JPH03217559A - How to assemble beam reinforcements - Google Patents

How to assemble beam reinforcements

Info

Publication number
JPH03217559A
JPH03217559A JP1389890A JP1389890A JPH03217559A JP H03217559 A JPH03217559 A JP H03217559A JP 1389890 A JP1389890 A JP 1389890A JP 1389890 A JP1389890 A JP 1389890A JP H03217559 A JPH03217559 A JP H03217559A
Authority
JP
Japan
Prior art keywords
reinforcement
unit
assembled
reinforcing bars
reinforcements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1389890A
Other languages
Japanese (ja)
Inventor
Kazuo Sakamoto
和夫 坂本
Masashi Adachi
安達 昌史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP1389890A priority Critical patent/JPH03217559A/en
Publication of JPH03217559A publication Critical patent/JPH03217559A/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、大型機械台基礎や架台、大型建築物の地中梁
などを構築する場合の梁筋の組立方法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for assembling beam reinforcements when constructing large machine platform foundations, frames, underground beams for large buildings, and the like.

〔従来の技術〕[Conventional technology]

従来、鉄筋コンクリート造による建築物の梁構築に際し
て、一般には型枠の組み建て作業によって梁型枠を組み
、この梁型枠内に上端筋、下端筋、スタラップなどの所
定の鉄筋を配筋するとともに、スラブ筋、柱筋、梁がか
かる他の梁の梁筋などに連結して、梁筋が組み上げられ
ている。そして梁に貫通孔を設けたり埋設配管するなど
の場合は、梁型枠上で梁筋を組み立ててスリーブや配管
を取付固定し、その後に梁筋を梁型枠内に落とし込んで
いる。
Conventionally, when constructing beams for buildings made of reinforced concrete, the beam formwork is generally assembled by formwork erection work, and predetermined reinforcing bars such as top end reinforcement, bottom end reinforcement, stirrup, etc. are arranged within this beam formwork. , beam reinforcements are assembled by connecting them to slab reinforcements, column reinforcements, and beam reinforcements of other beams on which the beam rests. In the case of providing through holes in a beam or installing buried piping, the beam reinforcements are assembled on the beam form, the sleeves and piping are attached and fixed, and then the beam reinforcement is dropped into the beam form.

また、ビルや住宅などの一般建築物とは異なって大型機
械台基礎や架台、大型建築物の地中梁などを構築する場
合は、梁筋の組立作業は大規模なものとなっており、ま
ず梁構築部分に、鉄筋受け台および配筋作業足場を組み
、上端筋や下端筋などの鉄筋をクレーンなどの揚重機に
よって吊り込みながらそれぞれを所定位置にセントし鉄
筋工によって結束している。モして配筋後、構築物の用
途に応じた加工がなされる。例えば梁天面などに表出す
るようにアンカーボルトを埋設したり、埋め込み金物や
スリーブを取り付けるなどの加工が行われる。そののち
前記配筋作業足場を解体して梁型枠を組上げる手順とな
っていた。
In addition, unlike general structures such as buildings and houses, when constructing large machine platform foundations, trestles, and underground beams for large buildings, the beam reinforcement assembly work is large-scale. First, a reinforcing bar pedestal and a reinforcement work scaffold are assembled in the beam construction area, and the reinforcing bars, such as the upper end reinforcement and lower end reinforcement, are lifted by a lifting machine such as a crane, and each is placed in a predetermined position and tied together by a reinforcing bar worker. After reinforcement is placed, processing is performed according to the purpose of the structure. For example, processes such as burying anchor bolts so that they are visible on the top of a beam, or attaching embedded hardware or sleeves are performed. The procedure was then to dismantle the reinforcement work scaffold and assemble the beam formwork.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかしながら、上記した大規模な梁構築の場合には、配
筋を行うための数多くの鳶工、鉄筋工が必要であり、ま
た各鉄筋の重量が大きくて手持ち作業することができず
揚重機を長時間使用しなければならなかった。さらには
各種の加工が完了するまで工事現場での高所作業が連続
し、安全作業の確保が難しいという問題がある。そして
梁構築部分までの材料搬入や他の部分の進行度合いとの
兼ね合いなどによって梁筋組立完了までに可なりの日数
を要するという問題もあった。
However, in the case of large-scale beam construction as described above, a large number of steel workers and reinforcing bar workers are required to arrange the reinforcement, and each reinforcing bar is so heavy that it cannot be carried out by hand, so a lifting machine is required. Had to use it for a long time. Furthermore, there is the problem that work at high places at construction sites continues until various types of processing are completed, making it difficult to ensure safe work. There was also the problem that it took a considerable number of days to complete the beam reinforcement due to factors such as bringing in materials to the beam construction section and the progress of other sections.

そこで本発明は、構外地組ヤード、すなわち建築作業現
場以外の場所で梁筋を独立したユニットとして組み上げ
るようにし、組み上げられたこの梁筋ユニットを梁構築
部分に据え付けして、現場にて梁筋が簡単に組み立てら
れるようにすることを課題とし、梁筋組立作業の省力化
、躯体工事の短縮化を図ることを目的とする。
Therefore, in the present invention, the beam reinforcements are assembled as independent units in an off-site assembly yard, that is, a place other than the construction work site, and the assembled beam reinforcement units are installed in the beam construction area, and the beam reinforcements are assembled on-site. The objective is to make it easier to assemble the beams, and to save labor in beam assembly work and shorten the time required for frame construction.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は、上記した課題を考慮してなされたもので、複
数列にして梁の長手方向に配列した複数本の支柱を相互
に連結し、梁の上端筋を受ける受材と下端筋を受ける受
材とを梁の幅方向に備える支持フレームを、構外地組ヤ
ードにて組み、前記支持フレームに、梁を渡すスパンに
対応して設定された下端筋、上端筋、腹筋、スタラップ
などの鉄筋を配筋固定して梁筋ユニットを組上げ、前記
梁筋ユニットを梁構築部へ搬入して据付したのち、前記
梁筋ユニットの端部側の鉄筋それぞれを、既設鉄筋と連
結することによって、梁筋の組立を完了し、上記課題を
解消するものである。
The present invention has been made in consideration of the above-mentioned problems, and involves interconnecting a plurality of columns arranged in a plurality of rows in the longitudinal direction of a beam, and receiving a receiving member for receiving the upper end reinforcement of the beam and a receiving member for receiving the lower end reinforcement of the beam. A support frame with receiving materials in the width direction of the beam is assembled in an off-site construction yard, and reinforcing bars such as lower end reinforcement, upper end reinforcement, abdominal reinforcement, stirrup, etc. are set on the support frame in accordance with the span across which the beam is passed. After fixing the reinforcement and assembling the beam reinforcement unit, transporting the beam reinforcement unit to the beam construction department and installing it, the beam This completes the assembly of the striations and solves the above problem.

〔作 用〕[For production]

本発明においては、構外地組ヤードにて建築作業現場と
は別途に梁筋ユニットが組み上げられ、完成した梁筋ユ
ニットを建築作業現場の梁構築部に搬入据付し、梁筋ユ
ニソトの鉄筋の連結が行われるものであり、構外地組ヤ
ードにおいて、すなわち建築作業現場とは異なる場所に
おいて、まず鉄筋を支えるための支持フレームが組まれ
、この支持フレームに各種の鉄筋を配筋固定し、そして
アンカーボルトやスリーブ、電線管などの管材、埋込金
物などの取付が必要であればそれらを取り付けることに
より、梁筋ユニットが組み上げられる。
In the present invention, the beam reinforcement unit is assembled separately from the construction work site in an off-site assembly yard, and the completed beam reinforcement unit is carried and installed in the beam construction department of the construction work site, and the reinforcement of the beam reinforcement UNISOTO is connected. This is done in an off-site assembly yard, that is, in a location different from the construction work site, where a support frame is first constructed to support the reinforcing bars, various types of reinforcing bars are arranged and fixed to this support frame, and then anchors are attached. The beam reinforcement unit is assembled by attaching bolts, sleeves, pipe materials such as electrical conduits, embedded hardware, etc., if necessary.

前記梁筋ユニットは、建設する建築物の梁構築部分の全
て、または特定された部分に対応して組み上げられるも
のであり、複数の梁筋ユニットが用意される。梁筋ユニ
ットはそれぞれが据え付けする梁構築部分の状況に対応
するように組み上げられる。すなわち二体の梁筋ユニッ
トを直角にして連続させる場合のように、粱筋ユニット
相互の重なり部分などで一方の梁筋ユニットの据え付け
が不可能とならないよう、据え付け手順や状況に応じて
上端筋や上面側のスタラップを配筋しない状態で組上げ
る梁筋ユニットもある。
The beam reinforcement unit is assembled to correspond to all or a specified portion of the beam construction portion of the building to be constructed, and a plurality of beam reinforcement units are prepared. Each beam reinforcement unit is assembled to correspond to the situation of the beam construction part to be installed. In other words, as in the case where two beam reinforcement units are connected at right angles, the upper end reinforcement should be adjusted according to the installation procedure and situation so that one beam reinforcement unit does not become impossible to install due to the overlap between the two beam reinforcement units. There is also a beam reinforcement unit that is assembled without reinforcing the stirrup on the top side.

こうして得られた梁筋ユニットをトラックなどの手段を
用いて建築作業現場に搬入し、揚重機などで梁構築部に
吊り込んで据え付けする。据え付けの後は、梁筋ユニッ
トと他の梁筋ユニットや柱筋などの既設鉄筋と連結して
梁筋の組立が終了し、梁型枠の組み建て作業、コンクリ
ート打設作業を経て建築物が構築されていくようになる
The beam reinforcement unit thus obtained is transported to a construction work site using means such as a truck, and is hung onto a beam construction section using a lifting machine or the like and installed. After installation, the beam reinforcement units are connected to existing reinforcement such as other beam reinforcement units and column reinforcements to complete the assembly of the beam reinforcements, and the building is completed through beam formwork assembly work and concrete pouring work. It will continue to be built.

〔実施例〕〔Example〕

つぎに本発明を、第1図から第15図に示すタービン架
台の梁構築に際してなされた実施例に基づいて詳細に説
明する。なおタービン架台はタービンおよび発電機を据
え付ける機械台基礎をいい、鉄筋コンクリート造である
Next, the present invention will be explained in detail based on an example made when constructing a beam of a turbine frame shown in FIGS. 1 to 15. The turbine pedestal refers to the machine base on which the turbine and generator are installed, and is constructed of reinforced concrete.

第1図はタービン架台の上部梁を構築する際の梁筋ユニ
ット1を示すもので、完全ユニッ}Aを、据え付けが終
了したセミュニッ}Bのスパンと直交するスパンの柱間
に吊り込みする状態である。なお、完全ユニットとはス
パンに対して設定された鉄筋を完全に組み上げた梁筋ユ
ニソトであり、セミユニットとは前記完全ユニットの据
え付けおよび柱筋を考慮して組まれた梁筋ユニソトで、
スパンに対して設定された鉄筋のうち上端筋、スタラッ
プの一部を現地組し、また腹筋、下端筋の一部を現地ス
ライドするようにしたものである。
Figure 1 shows the beam reinforcement unit 1 used when constructing the upper beam of the turbine frame, with the complete unit A being suspended between the columns in a span orthogonal to the span of the semi-B that has been installed. It is. In addition, a complete unit is a beam reinforcement unit that is completely assembled with the reinforcing bars set for the span, and a semi-unit is a beam reinforcement unit that is assembled by taking into account the installation of the complete unit and column reinforcement.
Of the reinforcing bars set for the span, some of the upper end reinforcement and stirrups are assembled on-site, and some of the abdominal reinforcement and lower end reinforcement are slid on-site.

つぎに、上記完全ユニッ}Aの組み上げ手順を示す第2
図以降の図面により梁筋ユニット1を説明する。
Next, the second part showing the assembly procedure of the complete unit A mentioned above.
The beam reinforcement unit 1 will be explained with reference to the drawings that follow.

●工程1(第2図) 梁筋ユニット1を組み上げるにあたっては、第2図に示
すように、まず構外地組ヤードにて水平なベースコンク
リート2上に梁の長手方向に一定の間隔で複数本の架台
(同一形状)3を配列する。破線aは粱筋ユニットの組
上げ空間を仮想的に示す。
●Process 1 (Fig. 2) When assembling the beam reinforcement unit 1, as shown in Fig. 2, first, multiple beam reinforcements are placed at regular intervals in the longitudinal direction on a horizontal base concrete 2 in an off-site construction yard. mounts (same shape) 3 are arranged. The broken line a virtually indicates the space for assembling the gluteus muscle unit.

ここでベースコンクリート2を打設し、同一の架台3を
配列することにより、架台3のレベル合わせが容易であ
り、また前記架台3それぞれがその長手を梁幅方向に合
わせられ、この架台3上に梁筋ユニットを組むことによ
り、梁底の埋込金物プレートの取付、スタラップ配筋を
可能にする。
By pouring the base concrete 2 and arranging the same mounts 3, it is easy to level the mounts 3, and the lengths of the mounts 3 can be aligned in the beam width direction. By assembling a beam reinforcement unit, it is possible to install embedded hardware plates at the bottom of the beam and arrange stirrup reinforcement.

●工程2(第3図) 上記架台3上にベースプレート4を介して一対の支柱5
を立設させる。前記一対の支柱5には、予め梁の上端筋
を受ける受材6および梁の下端筋を受ける受材7が梁の
幅方向に渡るように架設されるとともに、垂直プレース
8が支柱間に架け渡されるものであって、各面の支柱5
が予め地組され、これを揚重機bによって架台3上に立
設する。
●Process 2 (Fig. 3) A pair of support columns 5 are placed on the above mount 3 via the base plate 4.
erected. A receiving member 6 for receiving the upper end reinforcement of the beam and a receiving member 7 for receiving the lower end reinforcement of the beam are installed in advance on the pair of pillars 5 so as to cross in the width direction of the beam, and a vertical place 8 is installed between the pillars. It is handed over, and the pillars 5 on each side
is assembled on the ground in advance, and is erected on the pedestal 3 by a lifting machine b.

面組された一対の支柱5は仮セットの状態で架台上に立
設しているものであって、両脇で組み上げられた枠組足
場(図示せず)を利用して例えば番線結束し、そして万
力にてベースプレート4と架台3とを締め付け固定する
A pair of struts 5, which are assembled together, are temporarily set up on a pedestal, and are tied together using, for example, wires, using framework scaffolding (not shown) assembled on both sides. Tighten and fix the base plate 4 and the pedestal 3 using a vise.

なお、受材6,7は例えば断面[状の軽量溝型鋼からな
るものである。また支柱5は例えばL型鋼からなり、前
記ベースプレート4を備えたものである。また組立精度
をより良くするために上記垂直プレース8は全てターン
バ,タルを付けたものであって、調整がスムーズに行え
るように図られている。
Note that the receiving members 6 and 7 are made of lightweight channel steel having a cross section of, for example. Further, the support column 5 is made of, for example, L-shaped steel, and is provided with the base plate 4 described above. Further, in order to improve assembly accuracy, all of the vertical places 8 are equipped with turn bars and barrels so that adjustments can be made smoothly.

工程3(第4図) 上記工程2により架台3上で立設している支柱5それぞ
れに対して水平継ぎ材9を梁の長手方向に通すようにし
て取付固定し、梁の長手方向に並ぶ支柱間に上記と同様
に垂直プレース8を架け渡すとともに、上面側および下
面側にも水平プレース10を架け渡し、支持フレーム1
1を組上げる。以降この支持フレーム11に所定の鉄筋
を取り付ける工程に移る。
Step 3 (Fig. 4) Attach and fix the horizontal splicing material 9 to each of the pillars 5 erected on the frame 3 in step 2 above by passing it in the longitudinal direction of the beam, so that they line up in the longitudinal direction of the beam. A vertical place 8 is placed between the pillars in the same manner as above, and a horizontal place 10 is placed on the upper and lower sides as well, and the support frame 1
Assemble 1. Thereafter, the process moves on to attaching predetermined reinforcing bars to this support frame 11.

工程4(第5図) この工程4においては、下端筋(異径鉄筋)の配筋が行
われるものであって、揚重機bによって下端筋12を吊
支しながらスライドさせて上記下端筋受材7に取り付け
る。第6図に示すように下端筋12のピンチを確保する
ため、下端筋受材7に定ピッチで孔を開けておき、これ
にUボルトを締め付けるようにして下端筋12を固定す
る。
Step 4 (Fig. 5) In this step 4, the lower end reinforcements (different diameter reinforcing bars) are arranged, and the lower end reinforcements 12 are suspended and slid by the lifting machine b to the lower end reinforcement receivers. Attach to material 7. As shown in FIG. 6, in order to secure the pinch of the lower end reinforcement 12, holes are drilled at a constant pitch in the lower end reinforcement receiving material 7, and the lower end reinforcement 12 is fixed thereto by tightening U bolts.

工程5(第7図) つぎに、支柱フレーム11の側面に梁の長手方向に渡る
ようにして腹筋(異径鉄筋)13をすだれ状に下部から
取付固定する。この腹筋13の取付4に際しても上記工
程4と同様にUボルトを用いる。また架台側から口状の
スターラップ14(異径鉄筋)を差し込み、水平継ぎ材
や下端筋に結束固定する。
Step 5 (FIG. 7) Next, the abdominal reinforcement (different diameter reinforcing bars) 13 is attached and fixed from the bottom to the side of the support frame 11 in a sash-like manner so as to extend in the longitudinal direction of the beam. U-bolts are used in the attachment 4 of the abdominal muscles 13 as in step 4 above. In addition, a mouth-shaped stirrup 14 (different diameter reinforcing bar) is inserted from the mount side and tied and fixed to the horizontal joint material or lower end reinforcement.

工程6(第8図) 支持フレーム11の側面側にL型吠のスターラップ(異
径鉄筋)15を取り付けるとともに、梁の幅方向に[状
の幅止め材(異径鉄筋)16を支持フレーム11の内方
から架け渡し固定する。
Step 6 (Fig. 8) Attach an L-shaped stirrup (different diameter reinforcing bar) 15 to the side surface of the support frame 11, and add a width stopper (different diameter reinforcing bar) 16 to the support frame in the width direction of the beam. 11 from the inside and fix it.

工程7(第9図) 支持フレーム11の上面側から梁の長手方向に亘る上端
筋(異径鉄筋)17を上端筋受材6に取付固定する。上
記下端筋12の固定と同様にこの上端筋17もUボルト
を用いて固定が行われる。
Step 7 (FIG. 9) Upper end reinforcing bars (different diameter reinforcing bars) 17 extending from the upper surface side of the support frame 11 in the longitudinal direction of the beam are attached and fixed to the upper end reinforcing member 6. Similar to the fixation of the lower end reinforcement 12, this upper end reinforcement 17 is also fixed using U bolts.

こののち[状のスターランプ18が梁の幅方向に渡るよ
うにして前記上端筋の上方から架けて固定することによ
って梁筋ユニット1が組み上げられる。
Thereafter, the beam reinforcement unit 1 is assembled by hanging and fixing the star lamp 18 in the shape of [[] in the width direction of the beam from above the upper end reinforcement.

上記工程7までによって梁筋ユニット1が完成する。こ
ののち梁それぞれに応じて設定された金物などが取り付
けられる。
The beam reinforcement unit 1 is completed through the above steps 7. After this, hardware and other items set according to each beam are attached.

工程8(第10図) 構築する梁それぞれに応じて配管を通す場合やアンカー
ボルトを必要とする場合があるときに加工が施される。
Process 8 (Figure 10) Depending on the beam to be constructed, processing is performed when piping is passed through or anchor bolts are required.

例えばこの完全ユニッ}Aにおいては、梁筋ユニソト1
の上面にアンカーボルト19を取り付けるとともに、ス
リーブ2o1埋込プレート21、電線管22などの埋設
金物をこの時点で取り付ける。なお、配筋ユニットの据
付後にこれらの位置調整が行えるようにアンカーボルト
や埋設金物は仮固定される。
For example, in this complete unit} A, beam reinforcement unisoto 1
Anchor bolts 19 are attached to the upper surface of the sleeve 2o1, and embedded hardware such as the sleeve 2o1 embedded plate 21 and electric conduit 22 are attached at this point. Note that the anchor bolts and buried hardware are temporarily fixed so that their positions can be adjusted after the reinforcement unit is installed.

つぎに梁筋ユニットを所定場所へ搬入据付できるように
吊り治具を取り付ける作業となる。
The next step is to attach a hanging jig so that the beam reinforcement unit can be transported and installed at a designated location.

工程9(第11図) 第11図に示すように、梁幅方向に渡る断面[状の渡し
材23を支柱5の上端間に取付固定する(ボルトによる
連結)。そののち第12図に示すようにH型鋼の吊り材
24を前記渡し材23を受けるようにして梁の長手方向
に渡し、この吊り材24と渡し材23とを万力によって
固定する。
Step 9 (FIG. 11) As shown in FIG. 11, a bridge member 23 having a cross section extending in the beam width direction is attached and fixed between the upper ends of the columns 5 (connected with bolts). Thereafter, as shown in FIG. 12, a hanging member 24 made of H-shaped steel is passed in the longitudinal direction of the beam so as to receive the connecting member 23, and the hanging member 24 and the connecting member 23 are fixed in a vise.

また吊り材24の上面の所定箇所には吊りピース25が
固着されている(第13図参照)。なおこれらの吊り治
具(吊りピース、吊り材、渡し材)は、梁筋ユニソトの
据付完了後に支柱上端を切断することによって一括撤去
する。
Further, a hanging piece 25 is fixed to a predetermined location on the upper surface of the hanging member 24 (see FIG. 13). These hanging jigs (hanging pieces, hanging materials, and crossing materials) will be removed all at once by cutting off the upper ends of the columns after the installation of the beam reinforcements is completed.

なお、ベースプレート4と架台3とは、例えば第14図
に示すように万力を用いて固定されており、必要時に架
台を取り外すことができるよう図られている。
The base plate 4 and the pedestal 3 are fixed together using a vise, for example, as shown in FIG. 14, so that the pedestal can be removed when necessary.

上記までの工程は完全ユニットを組み上げる手順を示し
たものであるが、セミユニットとする梁筋ユニットの場
合、上端筋を配筋せずに現組としたり、腹筋も現地スラ
イドさせるなどの工夫がなされるほかは上記工程を経て
組み上げられるものである。
The process described above shows the procedure for assembling a complete unit, but in the case of a semi-unit beam reinforcement unit, it is possible to use measures such as leaving the upper reinforcement in place without reinforcing it, or sliding the abdominal reinforcement on-site. The rest is assembled through the above steps.

第15図は梁筋ユニット1の運搬を示す。上記工程を経
て構外地組ヤードで組み上げられた梁筋ユニント1は、
例えば第15図に示すトレーラーなどの移動手段を用い
て建設現場まで運搬される。このとき荷台幅がユニット
幅よりも狭い場合には、架台3を取り付けた状態のまま
吊り込むようにする。また吊り治具、埋設金物の取付に
よって梁筋ユニットの上部が重くなった場合にバランス
をとるためにウェイト用として架台を取り付けた状態の
まま運搬することもある。26は固定用ワイヤを示す。
FIG. 15 shows the transportation of the beam reinforcement unit 1. The beam reinforcement unit 1 assembled in the off-site assembly yard through the above process is
For example, it is transported to a construction site using a transportation means such as a trailer shown in FIG. 15. At this time, if the loading platform width is narrower than the unit width, the loading platform 3 is hung with the frame 3 attached. In addition, when the upper part of the beam reinforcement unit becomes heavy due to the attachment of hanging jigs and buried hardware, the unit may be transported with a frame attached as a weight to maintain balance. 26 indicates a fixing wire.

このようにして用意される梁筋ユニットを第1図に示す
ように揚重機bによって梁構築部それぞれに吊り込み、
据え付けが完了したのち、他の梁筋ユニット(例えばセ
ミユニット)の鉄筋や柱筋との連結を行うことによって
、梁構築部における梁筋の組立が完了する。なお架台が
輸送時に取り付けられている場合、吊り込み前にベース
プレートと架台との連結を解除する。
As shown in Fig. 1, the beam reinforcement units prepared in this way are hoisted onto each beam construction section by a lifting machine b.
After the installation is completed, the assembly of the beam reinforcements in the beam construction section is completed by connecting them to the reinforcing bars and column reinforcements of other beam reinforcement units (for example, semi-units). If the pedestal is attached during transportation, disconnect the base plate from the pedestal before hoisting the product.

第16図は梁筋ユニットを用いて梁の構築が行われたタ
ービン架台を示すもので、このタービン架台Cの上部梁
dや中間梁eの部分がこの梁筋ユニットを用いる。
FIG. 16 shows a turbine frame whose beams are constructed using a beam reinforcement unit, and the upper beam d and middle beam e of this turbine frame C use this beam reinforcement unit.

上記した実施例ではタービン架台の構築に基づいて説明
したが、本発明はこれに限定されるものではなく、他の
建築物などを構築する場合にも適用できるものである。
Although the above-described embodiments have been explained based on the construction of a turbine frame, the present invention is not limited thereto, and can be applied to the construction of other buildings.

〔発明の効果〕〔Effect of the invention〕

以上説明したように、本発明の構成により、建設作業現
場における作業工程を考慮することなく梁筋の配筋作業
が行えるとともに、梁筋ユニットの据付後も他の既設鉄
筋との結合だけで梁筋が組み立てられるようになり、地
組による鉄筋組立工程が短縮し躯体工事の短縮化が図れ
るようになる。また鉄筋労務工程が均一化して労務管理
が容易になる。そして梁構築部での鉄筋組立時の足場が
不要になり、作業安全の確保が容易になる。さらには専
用の場所でユニットが組まれ品質が向上するなど、実用
性にすぐれた効果を奏するものである。
As explained above, with the configuration of the present invention, it is possible to perform beam reinforcement work without considering the work process at a construction work site, and even after the beam reinforcement unit is installed, the beam reinforcement unit can be easily connected to other existing reinforcing bars. The reinforcing bars can now be assembled, which shortens the process of assembling the reinforcing bars by ground assembly, making it possible to shorten the period of frame work. In addition, the reinforcing steel labor process becomes uniform, making labor management easier. Furthermore, there is no need for scaffolding when assembling reinforcing bars in the beam construction section, making it easier to ensure work safety. Furthermore, the unit is assembled in a dedicated location, resulting in improved quality, which has excellent practical effects.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の梁筋の組立方法の一実施例を示すもので
、 第1図は梁筋ユニットの吊り込みを示す説明図、第2図
は架台の配設を示す説明図、 第3図は支柱を立設する状態を示す説明図、第4図は水
平継ぎ材を取り付けた状態を示す説明図、 第5図は下端筋の配筋を示す説明図、 第6図は下端筋の取付状態を示す説明図、第7図は腹筋
と下面側のスターラップを取付ける状態を示す説明図、 第8図は側面側のスターラップと幅止め材を取り付けた
状態を示す説明図、 第9図は上端筋と上面側のスターラップを取り付けた状
態を示す説明図、 第10図は埋設金物などを取り付けた状態を示す説明図
、 第11図は吊り治具を取り付けた状態を示す説明図、 第12図は吊り材を示す説明図、 第13図は吊りピースを示す説明図、 第14図はベースプレートの架台への固定を示す説明図
、 第15図は粱筋ユニットの運搬例を示す説明図、第16
図はタービン架台を示す説明図である。 1・・・・・・梁筋ユニット 3・・・・・・架台 4・・・・・・ベースペレー 5・・・・・・支柱 ト 6,7・・・・・・受材 11・・・・・・支持フレーム 12・・・・・・下端筋 13・・・・・・腹筋 14,15.18・・・・・・スターラップ17・・・
・・・上端筋 19・・・・・・アンカーボルト 23・・・・・・渡し材 24・・・・・・吊り材 25・・・・・・吊りピース A・・・・・・完全ユニット B・・・・・・セミユニット
The drawings show an embodiment of the method for assembling beam reinforcements according to the present invention, and FIG. 1 is an explanatory diagram showing the suspension of a beam reinforcement unit, FIG. 2 is an explanatory diagram showing the arrangement of a frame, and FIG. Figure 4 is an explanatory diagram showing the state in which the column is erected, Figure 4 is an explanatory diagram showing the horizontal joint material installed, Figure 5 is an explanatory diagram showing the reinforcement arrangement of the lower end reinforcement, and Figure 6 is the installation of the lower end reinforcement. An explanatory diagram showing the condition. Figure 7 is an explanatory diagram showing the state in which the abdominal muscles and bottom stirrup are attached. Figure 8 is an explanatory diagram showing the state in which the side stirrup and width stopper are attached. Figure 9 is an explanatory diagram showing the state in which the upper end reinforcement and stirrup on the top side are attached, Figure 10 is an explanatory diagram showing the state in which buried hardware etc. are attached, Figure 11 is an explanatory diagram showing the state in which the hanging jig is attached, Fig. 12 is an explanatory diagram showing the hanging material, Fig. 13 is an explanatory diagram showing the hanging piece, Fig. 14 is an explanatory diagram showing the fixing of the base plate to the pedestal, and Fig. 15 is an explanatory diagram showing an example of transporting the gluteus muscle unit. Figure, No. 16
The figure is an explanatory diagram showing a turbine mount. 1... Beam reinforcement unit 3... Frame 4... Base pallet 5... Support column 6, 7... Support material 11... ... Support frame 12 ... Lower end muscle 13 ... Abdominal muscle 14, 15.18 ... Stirrup 17 ...
...Top end reinforcement 19...Anchor bolt 23...Bridging material 24...Hanging material 25...Hanging piece A...Complete unit B・・・・・・Semi unit

Claims (1)

【特許請求の範囲】 複数列にして梁の長手方向に配列した複数本の支柱を相
互に連結し、梁の上端筋を受ける受材と下端筋を受ける
受材とを梁の幅方向に備える支持フレームを、構外地組
ヤードにて組み、 前記支持フレームに、梁を渡すスパンに対応して設定さ
れた下端筋、上端筋、腹筋、スタラップなどの鉄筋を配
筋固定して梁筋ユニットを組上げ、 前記梁筋ユニットを梁構築部へ搬入して据付したのち、 前記梁筋ユニットの端部側の鉄筋それぞれを、既設鉄筋
と連結することを特徴とする梁筋の組立方法。
[Claims] A plurality of columns arranged in a plurality of rows in the longitudinal direction of the beam are interconnected, and a receiving member for receiving the upper end reinforcement of the beam and a receiving member for receiving the lower end reinforcement are provided in the width direction of the beam. A support frame is assembled in an off-site construction yard, and reinforcing bars such as lower end reinforcement, upper end reinforcement, abdominal reinforcement, stirrup, etc. set according to the span across which the beam is passed are arranged and fixed to the support frame to form a beam reinforcement unit. Assembling: A method for assembling beam reinforcements, comprising: transporting the beam reinforcement unit to a beam construction section and installing it, and then connecting each of the reinforcing bars on the end side of the beam reinforcement unit to the existing reinforcing bars.
JP1389890A 1990-01-24 1990-01-24 How to assemble beam reinforcements Pending JPH03217559A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1389890A JPH03217559A (en) 1990-01-24 1990-01-24 How to assemble beam reinforcements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1389890A JPH03217559A (en) 1990-01-24 1990-01-24 How to assemble beam reinforcements

Publications (1)

Publication Number Publication Date
JPH03217559A true JPH03217559A (en) 1991-09-25

Family

ID=11845989

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1389890A Pending JPH03217559A (en) 1990-01-24 1990-01-24 How to assemble beam reinforcements

Country Status (1)

Country Link
JP (1) JPH03217559A (en)

Similar Documents

Publication Publication Date Title
KR100788396B1 (en) Unsupported prestressed formwork and its installation structure
JP2003193430A (en) Construction method of composite truss bridge
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
KR101665482B1 (en) Method for Constructing Long Span Continuous Bridge of Spliced Prestressed Concrete Girders without Temporary Supports
CN115387234A (en) Template system of lower beam of ultrahigh rhombic tower pier and construction method
JP2000045231A (en) Arch bridge erection method
JP2750368B2 (en) Construction method of reactor containment top slab
JP2003336213A (en) Concrete receiving beam and method for building girder by using it
JP2004183433A (en) Box girder bridge structure and its construction method
US20090165408A1 (en) Construction elements and methods of construction
JPH03217559A (en) How to assemble beam reinforcements
JP2000273946A (en) Method for constructing reinforced concrete structure
CN115522731A (en) A system and construction method for early demolition and support of formwork by suspension method in the construction of cantilevered structures
JP3032052U (en) Construction equipment for pier reinforcement work
JPH0214509B2 (en)
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
KR102558869B1 (en) Pre-fabricating formwork for rebar and construction method thereof
JPH05148817A (en) Construction of pc bridge
JP3187618B2 (en) How to assemble beam reinforcement
JPH0765297B2 (en) How to erection a cane ramen bridge
JPH108725A (en) Constructing method for building frame
JP2002256643A (en) Construction method of SRC construction
JPH0414567A (en) Laminated construction method for buildings
JP2025122529A (en) Building construction method and joint members used therein
JPH07166539A (en) Construction method for steel framed reinforced concrete continuous underground wall