JPH0347707A - Underground raw concrete factory equipment - Google Patents

Underground raw concrete factory equipment

Info

Publication number
JPH0347707A
JPH0347707A JP18319289A JP18319289A JPH0347707A JP H0347707 A JPH0347707 A JP H0347707A JP 18319289 A JP18319289 A JP 18319289A JP 18319289 A JP18319289 A JP 18319289A JP H0347707 A JPH0347707 A JP H0347707A
Authority
JP
Japan
Prior art keywords
underground
section
aggregate
silo
ready
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP18319289A
Other languages
Japanese (ja)
Inventor
Kazuyoshi Sakamoto
和義 坂本
Hiroshi Kazama
風間 広志
Toshio Sugimoto
杉本 俊夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP18319289A priority Critical patent/JPH0347707A/en
Publication of JPH0347707A publication Critical patent/JPH0347707A/en
Pending legal-status Critical Current

Links

Landscapes

  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 [産業上の利用分野] この発明はセメントと骨材とを計量混練してミキサ車に
供給する生コンクリートの地下工場設備に関するもので
ある。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to underground ready-mixed concrete factory equipment for measuring and kneading cement and aggregate and supplying the mixture to a mixer truck.

[従来の技術] 通常生コンクリートプラントと称されている工場設備は
、セメントサイロ及び骨材サイロとパッチャープラント
とから構成され、骨材をベルトコンベア装置によりパッ
チャープラントの上部に搬送ししている。またセメント
及び骨材、混和剤、水等の計量はパッチャープラント内
にて行なわれ、ミキサによる混練で生じた生コンクリー
トは、パッチャープラントの下側から直にミキサ車のド
ラムに送り込んでいる。
[Prior Art] Factory equipment, usually called a ready-mixed concrete plant, is comprised of a cement silo, an aggregate silo, and a patcher plant, and the aggregate is conveyed to the upper part of the patcher plant by a belt conveyor device. Cement, aggregates, admixtures, water, etc. are measured in the patcher plant, and the ready-mixed concrete produced by mixing with the mixer is directly fed into the drum of the mixer truck from the bottom of the patcher plant.

[発明が解決しようとする課題] このような生コンクリートの工場設備では、骨材のサイ
ズごとにサイロを必要とし、またミキサ車や大型トラッ
クの出入が頻繁なことから、広い敷地を要し、工場騒音
もあるので、市街地の近くに工場を、建設することは困
難とされている。
[Problems to be solved by the invention] Such ready-mixed concrete factory equipment requires silos for each size of aggregate, and requires a large site due to the frequent entry and exit of mixer trucks and large trucks. Due to the noise caused by factories, it is considered difficult to construct factories near urban areas.

また既存の工場でも、地理的に便利な所では、土地の再
開発によって移転を余儀なくされている。
Additionally, existing factories are being forced to relocate due to land redevelopment in geographically convenient locations.

この発明は上記事情から考えられたものであって、その
目的は工場設備の全てを地下に建設し、地上部は土地面
積を広く要せぬ事務棟等とすることができ、工場騒音も
極めて少ない新たな構成の地下生コンクリート工場設備
を提供することにある。
This invention was conceived from the above-mentioned circumstances, and its purpose is to construct all of the factory equipment underground, and the above-ground part can be used as an office building etc. that does not require a large land area, and the noise level of the factory is extremely low. The objective is to provide underground ready-mixed concrete factory equipment with a new configuration.

[課題を解決するための手段] 上記目的によるこの発明特徴は、骨材搬入部とサイロ部
及び骨材分離プラント部と移送部の各作業部を、コンク
リート造の地下構造体の内部に設けて地下操車場と共に
地中にSQ置し、その地下構造体の移送部から上方の地
下操車場にわたり、パッチャープラントを各処理部ごと
に段階的に配設して地下に設けてなることにある。
[Means for Solving the Problems] The feature of this invention according to the above-mentioned object is that the working sections of the aggregate import section, the silo section, the aggregate separation plant section, and the transfer section are provided inside an underground structure made of concrete. The SQ is placed underground together with an underground shunting yard, and a patcher plant is installed underground in stages from the transfer section of the underground structure to the underground shunting yard above, and for each processing section.

上記地下構造体は上部に地下操車場と連絡した骨材搬入
部を有し、その下側にサイロ部及び骨材分離プラント部
と移送部の各作業部を隔壁により区画して備え、上記サ
イロ部は格子状に配した仕切壁と供給口を有する底板と
により区画された上部開口の所要数の骨材サイロからな
り、された上部開口の所要数の骨材サイロからなり、そ
の骨材搬入部の床組が構成され、各作業部の下側の底盤
上にコンベア等の搬送機器が配設されている。
The above-mentioned underground structure has an aggregate loading section in the upper part connected to the underground shunting yard, and below it, the silo section, the aggregate separation plant section, and the transfer section are separated by partition walls, and the above-mentioned silo The section consists of a required number of aggregate silos with an upper opening partitioned by partition walls arranged in a lattice pattern and a bottom plate with a supply port. A floor structure is constructed for each working section, and transport equipment such as a conveyor is arranged on the bottom plate below each working section.

る。Ru.

また骨材分離プラント部と移送部がセメントサイロの収
容部を兼ね、地下構造体の周壁は連続地中壁により構成
されている。
In addition, the aggregate separation plant section and the transfer section also serve as a housing section for the cement silo, and the surrounding wall of the underground structure is composed of a continuous underground wall.

[作 用] 上記構成の地下生コンクリート工場設備では、大型トラ
ックを地下操車場から骨材搬入部に乗入れて、直接骨材
をサイズごとに各骨材サイロに落し入れることができる
[Function] In the underground ready-mixed concrete factory facility having the above configuration, a large truck can be driven into the aggregate delivery section from the underground yard and aggregate can be directly dropped into each aggregate silo by size.

各サイロ内の骨材はサイロ下側から底盤上のコンベアに
より移送部へと送られ、場合によっては骨材分離プラン
ト部からの骨材と共にコンベア装置に移されて、地中に
斜設したパッチャープラントに送出され、ここで通常の
ごとくセメントサイロからのセメントと骨材及び水等の
計量と混線が下方より段階的に行なわれる。
The aggregate in each silo is sent from the bottom of the silo to the transfer section by a conveyor on the bottom plate, and in some cases, is transferred to a conveyor device together with the aggregate from the aggregate separation plant section, and then transferred to a patcher installed diagonally in the ground. It is sent to the plant, where the cement, aggregate, water, etc. from the cement silo are weighed and mixed in stages from below as usual.

また連続地中壁により構成され地下構造体の周壁は止水
性に優れ、骨材サイロを区画形成する仕切壁は地中連続
壁の支保工として作用する。
Furthermore, the peripheral wall of the underground structure, which is composed of a continuous underground wall, has excellent water-stop properties, and the partition walls that partition the aggregate silos function as supports for the underground continuous wall.

以下この発明を図示の実施例により更に詳説する。The present invention will be explained in more detail below with reference to illustrated embodiments.

[実施例1 図中1は地中に建設したコンクリート造の地下構造体で
、地下操IrI場2の一区画に、周壁が連続地中壁3を
もって構成された平断面が方形の容器からなる。
[Example 1 1 in the figure is a concrete underground structure constructed underground, consisting of a container with a rectangular planar cross section and a continuous underground wall 3 in one section of the underground operation IrI field 2. .

この地下構造体1の側部から地下操車場2に対して、コ
ンクリート造のパッチャープラント収容部4が斜設しで
ある。
A patcher plant housing section 4 made of concrete is diagonally installed from the side of the underground structure 1 to the underground train yard 2.

また地下構造体1は、上部に地下操車場2と連絡した骨
材搬入部5を有し、その骨材搬入部5の下側に長方形の
サイロ部6及び骨材分離プラント部7と、移送部8の各
作業部が隔壁9をもって区画されている。
Moreover, the underground structure 1 has an aggregate carrying-in part 5 connected to the underground rail yard 2 at the upper part, and a rectangular silo part 6 and an aggregate separation plant part 7 below the aggregate carrying-in part 5. Each working section of the section 8 is divided by a partition wall 9.

上記サイロ部6と骨材分離プラント部7は側方に隣接し
て区画形成され、その両方の一端部にわたって隔19に
より上記移送部8が区画形成しである。
The silo section 6 and the aggregate separation plant section 7 are laterally adjacent to each other, and the transfer section 8 is defined by a gap 19 over one end of both.

またサイロ部6は、上記連続地中壁3及び隔壁9に接続
して格子状に配した仕切壁1oにより、8つの並列な骨
材サイロ11に区画形成され、底板12により仕切られ
た下側は搬送機器の設置部13として使用される。
Furthermore, the silo section 6 is divided into eight parallel aggregate silos 11 by partition walls 1o connected to the continuous underground wall 3 and the partition wall 9 and arranged in a lattice pattern, and the lower side partitioned by a bottom plate 12. is used as the installation section 13 of the transport equipment.

各骨材サイロ11の上部開口には、所要サイロごとに格
子の大きさが異なるグレーチング14が設けられ、この
グレーチング14と骨材分離プラント部7の上部開口に
設けた床版15とにより、上記骨材搬入部5の床組みが
なされている。
At the upper opening of each aggregate silo 11, a grating 14 whose grid size differs depending on the required silo is provided.This grating 14 and a floor slab 15 provided at the upper opening of the aggregate separation plant section 7 allow the above-mentioned The floor of the aggregate carrying-in section 5 is constructed.

上記地下構造体1の骨材分離プラント部側には、上記パ
ッチャープラント収容部4が、移送部8がら地下操車場
2に向けて斜設してあり、その内にバッ、チャープラン
ト16が、上がらミキサ装@15a、計量装置16b、
供給装置16cの順に配置を通常とは逆にして段階的に
設置しである。また各装置はベルトコンベア17.18
により連絡され、最下位のベルトコンベア18の一部1
8aは上記移送部8に水平に延設されている。
On the aggregate separation plant side of the underground structure 1, the patcher plant accommodating section 4 is installed diagonally toward the underground shunting yard 2 along with the transfer section 8, and a batcher plant 16 is installed therein. Upper mixer unit @15a, measuring device 16b,
The arrangement of the supply devices 16c is reversed from the usual order and is installed in stages. In addition, each device is a belt conveyor 17.18
part 1 of the lowest conveyor belt 18
8a extends horizontally to the transfer section 8.

上記地下構造体1の底盤19は、アースアンカー20に
より地盤にアンカーしてあり、これにより周囲地盤の地
下水の圧力による地下構造体1の浮上りを防止している
The bottom plate 19 of the underground structure 1 is anchored to the ground by an earth anchor 20, thereby preventing the underground structure 1 from floating up due to the pressure of groundwater in the surrounding ground.

また搬送Il器の設置部13及び骨材分離プラント部7
の底盤上には、ベルトコンベア21.22が移送部8の
上記ベルトコンベア18aに向けて水平に配設してあり
、そのベルトコンベア18aに骨材や分離骨材を送り出
すことができるようになっている。
In addition, the installation part 13 of the conveyance unit and the aggregate separation plant part 7
Belt conveyors 21, 22 are arranged horizontally on the bottom plate of the conveyor belt 21, 22 facing the belt conveyor 18a of the transfer section 8, so that aggregates and separated aggregates can be delivered to the belt conveyor 18a. ing.

23は洗車場で、地下操車[4の上記骨材分離プラント
部7に隣接した部分に設けられ、洗浄により生じた骨材
や水は、骨材分離プラント部7に設備した処理装置24
により分離されて、再利用できるようにしである。
Reference numeral 23 denotes a car wash facility, which is installed in a part adjacent to the above-mentioned aggregate separation plant section 7 of the underground car handling facility [4], and aggregates and water generated by washing are passed through a processing device 24 installed in the aggregate separation plant section 7.
It is then separated and made available for reuse.

なお、25はセメントサイロで、骨材分離プラント部7
及び移送部8の上側に設置しである。また26は地下操
車場4の上の事務棟である。
In addition, 25 is a cement silo, and aggregate separation plant section 7
and installed above the transfer section 8. 26 is an office building above the underground train yard 4.

このような地下工場設備では、地下操車vA2から骨材
搬入部5に大型トラックを乗り入れて、荷台の骨材を定
められた骨材サイ011の上に下すことができ、骨材は
トラックから直にグレーチング14を通して骨材サイロ
11に投入される。
In such an underground factory facility, a large truck can be driven into the aggregate delivery section 5 from the underground vehicle handling vA2, and the aggregate on the loading platform can be lowered onto a predetermined aggregate size 011, and the aggregate can be directly delivered from the truck. The aggregate is then fed into the aggregate silo 11 through the grating 14.

またグレーチング14を利用して、大きなサイズの異物
や骨材を篩分けすることができ、鉄片などの挟雑物は、
図面は省略したが、上記ベルトコンベア21に設けたマ
グネットセパレータにより除去することができる。
In addition, the grating 14 can be used to screen out large foreign objects and aggregates, and to remove impurities such as iron pieces.
Although not shown in the drawing, it can be removed by a magnetic separator provided on the belt conveyor 21.

各サイロの骨材または骨材分離プラント部の骨材は、必
要に応じてサイズごとに上記ベルトコンベア21.22
により移送部8へと送られ、更にベルトコンベア188
.18へと移し換えられて、パッチャープラント16の
下位の供給袋ff116cに送られる。骨材は更に上位
の計量装置16b。
The aggregate of each silo or the aggregate of the aggregate separation plant section is transported to the belt conveyor 21, 22 according to size as necessary.
is sent to the transfer section 8, and further transferred to the belt conveyor 188.
.. 18 and sent to the lower supply bag ff116c of the patcher plant 16. The aggregate is measured by a higher level measuring device 16b.

ミキサ装@16aへと移送され、ここにおいて他の経路
を経てセメントサイロ25から供給された計量後のセメ
ントと混練されて生コンクリートとなる。
The concrete is transferred to the mixer @ 16a, where it is mixed with weighed cement supplied from the cement silo 25 via another route to become ready-mixed concrete.

この生コンクリートはコンクリートボンにより地下操車
場2のコンクリートホッパ16dに押上げられて、待機
したミキサ車のドラムに流し込まれる。
This fresh concrete is pushed up by a concrete bong into the concrete hopper 16d of the underground train yard 2, and poured into the drum of a waiting mixer truck.

[発明の効果] この発明は上述のように、骨材搬入部とサイロ部及び骨
材分離プラント部と移送部の各作業部を、コンクリート
造の地下構造体の内部に設けて地下操車場と共に地中に
設置し、その地下構造体の移送部から上方の地下操車場
にわたり、パッチャープラントを各処理部ごとに段階的
に配設して地下に設け、これまで設置面積を広く要する
設備の全てを地上から除きいたので、工場敷地の地上を
伯の目的に有効に利用することができる。
[Effects of the Invention] As described above, the present invention provides the working sections of the aggregate import section, the silo section, the aggregate separation plant section, and the transfer section within an underground structure made of concrete, so that they can be installed together with the underground train yard. The patcher plant is installed underground, extending from the transfer section of the underground structure to the underground train yard above, and the patcher plant is installed in stages for each treatment section, replacing all of the equipment that previously required a large installation area. Since the above ground was removed from the ground, the above ground of the factory site can be effectively used for the purpose of the factory.

また多数の骨材サイロが地下にあるので、骨材の荷下し
に際する騒音も外部に洩れず、サイロへの供給も直接に
行なうことができるため、コンベアなどの搬送機器も不
要となる。
In addition, since many aggregate silos are located underground, the noise caused by unloading aggregate does not leak outside, and the supply to the silos can be carried out directly, eliminating the need for conveyors or other transport equipment. .

更にまたパッチャープラントを地中に斜設して高さを減
じたので、パッチャープラントを垂直に設置する場合に
比べて掘削深度が浅く済み、掘削作業に要する費用を節
減することができる。
Furthermore, since the patcher plant is installed diagonally underground to reduce its height, the excavation depth is shallower than in the case where the patcher plant is installed vertically, and the cost required for excavation work can be reduced.

しかも、骨材サイロも隔壁により区画した地下構造体内
を更に仕切壁により区画して形成しので、設置する場合
に比べて掘削深度が浅く済み、掘削作業に要する費用を
節減することができる。
Moreover, since the aggregate silo is also formed within an underground structure partitioned by partition walls and further partitioned by partition walls, the excavation depth can be shallower than in the case where the aggregate silo is installed, and the cost required for excavation work can be reduced.

しかも、骨材サイロも隔壁により区画した地下構造体内
を更に仕切壁により区画して形成しので、地上にサイロ
を個々に建設する場合よりもコスト減となり、連続地中
壁による周壁により止水性が保たれるとともに、仕切壁
が周壁の支保工を兼ねるので堅牢でもあるなど多くの利
点を有する。
Furthermore, since the aggregate silo is formed within an underground structure divided by partition walls and further partitioned by partition walls, the cost is lower than when constructing individual silos above ground, and the continuous underground wall provides water-tightness. It has many advantages, such as being durable and sturdy since the partition wall also serves as a support for the surrounding wall.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明に係る地下生コンクリート工場設備の1
実施例を略示するもので、第1図は隔壁を切除した状態
における第2図A−A線縦断面図、第2図は第1図B−
B線横断面図、第3図はパッチャープラント収容部の縦
断面図、第4図は第1図C−C,線横断面図である。 1・・・・・・地下構造体 2・・・・・・地下操車場 3・・・・・・周壁 4・・・・・・パッチャープラント収容部5・・・・・
・骨材搬入部     6・・・・・・サイロ部7・・
・・・・骨材分離プラント部 8・・・・・・移送部       9・・・・・・隔
壁10・・・・・・仕切壁      11・・・・・
・骨材サイ014・・・・・・グレーチング 16・・・・・・パッチャープラント 16a・・・・・・ミキサ装M    16b・・・・
・・計量装置16c・・・・・・供給装置 16d・・・・・・コンクリートホッパ17.18.1
8a・・・・・・ベルトコンベア19・・・・・・底盤 20・・・・・・アースアンカー
The drawing shows one of the underground ready-mixed concrete factory equipment according to this invention.
This schematically shows an embodiment, and FIG. 1 is a vertical sectional view taken along the line A-A in FIG. 2 with the partition wall removed, and FIG.
FIG. 3 is a vertical sectional view of the patcher plant housing section, and FIG. 4 is a cross sectional view taken along line C--C in FIG. 1. 1... Underground structure 2... Underground marshalling yard 3... Peripheral wall 4... Patcher plant housing section 5...
・Aggregate loading section 6... Silo section 7...
... Aggregate separation plant section 8 ... Transfer section 9 ... Partition wall 10 ... Partition wall 11 ...
・Aggregate size 014... Grating 16... Patcher plant 16a... Mixer installation M 16b...
...Measuring device 16c...Feeding device 16d...Concrete hopper 17.18.1
8a...Belt conveyor 19...Bottom plate 20...Earth anchor

Claims (4)

【特許請求の範囲】[Claims] (1)骨材搬入部とサイロ部及び骨材分離プラント部と
移送部の各作業部を、コンクリート造の地下構造体の内
部に設けて地下操車場と共に地中に設置し、その地下構
造体の移送部から上方の地下操車場にわたり、パッチャ
ープラントを各処理部ごとに段階的に配設して地下に設
けてなることを特徴とする地下生コンクリート工場設備
(1) The working parts of the aggregate carrying-in part, the silo part, the aggregate separation plant part, and the transport part are installed inside a concrete underground structure, and are installed underground together with the underground shunting yard, and the underground structure An underground ready-mixed concrete factory facility characterized in that a patcher plant is installed underground, extending from the transfer section to the underground train yard above, with patcher plants arranged in stages for each processing section.
(2)地下構造体は上部に地下操車場と連絡した骨材搬
入部を有し、その下側にサイロ部及び骨材分離プラント
部と移送部の各作業部を隔壁により区画して備え、上記
サイロ部は格子状に配した仕切壁と供給口を有する底板
とにより区画された上部開口の所要数の骨材サイロから
なり、その骨材サイロの上部開口に設けたグレーチング
により上記骨材搬入部の床組が構成され、各作業部の下
側の底盤上にコンベア等の搬送機器が配設されていると
を特徴とする請求項1記載の地下生コンクリート工場設
備。
(2) The underground structure has an aggregate loading section connected to the underground shunting yard in the upper part, and has a silo section, an aggregate separation plant section, and a transfer section on the lower side separated by partition walls, The silo section consists of a required number of aggregate silos with upper openings partitioned by partition walls arranged in a lattice pattern and a bottom plate having a supply port, and the aggregate is carried in through gratings provided at the upper openings of the aggregate silos. 2. The underground ready-mixed concrete factory facility according to claim 1, wherein a floor assembly is constructed for each working section, and transport equipment such as a conveyor is disposed on a bottom plate below each working section.
(3)骨材分離プラント部と移送部がセメントサイロの
収容部を兼ねることを特徴とする請求項1または2記載
の地下生コンクリート工場設備。
(3) The underground ready-mixed concrete factory equipment according to claim 1 or 2, wherein the aggregate separation plant section and the transfer section also serve as a housing section for a cement silo.
(4)地下構造体の周壁が連続地中壁により構成されて
いることを特徴とする請求項1または2記載の地下生コ
ンクリート工場設備。
(4) The underground ready-mixed concrete factory equipment according to claim 1 or 2, wherein the peripheral wall of the underground structure is constituted by a continuous underground wall.
JP18319289A 1989-07-15 1989-07-15 Underground raw concrete factory equipment Pending JPH0347707A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18319289A JPH0347707A (en) 1989-07-15 1989-07-15 Underground raw concrete factory equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18319289A JPH0347707A (en) 1989-07-15 1989-07-15 Underground raw concrete factory equipment

Publications (1)

Publication Number Publication Date
JPH0347707A true JPH0347707A (en) 1991-02-28

Family

ID=16131385

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18319289A Pending JPH0347707A (en) 1989-07-15 1989-07-15 Underground raw concrete factory equipment

Country Status (1)

Country Link
JP (1) JPH0347707A (en)

Similar Documents

Publication Publication Date Title
CA1067476A (en) Embedded housing for ore crusher
US11141882B2 (en) Concrete batching plant having reduced cycle time and reduced installation and dismantling time
CN108101456B (en) High-water-absorption coarse aggregate high-performance marine concrete and construction method thereof
RU2659362C1 (en) Mobile autonomous plant for production wall building and road materials
CN206426276U (en) Buried concrete mixing plant
KR200458276Y1 (en) Urban Batcher Plant
EP0504089A1 (en) Method and mixture of organic-vegetal coating on surface without a fertile bed
JPH0347707A (en) Underground raw concrete factory equipment
JPH0347706A (en) Underground raw concrete factory equipment
WO2011006532A1 (en) Mobile soil treatment plant and method
JPH0347704A (en) Underground raw concrete factory equipment
JPH03147982A (en) Underground raw concrete factory equipment
WO2018137638A1 (en) Sunken inclined lifting type concrete mixing plant combined with stockyard
JP5049662B2 (en) Method and system for producing fluidized soil
JP2024150173A (en) Concrete Plant
CN206765095U (en) With reference to the T-shaped sunk type stabilized soil mixing station in stock ground
CN2359084Y (en) Movable concrete batching and mixing station
Renáta et al. Comparison of human safety risks between old and new concrete mixing plant
KR0128101B1 (en) A mixing process selecting the ascon and the aspaly
CN215589605U (en) Integrated concrete mixing system
CN103590604B (en) A kind of forced stirrer construction method
KR20060066571A (en) Mixing and Construction System of Construction Repair Materials and Construction Method Using the Same
CN206796212U (en) Compact sunk type stabilized soil mixing station
JPS6021841B2 (en) Remaining green concrete processing equipment
Richardson Batching and mixing concrete