JPH0288848A - Formation method for through-hole form of reinforced concrete beam - Google Patents

Formation method for through-hole form of reinforced concrete beam

Info

Publication number
JPH0288848A
JPH0288848A JP24177588A JP24177588A JPH0288848A JP H0288848 A JPH0288848 A JP H0288848A JP 24177588 A JP24177588 A JP 24177588A JP 24177588 A JP24177588 A JP 24177588A JP H0288848 A JPH0288848 A JP H0288848A
Authority
JP
Japan
Prior art keywords
formwork
bar
anchorages
reinforced concrete
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP24177588A
Other languages
Japanese (ja)
Other versions
JPH0663367B2 (en
Inventor
Yatsunobu Nakayama
中山 八信
Masayuki Shigita
鴫田 雅行
Seiichi Suzaki
須崎 誠一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP63241775A priority Critical patent/JPH0663367B2/en
Publication of JPH0288848A publication Critical patent/JPH0288848A/en
Publication of JPH0663367B2 publication Critical patent/JPH0663367B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PURPOSE:To assemble a through-hole form simply and speedily, to reduce a construction period and to reduce a cost by inserting bar members, one by one, into circular channels afterward against anchorages previously provided to a beam form. CONSTITUTION:A circular channel member provided with groove insertion inlets 9 on the outside parts of the upper ends of circular channels 8 is anchorages 5, and the anchorages 5 are so fixed to the inside surfaces of beam forms 4 that they are opposed to each other. After that, both ends of a bar member 13 are inserted into the circular channels 8 through the groove insertion inlets 9 to lay the bar member 13 between the anchorages 5, and bar members 13 laid over previously are subsequently inserted into the circular channels to form cylinders 15 by placing a large number of bar members in parallel. According to the constitution, a through-hole form (a sleeve member) of reinforced concrete beam can be easily and speedily assembled.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、鉄筋コンクリート梁に配管用の貫通孔を形成
するための貫通孔用型枠の形成方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for forming a through-hole formwork for forming a through-hole for piping in a reinforced concrete beam.

〔従来の技術〕[Conventional technology]

第8図に示すような鉄筋コンクリート(RC)梁1の巾
方向に配管用の貫通孔(スリーブ)2を形成するには、
コンクリート打設前に祇チューブや金属製筒による孔形
成材(スリーブ材)を型枠内にセットして孔空間を確保
するようにしている。
To form a through hole (sleeve) 2 for piping in the width direction of a reinforced concrete (RC) beam 1 as shown in FIG.
Before pouring concrete, a hole-forming material (sleeve material) made of a tube or a metal tube is set in the formwork to secure the hole space.

ところで、梁部分は構造上重要な部分であるため鉄筋量
も多く、特に貫通孔2の周囲は補強用の鉄筋も加わるの
でより多くの鉄筋量となる。そして、このような鉄筋を
梁型枠内に配筋する方法としてスラブ3(このスラブ3
を形成前のスラブ型枠上の場合もある。)上で組立てて
型枠内に落とし込む方法もあるが、この方法では落とし
込み治具を必要とし、また、仮設通路等の計画も必要で
制約条件も多いことから工費もかさむ。
By the way, since the beam part is a structurally important part, there is a large amount of reinforcing bars, and especially around the through hole 2, reinforcement reinforcing bars are also added, so the amount of reinforcing bars is even larger. As a method of arranging such reinforcing bars within the beam formwork, slab 3 (this slab 3
In some cases, it may be on the slab formwork before it is formed. ) and then dropping it into the formwork, but this method requires a dropping jig, requires planning for temporary passageways, etc., and has many constraints, which increases construction costs.

従って、一般的には梁型枠内で梁鉄筋を組立てることが
多いが、その場合には前記スリーブ材の取付けとの関係
が問題となる。組立てようとする鉄筋は梁型枠内で巾い
っばいを占めるようになるので、径の比較的大きい場合
のスリーブ材は配筋工事の途中で型枠内にセットし、さ
らにこのスリーブ材を内部に取込みなから梁鉄筋の組立
を完成させることになる。
Therefore, generally, beam reinforcing bars are often assembled within the beam form, but in that case, the relationship with the attachment of the sleeve material becomes a problem. The reinforcing bars to be assembled will occupy the entire width of the beam formwork, so if the diameter is relatively large, the sleeve material is set in the formwork during the reinforcement work, and the sleeve material is then placed inside the formwork. The assembly of the beam reinforcing bars will now be completed.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかし、このように配筋工事の途中でスリーブ材を配設
するのでは、そのタイミングをみはからうのが大変であ
り作業の手待ち時間が多くなり、また鉄筋施工と組番と
なるため、配筋精度も低下する。
However, if sleeve materials are placed in the middle of reinforcing work, it is difficult to determine the timing, which increases the waiting time for the work, and also because of the need for reinforcing steel work and assembly numbers. , the reinforcement accuracy also decreases.

本発明の目的は前記従来例の不都合を解消し、梁型枠内
で梁鉄筋を完全に又は大部分組立てた後からでも径の大
きな貫通孔用型枠(スリーブ材)を簡単かつ迅速に組立
てることができる鉄筋コンクリ−ト梁の貫通孔用型枠の
形成方法を提供することにある。
An object of the present invention is to eliminate the disadvantages of the conventional example, and to easily and quickly assemble a formwork (sleeve material) for a large diameter through hole even after the beam reinforcing bars have been completely or mostly assembled within the beam formwork. An object of the present invention is to provide a method for forming a formwork for a through hole in a reinforced concrete beam.

〔課題を解決するための手段] 本発明は前記目的を達成するため、円形溝の上端外側部
分に切欠き挿入口を有する円形チャンネル材を固定具と
して相対向するように梁型枠の内側面に取付け、切欠き
挿入口を介してバー部材の両端を円形溝内に差入れて固
定具間に該バー部材を掛け渡し、かつ先に掛け渡したバ
ー部材を順次円形溝に沿って送り込んで多数並列させて
円筒体を形成することを要旨とするものである。
[Means for Solving the Problems] In order to achieve the above-mentioned object, the present invention uses a circular channel material having a cutout insertion opening at the outer part of the upper end of the circular groove as a fixture, and fixes the inner surface of the beam formwork so as to face each other. , insert both ends of the bar member into the circular groove through the notch insertion opening, and span the bar member between the fixtures, and feed the bar members that were spanned first sequentially along the circular groove to create a large number of bar members. The gist is to form a cylindrical body by arranging them in parallel.

(作用〕 本発明によれば、先に梁型枠に取付けである固定具に対
し、後から1本1本バー部材をその円形溝内に挿入して
いくものであるから、このバー部材の挿入は梁型枠内で
梁鉄筋を組立てた後でもその隙間をぬって行なうことが
できる。そして、順次挿入されて固定具間に掛け渡され
たバー部材は円筒体を形成し、コンクリート打設時の貫
通孔用型枠(スリーブ材)となる。
(Function) According to the present invention, the bar members are inserted one by one into the circular grooves of the fixture which is first attached to the beam formwork. Insertion can be carried out through the gaps even after the beam reinforcing bars have been assembled within the beam formwork.The bar members inserted one after another and stretched between the fixtures form a cylindrical body, and the bar members are inserted into the beam formwork and stretched between the fixing devices. It becomes the formwork (sleeve material) for the through-hole.

〔実施例] 以下、図面について本発明の実施例を詳細に説明する。〔Example] Embodiments of the present invention will be described in detail below with reference to the drawings.

第1図は本発明の鉄筋コンクリート梁の貫通孔用型枠の
形成方法の1実施例を示す縦断側面図、第2図はこの第
1図のA−A線断面図、第3図〜第5図は各工程を示す
。
Fig. 1 is a vertical side view showing one embodiment of the method for forming a formwork for through holes in reinforced concrete beams according to the present invention, Fig. 2 is a sectional view taken along line A-A of Fig. 1, and Figs. The figure shows each step.

図中4は梁型枠、14はスラブ型枠を示すが、第3図に
示すようにこの梁型枠4のうち梁側面を形成する立板部
材の内側面に固定具5を予め墨出しかわりに取付けるよ
うにする。
In the figure, 4 indicates a beam formwork, and 14 indicates a slab formwork. As shown in Fig. 3, a fixture 5 is marked out in advance on the inner surface of the standing board member that forms the beam side surface of the beam formwork 4. Install it instead.

この固定具5は第6図に示すように外リング6と内リン
グ7とで形成した円形溝8をその開口を横向きにして有
する縦の円形チャンネル材で、該円形溝8の上端の外側
部分で外リング6の一部を切欠いて挿入口9を形成した
。また、内リング7の奥深部端から内側直角方向にリン
グ状の取付フランジ10を突設し、このフランジ10に
針止め孔11を穿設する。
As shown in FIG. 6, this fixture 5 is a vertical circular channel material having a circular groove 8 formed by an outer ring 6 and an inner ring 7 with its opening facing horizontally, and the outer part of the upper end of the circular groove 8. An insertion opening 9 was formed by cutting out a part of the outer ring 6. Further, a ring-shaped mounting flange 10 is provided protruding from the deep end of the inner ring 7 in a direction perpendicular to the inner side, and a needle fixing hole 11 is bored in this flange 10.

該釘止め孔11を介してフランジ11を梁型枠4に釘止
めすることで、固定具5は梁型枠4の内側面に2個が相
対向するように取付けられる。なお、この固定具5の取
付けは梁型枠4を組む前でも、後でもよい。
By nailing the flange 11 to the beam formwork 4 through the nailing hole 11, the fixtures 5 are attached to the inner surface of the beam formwork 4 such that two of them face each other. Note that the fixture 5 may be attached before or after the beam form 4 is assembled.

次いで、第4図に示すように、梁型枠4内に梁鉄筋12
を組立てる。図中12aはこの梁鉄筋12のうちの梁主
筋、12bはスターラップ筋、12cは貫通孔の周囲の
補強鉄筋である。
Next, as shown in FIG. 4, beam reinforcing bars 12 are placed inside the beam formwork 4.
Assemble. In the figure, 12a is the main beam reinforcement of the beam reinforcing bars 12, 12b is the stirrup reinforcement, and 12c is the reinforcing reinforcement around the through hole.

このようにして梁鉄筋12を完全に又は大部分組立てた
後で、軽量溝型鋼又はCチャンネル材のごとき軽金属製
のバー部材13を第5図に示すように梁鉄筋12の隙間
を介してその両端を固定具5の切欠き挿入口9から円形
溝8内に差入れる。
After the beam reinforcing bars 12 are completely or mostly assembled in this way, a bar member 13 made of light metal such as lightweight channel steel or C-channel material is inserted through the gap between the beam reinforcing bars 12 as shown in FIG. Insert both ends into the circular groove 8 through the notch insertion opening 9 of the fixture 5.

この作業はスラブ型枠14上から梁型枠4の上端開口よ
り行なうことができ、両端が円形溝8内に入ったバー部
材13はその開口面を内側(固定具5の取付フランジ側
)にして固定具5,5間に水平に掛け渡される。
This work can be performed from the top of the slab formwork 14 through the upper end opening of the beam formwork 4, and the bar member 13, whose both ends are in the circular groove 8, should have its opening face inside (toward the mounting flange of the fixture 5). It is horizontally spanned between the fixtures 5, 5.

前記バー部材13は多数本を同様にして固定具55間に
掛け渡すものであり、先に円形溝8に差入れたバー部材
13は挿入口9の部分から溝8に沿って順次奥へ送り込
む(第2図矢印参照)。
A large number of the bar members 13 are inserted between the fixtures 55 in the same manner, and the bar members 13 that were first inserted into the circular groove 8 are sequentially fed into the back along the groove 8 from the insertion opening 9 ( (See arrow in Figure 2).

その結果、バー部材13は円形溝8に沿って並列し円筒
体15を構成する。
As a result, the bar members 13 are arranged in parallel along the circular groove 8 and form a cylindrical body 15.

このようにしてから梁型枠4内にコンクリートを打設す
れば、この円筒体15がスリーブ材として作用し、コン
クリート硬化後染型枠4を固定具5とともに脱型した時
に第7図に示すように円筒体15内に貫通孔2が形成さ
れている。なお、円筒体15を形成するバー部材13は
バラにして撤去し、転用することができる。
If concrete is poured into the beam formwork 4 in this way, this cylindrical body 15 acts as a sleeve material, and when the concrete hardening formwork 4 is demolded together with the fixture 5, it is shown in FIG. A through hole 2 is formed in the cylindrical body 15 as shown in FIG. Note that the bar member 13 forming the cylindrical body 15 can be removed in pieces and reused.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明の鉄筋コンクリート梁の貫通孔
用型枠の形成方法は、梁型枠内で梁鉄筋を完全に又は大
部分組立てた後でも径の大きな貫通孔用型枠を簡単かつ
迅速に組立てることができ、スリーブ工事における施工
の工期の短縮やコストの削減等大巾な合理化をもたらす
ことができるものである。
As described above, the method for forming a formwork for a through-hole in a reinforced concrete beam of the present invention allows the formation of a formwork for a through-hole with a large diameter easily and quickly even after the beam reinforcing bars have been completely or mostly assembled within the beam formwork. It can be assembled in a number of ways, and can bring about significant streamlining such as shortening the construction period and cost in sleeve construction.

また、配筋等を乱すおそれがなく、梁鉄筋の精度向上に
もつながるものである。
In addition, there is no risk of disturbing the reinforcement arrangement, etc., and it also leads to improved precision of beam reinforcing bars.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の鉄筋コンクリート梁の貫通孔用型枠の
形成方法の1実施例を示す間断側面図、第2図は第1図
のA−A線断面図、第3図〜第5図は本発明の各工程を
示す側面図、第6図は固定具の斜視図、第7図は梁型枠
脱型後の斜視図、第8図は梁貫通孔の説明図である。 1・・・鉄筋コンクリート梁 2・・・貫通孔     3・・・スラブ4・・・梁型
枠 6・・・外リング 8・・・円形溝 10・・・取付フランジ 12・・・梁鉄筋 12b・・・スターラップ筋 12c・・・補強鉄筋 14・・・スラブ型枠 5・・・固定具 7・・・内リング 9・・・挿入口 11・・・針止め孔 12a・・・梁主筋 13・・・バー部材 15・・・円筒体
FIG. 1 is a cross-sectional side view showing one embodiment of the method for forming a formwork for through-holes in reinforced concrete beams according to the present invention, FIG. 2 is a cross-sectional view taken along line A-A in FIG. 1, and FIGS. 3 to 5 6 is a side view showing each step of the present invention, FIG. 6 is a perspective view of a fixture, FIG. 7 is a perspective view after removing the beam formwork, and FIG. 8 is an explanatory view of a beam through hole. 1... Reinforced concrete beam 2... Through hole 3... Slab 4... Beam formwork 6... Outer ring 8... Circular groove 10... Mounting flange 12... Beam reinforcing bar 12b. ... Stirrup bar 12c... Reinforcement bar 14... Slab formwork 5... Fixture 7... Inner ring 9... Insertion port 11... Needle hole 12a... Beam main bar 13 ... Bar member 15 ... Cylindrical body

Claims (1)

【特許請求の範囲】[Claims] 円形溝の上端外側部分に切欠き挿入口を有する円形チャ
ンネル材を固定具として相対向するように梁型枠の内側
面に取付け、切欠き挿入口を介してバー部材の両端を円
形溝内に差入れて固定具間に該バー部材を掛け渡し、か
つ先に掛け渡したバー部材を順次円形溝に沿って送り込
んで多数並列させて円筒体を形成することを特徴とした
鉄筋コンクリート梁の貫通孔用型枠の形成方法。
A circular channel material having a notch insertion hole at the outer part of the upper end of the circular groove is installed as a fixture on the inner surface of the beam formwork so as to face each other, and both ends of the bar member are inserted into the circular groove through the notch insertion hole. For through-holes in reinforced concrete beams, characterized in that the bar member is inserted and spanned between fixtures, and the previously spanned bar members are sequentially fed along a circular groove and arranged in large numbers in parallel to form a cylindrical body. How to form formwork.
JP63241775A 1988-09-27 1988-09-27 Forming method for through hole of reinforced concrete beam Expired - Lifetime JPH0663367B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63241775A JPH0663367B2 (en) 1988-09-27 1988-09-27 Forming method for through hole of reinforced concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63241775A JPH0663367B2 (en) 1988-09-27 1988-09-27 Forming method for through hole of reinforced concrete beam

Publications (2)

Publication Number Publication Date
JPH0288848A true JPH0288848A (en) 1990-03-29
JPH0663367B2 JPH0663367B2 (en) 1994-08-22

Family

ID=17079339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63241775A Expired - Lifetime JPH0663367B2 (en) 1988-09-27 1988-09-27 Forming method for through hole of reinforced concrete beam

Country Status (1)

Country Link
JP (1) JPH0663367B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6147345U (en) * 1984-08-31 1986-03-29 テイエム技研株式会社 Material of penetration sleeve
JPS6152034U (en) * 1984-09-11 1986-04-08

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6147345U (en) * 1984-08-31 1986-03-29 テイエム技研株式会社 Material of penetration sleeve
JPS6152034U (en) * 1984-09-11 1986-04-08

Also Published As

Publication number Publication date
JPH0663367B2 (en) 1994-08-22

Similar Documents

Publication Publication Date Title
KR102178763B1 (en) Connecting joint structure and connecting method of reinforced concrete column and installaion system of reinforced concrete column
JPH08128568A (en) Holder for sleeve pipe for hole construction in reinforced concrete structure and method for making hole in reinforced concrete structure using this holder
KR102545182B1 (en) Apparatus for fixing concrete form
JPH0663367B2 (en) Forming method for through hole of reinforced concrete beam
JP2009281011A (en) Joint structure of concrete building, and its construction method
JP2000240207A (en) How to install void members in hollow slabs
JP2025082502A (en) Method for constructing building and building
JPH05141040A (en) Precast concrete panel for building
JP6871808B2 (en) Reinforcing material, reinforcing structure
JP6464069B2 (en) Templates, template sets and reinforcement methods
JPH10305343A (en) Assembling device for reinforcing bars for segments
JP6902747B2 (en) Reinforced concrete column-beam joint structure and its construction method
KR100201538B1 (en) Pc beam and executing method of horizental structure work with it
JP7663463B2 (en) Concrete joint method for beam construction
JPH084203A (en) Steel rebar beam and its construction method
KR102106107B1 (en) Distance maintenance apparatus for mold
JP3853442B2 (en) Segment manufacturing formwork
JPH0744652Y2 (en) Mechanical joint hardware support structure
JPH03100242A (en) Joint structure between pillar and beam
JPH05214764A (en) Precast concrete beams
JPH0351849B2 (en)
JPS6133170Y2 (en)
JP2836409B2 (en) Construction method of reinforced concrete wall using PC version
JPH0726721A (en) Reinforcement sticking structure
JPH08128198A (en) Formwork sleeve