法が要望され、この発明はこのような従来方法
の欠点を解決した場所打コンクリート杭頭の破壊
方法を提供することを目的とする。
Therefore, there is a need for a method for crushing the pile head of cast-in-place concrete using an expansive crushing agent that does not involve complicated management of water volume or mixing of the crushing agent, and the present invention is directed to such a method. The purpose of the present invention is to provide a method for destroying cast-in-place concrete pile caps that solves the drawbacks of conventional methods.

[問題点を解決するための手段] この発明は上述の問題を、粉末状又は顆粒状の
静的破砕剤を多数の透水用小孔を設けたパイプに
充填して杭頭破壊部境界線に沿つて杭の外周部の
内側をほぼ囲むように設置することにより解決す
るものである。
[Means for Solving the Problems] This invention solves the above-mentioned problems by filling a pipe with a large number of small holes for water permeation with a powdered or granular static crushing agent at the boundary line of the fractured pile head. This problem can be solved by installing the piles so as to almost surround the inside of the outer periphery of the piles.

即ちこの発明は、場所打コンクリートの杭頭破
壊部境界線に沿つて杭の外周部の内側をほぼ囲む
ように、粉末又は顆粒状の静的破砕剤を充填した
パイプを設置し、コンクリートを打設した後、予
めパイプに設けた透水用小孔を通してコンクリー
ト中の余剰水を吸水させることによつて該パイプ
中の静的破砕剤が反応して膨張圧を発現し、該杭
頭破壊部を破壊することを特徴とする場所打コン
クリート杭頭の破壊方法である。
That is, this invention installs a pipe filled with a static crushing agent in the form of powder or granules so as to substantially surround the inside of the outer periphery of the pile along the boundary line of the fractured part of the pile head of cast-in-place concrete, and casts concrete. After the pile is installed, excess water in the concrete is absorbed through small permeable holes previously provided in the pipe, and the static crushing agent in the pipe reacts and develops expansion pressure, causing the pile cap to fail. This is a method of destroying cast-in-place concrete pile heads, which is characterized by destroying them.

[作 用] この発明の実施は、まずパイプ(例えばスパイ
ラルシース管)に、静的破砕剤(例えば小野田セ
メント登録商標名ブライスター)を充填したの
ち、このパイプを第2図に示すように鉄筋篭を有
するコンクリート杭の余盛コンクリート切断予定
線に沿つて或いはその少し上部の鉄筋篭の内側に
結束線で取り付けて、この鉄筋篭を定位置にセツ
トしたのち、生コンクリートを打設してコンクリ
ート杭を形成する。この時コンクリート切断予定
線上部の鉄筋表面には、コンクリートとの剥離を
容易にするためビニール又はプラスチツク等を被
覆しておく。コンクリート中に完全に埋設された
予め設けられたパイプの透水用の小孔を通じて、
パイプ内部に充填された静的破砕剤にコンクリー
ト中の余剰水が供給されて水和反応が起こり、膨
張圧が発現されて杭頭の切り取り予定線に計画的
にクラツクを発生させることができる。パイプは
鉄筋篭の径に応じて余盛コンクリート切断予定線
の約5〜10cm位上部に設置するのが好ましい。
[Function] To carry out this invention, first, a pipe (for example, a spiral sheath pipe) is filled with a static crushing agent (for example, Onoda Cement registered trademark Blyster), and then the pipe is connected to reinforcing bars as shown in FIG. The reinforced concrete pile of the concrete pile with the cage is attached to the inside of the reinforcing bar cage along or slightly above the scheduled cutting line with a binding wire, and after this reinforcing bar cage is set in position, ready-mixed concrete is poured and concrete is made. Form a pile. At this time, the surface of the reinforcing bars above the planned concrete cutting line is covered with vinyl or plastic to make it easier to separate from the concrete. Through small permeable holes in pre-installed pipes completely buried in the concrete,
Excess water in the concrete is supplied to the static crushing agent filled inside the pipe, causing a hydration reaction, which generates expansion pressure and allows cracks to occur in planned cut lines of pile caps. It is preferable to install the pipe approximately 5 to 10 cm above the planned cutting line of the excess concrete, depending on the diameter of the reinforcing bar cage.

この発明に使用する静的破砕剤としては、上記
ブライスターの他一般の粉末状、顆粒状の各種公
知の市販されている静的破砕剤を使用できるが、
コンクリートの強度発現時間と対応するように遅
延剤等により成分調整され、膨張圧発現時間が調
整されているものが望ましい。
As the static crushing agent used in this invention, in addition to the above-mentioned Blister, various known commercially available static crushing agents in the form of general powders and granules can be used.
It is desirable that the composition be adjusted with a retardant or the like to correspond to the strength development time of concrete, and the expansion pressure development time should be adjusted.

パイプとしてはPC用シース管が好適であるが、
これと同程度の強度を有するプラスチツクの他各
種材料を使用することができる。パイプの直径は
30〜60mmが好適である。パイプに設ける透水用の
穴は、粉末の流出防止と透水性を考慮し、φ0.5〜
2.5m/m、好ましくはφ1.0〜1.5m/mがよい。
穴の数はパイプ1cm2当たり1〜10孔、好ましくは
4〜6孔がよい。第1図に透水用の穴を設けた
PC用シース管の斜視図を示す。
PC sheath pipes are suitable as pipes, but
Various other materials such as plastics having similar strength can be used. The diameter of the pipe is
30-60mm is suitable. The holes for water permeation provided in the pipe should be φ0.5~, taking into account the prevention of powder outflow and water permeability.
2.5 m/m, preferably φ1.0 to 1.5 m/m.
The number of holes is preferably 1 to 10 holes, preferably 4 to 6 holes per cm 2 of pipe. A hole for water permeation is provided in Figure 1.
The perspective view of the sheath tube for PC is shown.

パイプ中に静的破砕剤を充填するには、例えば
パイプを半円形状とし、片端を閉塞して破砕剤を
所定量充填したのち、他端をふさいで所定位置に
円形状に取り付ける。パイプをさらに分割して同
様に設置してもよい。また必要に応じ、静的破砕
剤を充填した複数個のパイプを鉄筋篭に結び付け
て縦方向に設けることによつて、コンクリートの
分割破砕を行つてもよい。
To fill a pipe with a static crushing agent, for example, the pipe is made into a semicircular shape, one end is closed, a predetermined amount of crushing agent is filled, the other end is closed, and the pipe is installed in a circular shape at a predetermined position. The pipe may be further divided and installed in the same manner. Further, if necessary, the concrete may be divided and crushed by connecting a plurality of pipes filled with a static crushing agent to a reinforcing bar cage and installing them in the vertical direction.

コンクリートから供給される水量は、シース管
に空けられた穴の径と数によつて調整が可能であ
り、静的破砕剤の水和反応に必要な量とほぼ等し
くすることができ、粉末の流出も殆ど防止するこ
とができる。
The amount of water supplied from concrete can be adjusted by the diameter and number of holes drilled in the sheath pipe, and can be made approximately equal to the amount required for the hydration reaction of the static crushing agent. Outflow can also be almost completely prevented.

[実施例] 以下実施例に基づきこの発明を説明する。[Example] The present invention will be explained below based on Examples.

実施例 1 φ40m/m、肉厚0.3m/mのPC用シース管に
φ1m/mの穴を1cm2当たり5孔設け、これを鉄
筋篭の円周の長さとほぼ等しく切断して半円形状
とし、片方を閉塞し、この中に静的破砕剤である
粉末状のブライスターを一杯になるまで充填し蓋
をする。この時、振動、突き固め、締め固め等を
する必要はなく、自然に流し込むだけでよい。次
に、これをφ1200m/mの杭の杭頭部の切断線に
沿つて鉄筋篭の内側に結束線で取り付ける。
Example 1 A PC sheath pipe with a diameter of 40 m/m and a wall thickness of 0.3 m/m was provided with 5 holes of 1 m/m in diameter per 1 cm2, and this was cut approximately equal to the length of the circumference of the reinforcing bar cage to form a semicircular shape. Close one end, fill it with powdered blister, which is a static crushing agent, until it is full and cover it with a lid. At this time, there is no need to perform vibration, tamping, compaction, etc., and it is sufficient to simply pour the material naturally. Next, this is attached to the inside of the reinforcing bar cage with a binding wire along the cutting line of the pile head of a φ1200m/m pile.

ブライスターはコンクリートの強度発現に合わ
せて膨張圧の発現が材令1日で0Kg/cm2、4日で
100Kg/cm2、5日で180Kg/cm2のものを使用した。
コンクリートを打設して7日後に掘り起こしを行
つたところ、切断予定線に沿つて幅3〜5m/m
のクラツクが発生し、杭頭部を切断することがで
きた。
Blister develops expansion pressure in line with the strength development of concrete, and the development of expansion pressure is 0 Kg/cm 2 in 1 day, and 0 kg/cm 2 in 4 days.
100Kg/cm 2 and 180Kg/cm 2 after 5 days were used.
When excavation was carried out 7 days after concrete was poured, a width of 3 to 5 m/m was found along the planned cutting line.
A crack occurred and the head of the pile was able to be severed.

実施例 2 φ40m/m、肉厚0.3m/mのPC用シース管に
φ2.5m/mの穴を1cm2当たり3孔設け、これを鉄
筋篭の円周の長さとほぼ等しく切断して片方を閉
塞し、この中に静的破砕剤である顆粒状のブライ
スターを充填し蓋をする。これをφ1000m/mの
ベツト杭の杭頭部の切断線に沿つて鉄筋篭の内側
に結束線で取り付ける。
Example 2 A PC sheath pipe with a diameter of 40 m/m and a wall thickness of 0.3 m/m was provided with 3 holes of 2.5 m/m in diameter per 1 cm2, and this was cut approximately equal to the length of the circumference of the reinforcing bar cage. , fill it with granular blister, which is a static crushing agent, and put a lid on it. This is attached to the inside of the reinforcing bar cage with a binding wire along the cutting line of the pile head of a φ1000m/m bed pile.

顆粒状のブライスターは粒度範囲0.3m/m〜
5.0m/m、嵩比重2.0〜2.7のものがよく、膨張圧
の発現が材令1日で0Kg/cm2、4日で100Kg/cm2
5日で180Kg/cm2のものを使用した。コンクリー
トを打設して7日後に掘り起こしを行つたとこ
ろ、切断線に沿つて幅2〜4m/mのクラツクが
発生し、杭頭部を切断することができた。
Granular Blister has a particle size range of 0.3m/m~
5.0 m/m and a bulk specific gravity of 2.0 to 2.7, and the development of expansion pressure is 0 Kg/cm 2 at 1 day of age, 100 Kg/cm 2 at 4 days,
180Kg/cm 2 was used in 5 days. When excavation was carried out 7 days after concrete was placed, a crack with a width of 2 to 4 m/m occurred along the cutting line, and the pile head was able to be severed.

実施例 3 φ40m/m、肉厚0.5m/mの樹脂製のパイプに
φ1m/mの孔を1cm2当たり5孔設け、これを鉄
筋篭の円周の長さとほぼ等しくして円形状とし、
片方を閉塞し、この中に粒度分布をJIS標準篩で
1.2m/m全通、0.6m/m残分65%、0.3m/m残
分90%に粗砕分級した静的破砕用焼結体を充填し
蓋をする。次にこれをφ1200m/mの場所打ちコ
ンクリート杭の杭頭部の切断予定線に沿つて結束
線で取り付ける。
Example 3 A resin pipe with a diameter of 40 m/m and a wall thickness of 0.5 m/m is provided with 5 holes of 1 m/m in diameter per 1 cm2, and the length is approximately equal to the circumference of the reinforcing bar cage to form a circular shape.
Close one side and check the particle size distribution using a JIS standard sieve.
Fill with sintered compacts for static crushing that have been coarsely crushed and classified to 1.2m/m all through, 65% remaining at 0.6m/m, and 90% remaining at 0.3m/m, and cover with a lid. Next, attach this to a cast-in-place concrete pile with a diameter of 1200 m/m along the planned cutting line of the pile head with a binding wire.

続いて生コンクリートを打設して杭を形成す
る。透水用の小孔を通じてコンクリート中の余剰
水が浸透し、膨張圧の発現が材令1日で15Kg/
cm2、3日で100Kg/cm2、5日で150Kg/cm2発現し
た。材令10日後に杭の堀起こしを行つたところ、
切断予定線に沿つて幅3〜5m/mのクラツクが
発生し杭頭を切断した。
Next, ready-mixed concrete is poured to form the piles. Excess water in the concrete permeates through the small holes for water permeation, and the expansion pressure is increased to 15 kg / 1 day after the material ages.
cm 2 , 100 Kg/cm 2 after 3 days, and 150 Kg/cm 2 after 5 days. When the piles were dug 10 days later,
A crack with a width of 3 to 5 m/m occurred along the planned cutting line, and the pile cap was severed.

この静的破砕用焼結体を使用すると、コンクリ
ート打設直後から透水用の小孔を通じてコンクリ
ート中の余剰水が供給されて水和反応が始まる
が、焼結体の粒度が大きく粉末状のものに比較し
て水の浸透速度が遅くなり、コンクリートの強度
の発現と並行して膨張圧が発現し杭頭の切り取り
予定線に計画的にクラツクを発生させることがで
きる。
When this sintered body for static crushing is used, surplus water in the concrete is supplied through the small holes for water permeation immediately after concrete is placed, and the hydration reaction begins. The rate of water penetration is slower than that in concrete, and expansion pressure develops in parallel with the development of concrete strength, making it possible to systematically create cracks on the planned cutting line of the pile cap.

[発明の効果] この発明によれば、粉末状又は顆粒状の静的破
砕剤を使用し、コンクリートの余剰水により破砕
剤を反応させて膨張圧を発現するので、水の計量
管理、混練り管理が不必要で操作が簡単であり、
静的に且つ計画的に杭頭の余盛コンクリートを破
壊することができる。
[Effect of the invention] According to this invention, a static crushing agent in the form of powder or granules is used, and expansion pressure is generated by reacting the crushing agent with excess water in the concrete. No management required, easy to operate,
It is possible to statically and systematically destroy the excess concrete of the pile cap.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の実施に使用するPC用シース
管の斜視図、第2図は実施例において第1図の
PC用シース管を鉄筋篭内側に取り付けた時の斜
視図である。図中、 1……PC用シース管、2……穴、3……鉄筋
篭。なお、各図中、同一符号は同一または相当部
分を示す。
FIG. 1 is a perspective view of a PC sheath tube used in carrying out the present invention, and FIG.
It is a perspective view when the PC sheath pipe is attached to the inside of the reinforcing bar cage. In the figure, 1...PC sheath pipe, 2...hole, 3...reinforced cage. In each figure, the same reference numerals indicate the same or corresponding parts.

Claims (1)

【特許請求の範囲】[Claims] 1 場所打コンクリートの杭頭破壊部境界線に沿
つて杭の外周部の鉄筋の内側をほぼ囲むように、
粉末又は夥粒状の静的破砕剤を充填したパイプを
設置し、コンクリートを打設した後、予めパイプ
に設けた透水用小孔を通してコンクリート中の余
剰水を吸水させることによつて該パイプ中の静的
破砕剤が反応して膨張圧を発現し、該杭頭破壊部
を破壊することを特徴とする、場所打コンクリー
ト杭頭の破壊方法。
1 Along the boundary line of the failed pile head of cast-in-place concrete, almost encircling the inside of the reinforcing bars on the outer periphery of the pile,
After installing a pipe filled with a powder or granular static crushing agent and pouring concrete, the excess water in the concrete is absorbed through small permeable holes prepared in the pipe in advance. A method for destroying a cast-in-place concrete pile cap, characterized in that a static crushing agent reacts and develops expansion pressure to destroy the pile cap destruction portion.
JP24179684A 1984-11-16 1984-11-16 Method of destroying cast-in-place concrete pile head Granted JPS61122322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24179684A JPS61122322A (en) 1984-11-16 1984-11-16 Method of destroying cast-in-place concrete pile head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24179684A JPS61122322A (en) 1984-11-16 1984-11-16 Method of destroying cast-in-place concrete pile head

Publications (2)

Publication Number Publication Date
JPS61122322A JPS61122322A (en) 1986-06-10
JPH026886B2 true JPH026886B2 (en) 1990-02-14

Family

ID=17079636

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24179684A Granted JPS61122322A (en) 1984-11-16 1984-11-16 Method of destroying cast-in-place concrete pile head

Country Status (1)

Country Link
JP (1) JPS61122322A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0559721A (en) * 1991-08-30 1993-03-09 Shigeru Iwakiri Head end treating method for cast-in-place pile
JPH08903B2 (en) * 1993-12-28 1996-01-10 住友大阪セメント株式会社 Static crushing agent

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58185823A (en) * 1982-04-24 1983-10-29 Nippon Cement Co Ltd Removal of head of on-site concrete pile
JPS58213989A (en) * 1982-06-07 1983-12-13 住友セメント株式会社 Crushing capsule and crushing method using same
JPS5980816A (en) * 1982-10-29 1984-05-10 Denki Kagaku Kogyo Kk Construction of on-site pile
JPS5980815A (en) * 1982-10-29 1984-05-10 Denki Kagaku Kogyo Kk Construction of on-site pile

Also Published As

Publication number Publication date
JPS61122322A (en) 1986-06-10

Similar Documents

Publication Publication Date Title
JPS6327488B2 (en)
JPH0410927B2 (en)
JPH026886B2 (en)
JP4010905B2 (en) Pile embedding method and equipment used therefor
JPH05148835A (en) Crushing method of pile head of concrete pile
JP2001200537A (en) Soil improving method and support pile for soil improvement
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JP3007940B2 (en) Lightweight ground to be cast on soft ground and construction method thereof
JPS6221924A (en) Breaking of in-site concrete pile head
JP3156180B2 (en) Earth retaining work
JPH10325141A (en) Crusher for pile head of cast-in-plate concrete pile and crushing method thereof
JP2839669B2 (en) Pile head crushing method for cast-in-place concrete piles
TW311957B (en) The improving method for weak foundation
JP4521848B2 (en) Earth removal backfill hole forming device
JP2774678B2 (en) Pile head crushing method for cast-in-place concrete piles
JP2020125648A (en) Columnar improvement method, and soil cement column row wall method using core material pressing-in and vibration pressing-in
JP2000310094A (en) Ground support method
JP2004353310A (en) Ground improvement method using kneaded material containing large amount of coal ash
JPH0586618A (en) Treatment of cast-in-place concrete pile head
JPH028412A (en) Method and device for treating pile head
JPH10140155A (en) Fluid backfill material and method for producing the same
JP4262041B2 (en) Anchor embedding caking agent and anchor embedding method using the same
JPH11132699A5 (en)
JPS5733616A (en) Forming method for steel pipe pile
JPH08269948A (en) Pile head treatment method for site construction pile