JPH0354726B2 - - Google Patents
Info
- Publication number
- JPH0354726B2 JPH0354726B2 JP23079285A JP23079285A JPH0354726B2 JP H0354726 B2 JPH0354726 B2 JP H0354726B2 JP 23079285 A JP23079285 A JP 23079285A JP 23079285 A JP23079285 A JP 23079285A JP H0354726 B2 JPH0354726 B2 JP H0354726B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- concrete
- filled
- axial
- upper beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 67
- 239000010959 steel Substances 0.000 claims description 67
- 239000004567 concrete Substances 0.000 claims description 38
- 230000000694 effects Effects 0.000 description 8
- 239000000463 material Substances 0.000 description 7
- 238000005452 bending Methods 0.000 description 3
- 238000009415 formwork Methods 0.000 description 3
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 239000012188 paraffin wax Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 238000000926 separation method Methods 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000010521 absorption reaction Methods 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 239000010426 asphalt Substances 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000008602 contraction Effects 0.000 description 1
- 239000004519 grease Substances 0.000 description 1
- 239000003921 oil Substances 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 229940099259 vaseline Drugs 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
- Rod-Shaped Construction Members (AREA)
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は、鉄道や道路等に利用される橋脚に係
り、詳しくは、支柱部に充填鋼管コンクリート構
造を採用した橋脚に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a bridge pier used for railways, roads, etc., and specifically relates to a pier that employs a filled steel pipe concrete structure for its support portion.
[従来の技術]
支柱部に充填鋼管コンクリート構造を採用する
場合、従来の充填鋼管コンクリートは、鋼管とそ
の内部に充填したコンクリートとが互いに付着し
て一体に挙動するものであるため、軸力、曲げ及
び剪断力等の強度を計算するにあたつては、コン
クリート断面+鋼管断面を計算の基準として算定
している。[Prior Art] When adopting a filled steel pipe concrete structure for a support column, in the conventional filled steel pipe concrete, the steel pipe and the concrete filled inside adhere to each other and behave as one, so axial force, When calculating the strength such as bending and shear force, the concrete cross section + steel pipe cross section is used as the basis for calculation.
[発明が解決しようとする問題点]
上記の充填鋼管コンクリート構造においては、
軸方向の圧縮力が作用した場合、鋼管とコンクリ
ートが一体的に歪むため、大きく歪んだ場合、鋼
管は軸方向の圧縮力だけでミーゼスの降伏条件を
越えたり、局部的な座屈を発生したりする。した
がつて、鋼管によるコンフアインド効果(鋼管の
周方向応力により、コンクリートが膨らもうとす
るのを締め付ける作用)でコンクリートの耐力上
昇を充分期待できるにも拘わらず、増大した軸方
向応力で鋼管がほとんど降伏に達してしまいコン
フアインド効果を充分発揮できず、必要以上に大
きな断面積の支柱部とならざるを得ない、という
問題がある。本発明は、支柱部の圧縮耐力を著し
く向上させ、さらに、曲げに対する鋼管の縁応力
の弾性圧縮、引張の範囲が広くなることにより、
従来のものより支柱部の断面積を小さくすること
のできる橋脚を提供することを目的とする。[Problems to be solved by the invention] In the above-mentioned filled steel pipe concrete structure,
When compressive force in the axial direction is applied, the steel pipe and concrete are distorted together, so if the pipe is significantly distorted, the pipe may exceed the Mises yield condition or cause local buckling due to the compressive force in the axial direction alone. or Therefore, although the confining effect of the steel pipe (the action of tightening the concrete to prevent it from expanding due to the circumferential stress of the steel pipe) can be expected to sufficiently increase the proof strength of the concrete, the increased axial stress causes the steel pipe to There is a problem in that the confining effect is not sufficiently exerted because the yielding is almost reached, and the support portion has to have a larger cross-sectional area than necessary. The present invention significantly improves the compressive strength of the support column, and furthermore, the range of elastic compression and tension of the edge stress of the steel pipe against bending is widened.
It is an object of the present invention to provide a bridge pier whose support section can have a smaller cross-sectional area than conventional ones.
[問題点を解決するための手段]
本発明の橋脚は、フーチングの上に充填鋼管コ
ンクリート製の支柱部を備え、支柱部の上端に上
梁部を備えた橋脚において、支柱部を、鋼管と鋼
管内部に充填したコンクリートとが非付着状態に
あるアンボンド型充填鋼管コンクリートにより構
成され、かつ前記鋼管の軸方向の少なくとも一部
に、鋼管に生じる軸方向の変形を吸収する変形吸
収部が設けたことを特徴としている。[Means for Solving the Problems] The pier of the present invention includes a column made of filled steel pipe concrete on a footing, and an upper beam portion at the upper end of the column, in which the column is made of steel pipes. The steel pipe is constructed of unbonded filled steel pipe concrete in which the concrete filled inside the steel pipe is in a non-adhesive state, and a deformation absorbing portion is provided in at least a part of the steel pipe in the axial direction to absorb axial deformation occurring in the steel pipe. It is characterized by
[作用]
上記構成の橋脚においては、上梁部にかかる荷
重は支柱部に伝達されるが、そのとき、軸方向の
圧縮荷重により鋼管に生じる変形は変形吸収部に
より吸収される。特に、この場合、鋼管と充填コ
ンクリートとがアンボンド状態にあることから、
軸方向の圧縮力は鋼管内の充填コンクリートにの
み作用し、鋼管にはほとんど作用しない。すなわ
ち、鋼管に作用する軸方向応力がゼロに近くな
る。このため、鋼管には、コンフアインド効果を
与える反作用としてのリングテンシヨンのみが作
用することになり、したがつて、ミーゼスの降伏
条件を適用すれば、円周方向応力による鋼管のコ
ンフアインド効果を十分発揮させることができ、
その結果、圧縮荷重に対する強度を著しく向上さ
せることができ、支柱部の断面積を小さくでき
る。[Operation] In the bridge pier configured as described above, the load applied to the upper beam portion is transmitted to the support portion, but at this time, deformation that occurs in the steel pipe due to the compressive load in the axial direction is absorbed by the deformation absorbing portion. In particular, in this case, since the steel pipe and the filling concrete are in an unbonded state,
The axial compressive force acts only on the filled concrete inside the steel pipe and has almost no effect on the steel pipe. That is, the axial stress acting on the steel pipe becomes close to zero. Therefore, only ring tension acts on the steel pipe as a reaction that gives a confining effect. Therefore, if the Mises yield condition is applied, the confining effect of the steel pipe due to the circumferential stress can be fully exerted. can be made,
As a result, the strength against compressive loads can be significantly improved, and the cross-sectional area of the support column can be reduced.
[実施例]
第1図及び第2図は本発明の一実施例を示すも
のである。[Embodiment] FIGS. 1 and 2 show an embodiment of the present invention.
地盤Sには、杭1が複数本並んで埋設され、杭
1の上端には、鉄筋コンクリート製のフーチング
2が連結されている。3が鉄筋である。このフー
チング2の上部には、下端をフーチング2に埋め
込んだ状態で、支柱部4を構成する鋼管5が立設
されている。この鋼管5には、その部分が伸縮し
たりすることにより鋼管5に生じる軸方向の変形
を吸収する変形吸収部5aが設けられている。変
形吸収部5aの位置や数や種類は適宜に選定する
ことができる。 A plurality of piles 1 are lined up and buried in the ground S, and a footing 2 made of reinforced concrete is connected to the upper end of the pile 1. 3 is the reinforcing steel. A steel pipe 5 constituting the support section 4 is erected on the upper part of the footing 2, with its lower end embedded in the footing 2. This steel pipe 5 is provided with a deformation absorbing portion 5a that absorbs deformation in the axial direction that occurs in the steel pipe 5 due to expansion and contraction of that portion. The position, number, and type of deformation absorbing portions 5a can be selected as appropriate.
種類については、例えば、鋼管5を上下に縁切
りするリング状間〓を形成したもの、そのリング
状間〓にゴム等の柔性材を充填したもの、あるい
は、鋼管5の内面または外面にリング状溝を切つ
てその部分を積極的に弱部として座屈しやすいよ
うにしたもの、また鋼管5に周方向に延在する複
数の長穴を形成しその部分に軸方向の伸縮性をも
たせたもの等、要は伸縮性や局部的な変形しやす
さを与えてその部位で鋼管5全体に発生する軸方
向の変形を吸収するようにしたものであればよ
い。なお、7は、鋼管5を立てるときの仮り受け
治具である。 As for the types, for example, there are those in which a ring-shaped gap is formed between the upper and lower edges of the steel pipe 5, those in which the ring-shaped gap is filled with a flexible material such as rubber, or those in which a ring-shaped groove is formed on the inner or outer surface of the steel pipe 5. such as those in which the steel pipe 5 is cut and actively used as a weak part to make it easy to buckle, and those in which a plurality of elongated holes extending in the circumferential direction are formed in the steel pipe 5 to give that part elasticity in the axial direction. In short, any material may be used as long as it has elasticity and local deformability so as to absorb the axial deformation that occurs in the entire steel pipe 5 at that location. Note that 7 is a temporary holding jig for setting up the steel pipe 5.
そして、そのように立設された鋼管5の内部に
コンクリート6が充填されている。この場合、鋼
管5の内面には、予め、鋼管5と充填コンクリー
ト6との付着をなくすための分離材(アンボンド
処理層)8が塗布されており、その上で、鋼管5
の内部にコンクリート6が打設されている。した
がつて、鋼管5とコンクリート6とは軸方向に相
対的に自由に変位できるようになつている。 The inside of the steel pipe 5 thus erected is filled with concrete 6. In this case, the inner surface of the steel pipe 5 is coated with a separation material (unbonding layer) 8 in advance to prevent adhesion between the steel pipe 5 and the filling concrete 6, and then the steel pipe 5 is
Concrete 6 is poured inside. Therefore, the steel pipe 5 and the concrete 6 can be relatively freely displaced in the axial direction.
前記分離材8としては、パラフイン、アスフア
ルト、オイル、グリース、ワセリン等を用い、こ
れを鋼管5の内面に塗布することによりアンボン
ド処理層を形成している。 As the separating material 8, paraffin, asphalt, oil, grease, vaseline, etc. are used, and by applying this to the inner surface of the steel pipe 5, an unbonding treatment layer is formed.
また、このように構成されたアンボンド型充填
鋼管コンクリート構造の支柱部4の上端には、上
梁部9が設けられている。この上梁部9は、支柱
部4のコンクリート6に一体的に連結されてい
る。この場合、上梁部8は、フーチング2と同様
現場打鉄筋コンクリートでできており、鋼管5の
上端は上梁部9内に固定されている。10は上梁
部9中の鉄筋である。なお、上梁部9は現場打コ
ンクリートで作る他、プレキヤストコンクリート
梁、あるいは鋼製梁としてもよい。 Further, an upper beam portion 9 is provided at the upper end of the support portion 4 of the unbonded type filled steel pipe concrete structure configured in this manner. This upper beam portion 9 is integrally connected to the concrete 6 of the support portion 4. In this case, the upper beam portion 8 is made of cast-in-place reinforced concrete like the footing 2, and the upper end of the steel pipe 5 is fixed within the upper beam portion 9. 10 is a reinforcing bar in the upper beam portion 9. In addition to being made of cast-in-place concrete, the upper beam portion 9 may also be a precast concrete beam or a steel beam.
図示の橋脚を作る手順としては、杭1を施工し
た後、まず、フーチング2用の型枠を組み、同時
に仮り受け治具7で支柱しながら鋼管5を立て
る。鋼管5には、予め内面にパラフイン等の分離
材8を塗布しておく。その後、フーチング2の上
端レベルまでコンクリートを打設してフーチング
2を構築する。 The steps for making the illustrated bridge pier are as follows: After constructing the piles 1, first, a formwork for the footing 2 is assembled, and at the same time, the steel pipe 5 is erected while being supported using a temporary support jig 7. A separating material 8 such as paraffin is applied to the inner surface of the steel pipe 5 in advance. Thereafter, the footing 2 is constructed by pouring concrete up to the upper end level of the footing 2.
次に、立設した鋼管5の上方に上梁部11用の
型枠を組み、そして、鋼管5内及び上梁部型枠内
にコンクリートを打設して、支柱部4の充填コン
クリート6部分及び上梁部9を構築し、橋脚を完
成する。なお、支柱部4のコンクリート6と上梁
部9のコンクリートは別々に打設してもよい。 Next, a formwork for the upper beam part 11 is constructed above the erected steel pipe 5, and concrete is poured into the steel pipe 5 and the upper beam part formwork to fill the 6 portions of the pillar part 4 with concrete. Then, the upper beam section 9 is constructed to complete the bridge pier. Incidentally, the concrete 6 for the column portion 4 and the concrete for the upper beam portion 9 may be cast separately.
このような構成の橋脚では、上梁部9にかかる
荷重は支柱部4に伝達され、支柱部4にかかる荷
重は、鋼管5内のコンクリート6に軸方向の圧縮
力として作用して、コンクリート6が圧縮する。
それが所定の強度を越えると、コンクリート6は
軸方向の歪を生じるとともに、径方向の急激な横
歪を生じる。 In a pier with such a configuration, the load applied to the upper beam part 9 is transmitted to the support part 4, and the load applied to the support part 4 acts as an axial compressive force on the concrete 6 in the steel pipe 5, causing the concrete 6 to be compressed. compresses.
If it exceeds a predetermined strength, the concrete 6 will undergo axial strain as well as rapid radial transverse strain.
ところが、鋼管5に生じる軸方向の歪は、変形
吸収部5aに吸収され、変形吸収部5aの上下間
において軸方向応力の伝達がなくなり、鋼管5に
はほとんど軸方向応力が発生しない。特に、この
場合、鋼管5は、充填コンクリート6のアンボン
ド状態にあり、鋼管5は軸方向においてコンクリ
ート6に全く拘束されない。したがつて、コンク
リート6には軸歪が生じるものの、鋼管5には全
く軸歪が生じない。したがつて、ミーゼスの降伏
条件を適用すれば円周方向応力による鋼管5のコ
ンフアインド効果を十分発揮させることができ、
その結果、圧縮荷重に対する強度の向上を図るこ
とができる。さらに、曲げに対する鋼管の縁応力
の弾性圧縮、引張の範囲が広くなることにより、
支柱部4の断面積を小さくすることができる。 However, the axial strain occurring in the steel pipe 5 is absorbed by the deformation absorbing portion 5a, and no axial stress is transmitted between the upper and lower portions of the deformation absorbing portion 5a, and almost no axial stress is generated in the steel pipe 5. In particular, in this case the steel pipe 5 is in the unbonded state of the filled concrete 6, and the steel pipe 5 is not constrained by the concrete 6 in the axial direction at all. Therefore, although axial strain occurs in the concrete 6, no axial strain occurs in the steel pipe 5. Therefore, by applying the Mises yield condition, the effect of confining the steel pipe 5 due to circumferential stress can be fully exhibited,
As a result, it is possible to improve the strength against compressive loads. Furthermore, by expanding the range of elastic compression and tension of the edge stress of the steel pipe against bending,
The cross-sectional area of the support portion 4 can be reduced.
なお、上の説明では、支柱部4が1本の場合を
説明したが、2本、あるいはそれ以上の場合にも
本発明は適用できる。第3図は2本の場合の例を
示しており、図中21は杭、22は基礎敷きコン
クリート、23はフーチング、24は支柱部、2
5は鋼管、25aは変形吸収部、26は支柱部コ
ンクリート、27は分離材、28は上梁部であ
る。 In addition, although the above description explained the case where there is one support|pillar part 4, this invention is applicable also to the case where there are two or more. Figure 3 shows an example in which there are two piles, 21 is the pile, 22 is the foundation concrete, 23 is the footing, 24 is the column, and 2
5 is a steel pipe, 25a is a deformation absorbing portion, 26 is a concrete column, 27 is a separating material, and 28 is an upper beam portion.
また、以上の説明では、支柱部4,24の断面
形状については特に触れなかつたが、本発明は、
図示例の如く断面円形のものに限らず、楕円、多
角形等、種々の形状のものに適用できる。 Further, in the above explanation, the cross-sectional shape of the support columns 4 and 24 was not particularly mentioned, but the present invention
The present invention is not limited to having a circular cross section as shown in the figure, but can be applied to various shapes such as an ellipse and a polygon.
[発明の効果]
本発明によれば、鋼管には軸方向荷重がほとん
ど作用しない構造になつているため、鋼管に軸方
向応力がほとんど発生せず、したがつて、ミーゼ
スの降伏条件を適用すれば円周方向応力による鋼
管のコンフアインド効果を十分発揮させることが
できる。その結果、圧縮荷重に対する強度を著し
く向上させることができ、支柱部の断面積を小さ
くできる。[Effects of the Invention] According to the present invention, since the steel pipe has a structure in which almost no axial load acts on the steel pipe, almost no axial stress is generated in the steel pipe, and therefore the Mises yield condition cannot be applied. In this case, the confining effect of the steel pipe due to the stress in the circumferential direction can be fully exerted. As a result, the strength against compressive loads can be significantly improved, and the cross-sectional area of the support column can be reduced.
第1図は本発明の一実施例の側断面図、第2図
は第1図の−線矢視断面図、第3図は本発明
の他の実施例の側断面図である。
2,23……フーチング、4,24……支柱
部、5,25……鋼管、5a,25a……変形吸
収部、6,26……充填コンクリート、8,27
……分離材、9,28……上梁部。
FIG. 1 is a side sectional view of one embodiment of the present invention, FIG. 2 is a sectional view taken along the - line in FIG. 1, and FIG. 3 is a side sectional view of another embodiment of the present invention. 2, 23...Footing, 4, 24...Strut part, 5, 25...Steel pipe, 5a, 25a...Deformation absorption part, 6, 26...Filled concrete, 8, 27
... Separation material, 9, 28 ... Upper beam part.
Claims (1)
支柱部を備え、支柱部の上端に上梁部を備えた橋
脚において、支柱部は、鋼管と鋼管内部に充填し
たコンクリートとが非付着状態にあるアンボンド
型充填鋼管コンクリートにより構成され、かつ前
記鋼管の軸方向の少なくとも一部には、鋼管に生
じる軸方向の変形を吸収する変形吸収部が設けら
れていることを特徴とする橋脚。1 In a bridge pier that has a column made of filled steel pipe concrete on the footing and an upper beam section at the upper end of the column, the column is an unbonded type in which the steel pipe and the concrete filled inside the steel pipe are not attached. 1. A bridge pier constructed of filled steel pipe concrete, and characterized in that a deformation absorbing portion is provided in at least a portion of the steel pipe in the axial direction to absorb deformation in the axial direction occurring in the steel pipe.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23079285A JPS6290404A (en) | 1985-10-16 | 1985-10-16 | pier |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23079285A JPS6290404A (en) | 1985-10-16 | 1985-10-16 | pier |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6290404A JPS6290404A (en) | 1987-04-24 |
| JPH0354726B2 true JPH0354726B2 (en) | 1991-08-21 |
Family
ID=16913337
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP23079285A Granted JPS6290404A (en) | 1985-10-16 | 1985-10-16 | pier |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6290404A (en) |
-
1985
- 1985-10-16 JP JP23079285A patent/JPS6290404A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6290404A (en) | 1987-04-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6326545B1 (en) | Viaduct using PC pier with double circular spiral shear reinforcement | |
| KR102153426B1 (en) | Rahmen bridge with integral approach slab and small type foundation and construction method thereof | |
| JP3855198B2 (en) | Seismic reinforcement structure for pile foundation structures | |
| EP0214800A2 (en) | Filler filled steel tube column | |
| JP4192125B2 (en) | Seismic reinforcement structure for existing steel structures | |
| JPH07317087A (en) | Joint structure of steel wall and reinforced concrete floor slab | |
| JPH0354726B2 (en) | ||
| JPH0354727B2 (en) | ||
| JPH0354725B2 (en) | ||
| JP2006257710A (en) | Joint structure between cast-in-place concrete pile and foundation | |
| JP3126676B2 (en) | Joint structure of joint groove and joint frame | |
| JPH0953229A (en) | Concrete-filled steel pipe column-applied structure using steel framed reinforced concrete structure underground-wall as foundation and execution method thereof | |
| JPH0428067B2 (en) | ||
| JPS6027151Y2 (en) | Support pile connection device | |
| JPH0448137B2 (en) | ||
| CN215052031U (en) | A self-resetting segmental anti-deformation concrete bridge pier | |
| JPH0354724B2 (en) | ||
| JP2001152535A (en) | Reinforcing structure for existing culvert | |
| JPH0418099B2 (en) | ||
| JPH0423138Y2 (en) | ||
| JPH0353420B2 (en) | ||
| JPH0450740Y2 (en) | ||
| JP2025001464A (en) | Unit for concrete ring and manufacturing method of unit for concrete ring | |
| JPH0477781B2 (en) | ||
| KR200377338Y1 (en) | Structure for earthquake-proof of a bridge pier |