JPH0354724B2 - - Google Patents

Info

Publication number
JPH0354724B2
JPH0354724B2 JP23079085A JP23079085A JPH0354724B2 JP H0354724 B2 JPH0354724 B2 JP H0354724B2 JP 23079085 A JP23079085 A JP 23079085A JP 23079085 A JP23079085 A JP 23079085A JP H0354724 B2 JPH0354724 B2 JP H0354724B2
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
column
thick
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP23079085A
Other languages
Japanese (ja)
Other versions
JPS6290402A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP23079085A priority Critical patent/JPS6290402A/en
Publication of JPS6290402A publication Critical patent/JPS6290402A/en
Publication of JPH0354724B2 publication Critical patent/JPH0354724B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、鉄道や道路等に利用される橋脚に係
り、詳しくは、支柱部に充填鋼管コンクリート構
造を採用した橋脚に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a bridge pier used for railways, roads, etc., and specifically relates to a pier that employs a filled steel pipe concrete structure for its support portion.

[従来の技術] 支柱部に充填鋼管コンクリート構造を採用する
場合、従来の充填鋼管コンクリートは、鋼管とそ
の内部に充填したコンクリートとが互いに付着し
て一体に挙動するものであるため、軸力、曲げ及
び剪断力等の強度を計算するにあたつては、コン
クリート断面+鋼管断面を計算の基準として算定
している。
[Prior Art] When adopting a filled steel pipe concrete structure for a support column, in the conventional filled steel pipe concrete, the steel pipe and the concrete filled inside adhere to each other and behave as one, so axial force, When calculating the strength such as bending and shear force, the concrete cross section + steel pipe cross section is used as the basis for calculation.

[発明が解決しようとする問題点] 上記の充填コンクリート構造においては、軸方
向の圧縮力が作用した場合、鋼管とコンクリート
が一体的に歪むため、大きく歪んだ場合、鋼管は
軸方向の圧縮力だけでミーゼスの降伏条件を越え
たり、局部的な座屈を発生したりする。したがつ
て、鋼管によるコンフアインド効果(鋼管の周方
向応力により、コンクリートが膨らもうとするの
を締め付ける作用)でコンクリートの耐力上昇を
充分期待できるにも拘わらず、増大した軸方向応
力で鋼管がほとんど降伏に達してしまいコンフア
インド効果を充分発揮できず、必要以上に大きな
断面積の支柱部とならざるを得ない、という問題
がある。本発明は、支柱部の圧縮耐力を著しく向
上させ、さらに、曲げに対する鋼管の縁応力の弾
性圧縮、引張の範囲が広くなることにより、従来
のものより支柱部の断面積を小さくすることので
きる橋脚を提供することを目的とする。
[Problems to be Solved by the Invention] In the above-mentioned filled concrete structure, when compressive force in the axial direction is applied, the steel pipe and concrete are distorted integrally, so if the steel pipe is greatly distorted, the compressive force in the axial direction The Mises yield condition may be exceeded or local buckling may occur. Therefore, although the confining effect of the steel pipe (the action of tightening the concrete to prevent it from expanding due to the circumferential stress of the steel pipe) can be expected to sufficiently increase the proof strength of the concrete, the increased axial stress causes the steel pipe to There is a problem in that the confining effect is not sufficiently exerted because the yielding is almost reached, and the support portion has to have a larger cross-sectional area than necessary. The present invention significantly improves the compressive strength of the strut, and further widens the range of elastic compression and tension of the edge stress of the steel pipe against bending, making it possible to reduce the cross-sectional area of the strut compared to conventional ones. The purpose is to provide a bridge pier.

[問題点を解決するための手段] 本発明の橋脚は、フーチングの上に充填鋼管コ
ンクリート製の支柱部を備え、支柱部の上端に上
梁部を備えた橋脚において、支柱部は、フーチン
グ側の太柱部と、段部を介してその太柱部の上に
設けられた上梁部側の細柱部とからなり、太柱部
及び細柱部はそれぞれ別々の鋼管を備えた鋼管コ
ンクリート鋼造のものであつて、しかも鋼管と鋼
管内部に充填したコンクリートとが非付着状態に
あるアンボンド型充填鋼管コンクリートにより構
成されており、さらに太柱部の鋼管の上端は開放
され、また細柱部の鋼管の上端と上梁部の下面と
の間には間〓があることを特徴としている。
[Means for Solving the Problems] The pier of the present invention includes a column made of filled steel pipe concrete on the footing, and an upper beam section at the upper end of the column, in which the column is located on the footing side. It consists of a thick column part and a thin column part on the upper beam side that is installed on the thick column part through a step part, and the thick column part and the thin column part are each made of steel pipe concrete with separate steel pipes. It is made of steel, and is constructed of unbonded steel pipe concrete in which the steel pipe and the concrete filled inside the steel pipe do not adhere to each other, and the upper ends of the steel pipes in the thick columns are open, and the tops of the steel pipes in the thick columns are open. The feature is that there is a gap between the upper end of the steel pipe in the section and the lower surface of the upper beam section.

[作用] 上記構成の橋脚においては、上梁部にかかる荷
重は支柱部に伝達されるが、そのとき、軸方向の
圧縮荷重は、細柱部の鋼管上端が開放しており、
かつ鋼管と充填コンクリートとがアンボンド状態
にあることから、鋼管にはほとんど作用せず、充
填コンクリートのみに作用する。すなわち、鋼管
に作用する軸方向応力がゼロに近くなる。このた
め、鋼管には、コンフアインド効果を与える反作
用としてのリングテンシヨンのみが作用すること
になり、したがつて、ミーゼスの降伏条件を適用
すれば、円周方向応力による鋼管のコンフアイン
ド効果を十分発揮させることができ、その結果、
圧縮荷重に対する強度を著しく向上させることが
でき、支柱部の細柱部の断面積を小さくできる。
このことは太柱部についても同様に言える。
[Function] In the pier with the above configuration, the load applied to the upper beam is transmitted to the support column, but at that time, the compressive load in the axial direction is transmitted to the upper end of the steel pipe of the thin column, which is open.
In addition, since the steel pipe and the filling concrete are in an unbonded state, it hardly acts on the steel pipe and acts only on the filling concrete. That is, the axial stress acting on the steel pipe becomes close to zero. Therefore, only ring tension acts on the steel pipe as a reaction that gives a confining effect. Therefore, if the Mises yield condition is applied, the confining effect of the steel pipe due to the circumferential stress can be fully exerted. As a result,
The strength against compressive loads can be significantly improved, and the cross-sectional area of the narrow column portions of the support columns can be reduced.
The same can be said of the thick column portion.

[実施例] 第1図及び第2図は本発明の一実施例を示すも
のである。
[Embodiment] FIGS. 1 and 2 show an embodiment of the present invention.

地盤Sには、杭1が複数本並んで埋設され、杭
1の上端には、鉄筋コンクリート製のフーチング
2が連結されている。3が鉄筋である。このフー
チング2の上部には、下端をフーチング2に埋め
込んだ状態で、支柱部4の太柱部5を構成する鋼
管6が立設されている。7は、鋼管6を立てると
きの仮り受け治具である。
A plurality of piles 1 are lined up and buried in the ground S, and a footing 2 made of reinforced concrete is connected to the upper end of the pile 1. 3 is the reinforcing steel. A steel pipe 6 constituting the thick column portion 5 of the support portion 4 is erected above the footing 2, with its lower end embedded in the footing 2. 7 is a temporary holding jig for setting up the steel pipe 6.

そして、そのように立設された鋼管6の内部に
コンクリート8が充填されている。この場合、鋼
管6の内面には、予め、鋼管6と充填コンクリー
ト8との付着をなくすための分離材(アンボンド
処理層)9が塗布されており、その上で、鋼管6
の内部にコンクリート8が打設されている。した
がつて、鋼管6とコンクリート8とは軸方向に相
対的に自由に変位できるようになつている。
The inside of the steel pipe 6 thus erected is filled with concrete 8. In this case, a separation material (unbonding layer) 9 is applied to the inner surface of the steel pipe 6 in advance to prevent adhesion between the steel pipe 6 and the filling concrete 8.
Concrete 8 is poured inside. Therefore, the steel pipe 6 and the concrete 8 can be relatively freely displaced in the axial direction.

前記分離材9としては、パラフイン、アスフア
ルト、オイル、グリース、ワセリン等を用い、こ
れを鋼管6の内面に塗布することによりアンボン
ド処理層を形成している。
As the separating material 9, paraffin, asphalt, oil, grease, vaseline, etc. are used, and by applying this to the inner surface of the steel pipe 6, an unbonding treatment layer is formed.

また、このように構成された太柱部5の上端に
は、段部10を介して太柱部5より径の小さい細
柱部11が設けられている。この細柱部11もア
ンボンド型充填鋼管コンクリート構造とされてお
り、この場合の鋼管12の下端は細柱部11の充
填コンクリート8の上端面に埋め込まれており、
鋼管6と鋼管12とは完全に縁が切れている。こ
の鋼管12も、その下側の太柱部5のコンクリー
ト8の打設前に仮り受け治具13により支えなが
ら立設されている。この場合の仮り受け治具13
は、支柱部4を上下に貫く鉄筋14に固定されて
いる。なお、15は充填コンクリート、16は鋼
管12の内面に塗布された分離材である。これ
は、前記分離材9と同じものである。
Further, at the upper end of the thick column part 5 configured in this way, a narrow column part 11 having a smaller diameter than the thick column part 5 is provided with a step part 10 interposed therebetween. This narrow column section 11 also has an unbonded type filled steel pipe concrete structure, and the lower end of the steel pipe 12 in this case is embedded in the upper end surface of the filled concrete 8 of the narrow column section 11.
The edges of the steel pipe 6 and the steel pipe 12 are completely cut off. This steel pipe 12 is also erected while being supported by a temporary holding jig 13 before concrete 8 is placed on the thick column portion 5 below it. Temporary holding jig 13 in this case
are fixed to reinforcing bars 14 that vertically pass through the support column 4. Note that 15 is filled concrete, and 16 is a separating material applied to the inner surface of the steel pipe 12. This is the same as the separation material 9 described above.

また、このように構成された支柱部4の細柱部
5の上端には、上梁部17が設けられている。こ
の上梁部17は、細柱部11のコンクリート15
に一体的に連結され、またこの上梁部17が鋼管
12と直接接触しないよう、鋼管12の上端と上
梁部17の下面との間には、間〓18が形成され
ている。この間〓18は上梁部17に荷重が加わ
つて、ほ柱部11のコンクリート15が縮んでも
上梁部17の下面が鋼管12の上端に接触しない
程度に設定されており、必要以上大きくあけられ
ていない。この場合、上梁部17は、フーチング
2と同様現場打鉄筋コンクリートでできている。
19は上梁部17中の鉄筋である。なお、上梁部
17は現場打コンクリートで作る他、プレキヤス
トコンクリート梁、あるいは鋼製梁としてもよ
い。
Further, an upper beam portion 17 is provided at the upper end of the narrow column portion 5 of the support portion 4 configured in this manner. This upper beam portion 17 is made of concrete 15 of the narrow column portion 11.
A gap 18 is formed between the upper end of the steel pipe 12 and the lower surface of the upper beam part 17 so that the upper beam part 17 does not come into direct contact with the steel pipe 12. During this time, the diameter 18 is set so that even if a load is applied to the upper beam part 17 and the concrete 15 of the pillar part 11 shrinks, the lower surface of the upper beam part 17 will not come into contact with the upper end of the steel pipe 12, so that the opening is not larger than necessary. Not yet. In this case, the upper beam portion 17 is made of cast-in-place reinforced concrete like the footing 2.
Reference numeral 19 indicates reinforcing bars in the upper beam portion 17. In addition to being made of cast-in-place concrete, the upper beam portion 17 may also be a precast concrete beam or a steel beam.

次に、図示の橋脚を作る手順について簡単に述
べる。杭1を施工した後、まず、フーチング2用
の型枠を組み、同時に仮り受け治具7で支柱しな
がら鋼管6を立てる。鋼管6には、予め内面にパ
ラフイン等の分離材9を塗布しておく。その後、
フーチング2の上端レベルまでコンクリートを打
設してフーチング2を構築する。
Next, the procedure for making the illustrated bridge pier will be briefly described. After constructing the pile 1, first, a formwork for the footing 2 is assembled, and at the same time, the steel pipe 6 is erected while being supported using a temporary support jig 7. A separating material 9 such as paraffin is applied to the inner surface of the steel pipe 6 in advance. after that,
The footing 2 is constructed by pouring concrete up to the upper end level of the footing 2.

次に、立設した鋼管6の上方に仮り受け治具1
3で支持をとつて細柱部11用の鋼管12を立設
し、その上で、上梁部17用の型枠を組み、その
際、前記間〓18を確保するための型枠も組む。
そして、鋼管12内及び上梁部型枠内にコンクリ
ートを打設して、細柱部11の充填コンクリート
15部分及び上梁部17を構築し、橋脚を完成す
る。なお、細柱部11のコンクリート15と上梁
部17のコンクリートは別々に打設してもよい。
Next, a temporary receiving jig 1 is placed above the steel pipe 6 that has been erected.
3, the steel pipe 12 for the thin column part 11 is erected with support, and on top of that, a formwork for the upper beam part 17 is assembled, and at this time, a formwork for securing the above-mentioned gap 18 is also assembled. .
Then, concrete is poured into the steel pipe 12 and the upper beam part formwork to construct the filling concrete 15 portion of the narrow column part 11 and the upper beam part 17, and the pier is completed. Note that the concrete 15 for the narrow column portion 11 and the concrete for the upper beam portion 17 may be cast separately.

このような構成の橋脚では、上梁部17にかか
る荷重は支柱部4の細柱部11にまず伝達される
が、そのとき、軸方向の圧縮荷重は、鋼管12の
上端が上梁部17の下面と接触していず、かつ鋼
管12と充填コンクリート15とがアンボンド状
態にあることから、鋼管12にはほとんど作用せ
ず、鋼管12の内部の充填コンクリート15のみ
に作用する。このため、鋼管12には、コンフア
インド効果を与える反作用としてのリングテンシ
ヨンのみが作用することになる。
In a bridge pier with such a configuration, the load applied to the upper beam portion 17 is first transmitted to the narrow column portion 11 of the column portion 4, but at that time, the compressive load in the axial direction is transmitted when the upper end of the steel pipe 12 Since the steel pipe 12 and the concrete filler 15 are not in contact with the lower surface of the steel pipe 12 and are in an unbonded state, it hardly acts on the steel pipe 12 and only acts on the filler concrete 15 inside the steel pipe 12. Therefore, only the ring tension acting as a reaction that gives a confine effect acts on the steel pipe 12.

したがつて、ミーゼスの降伏条件を適用すれ
ば、円周方向応力による鋼管のコンフアインド効
果を十分発揮させることができ、その結果、細柱
部11の圧縮荷重に対する強度を著しく向上させ
ることができ、さらに、曲げに対する鋼管の縁応
力の弾性圧縮、引張の範囲が広くなることによ
り、細柱部の断面積を小さくできる。
Therefore, by applying the Mises yield condition, the confining effect of the steel pipe due to circumferential stress can be fully exhibited, and as a result, the strength of the thin column part 11 against compressive load can be significantly improved, Furthermore, the range of elastic compression and tension of the edge stress of the steel pipe against bending is widened, so that the cross-sectional area of the narrow column portion can be reduced.

以上のことは、太柱部5にも同様に言える。し
たがつて、全体として見た場合も当然、支柱部4
の断面積を小さくできる。また、この橋脚では、
支柱部4を二段に構成し、下方部分を径大にして
いるから大きな曲げ耐力を有する、という特長も
ある。
The above can also be said to the thick pillar portion 5 as well. Therefore, when viewed as a whole, it is natural that the support portion 4
The cross-sectional area of can be reduced. Also, on this pier,
It also has the advantage of having a large bending strength because the support section 4 is structured in two stages and the lower portion has a larger diameter.

なお、上の実施例では、支柱部4の段が二段の
場合を説明したが、中間にさらに段を設けて中細
柱部を形成し、三段あるいはそれ以上の段の支柱
部としてもよい。
In addition, in the above embodiment, the case where the strut part 4 has two stages has been explained, but it is also possible to provide a further stage in the middle to form a medium-thin pillar part, and to form a pillar part with three or more stages. good.

また、上の実施例では、支柱部が1本の場合を
説明したが、2本、あるいはそれ以上の場合にも
本発明は適用できる。第3図は2本の場合の例を
示しており、図中21は杭、22は基礎敷きコン
クリート、23はフーチング、24は支柱部、2
5は太柱部、26は細柱部、27,28は鋼管、
29,30はコンクリート、31,32は分離
材、33は間〓、34は上梁部である。
Further, in the above embodiment, the case where there is one support column has been described, but the present invention can also be applied to a case where there are two or more support columns. Figure 3 shows an example in which there are two piles, 21 is the pile, 22 is the foundation concrete, 23 is the footing, 24 is the column, and 2
5 is a thick column part, 26 is a thin column part, 27 and 28 are steel pipes,
29 and 30 are concrete, 31 and 32 are separating materials, 33 is a gap, and 34 is an upper beam portion.

また、以上の説明では、支柱部4,24の断面
形状については特に触れなかつたが、本発明は、
図示例の如く断面円形のものに限らず、楕円、多
角形等、種々の形状のものに適用できる。
Further, in the above explanation, the cross-sectional shape of the support columns 4 and 24 was not particularly mentioned, but the present invention
The present invention is not limited to having a circular cross section as shown in the figure, but can be applied to various shapes such as an ellipse and a polygon.

[発明の効果] 本発明によれば、鋼管には軸方向荷重がほとん
ど作用しない構造になつているため、鋼管に軸方
向応力がほとんど発生せず、したがつて、ミーゼ
スの降伏条件を適用すれば円周方向応力による鋼
管のコンフアインド効果を十分発揮させることが
できる。その結果、圧縮荷重に対する強度を著し
く向上させることができ、支柱部の断面積を小さ
くできる。さらに、この橋脚では、支柱部を段々
に構成し、下方部分を径大にしているから大きな
曲げ耐力を有するという効果を奏する。
[Effects of the Invention] According to the present invention, since the steel pipe has a structure in which almost no axial load acts on the steel pipe, almost no axial stress is generated in the steel pipe, and therefore the Mises yield condition cannot be applied. In this case, the confining effect of the steel pipe due to the stress in the circumferential direction can be fully exerted. As a result, the strength against compressive loads can be significantly improved, and the cross-sectional area of the support column can be reduced. Furthermore, this pier has the effect of having a large bending strength because the support section is configured in stages and the diameter of the lower portion is increased.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例の側断面図、第2図
は第1図の−線矢視断面図、第3図は本発明
の他の実施例の側断面図である。 2,23……フーチング、4,24……支柱
部、5,25……太柱部、11,26……細柱
部、6,12,27,28……鋼管、8,15,
29,30……充填コンクリート、9,16,3
1,32……分離材、17,34……上梁部、1
8,33……間〓。
FIG. 1 is a side sectional view of one embodiment of the present invention, FIG. 2 is a sectional view taken along the - line in FIG. 1, and FIG. 3 is a side sectional view of another embodiment of the present invention. 2, 23... Footing, 4, 24... Pillar part, 5, 25... Thick column part, 11, 26... Thin column part, 6, 12, 27, 28... Steel pipe, 8, 15,
29,30...Filled concrete, 9,16,3
1, 32... Separation material, 17, 34... Upper beam part, 1
8,33….

Claims (1)

【特許請求の範囲】[Claims] 1 フーチングの上に充填鋼管コンクリート製の
支柱部を備え、支柱部の上端に上梁部を備えた橋
脚において、支柱部は、フーチング側の太柱部
と、段部を介してその太柱部の上に設けられた上
梁部側の細柱部とからなり、太柱部及び細柱部は
それぞれ別々の鋼管を備えた鋼管コンクリート鋼
造のものであつて、しかも鋼管と鋼管内部に充填
したコンクリートとが非付着状態にあるアンボン
ド型充填鋼管コンクリートにより構成されてお
り、さらに太柱部の鋼管の上端は開放されるとと
もに、細柱部の鋼管の上端と上梁部の下面との間
には間〓が設けられていることを特徴とする橋
脚。
1. In a pier that has a column made of filled steel pipe concrete on the footing and an upper beam section at the upper end of the column, the column is connected to the thick column on the footing side and the thick column via the step. The thick column part and the thin column part are each of steel pipe concrete steel construction with separate steel pipes, and the steel pipes and the steel pipes are filled inside. The structure is made of unbonded filled steel pipe concrete with no adhesion to the concrete in which it is attached, and the upper ends of the steel pipes in the thick columns are open, and the gaps between the top ends of the steel pipes in the thin columns and the bottom surface of the upper beams are open. A bridge pier characterized by having a gap.
JP23079085A 1985-10-16 1985-10-16 pier Granted JPS6290402A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23079085A JPS6290402A (en) 1985-10-16 1985-10-16 pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23079085A JPS6290402A (en) 1985-10-16 1985-10-16 pier

Publications (2)

Publication Number Publication Date
JPS6290402A JPS6290402A (en) 1987-04-24
JPH0354724B2 true JPH0354724B2 (en) 1991-08-21

Family

ID=16913303

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23079085A Granted JPS6290402A (en) 1985-10-16 1985-10-16 pier

Country Status (1)

Country Link
JP (1) JPS6290402A (en)

Also Published As

Publication number Publication date
JPS6290402A (en) 1987-04-24

Similar Documents

Publication Publication Date Title
US20200354905A1 (en) Prefabricated, prestressed bridge module
JP2009030350A (en) Precast horizontal beam and pier using it
JPH01256651A (en) Steel pipe concrete pillar structure and construction thereof
JPH07317087A (en) Joint structure of steel wall and reinforced concrete floor slab
JPH0354725B2 (en)
JPH0354727B2 (en)
JPS6290402A (en) pier
JPH0953229A (en) Concrete-filled steel tubular column applied structure and its construction method based on steel reinforced concrete underground wall
JPH05272197A (en) Prestressed concrete member
JPH11140863A (en) Joint member and joint structure of steel pipe sheet pile, and steel pipe sheet pile foundation using them
JPS61261556A (en) Reinforcement of connection part of pillar and beam/slab in inverse impact construction method
JPH05287801A (en) Beam Reinforcement Structure in Ramen Structure Made of Precast Reinforced Concrete
JPH0354726B2 (en)
JPH0415855B2 (en)
KR102671025B1 (en) Pier and Construction Method using Centrifugal High-Strength PHC Piles
JPH0448137B2 (en)
JPH11264190A (en) Connection structure of filled steel tube concrete column
JPH0428067B2 (en)
JP2025001464A (en) Unit for concrete ring and manufacturing method of unit for concrete ring
JPH01121441A (en) Flat slab structure
JPH0353420B2 (en)
JPS6215367Y2 (en)
JPH0423138Y2 (en)
JPH0448136B2 (en)
JPH0261582B2 (en)