JPH03218003A - Fixing method of on-load tap changer - Google Patents
Fixing method of on-load tap changerInfo
- Publication number
- JPH03218003A JPH03218003A JP1319590A JP1319590A JPH03218003A JP H03218003 A JPH03218003 A JP H03218003A JP 1319590 A JP1319590 A JP 1319590A JP 1319590 A JP1319590 A JP 1319590A JP H03218003 A JPH03218003 A JP H03218003A
- Authority
- JP
- Japan
- Prior art keywords
- tank
- tap changer
- load tap
- main body
- oltc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 10
- 239000000725 suspension Substances 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 2
- 238000009413 insulation Methods 0.000 description 2
- 238000004804 winding Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Landscapes
- Housings And Mounting Of Transformers (AREA)
Abstract
Description
【発明の詳細な説明】
A.産業上の利用分野
この発明は、変圧器のタンクの上タンクから負荷時タッ
プ切換器を吊支するベルタイプ・タンクにおける負荷時
タップ切換器の取り付け方法に関する。[Detailed Description of the Invention] A. INDUSTRIAL APPLICATION FIELD This invention relates to a method for mounting an on-load tap changer in a bell-type tank, in which the on-load tap changer is suspended from an upper tank of a transformer tank.
B,発明の概要
本発明は、上タンク側から負荷時タップ切換器を吊支す
るベルタイプ・タンクの負荷時タップ切換器の取り付け
方法において、
而記負荷時タップ切換器を下タンク若しくは下部締付金
具に取り付けた支持部材で固定して該負荷時タップ切換
器の結線を行い、結線完了後に負荷時タップ切換器本体
を吊り上げ、この負荷時タノブ切換器本体を上タンクの
フランノに取り付け、更にこのフランノに0リングを介
してカバーを取り付けろことにより、上部の複雑な支持
部材を廃止して構造の簡略化を図り、負荷時タップ切換
器のフランノを不要として、タンク外形寸法の縮小と重
量及び油量の低減を図ることができるようにした乙ので
ある。B. Summary of the Invention The present invention provides a method for installing a load tap changer in a bell-type tank in which the load tap changer is suspended from the upper tank side. Connect the on-load tap changer by fixing it with the support member attached to the mounting bracket, and after completing the wiring, lift the on-load tap changer body, attach the on-load tap changer body to the flange of the upper tank, and then By attaching a cover to this flange through an O-ring, the structure is simplified by eliminating the complicated support member at the top, eliminating the need for a flange for the load tap changer, reducing tank external dimensions and weight. This makes it possible to reduce the amount of oil used.
C.従来の技術
ペンタイプ(吊鐘型)タンクの変圧器は、負荷時タップ
切換器(on−load tap changer :
以下、OLTCと略称する)を、第3図(d)に示すよ
うにタンク上部から吊支する構造としたものである。第
3図はその取り付け方法を説明するための要部断面図で
、これらの図において、図の右側はOLTC部、左側は
変圧器部である。図中、3lはO L T Cの本体,
32は変圧器の上部締付金具、33は支持部材で、上郎
締付金具33に固着され、OLTCC7)木体3lを支
持する。34はOLTCの上部に設けられたフランジ、
35は上タンクを示している。C. Conventional technology pen-type (bell-shaped) tank transformers are equipped with on-load tap changers:
The OLTC (hereinafter abbreviated as OLTC) is suspended from the top of the tank as shown in FIG. 3(d). FIG. 3 is a sectional view of a main part for explaining the method of attachment. In these figures, the right side of the figure is the OLTC section, and the left side is the transformer section. In the figure, 3l is the main body of OLT C,
Reference numeral 32 denotes an upper clamping fitting of the transformer, and numeral 33 denotes a support member, which is fixed to the upper clamping fitting 33 and supports the OLTCC 7) wooden body 3l. 34 is a flange provided on the top of the OLTC,
35 indicates the upper tank.
OLTCの本体を取り付ける場合は、第3図(a)に示
すように、上部締付金具32に支持部材33を取り付け
、OLTCの本体上部のフランジ34をこれに吊り掛け
てOLTCの本体31を一時固定する。そしてこの状態
でOLTCのタップリードの結線や変圧器の中身締め付
けを行い、これが完了した後、上タンク35をかぶせ、
次に第3図(b)に示すように、吊りボルト41をOL
TCのフランジ34に取り付け、吊りワイヤ42でOL
TCの本体3lを吊り上げる。そして取付ボルト43で
、上タンクのフランジ36に取り付ける。When installing the OLTC main body, as shown in FIG. 3(a), attach the support member 33 to the upper clamping fitting 32, hang the flange 34 on the upper part of the OLTC main body from this, and temporarily hold the OLTC main body 31. Fix it. Then, in this state, connect the OLTC tap leads and tighten the contents of the transformer, and after completing this, cover the upper tank 35,
Next, as shown in FIG. 3(b), attach the hanging bolt 41 to the OL.
Attach to TC flange 34 and use hanging wire 42 to connect OL
Lift up the 3L main body of the TC. Then, it is attached to the flange 36 of the upper tank using a mounting bolt 43.
そしてワイヤ42と吊りボルト41とを取り外す。Then, the wire 42 and hanging bolt 41 are removed.
次に第3図(c)に示すように、0リング44を当てカ
バー45を取付ボルト46により、フランジ36に取り
付ける第3図(d)はその取り付けられた状態を示して
いる。Next, as shown in FIG. 3(c), the O-ring 44 is applied and the cover 45 is attached to the flange 36 using the mounting bolts 46. FIG. 3(d) shows the attached state.
D 発明か解決しようとする課題
しかしながら、中容量の変圧器の場合、電圧によっては
鉄心巻線の中身の高さによりOLTCの高さの方が高く
なることがあり、OLTC部のみタンク高さより上げる
必要も生じるので、そのような場合支持部材33の構造
か複雑にならざるを得ない。D. Invention or problem to be solved However, in the case of medium capacity transformers, depending on the voltage, the height of the OLTC may be higher than the height of the core winding, so it is necessary to raise only the OLTC part above the tank height. In such a case, the structure of the support member 33 must become complicated.
また、上記従来の方法では、本体3Iの上部にフランジ
34が必要であり、OLTC郎におけるタンクの幅方向
寸法は、OLTCとタンクとの間の絶縁寸法よりむしろ
フランジ34の寸法で決定される場合が多く、外形寸法
の増大や重量及び油量の増加を招いている。Further, in the above conventional method, the flange 34 is required on the upper part of the main body 3I, and the width direction dimension of the tank in the OLTC is determined by the dimension of the flange 34 rather than the insulation dimension between the OLTC and the tank. This results in an increase in external dimensions, weight, and oil volume.
本発明は、このような課題に鑑みて創案されたもので、
上部の複雑な支持部材を廃止して構造の簡略化を図り、
OLTCの上部フランジが不要で、タンク外形寸法の縮
小と重量及び油量の低減を図ることが可能な負荷時タッ
プ切換器の取り付け方法を提供することを目的としてい
る。The present invention was created in view of these problems, and
The structure was simplified by eliminating the complicated support member at the top.
It is an object of the present invention to provide a method for attaching an on-load tap changer that does not require an upper flange of an OLTC and can reduce tank external dimensions, weight, and oil amount.
E.課題を解決するための手段
本発明における上記課題を解決するための手段は、上タ
ンク側から負荷時タップ切換器を吊支するベルタイプ・
タンクの負荷時タップ切換器の取付方法において、萌記
負荷時タップ切換器を下タンク若しくは下郎締付金具に
取り付けた支持部材で固定して該負荷時タップ切換器の
結線を行い、結線完了後に上タンクをかぶせ、次に負荷
時タップ切換器本体を吊り上げ、この負荷時タップ切換
器本体を上タンクのフランジに取り付け、更にこのフラ
ンジにOリングを介してカバーを取り付けろ。E. Means for Solving the Problems Means for solving the above problems in the present invention is a bell-type device that suspends the on-load tap changer from the upper tank side.
In the installation method for a tank load tap changer, fix the load tap changer with a support member attached to the lower tank or the lower tank and connect the load tap changer, and then connect the load tap changer after completing the wiring. Cover with the upper tank, then lift the on-load tap changer body, attach the on-load tap changer body to the flange of the upper tank, and then attach the cover to this flange via an O-ring.
F 作用
本発明は、OLTCの結線を完了して上タンクへ吊り上
げるまでの間、作業のための一時的固定を下側から行な
う。一時的に固定する方法としては下タンクのフランジ
を利用して直接に仮置きしてもよいし、下タンクの底仮
に仮置き用の台を配設してもよいし、下部締付金具に支
持部材を取り付け、その支持部材により支承してもよい
。F. Function The present invention performs temporary fixing for work from below until the OLTC is wired and lifted into the upper tank. As a temporary fixing method, you can use the flange of the lower tank to temporarily place it directly, you can set up a temporary stand at the bottom of the lower tank, or you can use the bottom of the lower tank to fix it temporarily. A support member may be attached and supported by the support member.
G 実施例
以下、図面を参照して、本発明の実施例を詳細に説明す
る。G. Embodiments Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
第1図は、本発明の一実施例の取り付け方法を説明する
ための断面図である。従来例と同様に、同図(a)はO
LTCの取り付け途中の構造を示し、図(d)は取り付
けられた状態を示めしている。各図の右側はOLTC部
であり、左側は鉄心巻線部である。lはOLTCの本体
、2は変圧器鉄心の上部締付金具であって、OLTCの
結線を完了するまでの間は、図(2L)に示す如く、下
タンク3のフランノ4を利用して本体lを直接に仮置き
し、本体lを一時的に固定しておいて、タップリードの
結線や中身締め付けを行う。FIG. 1 is a sectional view for explaining an attachment method according to an embodiment of the present invention. Similarly to the conventional example, the figure (a) shows O
The structure of the LTC is shown in the middle of being installed, and Figure (d) shows the installed state. The right side of each figure is the OLTC section, and the left side is the core winding section. 1 is the main body of the OLTC, and 2 is the upper fastening fitting for the transformer core. Until the OLTC wiring is completed, the flange 4 of the lower tank 3 is used to tighten the main body. 1 directly and temporarily fix the main body 1, then connect the tap leads and tighten the contents.
次に、上タンク5をかぶせ、図(b)のように吊ボルト
11をOLTCの本体1の上部に取り付け、ワイヤI2
でOLTCの本体lを吊り上げる。Next, cover the upper tank 5, attach the hanging bolt 11 to the top of the OLTC main body 1 as shown in Figure (b), and wire I2
Lift up the OLTC main body l.
そして取付ポルトl3により、上タンク5のフランジI
4にOLTCの本体lを取り付ける。次に図(c)に示
すようにワイヤl2と吊ボルトl1を取り外し、0リン
グl5をフランジ14の上部の溝に入れてカバー16を
かぶせ、取付ポルトl7によりカバー16をフランジI
4に取り付ける。Then, attach the flange I of the upper tank 5 using the mounting port L3.
Attach the OLTC main body l to 4. Next, as shown in Figure (c), remove the wire l2 and the hanging bolt l1, put the O-ring l5 into the groove at the top of the flange 14, cover the cover 16, and attach the cover 16 to the flange I using the mounting port l7.
Attach to 4.
図(d)はこの取り付けか完了した状態を示している。Figure (d) shows the state in which this installation is completed.
なお、上記の実施例においては、OLTCの本体1を一
時的に仮買き固定する手段として、下タンクのフランジ
4を利用したが、第2図(a)に示すように、下部締付
金具6に支持部材7を取り付け、端部を台8で支持し、
この支持部材7に支持してもよく、また図(b)のよう
に単に下タンクの底坂上に仮置き用の台8を置き、この
台上に支持してしよい。In the above embodiment, the flange 4 of the lower tank was used as a means for temporarily fixing the main body 1 of the OLTC, but as shown in FIG. A support member 7 is attached to 6, the end is supported by a stand 8,
It may be supported by this support member 7, or it may be simply placed on a temporary stand 8 on the bottom slope of the lower tank and supported on this stand, as shown in FIG. 7(b).
H.発明の効果
以上のように本発明は、OLTC部が変圧器の中身より
高くなっても複雑な上部支持部材を廃止することができ
て構造の簡略化が図れ、またタップ切換器の上部のフラ
ンンも不要となり、タップ切換器とタンク間の絶縁寸法
はフランノの無い分短縮できてタンクの外形寸法が縮小
できる。従って油量および全体の重量の低減ができる。H. Effects of the Invention As described above, the present invention makes it possible to simplify the structure by eliminating the need for a complicated upper support member even if the OLTC section is higher than the contents of the transformer. The insulation dimension between the tap changer and the tank can be shortened due to the absence of a flange, and the external dimensions of the tank can be reduced. Therefore, the amount of oil and the overall weight can be reduced.
第1図は本発明の取り付け寸法の一実施例を説明するた
めの要部断面図、第2図は本発明の他の実施例の説明図
、第3図は従来例の取り付け方法の説明図。
1,3I・・・OLTCの本体、2.32・・・上部締
付金具、3 ・下タンク、4・フランジ、5・・・上タ
ンク、6・・・下部締付金具、7・・・支持部材、8・
・台、l1・・・吊ボルト、l2・・・ワイヤ、13・
・・取付ボルト、14・・・タンクのフランジ、15・
・・Oリング、16 カバー
外2名
第1図(1)
,2トくデでミシqtn 一實シ^=?干シ゛弓0ブh
FI立謀η11し冫コ(a)
第1図(2)
ホ売明り一寅先号10組立説明閃
(d)
第2図
Aシ肋だQ支充分・1f号邪館面関
(a)
(b)
第3図(2)Fig. 1 is a sectional view of a main part for explaining one embodiment of the mounting dimensions of the present invention, Fig. 2 is an explanatory drawing of another embodiment of the present invention, and Fig. 3 is an explanatory drawing of a conventional mounting method. . 1, 3I...OLTC main body, 2.32...Upper clamping bracket, 3.Lower tank, 4.Flange, 5...Upper tank, 6...Lower clamping bracket, 7... Support member, 8.
・Stand, l1... Hanging bolt, l2... Wire, 13.
...Mounting bolt, 14...Tank flange, 15.
・・O-ring, 16 2 people outside the cover Figure 1 (1) , 2 pieces and qtn Ichijishi =? Dry bow 0bh
FI plot η11 Shishiko (a) Figure 1 (2) Houri Akira Ichitora first issue 10 assembly explanation flash (d) Figure 2 (b) Figure 3 (2)
Claims (1)
ルタイプ・タンクの負荷時タップ切換器の取り付け方法
において、 前記負荷時タップ切換器を下タンク若しくは下部締付金
具に取り付けた支持部材で固定して該負荷時タップ切換
器の結線を行い、結線完了後に上タンクをかぶせ、次に
負荷時タップ切換器本体を吊り上げ、この負荷時タップ
切換器本体を上タンクのフランジに取り付け、更にこの
フランジにOリングを介してカバーを取り付けるように
したことを特徴とする負荷時タップ切換器の取り付け方(1) In a method for installing a load tap changer in a bell-type tank in which the load tap changer is suspended from the upper tank side, a support member is provided in which the load tap changer is attached to the lower tank or lower clamping fitting. , then connect the on-load tap changer with How to install an on-load tap changer characterized by attaching a cover to this flange via an O-ring
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1319590A JPH03218003A (en) | 1990-01-23 | 1990-01-23 | Fixing method of on-load tap changer |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1319590A JPH03218003A (en) | 1990-01-23 | 1990-01-23 | Fixing method of on-load tap changer |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH03218003A true JPH03218003A (en) | 1991-09-25 |
Family
ID=11826378
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1319590A Pending JPH03218003A (en) | 1990-01-23 | 1990-01-23 | Fixing method of on-load tap changer |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH03218003A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102701091A (en) * | 2012-01-04 | 2012-10-03 | 吴江市东泰电力特种开关有限公司 | On-load tap-changer hanger frame |
-
1990
- 1990-01-23 JP JP1319590A patent/JPH03218003A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102701091A (en) * | 2012-01-04 | 2012-10-03 | 吴江市东泰电力特种开关有限公司 | On-load tap-changer hanger frame |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH03218003A (en) | Fixing method of on-load tap changer | |
| CN208761965U (en) | A kind of multi-coil magnechuck | |
| CN208111252U (en) | A kind of auxiliary device of oil-immersed transformer | |
| CN210223702U (en) | Auxiliary device for transformer | |
| JPH027450Y2 (en) | ||
| JPS583284Y2 (en) | Contents of transformer Hanging ear and steadying device | |
| JPH04201966A (en) | Moving cable for elevator | |
| JPH04332109A (en) | Lifting device for on-load tap changer | |
| JPS582021Y2 (en) | Electrical equipment with tap changer | |
| JPH0331064Y2 (en) | ||
| CN215643984U (en) | Dry-type transformer convenient to installation | |
| JPH0775444B2 (en) | How to install a transformer on a cubicle | |
| KR101916220B1 (en) | Molded Transformer | |
| CN105047379B (en) | Suspended load type transformer | |
| CN113285410B (en) | Cable support and construction method thereof | |
| JPH0751783Y2 (en) | Neutral point grounding device | |
| CN223650640U (en) | A multi-functional analog circuit breaker | |
| CN217788185U (en) | Novel reactor core limb mounting tool | |
| CN214883177U (en) | Device for road traffic indication | |
| CN208831898U (en) | A kind of antidetonation suspension and support | |
| JPS57126115A (en) | Assembling method for transformer with on-load tap changer | |
| JPS649725B2 (en) | ||
| JP2513663Y2 (en) | Neutral point grounding device | |
| JPS589572B2 (en) | On-load tap-changing transformer | |
| CN109319650A (en) | Spreader for installing gamma-ray burst detector and installation method of gamma-ray burst detector |