JPH03180526A - Simultaneous doffing of fine spinning frame or the like - Google Patents
Simultaneous doffing of fine spinning frame or the likeInfo
- Publication number
- JPH03180526A JPH03180526A JP31486789A JP31486789A JPH03180526A JP H03180526 A JPH03180526 A JP H03180526A JP 31486789 A JP31486789 A JP 31486789A JP 31486789 A JP31486789 A JP 31486789A JP H03180526 A JPH03180526 A JP H03180526A
- Authority
- JP
- Japan
- Prior art keywords
- spindle
- bobbin
- full
- cutter
- winding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009987 spinning Methods 0.000 title claims abstract description 30
- 238000004804 winding Methods 0.000 claims abstract description 34
- 238000005520 cutting process Methods 0.000 claims abstract description 23
- 238000000034 method Methods 0.000 claims description 25
- 230000008859 change Effects 0.000 claims description 10
- 230000008569 process Effects 0.000 claims description 10
- 238000003825 pressing Methods 0.000 claims description 2
- 230000000717 retained effect Effects 0.000 abstract 1
- 238000000926 separation method Methods 0.000 abstract 1
- 230000008901 benefit Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000284 extract Substances 0.000 description 2
- 244000144992 flock Species 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 238000003860 storage Methods 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000000151 deposition Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
Landscapes
- Replacing, Conveying, And Pick-Finding For Filamentary Materials (AREA)
- Spinning Or Twisting Of Yarns (AREA)
Abstract
Description
【発明の詳細な説明】
産業上の利用分野
本願は精紡機等の一斉管換方法更に詳しくは、−斉管換
時の尻糸の処理を確実適格に行なう方法に関する。DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to a method for simultaneously changing tubes of spinning machines, etc., and more particularly to a method for ensuring proper treatment of tail threads during simultaneous tube changes.
従来の技術とその問題点
一斉管換においてスピンドルがら満ボビンを抜き取った
後に、次の空ボビンに紡糸を巻取る際の緒糸の確保は極
めて重要で、これが完全に行なわれないと糸切れが発生
する。緒糸の確保を確実に行なう対策として従来は、ス
ピンドルの下部にウェストスプールを設け、このウェス
トスプールに巻き終りの尻糸を巻き付ける方式と、スピ
ンドル上のボビンが満ボビンになると胴巻きと尻巻を行
ない、満ボビンを抜き取る際にこの尻巻きを解きほぐし
ながら、ループ巻きとしてスピンドル上に捲回する方式
との二つの方式が採用されており、本願は上記二つの方
式のうち後者の改良に関するものである。Conventional technology and its problems After removing a full bobbin from the spindle in simultaneous tube change, it is extremely important to secure the yarn when winding the yarn onto the next empty bobbin.If this is not done completely, the yarn may break. Occur. Conventionally, as a measure to secure the yarn, a waist spool is installed at the bottom of the spindle, and the end of the yarn is wound on this waist spool, and when the bobbin on the spindle is full, the bobbin and the butt are wrapped. Two methods have been adopted: a method in which the bobbin is wound on the spindle as a loop winding while unwinding the end winding when a full bobbin is removed.The present application relates to an improvement of the latter of the above two methods. be.
上記第二の方式は第一の方式に比べ、スピンドルの全長
が短かいので回転が安定するのみならず消費電力が少な
く、ウェストスプールに巻き付いた尻糸処理の必要がな
い等の利点を有しているが、従来ループ巻のスピンドル
への撃留は、紡糸の毛羽による僅かな摩擦により行なっ
ていたので、しばしばループ巻がスピンドルから脱落す
るループ外れを起し、その対策として、例えば特開昭6
1−132642号に示すように、スピンドルとボビン
のスピンドルへの嵌合孔の所定の位置に、電気植毛等に
より短繊維を植毛した引掛具を取り付け(第7図、第8
図)、ループ外れを防止するとともに巻き付いているル
ープ巻の除去を容易にしたものが提案されている。黙し
ながらこれ等の改良手段は、スピンドルとボビン双方の
引掛具の植毛同志の摩擦により、植毛の損耗や脱落等が
生じ機能低下を来たして定期的に交換しなければならず
、必ずしも満足した結果が得られていない。Compared to the first method, the second method has advantages such as not only stable rotation but also less power consumption because the spindle has a shorter overall length, and there is no need to dispose of the tail thread wrapped around the waist spool. However, conventionally, the loop winding was held onto the spindle by slight friction caused by the fuzz of the spinning yarn, which often caused the loop winding to fall off the spindle. 6
As shown in No. 1-132642, a hook with short fibers flocked by electric flocking etc. is attached to a predetermined position of the fitting hole of the spindle and bobbin to the spindle (Figs. 7 and 8).
Figure) has been proposed that prevents the loop from coming off and makes it easy to remove the loop wound around it. However, these improvement measures are not always satisfactory, as friction between the flocks on the hooks of both the spindle and the bobbin causes the flocks to wear out or fall off, resulting in a decline in functionality and the need for periodic replacement. is not obtained.
問題点を解決するための手段
本願は上述した従来方式の問題点に臨み、スピンドル上
のボビンが満ボビンになると胴巻きと尻巻きを行ない、
満ボビンの抜き取りに伴って尻糸を解きほぐし、スピン
ドルにループ巻きを施して管換を行なう精紡機等の一斉
管換において、精紡機等の稼動中にスピンドルと巻取中
のボビン間に連なる緒糸をカッターで切断する工程、
スピンドル上のボビンが満ボビンになると停台させ、こ
の満ボビンをスピンドルから抜き取って預けペッグに挿
着する工程、
精紡機等に付設した管保持装置が保持している空ボビン
を抜き取り、この空ボビンをスピンドルに挿着してルー
プ巻きを押える工程。Means for Solving the Problems The present application addresses the problems of the conventional method described above, and when the bobbin on the spindle becomes full, the bobbin winding and the tail winding are performed.
In simultaneous tube change of spinning machines, etc., in which the tail thread is unraveled when a full bobbin is taken out, and the spindle is loop-wound to perform the tube change, the thread running between the spindle and the bobbin being wound is removed during the operation of the spinning machine, etc. The process of cutting the thread with a cutter, the process of stopping the bobbin on the spindle when it is full, and the process of removing the full bobbin from the spindle and inserting it into the deposit peg, and the process of holding the bobbin with a tube holding device attached to the spinning machine, etc. The process of removing the empty bobbin, inserting it into the spindle, and pressing down on the loop winding.
預けペッグに挿着した満ボビンを抜き取り。Remove the full bobbin inserted into the deposit peg.
この満ボビンを管保持装置に挿着するまでの間に、スピ
ンドルと満ボビン間に連なる尻糸をカッターで切断する
工程。Before inserting this full bobbin into the tube holding device, the step is to cut the tail thread that is connected between the spindle and the full bobbin with a cutter.
とからなる精紡機等の一斉管換方法により、ループ外れ
を完全に防止するとともに、スピンドル上の残糸の除去
を確実にして従来の問題点を除いたものである。This method completely prevents the loop from coming off, and also ensures the removal of the remaining yarn on the spindle, thereby eliminating the problems of the conventional method.
実施例 以下本願を、実施例を示す図面により詳細に説明する。Example The present application will be described in detail below with reference to drawings showing examples.
−斉管換装置は広く知られるように種々の形式のものが
採用され、管換方法も飛程々の工程からなるものが採用
されているがその要諦は。- As is widely known, various types of pipe switching equipment have been adopted, and pipe switching methods have been adopted that involve numerous steps, but what is the essence of it?
まず最初に、精紡機等が稼動中にスピンドルとボビン間
に連なる緒糸をカッターで切断しくこの切断によりスピ
ンドル上のループ巻は残糸となる〉。First, while the spinning machine or the like is in operation, the thread connected between the spindle and the bobbin is cut with a cutter, and the loop winding on the spindle becomes residual thread by this cutting.
その後、多数の管把持装置が取付けられたドツフィング
バーが、所定の順序で上下、揺動あるいは前後動を行な
い、スピンドル上の満ボビンを抜き取ってこのスピンド
ルに空ボビンを挿着するとともに、スピンドルと満ボビ
ン間に連なる尻糸をカッターで切断することにある。而
してこの尻糸切断用のカッター及び上記緒糸切断用のカ
ッターも種々提案されているが、以下本願実施例の説明
において一斉管換装置は、特開平1−3758号公報に
開示された装置を採用し、又尻糸切断用のカッターにつ
いては、特開昭60−81337号公報及び特開昭60
−185828号公報に開示されたものを、更に緒糸切
断用のカッターは、上記尻糸切断用のカッターに搭載し
たものについて述べるが、これ等夫々の装置の構成その
ものが本願の消長を左右するものではないので、以下の
説明において構成の詳細な説明は省略する。After that, a dotting bar equipped with a number of tube gripping devices moves up and down, swings, or back and forth in a predetermined order, extracts the full bobbin from the spindle, inserts an empty bobbin into this spindle, and removes the full bobbin from the spindle. The purpose is to cut the tail thread that runs between the full bobbin and the full bobbin with a cutter. Various cutters for cutting this tail thread and cutters for cutting the above-mentioned cord have also been proposed, but in the following description of the embodiments of the present application, a simultaneous pipe change device is disclosed in Japanese Patent Laid-Open No. 1-3758. Regarding the cutter for cutting the tail thread, Japanese Patent Application Laid-open No. 60-81337 and Japanese Patent Application Laid-Open No. 60-60
In addition to the cutter disclosed in Japanese Patent No. 185828, the cutter for cutting the webbing will be described as being mounted on the cutter for cutting the tail thread described above, but the structure of each of these devices itself will determine the pros and cons of the present application. Therefore, a detailed explanation of the configuration will be omitted in the following explanation.
第1図〜第3図において、1は精紡機、又2は精紡機1
のR,L両側(第2図において上下)に取付けられた一
斉管換装置で、該管換装置!2のドツフィングバー3に
はスピンドル39に対応させて多数の管把持装置14が
配設され、上下動装置i!5と揺動装w6とにより、後
に詳記する所定の順序に従って上下及び揺動運動を行な
って、満、空管の入換即ち管換を行ない1図面において
7は、各スピンドル39に対応して設けられた預けベツ
グである0次に8は精紡機1に付設した管保持装置で、
ガイドレール9内に、ペッグ11が突設されスピンドル
ピッチと等しい直径を持った多数のペッグトレイ10が
嵌装されており、図示を省略した駆動機構により間欠移
動を行ない、停止位置において上記ペッグ11がスピン
ドル39と上下に正対する。In Figures 1 to 3, 1 is a spinning machine, or 2 is a spinning machine 1
A simultaneous pipe switching device installed on both R and L sides (upper and lower in Figure 2) of the pipe switching device! A large number of tube gripping devices 14 are arranged on the dotting bar 3 of No. 2 in correspondence with the spindle 39, and a vertical movement device i! 5 and the swinging device w6 perform vertical and swinging movements in accordance with a predetermined sequence to be detailed later, thereby replacing full and empty pipes, that is, replacing the pipes. In one drawing, 7 corresponds to each spindle 39. The 0th order 8, which is the holding bed installed in the machine, is a tube holding device attached to the spinning machine 1.
A large number of peg trays 10 with protruding pegs 11 and having a diameter equal to the spindle pitch are fitted into the guide rail 9, and are intermittently moved by a drive mechanism (not shown), so that the pegs 11 are at the stop position. It directly faces the spindle 39 vertically.
次に、尻糸切断用のカッター12の概要について説明す
る。このカッター12は前記した特開昭60−8133
7号及び特開昭60−185828号に開示された装置
に、後記する緒糸切断用のカッター13を搭載したり、
回転刃14を片側−組にした等の変更はあるが、作動原
理は全て上記従来の装置と同様である。Next, the outline of the cutter 12 for cutting the tail thread will be explained. This cutter 12 is manufactured by the above-mentioned Japanese Patent Application Laid-open No. 60-8133.
No. 7 and Japanese Patent Application Laid-Open No. 60-185828, a cutter 13 for cutting cords, which will be described later, is installed,
Although there are some changes such as having the rotary blades 14 set on one side, the operating principle is all the same as that of the conventional device described above.
該尻糸切断用のカッター12は第3図及び第4図に示す
ように、精紡機台の前面に設けた案内レール15に走行
機体16を装架し、この走行機体16は第2図に示すよ
うに、GE、GE側に設けたプーリー17.17a間に
張設したロープ18に連結金具19(第4図)で連結さ
れ、モータ20の正逆回転によりスピンドル列に沿って
往復動する。この走行機体16の上部の第4図において
右側には二枚一対の回転刃14が回転自在に上下に枢着
され、この回転刃14は適度の接圧を持つてその一部分
が重合している。次に21は、上記回転刃14に駆動軸
22の回転を伝える駆動系で。As shown in FIGS. 3 and 4, the cutter 12 for cutting the tail yarn has a traveling body 16 mounted on a guide rail 15 provided in the front of the spinning machine stand, and this traveling body 16 is shown in FIG. As shown, it is connected by a connecting fitting 19 (Fig. 4) to a rope 18 stretched between the GE and pulleys 17 and 17a provided on the GE side, and is reciprocated along the spindle row by the forward and reverse rotation of the motor 20. . On the right side of the upper part of the traveling body 16 in FIG. 4, a pair of rotary blades 14 are rotatably vertically pivoted, and the rotary blades 14 have a moderate contact pressure and a portion of the levers overlap. . Next, 21 is a drive system that transmits the rotation of the drive shaft 22 to the rotary blade 14.
走行機体16の駆動軸22に取付けた■プーリー23と
、下側の回転刃14に取付けた■プーリー24との間に
一対の中間Vプーリー25.26を設け、これ等のVプ
ーリー23.24,25.26間にベルト27を夫々張
設して構成されているが、ベルト27の張設は、走行機
体12が第1図において左側GEから右側OEに走行し
た際回転カニ4が、第4図矢印で示すように互いに物を
引き込む方向に回転するようになされている。緒糸切断
用のカッター13はこの尻糸切断用のカッター12に搭
載されており、その概要は次の通りである。第3図にお
いて、28は、走行機体16に回動可能に支承した駆動
軸で、走行機体16の精紡機1側に突出した軸端にはロ
ーラ30を枢支した駆動腕29が、又反対側の軸端には
ピニオン31が取付けられ、このピニオン31は、走行
機体16に所定範囲の上下動が可能に支承されたラック
パー32に噛合している。次に33は、走行機体16に
回動自在に枢支したセクタータイプのピニオンで、上記
したラックパー32の上部に噛合しており、このピニオ
ン33には先端に切断刃34を有する腕杆35が取付け
られている。走行機体16は上記したように、案内レー
ル15に案内されスピンドル列に沿って第1図において
左右に走行し、左右夫々の待機位置において所定時まで
待機するが、夫々の待機位置に至ると駆動腕29のロー
ラ30が図示を省略した回動部材に当り、駆動腕29を
交互に所定角度宛正逆回転(第4図)させ、これにより
腕杆35は第3図に実線で示す作用位置と、仮想線で示
す収納位置とに回動し。A pair of intermediate V pulleys 25 and 26 are provided between the ■ pulley 23 attached to the drive shaft 22 of the traveling body 16 and the ■ pulley 24 attached to the lower rotary blade 14, and these V pulleys 23, 24 , 25 and 26, respectively. The tensioning of the belt 27 is such that when the traveling body 12 travels from the left side GE to the right side OE in FIG. As shown by the arrows in Figure 4, they rotate in the direction of drawing objects into each other. A cutter 13 for cutting the cord is mounted on the cutter 12 for cutting the tail thread, and its outline is as follows. In FIG. 3, reference numeral 28 denotes a drive shaft rotatably supported on the traveling body 16. At the shaft end of the traveling body 16 protruding toward the spinning machine 1 side, there is a drive arm 29 on which a roller 30 is pivotally supported; A pinion 31 is attached to the side shaft end, and this pinion 31 meshes with a rack par 32 supported by the traveling body 16 so as to be able to move up and down within a predetermined range. Next, 33 is a sector type pinion that is rotatably supported on the traveling body 16 and meshes with the upper part of the rack parr 32 described above, and this pinion 33 has an arm rod 35 having a cutting blade 34 at the tip. installed. As described above, the traveling body 16 is guided by the guide rail 15 and travels left and right in FIG. 1 along the spindle row, and waits at the left and right standby positions until a predetermined time. The roller 30 of the arm 29 hits a rotating member (not shown), causing the driving arm 29 to alternately rotate forward and backward at a predetermined angle (FIG. 4), thereby moving the arm rod 35 to the operating position shown by the solid line in FIG. 3. and the storage position shown by the imaginary line.
本実施例では、第1図において右側OEの待機位置にお
いて作用位置になり、左側GEの待機位置で収納位置と
なる。In this embodiment, in FIG. 1, the standby position of the right side OE is the working position, and the standby position of the left side GE is the storage position.
以上の如くにおいて、本願管換方法は以下の如くに行な
われ、この管換方法を第9図に示す作動説明図によって
順に説明する。精紡機1が稼動中。In the above manner, the pipe changing method of the present invention is carried out as follows, and this pipe changing method will be explained in order with reference to the operation diagram shown in FIG. Spinning machine 1 is in operation.
ドツフィングバー3は第3図に示すようにスピンドル3
9下方の待機位置に待機し、ペッグトレイ10のペッグ
11には空ボビン36が挿着されている。第9図Aに示
すようにスピンドル39上のボビン36Aが略五分玉3
8に達しリングレール40が上昇すると精紡機のGE側
に待機していたカッター12が走行を開始し、緒糸切断
用のカッター13により順次緒糸42A(第6図)を切
断する。この切断作業により、先の管換によりスピンド
ル39に捲回されて緒糸42Aとなり、更に巻取中の紡
糸41に連なっているループ巻42は紡糸41との関係
が断たれて、スピンドル39に捲き付いた残余となり、
カッター12は上記と反対側において次の作業を待機す
る(第9図A)。The dotting bar 3 is connected to the spindle 3 as shown in FIG.
9, and an empty bobbin 36 is inserted into the peg 11 of the peg tray 10. As shown in FIG. 9A, the bobbin 36A on the spindle 39 is approximately 3
8 and the ring rail 40 rises, the cutter 12 that has been waiting on the GE side of the spinning machine starts running, and the webbing cutter 13 sequentially cuts the webbing 42A (FIG. 6). Through this cutting operation, the yarn 42A is wound around the spindle 39 due to the previous tube exchange, and the loop winding 42 connected to the spinning yarn 41 being wound is severed from the spinning yarn 41, and the loop winding 42 is wound onto the spindle 39. It becomes a rolled-up residue,
The cutter 12 waits for the next operation on the opposite side (FIG. 9A).
この時カッター13は、上記したように第3図仮想線の
収納位置となる。スピンドル39上のボビンが満ボビン
37になると、リングレール4oを操作して胴巻43と
尻巻44とが行なわれる(第3図)。次いで待機位置に
あるドツフィングバー3が、大きく機台より遠ざかる方
向〔以後(−)側と称す〕に揺動した後上昇し、機台に
接近する方向〔以後(+)側と称す〕に揺動して更に下
降動作を行ない、管把持装置4が満ボビン37を把持す
る(第9図B)、ドツフィングバー3が上昇してスピン
ドル39から満ボビン37を抜き取り、この抜き取り動
作により上記のように残糸としてスピンドル39に捲回
しているループ巻42は、ボビン36Aに取付けられた
引掛具45(第8図)に引掛けられボビン36Aの孔内
に係止保持されてスピンドル39より除去される。又満
ボビン37の抜き取りにより尻巻44が解きほぐされ、
残余(先のループ巻42)を取り除いたスピンドル39
にループ巻42として捲回する(第9図C)。At this time, the cutter 13 is in the retracted position indicated by the imaginary line in FIG. 3, as described above. When the bobbin 37 on the spindle 39 is full, the ring rail 4o is operated to perform the bobbin winding 43 and the tail winding 44 (FIG. 3). Next, the dotting bar 3 in the standby position swings greatly in the direction away from the machine base [hereinafter referred to as the (-) side], then rises, and moves in the direction closer to the machine base [hereinafter referred to as the (+) side]. The tube gripping device 4 grips the full bobbin 37 by swinging and further lowering the bobbin 37 (FIG. 9B), the dotting bar 3 rises and extracts the full bobbin 37 from the spindle 39, and this removing operation causes the above-mentioned The loop winding 42 wound around the spindle 39 as a residual thread is hooked onto a hook 45 (FIG. 8) attached to the bobbin 36A and held in the hole of the bobbin 36A, so that the loop winding 42 is wound on the spindle 39 as a residual yarn. removed. Also, by removing the full bobbin 37, the buttband 44 is unraveled,
Spindle 39 from which the remainder (previous loop winding 42) has been removed
It is wound as a loop winding 42 (FIG. 9C).
満ボビン37を抜き取ったドツフィングバー3は少許ば
かり(−)側に揺動した後下降動作を行ない1把持して
いる満ボビン37を預けペッグ7に挿着し、これにより
満ボビン37から引きほどかれた尻糸46は、満ボビン
37からアンチノードリング47を経てスピンドル39
に、至り、紡糸41はスピンドル39にループ巻42と
して捲回した後トラベラ−48を経てドラフトパート4
9に至っているが、該ループ巻42はスピンドル39と
アンチノードリング47間に張り渡されている尻糸46
により、引張られるような形で僅かな張力が与えられて
いるのでループ外れは発生しない(第9図D)。The dotting bar 3 that has taken out the full bobbin 37 swings a little to the (-) side, then performs a downward movement, inserts the full bobbin 37 that is being gripped into the holding peg 7, and thereby pulls it out from the full bobbin 37. The unraveled tail thread 46 passes from the full bobbin 37 to the anti-node ring 47 to the spindle 39.
Finally, the spinning yarn 41 is wound around the spindle 39 as a loop winding 42, and then passed through the traveler 48 to the draft part 4.
9, the loop winding 42 is connected to the tail thread 46 stretched between the spindle 39 and the anti-node ring 47.
As a result, a slight tension is applied in such a way that the loop is pulled, so no loop disconnection occurs (FIG. 9D).
その後ドツフィングバー3が上昇し更に(−)側に揺動
を行ない1次いで大きく下降し続いて大きく(+)側に
揺動し、最後に少許ばかり下降動作を行なって空ボビン
36を把持する(第9図E)、空ボビン36を把持した
ドツフィングバー3は、少許ばかり上昇して空ボビン3
6をペッグトレイ10から抜き取り、次いで大きく(−
)側に揺動して更に最上昇位置に上昇し、該上昇位置か
ら大きく(+)側に揺動した後下降動作を行ない、把持
している空ボビン36をスピンドル39に挿着する。而
してスピンドル39には上記したようにループ巻42が
施されているが、このループ巻42は挿着された仝ボビ
ン36とスピンドル39間に挟まれて押えられ、後に述
べる再起動時の緒糸42Aは確実に確保される(第9図
F)、空ボビン36を挿着したドツフィングバー3は、
少許ばかり上昇及び(−)側に揺動した後に下降し、預
けペッグ7上の満ボビン37を把持する1次いでドツフ
ィングバー3が最上昇位!まで上昇した後頁に(−)側
に揺動することにより、尻糸46は満ボビン37からア
ンチノードリング47を経てスピンドル39間に斜めに
張り渡され、紡糸41はループ巻42からトラベラ−4
8を通ってドラフトパート47に連なっている(第9図
G)、このように解きほぐされた尻糸46が張り渡され
ると、上記において緒糸42Aを切断し、精紡機lのG
E側で待機していたカッター12が再びスピンドル列に
沿って走行を行ない、満ボビン3フとスピンドル39間
の尻糸46を切断する。而してこの切断は1回転刃14
の回転が前記の如くであるから、張り渡されている尻糸
46を引き込むようにしてくわえ込み確実に切断する(
第9図H)。After that, the dotting bar 3 rises, further swings to the (-) side, then descends greatly, then swings greatly to the (+) side, and finally performs a slight downward movement to grip the empty bobbin 36. (Fig. 9E), the dotting bar 3 that grips the empty bobbin 36 rises a little and moves the empty bobbin 3
6 from the peg tray 10, then large (-
) side and further rises to the highest position, and after swinging greatly from the raised position to the (+) side, a downward movement is performed to insert the empty bobbin 36 being held into the spindle 39. The loop winding 42 is applied to the spindle 39 as described above, and this loop winding 42 is held between the inserted bobbin 36 and the spindle 39, and is held down during restart as described later. The thread 42A is securely secured (FIG. 9F), and the dotting bar 3 into which the empty bobbin 36 is inserted is
After rising a little and swinging to the (-) side, it descends, and the first dotting bar 3, which grips the full bobbin 37 on the deposit peg 7, reaches its highest position! By swinging to the (-) side after rising to the page, the tail thread 46 is stretched obliquely between the spindles 39 from the full bobbin 37 via the anti-node ring 47, and the spinning thread 41 is passed from the loop winding 42 to the traveler. 4
8 to the draft part 47 (FIG. 9G). When the tail thread 46 unraveled in this way is stretched, the thread 42A is cut in the above manner, and
The cutter 12 that was waiting on the E side runs along the spindle row again and cuts the tail thread 46 between the full bobbin 3f and the spindle 39. Therefore, this cutting is performed with one rotation of the blade 14.
Since the rotation is as described above, hold it in your mouth so as to pull in the stretched tail thread 46 and cut it securely (
Figure 9H).
尻糸46が切断されるとドツフィングバー3は下降し1
次いで大きく(+〉側に揺動した後、少許ばかり下降し
把持している満ボビン37をペッグトレイ10のベツグ
11に挿着し、その後僅かに上昇し又待機位置に復する
(第9図工)、なお。When the tail thread 46 is cut, the doffing bar 3 descends to 1
Next, after swinging greatly to the (+> side), it descends a little and inserts the full bobbin 37 it is gripping into the beng 11 of the peg tray 10, and then rises slightly and returns to the standby position (Fig. 9) ,In addition.
上記方法において、空ボビン36をスピンドル39に挿
着するときに管把持装置によって空ボビン36の頭を智
把持装置4によって押え込んでも良いが、それに代えて
上記ドツフィングバー3の特撮位置への復帰動作に先立
ち、ドツフィングバー3の管把持装置4を再びスピンド
ル39に挿着した空ボビン36の頭の上へ移動させ、管
把持装置4によって空ボビン36の頭を押え込むように
しても良い。In the above method, when inserting the empty bobbin 36 into the spindle 39, the head of the empty bobbin 36 may be held down by the pipe gripping device 4, but instead of this, the dotting bar 3 may be moved to the special position. Prior to the return operation, the tube gripping device 4 of the dotting bar 3 may be moved again onto the head of the empty bobbin 36 inserted into the spindle 39, and the tube gripping device 4 may press down the head of the empty bobbin 36.
以上において管換動作の一サイクルは終了し、精紡機1
は再起動を行なうがこの時リングレール40は第9図工
に示すように空ボビン36の下端部付近にありこのまま
では巻取りができないので、再起動に先立ってリングレ
ール40を少許ばかり上昇させて再起動を行ない、この
上昇により、第9図工に示す状態でスピンドル39とト
ラベラ−48間に張り渡されている紡糸41は、空ボビ
ン36の外周面に略沿うような形で接近し、再起動に当
っては、この部分が第eyhピ示す緒糸42Aとなって
巻き取りが行なわれ、この緒糸42Aは前記したように
、巻き量が所定量に達した時に緒糸切断用のカッター1
3により切断される。又スピンドル39に連なっている
尻糸46の切断端(第9図Iにおいてスピンドル39と
アンチノードリング17に引掛っている部分)は、スピ
ンドル39の回転によりほぐれて風綿となって飛散する
。With the above steps, one cycle of tube change operation is completed, and the spinning machine 1
At this time, the ring rail 40 is near the lower end of the empty bobbin 36 as shown in Figure 9, and winding cannot be done in this state, so the ring rail 40 must be raised a little before restarting. The restart is performed, and as a result of this rise, the spinning yarn 41 stretched between the spindle 39 and the traveler 48 in the state shown in Fig. 9 approaches the empty bobbin 36 in a manner substantially along the outer circumferential surface of the empty bobbin 36, and is restarted. At startup, this part becomes the webbing 42A shown in step eyh and is wound, and as described above, this webbing 42A is cut by a cutter for cutting the webbing when the amount of winding reaches a predetermined amount. 1
3. Further, the cut end of the tail thread 46 connected to the spindle 39 (the part hooked on the spindle 39 and the antinode ring 17 in FIG. 9I) is loosened by the rotation of the spindle 39 and scattered as fluff.
上記実施例において、尻糸切断用のカッター12は、ス
ピンドル列に沿って走行しながら張り渡されている尻糸
46を順次切断するものについて述べたが、本願の実施
はこれにか限るものでなく、各スピンドル39に対応さ
せ各個に独立又は連動して作用する鋏又はナイフ等のカ
ッターを設け、各尻糸46を順次又は−斉に切断しても
よく、又緒糸切断用のカッター13についても同様であ
り。In the above embodiment, the cutter 12 for cutting the tail threads was described as one that sequentially cuts the stretched tail threads 46 while running along the spindle row, but the implementation of the present application is not limited to this. Alternatively, a cutter such as scissors or a knife may be provided corresponding to each spindle 39 and act independently or in conjunction with each other to cut the tail threads 46 sequentially or simultaneously. The same applies to
例えば特開平1−2080号に示すように独立して作用
するものであっても本願の目的を達し、要は所定の時期
に所定の位置で尻糸46及び緒糸42Aを切断し得るも
のであれば構成は問わない。For example, as shown in Japanese Unexamined Patent Application Publication No. 1-2080, even if the device acts independently, the purpose of the present application is achieved, and the point is that it can cut the tail thread 46 and the webbing thread 42A at a predetermined position at a predetermined time. If so, the configuration does not matter.
発明の効果
本願は以上詳述したように、スピンドルから抜き取った
満ボビンの尻糸を切断することなく預けペッグに一旦預
けるので、スピンドルに捲回しているループ巻は、スピ
ンドルよりアンチノードリングを経て満ボビンに連なる
尻糸の張力により、従来装置の如く引掛具を要せずして
ループ外れを起すことなく、更にこの状態のスピンドル
に空ボビンを挿着し、その後に尻糸の切断を行なう工程
を採用したので、尻糸切断時のショックによるループ外
れは発生すべくもなく、緒糸は確実に確保されて糸切れ
は発生しない。Effects of the Invention As detailed above, in the present application, the tail thread of a full bobbin extracted from the spindle is temporarily deposited in the deposit peg without cutting it, so that the loop winding on the spindle is passed through the anti-node ring from the spindle. Due to the tension of the tail thread connected to the full bobbin, an empty bobbin can be inserted into the spindle in this state, and the tail thread can then be cut, without requiring a hooking tool or causing the loop to come off like in conventional devices. Since this process is adopted, there is no possibility that the loop will come off due to shock when the tail thread is cut, and the thread is securely secured and no thread breakage occurs.
更に本願方法においては、スピンドル上のボビンが所定
の巻量に達すると緒糸を切断し、先の着換時のループ巻
を残糸とすることと、上記のようにスピンドルに引掛具
を必要としないことの双方の作用により、満ボビン抜き
取り時に行なう残糸の除去はその都度確実に行なわれ、
スピンドル上に残留したり紡糸に絡み付いたりすること
なく。Furthermore, in the present method, when the bobbin on the spindle reaches a predetermined winding amount, the yarn is cut, the loop winding from the previous change is used as the remaining yarn, and a hooking device is required on the spindle as described above. Due to the effects of both the above and the above, the removal of the remaining thread when unloading a full bobbin is carried out reliably each time.
without remaining on the spindle or getting tangled in the spinning yarn.
後に行なわれるワインダー工程で口出し作業の妨げとな
らない。It does not interfere with the opening work in the winder process that will be performed later.
最後に本願方法のもう一つの利点は、上記の説明から明
らかなように、既設の機台でも容易に実施し得ることで
ある。Finally, another advantage of the present method is that, as is clear from the above description, it can be easily implemented on existing machines.
図面は本願実施例を示し、第1図は精紡機の概略正面図
、第2図は第1図の平面図、第3図は第2図の■−■線
断面図、第4図は精紡機側から見たカッターの正面図、
第5図は満ボビンの抜き取り状態を示す部分図、第6図
は五分玉でリングレールが上昇状態を示す部分図、第7
図は従来のスピンドルを示し、第8図は空ボビンの断面
図、第9図A−Iは作動説明図である。
1・・・精紡機、2・・・−斉管換装置、3・・・ドツ
フィングバー 7・・・預けベツグ、12・・・尻糸切
断用カッター、13・・・緒糸切断用カッター 36・
・・空ボビン、37・・・満ボビン、39・・・スピン
ドル、42・・・ループ巻、42A・・・緒糸、43・
・・胴巻、44・・・尻巻、46・・・尻糸The drawings show the embodiment of the present application, and FIG. 1 is a schematic front view of the spinning machine, FIG. 2 is a plan view of FIG. 1, FIG. 3 is a sectional view taken along the line ■-■ of FIG. Front view of the cutter seen from the spinning machine side,
Fig. 5 is a partial view showing the full bobbin being removed, Fig. 6 is a partial view showing the ring rail in the raised state with a quintile, and Fig. 7
The figures show a conventional spindle, FIG. 8 is a sectional view of an empty bobbin, and FIG. 9 A-I is an explanatory view of the operation. DESCRIPTION OF SYMBOLS 1... Spinning machine, 2... - Simultaneous pipe change device, 3... Dotting bar 7... Depositing bed, 12... Cutter for cutting the tail thread, 13... Cutter for cutting the cord 36・
... Empty bobbin, 37... Full bobbin, 39... Spindle, 42... Loop winding, 42A... Thread, 43.
... body wrap, 44... butt wrap, 46... butt thread
Claims (1)
尻巻きを行ない、満ボビンの抜き取りに伴って尻糸を解
きほぐし、スピンドルにループ巻を施して管換を行なう
精紡機等の一斉管換において、巻き量が所定量に達した
時、精紡機等の稼動中にスピンドルと巻取中のボビン間
に連なる緒糸をカッターで切断する工程、 スピンドル上のボビンが満ボビンになると停台させ、こ
の満ボビンをスピンドルから抜き取って預けペッグに挿
着する工程、 精紡機等に付設した管保持装置が保持している空ボビン
を抜き取り、この空ボビンをスピンドルに挿着してルー
プ巻きを押える工程、預けペッグに挿着した満ボビンを
抜き取り、この満ボビンを管保持装置に挿着するまでの
間に、スピンドルと満ボビン間に連なる尻糸をカッター
で切断する工程、 とからなる精紡機等の一斉管換方法。[Scope of Claims] 1. A spinning machine, etc. that performs bodice winding and tail winding when the bobbin on the spindle becomes full, unwinds the tail thread as the full bobbin is removed, and performs loop winding on the spindle to change the tube. In simultaneous tube change, when the amount of winding reaches a predetermined amount, the process of using a cutter to cut the continuous yarn between the spindle and the bobbin being wound while the spinning machine is in operation, and the bobbin on the spindle becomes full. When this happens, the machine is stopped, the full bobbin is removed from the spindle and inserted into the deposit peg, and the empty bobbin held by the tube holding device attached to the spinning machine is removed and the empty bobbin is inserted into the spindle. A process of pressing down the loop winding, a process of removing the full bobbin inserted in the deposit peg, and cutting the tail thread connected between the spindle and the full bobbin with a cutter before inserting the full bobbin into the tube holding device. A simultaneous tube change method for spinning machines, etc.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31486789A JPH03180526A (en) | 1989-12-04 | 1989-12-04 | Simultaneous doffing of fine spinning frame or the like |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31486789A JPH03180526A (en) | 1989-12-04 | 1989-12-04 | Simultaneous doffing of fine spinning frame or the like |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH03180526A true JPH03180526A (en) | 1991-08-06 |
Family
ID=18058577
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP31486789A Pending JPH03180526A (en) | 1989-12-04 | 1989-12-04 | Simultaneous doffing of fine spinning frame or the like |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH03180526A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6874654B2 (en) * | 2000-07-07 | 2005-04-05 | Intier Automotive Inc. | Apparatus for exchanging bobbins |
-
1989
- 1989-12-04 JP JP31486789A patent/JPH03180526A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6874654B2 (en) * | 2000-07-07 | 2005-04-05 | Intier Automotive Inc. | Apparatus for exchanging bobbins |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4083171A (en) | Method and apparatus for eliminating an abnormality in a thread to be wound onto the bobbin of an open-end spinning device | |
| CZ269495A3 (en) | Process and apparatus for for spinning yarn on a rotor spinning machine | |
| JPS5971430A (en) | Improved apparatus for connecting yarn in open end spinning frame and doffing yarn package | |
| US5356085A (en) | Method and apparatus for treating package yarn end | |
| JP3698873B2 (en) | Yarn package forming method and forming apparatus | |
| JPH03180526A (en) | Simultaneous doffing of fine spinning frame or the like | |
| US3043529A (en) | Apparatus for preparing coils of yarn for further fabrication | |
| JP3114911B2 (en) | Cutting method of tail thread in simultaneous re-exchange of spinning machines | |
| JPH08100335A (en) | Simultaneous cop-change of fine spinning frame | |
| JPH10109830A (en) | Doffing method for spinning machine | |
| JPH0712885B2 (en) | Winding method, device and product obtained thereby | |
| CN103010832A (en) | Rolling unit and yarn rolling machine | |
| CN213037119U (en) | Cotton yarn branching device | |
| JPH02127368A (en) | Rough yarn exchanging method for fine spinning machine | |
| CN210456980U (en) | Thread hooking and breaking device of automatic doffing machine | |
| JPS6366334A (en) | Removing method for tail wound yarn and device therefor in spinning machine | |
| JPH0411652B2 (en) | ||
| JPH0426458Y2 (en) | ||
| JPH06158450A (en) | Tail yarn cutting device for fine spinning machine with simultaneous doffer | |
| JPS60144280A (en) | Spun yarn wind-up device | |
| JPH0930732A (en) | Yarn winding device | |
| TWM582966U (en) | Hooking filament break device of automatic doffing machine | |
| JPH06313220A (en) | Yarn knotter for end yarn in yarn package | |
| JPS5994625A (en) | Yarn handling apparatus in automatic doffing machine | |
| JPS61160432A (en) | Doffing in spinning frame |