JPH0342365B2 - - Google Patents
Info
- Publication number
- JPH0342365B2 JPH0342365B2 JP4553684A JP4553684A JPH0342365B2 JP H0342365 B2 JPH0342365 B2 JP H0342365B2 JP 4553684 A JP4553684 A JP 4553684A JP 4553684 A JP4553684 A JP 4553684A JP H0342365 B2 JPH0342365 B2 JP H0342365B2
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- construction
- frame
- column
- viaduct
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000009415 formwork Methods 0.000 claims description 58
- 238000010276 construction Methods 0.000 claims description 27
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 8
- 239000000725 suspension Substances 0.000 claims description 8
- 238000000034 method Methods 0.000 claims description 6
- 239000000463 material Substances 0.000 description 3
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】
本発明は、鉄道、道路等の高架コンクリート構
造物のように、多数列設された柱体上に構築され
るスラブを、柱体間に型枠を移動させながら連続
的に施工する、高架橋スラブの移動式型枠工法に
関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention is a method for constructing slabs constructed on multiple rows of columns, such as elevated concrete structures for railways, roads, etc., by moving formwork between the columns. This relates to a mobile formwork method for constructing viaduct slabs.
コンクリートの高架橋等の工事は、殆んど同じ
形状の構造物を連続的に構築する工事であるた
め、その型枠施工においては、能率的、省力的な
移動式の型枠を使用した工法が採用されてきてい
る。この種工法は、例えば特公昭56−37363号公
報に示されているように、型枠の取扱いには門型
クレーン等のような大型クレーンを使つて吊上
げ、吊降し、移動を行つており、その取扱うため
の装置が極めて大型なものになるとともに、クレ
ーンの移動のために広い専用敷地が必要となり、
施工経費が増大するばかりでなく、工事の専用敷
地が十分にとれないところでは、移動式の型枠工
法を導入することができず、旧来の手組み、手払
いによる非能率的な型枠施工によらざるを得ない
という実情である。 Construction of concrete viaducts involves constructing structures of almost the same shape continuously, so it is recommended to use a method that uses mobile formwork, which is efficient and labor-saving. It is being adopted. In this type of construction method, for example, as shown in Japanese Patent Publication No. 56-37363, a large crane such as a portal crane is used to lift, lower, and move the formwork. , the equipment used to handle it becomes extremely large, and a large dedicated site is required to move the crane.
Not only does construction cost increase, but in places where there is not enough dedicated land for construction, it is not possible to introduce mobile formwork construction methods, and the traditional method of hand-assembling and hand-painting formwork construction is inefficient. The reality is that we have no choice but to do so.
本発明は、前記のような従来の移動式型枠工法
による欠点を解決して、型枠の移動等の取扱いが
容易で施工が能率よく行い得るとともに、型枠取
扱いのために大型クレーン等を使用することな
く、しかも、型枠取扱い装置のための専用敷地が
不要で施工経費を大巾に節減することのできる新
規な移動式型枠工法を提供しようとするものであ
つて、柱体を高架橋の長さ方向に所要の間隔をお
いて列設した柱体列の複数を、高架橋の巾方向に
所要の間隔をおいて対設し、それら対向する支柱
列の間に、施工方向にわたつて型枠の支持、移動
用の架台を移動自在に設けるとともに、各柱体上
に施工方向にわたつて型枠吊台車を移動自在に設
け、型枠体を型枠吊台車により所定の位置に吊上
げ、型枠体と架台との間に支持台を介入して型枠
を支持させてコンクリートの打設を可能となし、
後支持台を除去して型枠体を架台上に吊降し、型
枠体の吊具を引き上げて、型枠吊台車及び型枠体
を載置した架台を次の施工場所に移動させること
を特徴とするものである。 The present invention solves the drawbacks of the conventional mobile formwork construction method as described above, allows easy handling of the formwork, enables efficient construction, and eliminates the need for large cranes, etc. to handle the formwork. The purpose of this project is to provide a new mobile formwork construction method that can significantly reduce construction costs by eliminating the need for a dedicated site for formwork handling equipment. A plurality of rows of pillars arranged at the required intervals in the length direction of the viaduct are placed opposite each other at the required intervals in the width direction of the viaduct, and between these rows of columns facing each other, a column is placed across the construction direction. A frame for supporting and moving the formwork is provided in a movable manner, and a formwork suspension cart is provided movably in the construction direction on each pillar, and the formwork is held in a predetermined position by the formwork suspension cart. Lift it up, interpose a support stand between the formwork body and the frame to support the formwork, and enable concrete pouring.
Remove the rear support stand, suspend the formwork onto the stand, pull up the hanger for the formwork, and move the formwork suspension truck and the stand on which the formwork is placed to the next construction site. It is characterized by:
以下、本発明の実施例について図面を参照して
説明する。 Embodiments of the present invention will be described below with reference to the drawings.
図において1,1′……は高架橋の柱体で、高
架橋の長さ方向に所要の間隔をおいて多数列設し
た柱体1,1により一方の柱体列が形成され、そ
れら各柱体1,1と高架橋の巾方向に所要の間隔
をおいて対向し多数の柱体1′,1′(第6図参
照)を列設した他方の柱体列が形成されている。
そして、上記各柱1,1′の互に対向する側であ
る内側には、それぞれ所要の高さに埋込ボルトを
介して上面に車輪3を設けたブラケツト2が取付
けられる。 In the figure, 1, 1'... are the columns of the viaduct, and one column row is formed by a large number of columns 1, 1 arranged at required intervals in the length direction of the viaduct. 1, 1, and the other pillar row is formed in which a large number of pillars 1', 1' (see FIG. 6) are arranged in a row facing each other at a required interval in the width direction of the viaduct.
A bracket 2 having a wheel 3 on its upper surface is attached to the inner side of each of the pillars 1, 1', which are opposite to each other, at a required height via embedded bolts.
そして、上記の対向する両柱体列の間には、各
柱体列の車輪3,3上に載架されて、施工方向即
ち高架橋の長さ方向に延長する一対の桁材4a,
4a及びこれと直交して架設された梁材4b,4
bよりなる架台4を走行移動自在に設ける。 A pair of girder members 4a, which are mounted on the wheels 3, 3 of each column column and extend in the construction direction, that is, the length direction of the viaduct, are provided between the above-mentioned opposing columns.
4a and beam members 4b and 4 installed perpendicularly thereto.
A frame 4 consisting of a frame 4 is provided so as to be freely movable.
型枠の施工は対向する4本の柱体間を単位場所
として行うのであるが、第1図のようにその当初
は、架台4に所要高さの支持台5を載置し、さら
にその上に型枠体6を組立て載置する。支持台5
は一般的には杆材等を適宜結合して箱枠状に形成
し、また型枠体6は、箱枠状に形成した受枠6a
上に構築するスラブの下面形状に応じた形の型枠
6bを組付けて形成されており、型枠6bの中央
部には型枠吊用の窓孔6cが設けられ、この窓孔
6cはコンクリートの打設時に栓体7により閉塞
される。 The construction of formwork is carried out between the four opposing columns as a unit, but as shown in Figure 1, at the beginning, a support stand 5 of the required height is placed on the pedestal 4, and then a The form body 6 is assembled and placed on. Support stand 5
is generally formed into a box frame shape by appropriately bonding rod materials, etc., and the form body 6 is a receiving frame 6a formed into a box frame shape.
It is formed by assembling a formwork 6b with a shape corresponding to the lower surface shape of the slab to be constructed above, and a window hole 6c for hanging the formwork is provided in the center of the formwork 6b. It is closed by the plug body 7 when concrete is placed.
前述のようにして型枠体6の設置が完了したな
らば、この型枠以外に必要な型枠8は例えば第1
図の鎖線で示すように組立てられ、これら型枠内
にはコンクリート9が打設される。その際、窓孔
6c上にこの窓孔6cに連通して型枠吊りのため
のワイヤー用の吊孔10を形成させる。それには
型枠6bの窓孔6cに吊孔10形成用の管体を接
続してコンクリートを打設し、その硬化後管体を
抜取るようにすればよい。 Once the installation of the formwork body 6 is completed as described above, the formwork 8 that is necessary other than this formwork is, for example, the first
They are assembled as shown by the chain lines in the figure, and concrete 9 is poured into these forms. At that time, a hanging hole 10 for a wire for hanging the formwork is formed above the window hole 6c and communicating with the window hole 6c. This can be done by connecting a tube for forming the hanging hole 10 to the window hole 6c of the formwork 6b, pouring concrete, and removing the tube after it hardens.
打設したコンクリートが硬化したならば、第2
図のように、コンクリート9上に当材16を置く
とともに、次の施工場所に位置する柱体1,1′
上に仮設台11を載置し、それら当材16と仮設
台11を介して各柱体1,1′の施工方向にわた
つてレール12,12を敷設し、そのレール1
2,12上に門型に形成し吊揚器14を備えた型
枠吊台車13を載置する。そして、型枠の栓体7
を取外し、吊揚器14のワイヤ14aを伸し、コ
ンクリートの吊孔10及び型枠の窓孔6cを通し
て、型枠体の受枠6aに取付けた受ロープ15に
フツク14bを掛け、型枠体6を吊持する。次い
で支持台5を除去し、第3図のようにさらにワイ
ヤ14aを伸して、型枠体6を直接架台4上に載
置する。 Once the poured concrete has hardened, the second
As shown in the figure, the material 16 is placed on the concrete 9, and the columns 1 and 1' are placed at the next construction site.
A temporary stand 11 is placed on top, and rails 12, 12 are laid across the construction direction of each column 1, 1' via the material 16 and the temporary stand 11, and the rails 1
A formwork lifting cart 13 formed into a gate shape and equipped with a lifting device 14 is placed on 2 and 12. And the stopper 7 of the formwork
The wire 14a of the hoist 14 is stretched out, passed through the concrete hoisting hole 10 and the window hole 6c of the formwork, and the hook 14b is hung on the receiving rope 15 attached to the receiving frame 6a of the formwork body. to hang. Next, the support stand 5 is removed, the wire 14a is further extended as shown in FIG. 3, and the frame body 6 is placed directly on the stand 4.
次に、ワイヤ14aを巻揚げて、型枠吊台車1
3をレール12に沿つて次の施工場所まで移動さ
せるとともに、架台4も車輪3,3上を次の施工
場所まで第4図のように移動する。そして、再び
ワイヤ14aを伸して型枠6bの窓孔6cにフツ
ク14bを通して受ロープ15に掛合せ、第5図
のように型枠体6を吊上げ、所定の位置において
支持台5を介入し、型枠体6を固定させ、フツク
14bをはずしてロープ14aを巻上げる。その
後は前記の作業を繰返すことにより施工を順次進
めて行くのである。また、コンクリート9に形成
された吊孔10には、その後モルタル等を充填す
るのである。 Next, the wire 14a is hoisted up and the formwork hanging trolley 1 is
3 is moved along the rails 12 to the next construction site, and the frame 4 is also moved on the wheels 3, 3 to the next construction site as shown in FIG. Then, extend the wire 14a again, pass the hook 14b through the window hole 6c of the formwork 6b, hook it to the receiving rope 15, lift the formwork 6 as shown in FIG. 5, and insert the support stand 5 at a predetermined position. , fix the form body 6, remove the hook 14b, and wind up the rope 14a. After that, construction progresses one by one by repeating the above-mentioned operations. Further, the suspension holes 10 formed in the concrete 9 are then filled with mortar or the like.
なお、前記実施例において、型枠移動用の架台
4は、各柱体1,1′に設けたブラケツト2の車
輪3上に載つて移動するものとなつているが、こ
の架台4の移動手段としてはこれに限定されるも
のではなく、他に例えば第7図に示すように、各
柱体1,1……の施工方向にわたつてレール18
を架設しておき、架台4の方に車輪17を設けて
レール18上を走行移動させるようにしてもよ
く、また、図示を省略したが各柱体1,1′間の
地盤にレールを敷設し、この上で架台を走行移動
させてもよく、他に各種公知の手段が採用でき
る。 In the above embodiment, the pedestal 4 for moving the formwork is moved by riding on the wheels 3 of the bracket 2 provided on each column 1, 1', but the means for moving the pedestal 4 is However, as shown in FIG. 7, for example, as shown in FIG.
It is also possible to install wheels 17 on the pedestal 4 and run it on rails 18, or, although not shown, rails may be laid on the ground between each column 1, 1'. However, the pedestal may be moved on this basis, and various other known means may be employed.
以上説明したように、本発明は、高架橋の巾方
向に間隔をおいて対設した柱体列の間に型枠を支
持する架台を移動自在に設けるとともに、各柱体
列上に型枠の吊揚げ、吊降しをする型枠吊台車を
移動自在に設けて、架台と型枠吊台車との相互操
作により、型枠の設定、脱型、移動の各作業を反
覆して連続的に行うようにしたので、型枠を取扱
うためのクレーン等の大規模な装置や支保工等を
使用することなく施工が簡易、能率的、省力的に
行い得るとともに、大型クレーン等の移動のため
の敷地を要することなく、施工費を大巾に低減す
ることができる等、多くの優れた効果を有するも
のである。 As explained above, the present invention movably provides a pedestal for supporting formwork between rows of pillars arranged at intervals in the width direction of a viaduct, and also provides a platform for supporting formwork on each row of pillars. A movable formwork hoisting trolley for lifting and lowering is provided, and mutual operation between the frame and the formwork hoisting trolley allows the work of setting, demolding, and moving the formwork to be repeated and repeated continuously. As a result, construction can be carried out easily, efficiently, and labor-savingly without using large-scale equipment such as cranes to handle the formwork, and without the use of supporting structures. It has many excellent effects, such as not requiring a lot of land and significantly reducing construction costs.
図面は本発明工法の実施例を示したもので第1
図乃至第5図は工程を順に説明する側面図、第6
図は第2図工程における正面図、第7図は型枠移
動用架台の移動手段の他の実施例を示す側面図で
ある。
1,1′……柱体、2……ブラケツト、3……
車輪、4……架台、5……支持台、6……型枠
体、6b……型枠、6c……窓孔、7……栓体、
9……コンクリート、10……吊孔、12……レ
ール、13……型枠吊台車、14……吊揚器、1
4a……ワイヤ。
The drawings show an example of the construction method of the present invention.
Figures 5 to 5 are side views explaining the steps in order; Figure 6 is a side view explaining the steps in order;
The figure is a front view in the process shown in FIG. 2, and FIG. 7 is a side view showing another embodiment of the moving means for the frame for moving the formwork. 1, 1'...Column, 2...Bracket, 3...
Wheel, 4... Frame, 5... Support stand, 6... Form body, 6b... Formwork, 6c... Window hole, 7... Plug body,
9... Concrete, 10... Hanging hole, 12... Rail, 13... Formwork suspension truck, 14... Lifting device, 1
4a...Wire.
Claims (1)
て列設した柱体列の複数を、高架橋の巾方向に所
要の間隔をおいて対設し、それら対向する支柱列
の間に、施工方向にわたつて、型枠の支持、移動
用の架台を移動自在に設けるとともに、各柱体上
に施工方向にわたつて型枠吊台車を移動自在に設
け、型枠体を型枠吊台車により所定の位置に吊上
げ、型枠体と架台との間に支持台を介入して型枠
を支持させてコンクリートを打設し、その後型枠
体を吊持して支持台を取除き、型枠体を架台に吊
降し、次に型枠吊台車及び型枠体を載置した架台
を次の施工場所に移動させることを特徴とする、
高架橋等スラブの移動式型枠工法。1. A plurality of column columns in which column bodies are arranged at the required intervals in the length direction of the viaduct are arranged oppositely at the required intervals in the width direction of the viaduct, and between these column columns facing each other, A frame for supporting and moving the formwork is provided movably in the construction direction, and a formwork suspension cart is provided movably in the construction direction on each column, and the formwork body is moved on the formwork suspension cart. The formwork is hoisted to a predetermined position, a support stand is inserted between the formwork body and the frame to support the formwork, and concrete is poured.Then, the formwork body is suspended, the support stand is removed, and the mold The method is characterized by suspending the frame body onto a pedestal, and then moving the formwork suspension cart and the pedestal on which the formwork body is placed to the next construction site.
Mobile formwork construction method for slabs such as viaducts.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4553684A JPS60192009A (en) | 1984-03-12 | 1984-03-12 | Moving type mold frame construction method of slab of high bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4553684A JPS60192009A (en) | 1984-03-12 | 1984-03-12 | Moving type mold frame construction method of slab of high bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60192009A JPS60192009A (en) | 1985-09-30 |
| JPH0342365B2 true JPH0342365B2 (en) | 1991-06-27 |
Family
ID=12722103
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4553684A Granted JPS60192009A (en) | 1984-03-12 | 1984-03-12 | Moving type mold frame construction method of slab of high bridge |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60192009A (en) |
-
1984
- 1984-03-12 JP JP4553684A patent/JPS60192009A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS60192009A (en) | 1985-09-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107201719A (en) | Overpass anti-collision wall formwork hoisting conveyance and anti-collision wall construction method | |
| JP3110985B2 (en) | Construction method of column capital of overhang girder bridge | |
| JP2539150B2 (en) | Bridge erection equipment | |
| CN208844424U (en) | Multifunctional assembled construction trolley | |
| US6412132B1 (en) | Methods for constructing a bridge utilizing in-situ forms supported by beams | |
| JP3356048B2 (en) | Construction method of elevated structure using building girder | |
| JP2709091B2 (en) | Manufacturing and stocking method of unit floor | |
| JPH0342365B2 (en) | ||
| JPH0342367B2 (en) | ||
| JPH0342366B2 (en) | ||
| JPH0745799B2 (en) | Method and apparatus for installing precast plate for tunnel | |
| JP3999556B2 (en) | Three-dimensional intersection construction method and three-dimensional intersection | |
| JPS60258311A (en) | Construction of high structure | |
| JP2653644B2 (en) | Formwork support structure and construction method | |
| JP3750089B2 (en) | Construction method of underground structure | |
| JPH0475323B2 (en) | ||
| JP3848758B2 (en) | Construction method for direct suspension of structures | |
| JPH03103572A (en) | Construction of building body | |
| JPS62185905A (en) | Moving type mold frame construction method of slab of high bridge | |
| JP2676600B2 (en) | How to lift and connect beams between columns | |
| JPH06108646A (en) | Method for building stair | |
| JPS62288260A (en) | Moving type mold frame construction method of high bridging slab | |
| JPH0226009B2 (en) | ||
| JPH0546407B2 (en) | ||
| JPH0248684B2 (en) | 2SOPCKOKAKYONODOJISEKOSOCHI |