JPH0321789A - Sharp bending shield method - Google Patents
Sharp bending shield methodInfo
- Publication number
- JPH0321789A JPH0321789A JP15241489A JP15241489A JPH0321789A JP H0321789 A JPH0321789 A JP H0321789A JP 15241489 A JP15241489 A JP 15241489A JP 15241489 A JP15241489 A JP 15241489A JP H0321789 A JPH0321789 A JP H0321789A
- Authority
- JP
- Japan
- Prior art keywords
- shield
- shield tail
- shield machine
- machine
- tail part
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
本発明は、シールド機の推進によりトンネルを掘削構築
するシールド工法、さらに詳しくは急曲線に沿って掘進
して行く急曲進シールド工法に関する.The present invention relates to a shield construction method in which a tunnel is excavated and constructed using the propulsion of a shield machine, and more particularly to a shield construction method in which tunnels are excavated along sharp curves.
従来、半径15m以下の急曲線に沿って掘進するような
急曲進シールド工法においては、所要の位置に方向転換
用立坑を開削し、その中でシールド機の方向転換とそれ
にともなう所要の処理作業を行った後に再掘進をしてい
るものである.これを第12図及び第13図により、簡
単に説明すると、シールド4!l1を予め開削してある
方向転換用立坑2内に土留壁3の引出し用坑口4を通じ
て引き出し(第12図、同図の符号lOは既設のセグメ
ント、11は該セグメントlOと地山の間のテールボイ
ドを示す)、そのシールド機1を架台5上で方向転換さ
せて、前面カッタービット1′を新たな掘進方向に向け
るとともに、支圧壁6及び仮支保工7を設置し(第13
図)、慣行の方法にしたがい坑口8から再掘進して行く
ものである.Conventionally, in the steep curve shield construction method in which excavation is carried out along a sharp curve with a radius of 15 m or less, a vertical shaft for turning is excavated at the required position, and the shield machine is turned in the shaft and the necessary processing work is carried out. After the excavation was carried out, the excavation was carried out again. To briefly explain this with reference to FIGS. 12 and 13, Shield 4! 11 is drawn out through the extraction shaft 4 of the retaining wall 3 into the direction change vertical shaft 2 which has been excavated in advance. The shielding machine 1 is turned around on the pedestal 5, the front cutter bit 1' is directed to the new excavation direction, and the bearing wall 6 and temporary shoring 7 are installed (the 13th
Figure), the tunnel will be re-excavated from the pit entrance 8 according to the customary method.
【発明が解決しようとする謀l!】
上記方向転換用立坑2としては、シールド機i自体の方
向転換に必要な領域9の他に、支圧壁6及び仮支保工7
の併設領域、各種の作業のための余裕領域等を含めると
、シールドatの長さの略2倍の口径の大きなものとす
る必要があると認められるが、最近のように、狭い道路
の下での施工、また既設埋設物あるいは構造物の近接位
置での施工等において、近隣住民への影響、当該埋設物
等への影響を考慮すると、大口径の立坑の開削が非常に
困難になってきている.
また、上記において、シールドatを方向転換用立坑2
に引き出すときその引出し用坑口4の周辺部分の崩壊事
故を惹起したり、引き出した後に坑口処理を十分にしな
ければならない等、シールドIllの方向転換から再掘
進開始までには意外に手間取るものであった.
本発明の主たる目的は、方向転換用立坑が小さくてもシ
ールド機の方向転換が容易にできるようにすること、ま
た、他の目的は、引出し用坑口の崩壊を防止するととも
に引き出し後の坑口処理を簡単に実施できるようにし、
これによって、シールド機の方向転換から再掘進の開始
までを短時間のうちに行い得るようにすることにある.
[The invention is trying to solve the problem! ] The above-mentioned direction change vertical shaft 2 includes a bearing wall 6 and a temporary support 7 in addition to an area 9 necessary for changing the direction of the shield machine i itself.
It is recognized that it is necessary to use a shield with a diameter approximately twice as long as the length of the AT, including the area where the AT is attached and the extra space for various types of work. It has become extremely difficult to excavate large-diameter shafts when considering the impact on nearby residents and the buried objects, etc., in construction work in the vicinity of existing buried objects or structures. ing. In addition, in the above, the shield at is connected to the vertical shaft 2 for direction change.
When the shield Ill is pulled out, the surrounding area of the extraction pit 4 may collapse, and the tunnel opening must be thoroughly cleaned after being pulled out. It takes a surprising amount of time from changing the direction of the shield Ill to starting digging again. Ta. The main object of the present invention is to make it possible to easily change the direction of a shield machine even if the vertical shaft for turning is small, and another object is to prevent the collapse of the extraction tunnel entrance and to handle the tunnel opening after extraction. make it easy to implement,
The purpose of this is to make it possible to change the direction of the shield machine and start digging again in a short period of time.
上記の目的を達或するために提案された本発明の構戒は
、次のとおりである.
本発明急曲進シールド工法は、方向転換用立坑内でシー
ルド機の方向転換をし、その後、該シールド機で再掘進
する急曲進シールド工法に関するものである.
・それは、まず、掘進してきたシールドaAを、方向転
換用立坑Bに引出し用坑口Dを通じ途中まで進入させ、
それのシールドテール部bを引出し用坑口Dにおいて切
り離し、それを地中にV!l置する.
次に、シールドテール部bを切り離したシールド機A′
を上記方向転換用立坑B内で方向転換する.
そして、該シールドliA’が有しているシールド前半
部後端に別途製作してあるシールドテール部Cを接続し
、シールド機Aと同じくシールドテール部を備えたシー
ルドaA’とする.その後、該シールドaA#による再
掘進を開始する.
上記において、シールドテール部bを切り離したシール
ドlIA’に、上記方向転換をした後一旦仮掘進させた
後、上記の別途製作してあるシールドテール部Cを接続
するようにすると、後記のように方向転換用立坑Bを一
層小さくできる.また、上記シールドテール部bの切り
離し及び接続を切断及び溶接で行うことにより、当該作
業を簡単にかつ強固にできるものである.しかし、シー
ルドmAのシールドテール部bを所要の接離手段で接離
自在としておき、また、継ぎ足し用シールドテール部C
にも予め所要の接離手段を備えておき、これら両シール
ドテール部b,Cの切り離し及び接続をその接離手段に
より行うのも便利である。
なお、シールドテール部bの切り離し及び接続を、上記
した切断及び溶接と、そのシールドテール部b及び継ぎ
足し用シールドテール部Cに予め備えた接離手段との併
用によって行うこともできるものである.The principles of the present invention proposed to achieve the above objectives are as follows. The steep curve shield construction method of the present invention relates to a steep curve shield construction method in which the direction of the shield machine is changed within the direction change shaft, and then the shield machine excavates again.・First, the shield aA that has been dug is entered halfway into the direction change vertical shaft B through the extraction shaft D,
Separate the shield tail part b of it at the extraction pit D and insert it into the ground. Place it. Next, the shield machine A' with the shield tail part b cut off
The direction is changed in the above-mentioned direction change shaft B. Then, a separately manufactured shield tail part C is connected to the rear end of the shield front half of the shield liA', and a shield aA' having a shield tail part like the shield machine A is obtained. After that, the shield aA# starts digging again. In the above, if the separately manufactured shield tail C is connected to the shield lIA' from which the shield tail part b has been cut off, after the above direction change and the shield lIA' is temporarily dug, the result will be as shown below. The vertical shaft B for changing direction can be made even smaller. Further, by separating and connecting the shield tail portion b by cutting and welding, the work can be made simple and strong. However, the shield tail part b of the shield mA is made to be freely accessible and detachable using a required approach and detachment means, and the additional shield tail part C
It is also convenient to provide a necessary contact/separation means in advance and to separate and connect these shield tail portions b and C using the contact/separation means. Incidentally, the separation and connection of the shield tail part b can also be carried out by combining the above-described cutting and welding with the connecting and separating means provided in advance on the shield tail part b and the additional shield tail part C.
上記のように、シールドテール部bを切り離したシール
ドIa八′を方向転換用立坑B内で方向転換するので、
その方向転換用立坑Bは、シールドテール部bを備えた
ままのシールド機を方向転換する場合に比べて、はるか
に小さくて足りる.しかし、該シールドvlA’に別途
製作してあるシ,−ルドテール部Cを接続することによ
って、従来と同様にして再掘進をすることができる.As mentioned above, since the shield Ia 8' from which the shield tail part b has been separated is changed direction in the direction change shaft B,
The vertical shaft B for changing the direction needs to be much smaller than when changing the direction of a shield machine that is still equipped with the shield tail part B. However, by connecting a separately manufactured shield tail portion C to the shield vlA', it is possible to re-excavate in the same manner as before.
以下には、まず本発明の第1実施例を第1図乃至第6図
を参照しながら詳述する.
Aはシールド機で、慣行の掘進方法により掘進してきた
該シールド機Aが、横断面方形の方向転換用立坑Bに到
達したとき、土留壁Cに引出し用坑口Dを開設する.
次に、その引出し用坑口Dを通じシールド機Aを、方向
転換用立坑Bに途中まで、すなわち、少なくとも機械室
aを囲繞形戊するシールド(鋼製M)の前半部が上記方
向転換用立坑B内に進入し、シールドジャッキ等の機械
が内装されていないシールドテール部bが、上記引出し
用坑口Dから後方に位置する関係位置のところまで、引
き出す(第1.2図).
そして、上記土留壁Cとシールドテール部bとの間を公
知の手段によりコーキングした後、方向転換用立坑Bの
内壁面、換言すると土留壁Cの内面に沿って、シールド
iAのシールドを溶断等適宜の方法で切断し、そのシー
ルド前半部からシールドテール部bを切り離す.
その切り離されたシールドテール部bは、そのまま地ψ
に留置されて、引出し用坑口Dの周辺部分の土砂の崩壊
を防止するとともに、既設セグメントと地山との間に形
威されるテールボイドの処理を省略させる.換言すると
、坑口処理としては、上記のコーキングだけで足りもの
であり、またその分だけ裏込注入量を少なくできる等、
到達部の補助処理を少なくするのに寄与する.
つづいて、シールドテール部bを切り離したシールド機
A′を方向転換用立坑Bの中央に進め、架台E上で慣行
にしたがい方向転換させる(第3図).
さらに、方向転換用立坑B内の所定位置に支圧壁Fを設
置するとともに、再掘進方向側に再掘進用坑口Gを設置
する.
その後、幅の狭いセグメント等を仮支保工として、シー
ルドaA′を後記継ぎ足し用シールドテー.ル部の継ぎ
足し作業に必要な空処を確保できるところまで仮厖進し
、そのシールドImA’に地山の土庄保持をさせるとと
もに、その位置において、別途製作用意してある継ぎ足
し用シールドテール部Cをシールド4l!A’のシール
ド前半部の後端に一体に溶接接続し、これによって前記
シールド機Aと実質上同様のシールドellA’を得る
(第5図).
継ぎ足し用シールドテール部Cは、地中に留置された前
記シールドテール部bと実質上同じに鋼製筒で別途製作
しておくものである.
そこで、上記支圧壁Fに仮支保工Hを併設し、シールド
機A#を通常の方法すなわちジャッキ推力で押し、掘進
を再開させる.
第7図乃至第11図は本発明の第2実施例を示す.
この第2実施例は、方向転換用立坑B′が横断面円形で
あること、それにともない支圧壁F′の該立坑B′の内
壁面に当接する側が湾曲していることにおいて、上記第
1実施例と相違するだけで、そ0他の点は第1実施例と
変わるところがなく、第7図乃至第11図は第2図乃至
第6図にそれぞれ対応する.
そこで、重複の煩を避けるため、同一部分に同一の符号
を付してその説明を省略する.この第2実施例において
、シールドI!Aのシールドテール部bは、それを第1
実施例と同しく直線状に切断すると、方向転換用立坑B
′内に三日月形に突出するが、この突出は特に支障にな
るものではない.
ただし、必要に応じ該立坑B′の内壁面に沿わせ湾曲状
態に、すなわち第7図の弧状点線lに沿って切断するこ
とにより、テール部bが方向転換用立坑B′内に平面三
日月形に突出しないようにすることができる.
図中符号Jはシールド機受台、Kは既設のセグメント、
LはセグメントKと地山の間のテールボイドを示し、こ
のテールボイドしは掘進作業中適宜裏込充填されるもの
である.
なお、シールドIIAのシールドテール部bを切り・離
したり接続したりする手段としては、第1実施例及び第
2実施例における切断と溶接に限るものではなく、例え
ば、シールドaAのシールドテール部を所要の接離手段
で接離自在としておき、また、継ぎ足し用シールドテー
ル部にも予め所要の接離手段を備えておき、その接離手
段によって、切り離し及び接続を行うこと、さらにこの
接離手段と上記切断及び溶接を併用するようにしてもよ
いものである.In the following, a first embodiment of the present invention will be described in detail with reference to FIGS. 1 to 6. A is a shield machine, and when the shield machine A, which has been excavating using a conventional excavation method, reaches a turning shaft B with a rectangular cross section, it opens a withdrawal shaft D in a retaining wall C. Next, the shield machine A is moved halfway into the direction change shaft B through the extraction shaft D, that is, at least the front half of the shield (made of steel M) that surrounds the machine room a is inserted into the direction change shaft B. The shield tail part b, which does not have a machine such as a shield jack installed inside, is pulled out to the relevant position located rearward from the extraction shaft D (Fig. 1.2). After caulking between the earth retaining wall C and the shield tail part b by known means, the shield of the shield iA is cut by melting along the inner wall surface of the direction change shaft B, in other words, along the inner surface of the earth retaining wall C. Cut it using an appropriate method and separate the shield tail part b from the front half of the shield. The separated shield tail part b remains as it is on the ground ψ
This prevents the collapse of the earth and sand around the extraction tunnel entrance D, and also eliminates the need to deal with tail voids formed between the existing segment and the ground. In other words, the above-mentioned caulking is sufficient for wellhead treatment, and the amount of backfill injection can be reduced accordingly.
This contributes to reducing the amount of auxiliary processing in the reaching section. Next, the shield machine A' with the shield tail part b cut off is advanced to the center of the direction change shaft B, and the direction is changed according to the customary method on the mount E (Fig. 3). Furthermore, a bearing wall F is installed at a predetermined position within the direction change shaft B, and a re-excavation tunnel entrance G is installed on the re-excavation direction side. After that, use the narrow segments as temporary support and attach the shield aA' to the additional shield tape described later. Temporarily advance to a place where you can secure the space necessary for the work of adding the part, and use the shield ImA' to hold the ground, and at that position, shield tail part C for the addition, which is prepared separately. Shield 4L! It is integrally welded and connected to the rear end of the front half of the shield A', thereby obtaining a shield ellA' that is substantially the same as the shield machine A (Fig. 5). The supplementary shield tail part C is made separately from a steel cylinder and is substantially the same as the shield tail part B, which is placed underground. Therefore, temporary shoring H is installed on the bearing wall F, and the shield machine A# is pushed in the usual way, that is, with jack thrust, to resume excavation. 7 to 11 show a second embodiment of the present invention. This second embodiment differs from the first embodiment in that the direction change shaft B' has a circular cross section, and that the side of the bearing wall F' that contacts the inner wall surface of the shaft B' is curved. Other than the difference from the embodiment, there are no other differences from the first embodiment, and FIGS. 7 to 11 correspond to FIGS. 2 to 6, respectively. Therefore, to avoid redundancy, the same parts will be given the same reference numerals and their explanations will be omitted. In this second embodiment, the shield I! The shield tail part b of A is
When cut in a straight line as in the example, the vertical shaft for changing direction B
Although there is a crescent-shaped protrusion within ′, this protrusion does not pose any particular problem. However, if necessary, by cutting it in a curved state along the inner wall surface of the shaft B', that is, along the arcuate dotted line l in FIG. This can be done so that it does not stick out. In the figure, J is the shield machine cradle, K is the existing segment,
L indicates the tail void between segment K and the ground, and this tail void is backfilled as appropriate during excavation work. Note that the means for cutting/separating and connecting the shield tail part b of the shield IIA is not limited to cutting and welding in the first and second embodiments; It is possible to freely connect and disconnect using a required connecting and disconnecting means, and the additional shield tail part is also provided with a required connecting and disconnecting means in advance, and the connecting and disconnecting means is used to perform disconnection and connection, and furthermore, this connecting and disconnecting means It is also possible to use the above-mentioned cutting and welding together.
以上述べたところから明らかなように、本発明急曲進シ
ールド工法によれば、次の効果を奏すると認められる.
■ シールドテール部を切り離したシールド機を方向転
換用立坑内で方向転換するので、その方向転換用立坑は
、シールドテール部を備えたままのシールド機を方向転
換する場合に比べて、はるかに小さくて足りる.
もちろん、シールド機の前方切羽に出て、手作業による
先行掘削の必要はない.
■.狭い道路の下、また既設埋設物あるいは構造物の近
接位置というような比較的狭小な場所において、近隣住
民への影響、当該埋設物等への影響等にあまり煩わされ
ないで、所期の方向転換用立坑を開削するのに好都合で
ある.■ 上記シールドテール部を備えていないシール
ド機の方向転換後において、それに別途製作してあるシ
ールドテール部を接続することによって、従来と同様に
して直ちに再掘進を開始することができる.
■ また、上記シールドテール部は、引出し用坑口にお
いて切り離され地中に留置されて、引出し用坑口のrt
1辺部分の土砂の崩壊を防止するとともに、テールボイ
ドの処理等を簡略にする.換言すると、坑口処理として
は、その留置のシールドテール部と引出し用坑口間の比
較的狭い隙間のコーキングだけで足りものであり、また
その分だけ裏込注入逍を少なくできる.■ 到達時にお
ける他山の強化等の補助工法の施工範囲が少なくて済む
.
■ シールドテール部を切り離したシールド機に、上記
方向転換をした後一旦仮聞進させると、その分だけ、別
途製作してあるシールドテール部を接続する作業領域を
さらに広くでき、したがってまた、それに対応する分だ
け方向転換用立坑を小さくできる.
■ 上記シールドテール部の切り離し及び接続は、切断
及び溶接、あるいはシールド機のシールドテール部及び
継ぎ足し用シールドテール部に設けた所要の接離手段、
さらには、それらの併用によって、簡単にしかもしっか
りと行うことができる.As is clear from the above description, the steep bend shield construction method of the present invention is recognized to have the following effects. ■ The direction of the shield machine with the shield tail section separated is changed within the direction change shaft, so the direction change shaft is much smaller than when changing the direction of the shield machine with the shield tail section still attached. That's enough. Of course, there is no need to go to the front face of the shield machine and perform preliminary excavation by hand. ■. In relatively narrow places such as under narrow roads or in close proximity to existing buried objects or structures, it is possible to change the direction as desired without worrying too much about the impact on neighboring residents or the buried objects, etc. It is convenient for excavating a vertical shaft. ■ After changing the direction of the shield machine that is not equipped with the above-mentioned shield tail part, by connecting the separately manufactured shield tail part to it, it is possible to immediately start digging again in the same way as before. ■ Also, the shield tail part is separated at the extraction tunnel entrance and placed underground, and
This prevents the collapse of earth and sand on one side and simplifies the treatment of tail voids. In other words, as a wellhead treatment, it is sufficient to caulk the relatively narrow gap between the detention shield tail and the extraction wellhead, and the amount of backfill injection can be reduced accordingly. ■ The construction area for auxiliary construction methods such as strengthening other mountains upon arrival can be reduced. ■ If the shield machine from which the shield tail section has been separated is temporarily moved forward after changing the direction described above, the work area for connecting the separately manufactured shield tail section can be further expanded, and therefore, it can also be used to The vertical shaft for turning can be made smaller by the corresponding amount. ■ The above-mentioned separation and connection of the shield tail part can be done by cutting and welding, or by using the necessary connecting/disconnecting means provided on the shield tail part of the shield machine and the shield tail part for addition.
Furthermore, by using these methods together, it can be done easily and firmly.
図面第1図乃至第6図は本発明の第1実施例を示すもの
で、第1図はシールド機が方向転換用立坑に途中まで進
入した状態の断面図、第2図は同上の平面図、第3図は
シールドテール部を切り離したシールド機の方向転換状
態を示す平面図、第4図は支圧壁を設置した状態の平面
図、第5図は別途作或のシールドテール部を接続した状
態の平面図、第6図は再mil&を開始した状態の平面
図、第7図乃至第11図は第2実施例を示すものであっ
て、第7図はシールド機が方向転換用立坑に途中まで進
入した状態の断面図、第8図はシールドテール部を切り
離したシールド機の方向転換状態を示す平面図、第9V
!Jは支圧壁を設置した状態の平面図、第10図は別途
作或のシールドテール部を接続した状熊の平面図、.第
11図は再掘進を開始した状態の平面図、第12図及び
第13図は従来公知のシールド工法を説明するためのも
ので、第12図はシールド機が方向転換立坑に進入した
状態の断面図、第13図は上記シールド機が方向転換し
再掘進を開始しようとしている状態の平面図である.Drawings 1 to 6 show a first embodiment of the present invention, in which Fig. 1 is a cross-sectional view of the shield machine having entered halfway into the direction change shaft, and Fig. 2 is a plan view of the same. , Figure 3 is a plan view showing the shield machine changing direction with the shield tail section separated, Figure 4 is a plan view with the bearing wall installed, and Figure 5 is the separately made shield tail section connected. FIG. 6 is a plan view of the state in which re-mil& has been started, FIGS. 7 to 11 show the second embodiment, and FIG. Figure 8 is a cross-sectional view showing the state where the shield machine has entered halfway, Figure 8 is a plan view showing the direction change state of the shield machine with the shield tail section separated, Figure 9V
! J is a plan view with the bearing wall installed, and Figure 10 is a plan view of the bear with a separately manufactured shield tail connected. Figure 11 is a plan view of the state in which re-excavation has started, Figures 12 and 13 are for explaining the conventionally known shield construction method, and Figure 12 is a diagram of the state in which the shield machine has entered the diversion shaft. The sectional view and FIG. 13 are plan views of the shield machine in a state where it is about to change direction and start digging again.
Claims (1)
の後、該シールド機で再掘進する急曲進シールド工法に
おいて、掘進してきたシールド機を、方向転換用立坑に
引出し用坑口を通じ途中まで進入させるとともに、それ
のシールドテール部を引出し用坑口において切り離して
地中に留置し、そのシールドテール部を切り離したシー
ルド機を上記方向転換用立坑内で方向転換し、その後、
該シールド機に別途製作してあるシールドテール部を接
続し、再掘進を開始することを特徴とする急曲進シール
ド工法。 2、シールドテール部を切り離したシールド機に、上記
方向転換をした後一旦仮掘進させた後、上記の別途製作
してあるシールドテール部を接続し、再掘進を開始する
ことを特徴とする請求項1記載の急曲進シールド工法。 3、上記シールドテール部の切り離し及び接続を切断及
び溶接で行うことを特徴とする請求項1または2記載の
急曲進シールド工法。 4、シールド機のシールドテール部を所要の接離手段で
接離自在としておき、また、継ぎ足し用シールドテール
部にも予め所要の接離手段を備えておき、これら両シー
ルドテール部の切り離し及び接続をその接離手段により
行うことを特徴とする請求項1または2記載の急曲進シ
ールド工法。 5、上記シールドテール部の切り離し及び接続を、切断
及び溶接と、そのシールドテール部及び継ぎ足し用シー
ルドテール部に予め備えた接離手段との併用によって行
うことを特徴とする請求項1または2記載の急曲進シー
ルド工法。[Scope of Claims] 1. In the sharp turn shield construction method, in which the direction of the shield machine is changed in the direction change shaft, and then the shield machine excavates again, the shield machine that has been excavated is moved into the direction change shaft. The shield machine is entered halfway through the extraction shaft, and its shield tail is cut off at the extraction shaft and kept underground, and the shield machine with its shield tail cut off is turned in the direction change shaft, and then ,
A sharp turn shield construction method characterized by connecting a separately manufactured shield tail part to the shield machine and starting re-excavation. 2. A claim characterized in that the shield machine from which the shield tail part has been separated is temporarily excavated after the above direction change, and then the separately manufactured shield tail part is connected to start excavation again. The steep curve shield construction method described in Section 1. 3. The steep turn shield construction method according to claim 1 or 2, wherein the shield tail portion is separated and connected by cutting and welding. 4. The shield tail part of the shield machine can be freely connected and detached using a required connection/detachment means, and the additional shield tail part is also provided with the required connection/detachment means in advance, and these two shield tail parts can be disconnected and connected. 3. The steep curve shield construction method according to claim 1 or 2, wherein: 5. According to claim 1 or 2, the separation and connection of the shield tail portion is performed by cutting and welding in combination with a connecting/separating means provided in advance on the shield tail portion and the supplementary shield tail portion. Sharp curve shield construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15241489A JPH0689631B2 (en) | 1989-06-16 | 1989-06-16 | Sharp bend shield method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15241489A JPH0689631B2 (en) | 1989-06-16 | 1989-06-16 | Sharp bend shield method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0321789A true JPH0321789A (en) | 1991-01-30 |
| JPH0689631B2 JPH0689631B2 (en) | 1994-11-09 |
Family
ID=15539992
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15241489A Expired - Lifetime JPH0689631B2 (en) | 1989-06-16 | 1989-06-16 | Sharp bend shield method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0689631B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115012964A (en) * | 2022-05-31 | 2022-09-06 | 中交隧道工程局有限公司 | Large-diameter shield machine convenient for shield turning and closed groove type shield machine |
-
1989
- 1989-06-16 JP JP15241489A patent/JPH0689631B2/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115012964A (en) * | 2022-05-31 | 2022-09-06 | 中交隧道工程局有限公司 | Large-diameter shield machine convenient for shield turning and closed groove type shield machine |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0689631B2 (en) | 1994-11-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0321789A (en) | Sharp bending shield method | |
| JP2742026B2 (en) | Underground tunnel joining method and segment | |
| JP3181242B2 (en) | Equipment for middle pressing method | |
| JP3765048B2 (en) | How to build a tunnel | |
| JP3616898B2 (en) | Method for joining underground structures using propulsion device | |
| JP3830918B2 (en) | Tunnel excavator for pipe formation | |
| JP2538314B2 (en) | Shield tunnel construction method without vertical shaft | |
| JPH01121423A (en) | How to bury branch pipes | |
| JPS6362637B2 (en) | ||
| JP3172432B2 (en) | Starting a shield machine from a shaft | |
| JP2835388B2 (en) | Branch shield method | |
| JP2562938B2 (en) | How to replace an existing main with a new main | |
| JP2538370B2 (en) | Ground improvement method associated with the construction of vertical or inclined shafts and side shafts | |
| JP3068517B2 (en) | Two-stage shield machine | |
| JP4160681B2 (en) | Propulsion steel pipe joint structure | |
| JP2932957B2 (en) | Underground joint structure of shield machine | |
| JPH07127384A (en) | Small-sized pipe jacking and layout device | |
| JPH0369438B2 (en) | ||
| JP3110927B2 (en) | Backfill injection method in propulsion method | |
| JP3161890B2 (en) | Multifunctional shield machine | |
| JPH0127240B2 (en) | ||
| JP3182100B2 (en) | Method of propelling and burying tubular body and tubular body used in this method | |
| JP2000038897A (en) | Pipe propulsion method and pipe propulsion machine | |
| JP3511429B2 (en) | Replacement of existing buried pipes | |
| JPS59102085A (en) | Enlarging shield machine |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081109 Year of fee payment: 14 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091109 Year of fee payment: 15 |
|
| EXPY | Cancellation because of completion of term | ||
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091109 Year of fee payment: 15 |