JPH0363604B2 - - Google Patents

Info

Publication number
JPH0363604B2
JPH0363604B2 JP14647983A JP14647983A JPH0363604B2 JP H0363604 B2 JPH0363604 B2 JP H0363604B2 JP 14647983 A JP14647983 A JP 14647983A JP 14647983 A JP14647983 A JP 14647983A JP H0363604 B2 JPH0363604 B2 JP H0363604B2
Authority
JP
Japan
Prior art keywords
caisson
sand
installation
filling
filling sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14647983A
Other languages
Japanese (ja)
Other versions
JPS6040740A (en
Inventor
Masanori Akagi
Akira Irie
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WAKACHIKU CONSTR
Original Assignee
WAKACHIKU CONSTR
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WAKACHIKU CONSTR filed Critical WAKACHIKU CONSTR
Priority to JP14647983A priority Critical patent/JPS6040740A/en
Publication of JPS6040740A publication Critical patent/JPS6040740A/en
Publication of JPH0363604B2 publication Critical patent/JPH0363604B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)

Description

【発明の詳細な説明】 本発明は海洋及び港湾等にケーソンタイプの構
築物を構築するに際して、工期に大きく影響する
ケーソンの据付工事を、海象には余り影響されな
いで実施することのできる海象悪化時におけるケ
ーソンの据付工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION When building caisson-type structures on the ocean, in ports, etc., the present invention enables caisson installation work, which greatly affects the construction period, to be carried out without being affected much by sea conditions. This is related to the installation method of caisson.

防波堤,岸壁,護岸,係船施設等をケーソン工
法により構築する海工事において実施されるケー
ソンの据付は、従来の据付工法に従つて次のよう
に実施されてきた。すなわち、ケーソンの据付予
定位置とその付近に基礎捨石を投入し均してケー
ソンの据付基礎とし、ケーソンをこの据付基礎上
の所定位置に載置し、次いでガツト船等によつて
運搬された中詰め用砂をケーソンの各区画室に投
入し、投入された中詰め用の砂(以下、中詰め砂
と言うことがある)の上部に蓋コンクリートを載
置した後にその上部に上部コンクリートを打設し
ていたのである。
Caisson installation, which is carried out in marine construction work to construct breakwaters, quays, seawalls, mooring facilities, etc. using the caisson construction method, has been carried out in accordance with the conventional installation method as follows. In other words, foundation rubble is poured into and around the planned installation location of the caisson and leveled to form the installation foundation for the caisson, the caisson is placed at a predetermined position on this installation foundation, and then the caisson is placed at a predetermined position on the installation foundation, and then the foundation rubble is placed in the area where the caisson is to be installed. Packing sand is poured into each compartment of the caisson, and after placing cover concrete on top of the loaded sand for filling (hereinafter sometimes referred to as filling sand), upper concrete is placed on top of it. That's what I was doing.

このような従来のケーソン据付工法を実施する
には、所要日数に伴う次のような海象条件が必要
である。ケーソンの据付工事は基礎捨石を投入し
潜水士による均し作業の第1段階工程と、ケーソ
ンを据付基礎上に載置するまでの第2段階工程
と、中詰め用砂を投入し、蓋コンクリートを載置
する第3段階工程と、上部コンクリートを打つ第
4段階工程とに分けられる。そして上記第2段階
工程終了後においては、載置されただけのケーソ
ンは波により所定位置から移動し易く、場合によ
つてはケーソンの側壁や隔壁が破壊されることが
あるから、このような事故を防止するため、第2
段階工程終了後は直ちに第3段階工程を行ない、
ケーソンを所定位置に定着させなければならな
い。そしてケーソン据付を完了するには、第2段
階工程のケーソンを据付基礎上に載置する工程に
1〜1.5日が必要であり、第3段階工程の中詰め
用砂を投入し蓋コンクリートを載置する工程に1
〜1.5日が必要である。よつて、ケーソンを据付
基礎上に載置し中詰め用砂を投入し蓋コンクリー
トを載置するためには、合計2〜3日が必要であ
る。従つてケーソン据付に必要な上記合計日数2
〜3日は静穏に連続する日数である必要がある。
しかるに一般に海域、特に海象条件の厳しい大水
深の海域においては2〜3日間静穏に連続する海
象の出現率は極めて低い。従つて、ケーソンの従
来の据付工法によれば、2〜3日間静穏に連続す
ると予知された日が到来するまではケーソンの据
付工事を開始することができないから据付工事開
始がおくれ、また据付工事を開始しても予想と異
なり工事途中で海象が急変して悪化し据付作業が
危険となり工事を中断することによりしばしばケ
ーソンの移動,中詰め用砂の逸出,ケーソンの壁
破壊等の事故が起つてその位置修正又は工事のや
り直しに手数がかかり、このようなことからケー
ソンの据付完了がおくれることにより、従来工法
によるケーソンの据付が全体の工期を長びかせる
主要な原因となつていた。
In order to implement such a conventional caisson installation method, the following sea conditions are required depending on the required number of days. The caisson installation work consists of the first step of putting in foundation rubble and leveling work by divers, the second step of placing the caisson on the installation foundation, adding filler sand, and covering with concrete. The process is divided into the third stage, which involves placing the concrete, and the fourth stage, which involves pouring concrete on top. After the completion of the second stage process, the caisson that has just been placed is likely to be moved from its predetermined position by waves, and in some cases, the side walls and bulkheads of the caisson may be destroyed. To prevent accidents,
Immediately after the step process is completed, the third step process is carried out,
The caissons must be anchored in place. In order to complete the caisson installation, the second stage of placing the caisson on the installation foundation requires 1 to 1.5 days, and the third stage of filling the caisson with filling sand and placing the cap concrete. 1 in the process of placing
~1.5 days are required. Therefore, it takes a total of 2 to 3 days to place the caisson on the installation foundation, fill it with sand, and place the lid concrete. Therefore, the above total number of days required for caisson installation is 2.
~3 days must be consecutive days of calm.
However, in general, in sea areas, particularly deep sea areas with severe sea conditions, the incidence of continuous calm sea conditions for two to three days is extremely low. Therefore, according to the conventional caisson installation method, the caisson installation work cannot be started until the day when it is predicted that there will be continuous calm for 2 to 3 days, resulting in a delay in the start of the installation work, and a delay in the installation work. Even after starting construction, the sea conditions suddenly changed and worsened during the construction work, making the installation work dangerous and causing construction to be interrupted, often resulting in accidents such as movement of the caisson, escape of filler sand, and destruction of the caisson wall. Once the caisson has been installed, it takes time to correct its position or redo the work, and this delays the completion of the caisson installation, which is the main cause of prolonging the overall construction period when installing the caisson using the conventional method. .

本発明者らは上記の如き欠点がなく海象の静穏
な連続状態の短命や急変などに余り影響されない
で実施できるケーソンの据付工法を提供すること
を目的に鋭意検討した結果、海象が悪化したとき
はケーソンの定着及び中詰め砂逸出防止のための
仮蓋体を使用して据付工事を中断することにより
目的を達成することができることを究明して本発
明を成した。
The inventors of the present invention have conducted intensive studies with the aim of providing a caisson installation method that does not have the above-mentioned drawbacks and can be carried out without being affected by short-lived or sudden changes in continuous calm sea conditions. discovered that the object could be achieved by interrupting the installation work by using a temporary cover for anchoring the caisson and preventing the filling sand from escaping, and thus developed the present invention.

すなわち本発明は、ケーソンを水中に設けられ
た据付基礎上に載置した後に中詰め用砂の投入,
蓋コンクリートの載置及び上部コンクリート打ち
を行なつてケーソンを据え付けるに当り、該ケー
ソンの区画室の中詰め用砂投入口をほぼ閉塞する
状態に係止される形状を有し且つ施工時に予想さ
れ得る波力に対して中詰め用砂未投入の状態のケ
ーソンを前記据付基礎上の所定位置に定着せしめ
る重量を分担して有する仮蓋体を予め区画室の数
だけ準備し、ケーソンの据付工事中に変化する海
象に応じて前記据付基礎上に載置されたケーソン
への中詰め用砂の投入未完の状態で一旦上記仮蓋
体をケーソンの各区画室の中詰め用砂投入口をほ
ぼ閉塞する状態に係止せしめてケーソンを定着状
態にして据付工事を中断し、海象の回復を待つて
据付工事を再開して仮蓋体の撤去と中詰め用砂の
投入とを蓋コンクリートの載置までに行なうこと
を特徴とする海象悪化時におけるケーソンの据付
工法に関するものである。
In other words, the present invention involves placing sand for filling after placing the caisson on an installation foundation provided underwater.
When installing the caisson by placing the lid concrete and pouring the upper concrete, the caisson has a shape that is locked in a state that almost closes the filling sand inlet of the compartment of the caisson, and it has a shape that is locked in a state that almost blocks the filling sand inlet of the compartment of the caisson. Temporary lids for the number of compartments are prepared in advance and have the same weight as the number of compartments, and the caisson installation work is carried out by dividing the weight of the caisson without filling sand into a predetermined position on the installation foundation in response to the wave force. Depending on the changing sea conditions during the construction, the temporary lid is temporarily inserted to almost block the filling sand inlet of each compartment of the caisson while the filling sand is not yet being poured into the caisson placed on the installation foundation. The installation work was stopped by locking the caisson in the fixed state, and after waiting for the sea conditions to recover, the installation work was restarted, and the temporary cover was removed, filling sand was put in, and the cover concrete was placed. This article relates to a method for installing caissons during deterioration of sea conditions, which is characterized by the fact that

以下、本発明工法を図面によつて詳細に説明す
る。第1図は本発明工法の1実施例において中詰
め用砂未投入のまま仮蓋体を係止せしめた状態を
示す縦断面説明図、第2図は本発明工法の他の実
施例において中詰め用砂投入未完の状態で仮蓋体
を係止せしめた状態を示す縦断面説明図、第3
図,第4図及び第5図は仮蓋体の1例を示すそれ
ぞれの斜視図,平面図及び正面図、第6図,第7
図及び第8図は仮蓋体の他の1例を示すそれぞれ
の斜視図,平面図及び正面図である。
Hereinafter, the construction method of the present invention will be explained in detail with reference to the drawings. Fig. 1 is a vertical cross-sectional explanatory diagram showing a state in which the temporary lid is locked without filling sand in one embodiment of the method of the present invention, and Fig. 2 is an explanatory longitudinal cross-sectional view showing a state in which the temporary lid is locked without filling sand in one embodiment of the method of the present invention. Vertical cross-sectional explanatory view showing a state in which the temporary lid is locked in a state where filling sand has not been completely inserted, No. 3
Figures 4 and 5 are a perspective view, a top view, a front view, and a front view, respectively, showing one example of a temporary lid body, and Figures 6 and 7.
The figure and FIG. 8 are a perspective view, a plan view, and a front view, respectively, showing another example of the temporary lid.

本発明工法を実施するに当り、基礎捨石を石運
船やガツト船で運搬してケーソンの据付予定位置
やその囲りに投入し均して第1図,第2図に示す
如きケーソンの据付基礎1とすることは従来工法
通りである。据付基礎1が造成されれば、次にそ
の所定位置にケーソン2を常法に従つて載置する
が、本発明工法ではそれに先立ち、仮蓋体3をケ
ーソン2の区画室2aの数だけ用意しておくので
ある。本発明工法で使用する仮蓋体3は次のよう
な形状と重量を有している。その形状は、第1図
に例示する如くケーソン2の区画室2aの中詰め
用砂投入口をほぼ閉塞する状態に係止されるよう
になつている。またその重量は、ケーソン工法に
より構築物を構築しようとするその海域で施工時
に予想され得る大きな波の波力に対して、海水が
満たされて据付基礎1上の所定位置に載置されて
はいるが末だ中詰め用砂が投入されていない状態
にあるケーソン2の各区画室2aの中詰め砂投入
口に係止されたときに、ケーソン2を据付基礎1
上に定着せしめるのに充分な総重量をそれぞれの
仮蓋体3が数に応じて分担する重量である。仮蓋
体3はコンクリート,鉄筋コンクリートあるいは
鉄等で構成される。
In carrying out the construction method of the present invention, the foundation rubble is transported by a stone carrier or a gas boat and thrown into the planned installation position of the caisson or around it, and the caisson is installed as shown in Figures 1 and 2. Setting it as foundation 1 is the same as in the conventional construction method. Once the installation foundation 1 has been constructed, the caisson 2 is then placed in its predetermined position according to a conventional method, but in the construction method of the present invention, prior to this, temporary lid bodies 3 are prepared in the number of compartments 2a of the caisson 2. I'll keep it that way. The temporary lid body 3 used in the construction method of the present invention has the following shape and weight. Its shape is such that it is locked in a state that substantially closes the filling sand inlet of the compartment 2a of the caisson 2, as illustrated in FIG. In addition, its weight is large enough to withstand the wave force of large waves that can be expected during construction in the sea area where a structure is to be constructed using the caisson construction method. When the caisson 2 is locked in the filling sand inlet of each compartment 2a of the caisson 2 with no filling sand loaded, the caisson 2 is installed on the foundation 1.
This is the weight that each temporary lid body 3 shares in proportion to the number of total weights sufficient for fixing on the top. The temporary lid body 3 is made of concrete, reinforced concrete, iron, or the like.

このような仮蓋体3を区画室の数だけ用意して
前記したように常法に従い海水を注入しながら引
船あるいはクレーン船等でケーソン2を据付基礎
1上の所定位置に載置する。ケーソン2が載置さ
れた後も引き続き静穏な海象であれば常法に従い
直ちにガツト船あるいはサンドポンプ等により中
詰め用砂を各区画室2aへ中詰め用砂投入口から
投入するのであるが、ケーソン2が載置されて後
の中詰め用砂投入が未完了のうちに海象が悪化し
たときは、本発明工法により次のような措置を講
ずることができる。すなわち、中詰め用砂の投入
が未完の状態、例えば第1図に示す如く中詰め用
砂の投入が未だ開始されておらず中詰め用砂が全
く投入されていない状態、或いは第2図に示す如
く中詰め用砂の投入が開始されて各区画室2a内
には中詰め用砂4が途中まで投入されているが所
定量には未だ達していない状態のそれぞれの状態
のときに海象が悪化したときは、第1図,第2図
の如く仮蓋体3を各区画室2aの中詰め用砂投入
口をほぼ閉塞する状態に係止せしめてケーソン2
を定着状態にして一旦据付工事を中断するのであ
る。この仮蓋体3は第1図の如くケーソン2への
中詰め用砂が未投入の場合でもケーソン2を定着
状態にせしめるだけの重量を有しているから、第
2図の如くケーソン2へ中詰め用砂が途中まで投
入されている場合はその定着状態は一層良好であ
る。このようにしてケーソン2の自重と仮蓋体3
の重量と更に加わることのある中詰め砂4の重量
とが合計された重さがケーソン2を据付基礎1上
に定着せしめ、悪化した海象条件下においても、
ケーソン2の移動,壁破壊は起ることがなく、ま
たほぼ閉塞された中詰め用砂投入口から中詰め砂
4が逸出することもない。このような仮蓋体3の
ケーソン2への係止作業を容易にするため、第3
図〜第5図の如く仮蓋体3の上面に、クレーン吊
りのための吊り金具3aを埋め込んでその頭部を
凹状の箱抜き3b内に露出させておき、また中詰
め用砂投入口をほぼ閉塞する際の各区画室2a内
の空気又は水を抜け易くするための流体抜き孔3
cを穿設しておくのが好ましい。
Such temporary lids 3 as many as the number of compartments are prepared, and the caisson 2 is placed at a predetermined position on the installation foundation 1 using a tugboat, a crane boat, etc. while injecting seawater according to the conventional method as described above. If the sea conditions continue to be calm even after the caisson 2 has been placed, filler sand is immediately poured into each compartment 2a from the filler sand inlet into each compartment 2a using a Gatsuto boat or sand pump according to the usual method. If the sea conditions worsen before the filling sand has been placed and the filling sand has not yet been completed, the following measures can be taken using the construction method of the present invention. That is, a state in which the filling sand has not been completely added, for example, a state in which the filling sand has not been started and no filling sand has been added at all as shown in FIG. As shown in the figure, when the charging of sand for filling has started and the sand for filling 4 has been poured halfway into each compartment 2a, but the predetermined amount has not yet been reached, the sea conditions deteriorate. In this case, as shown in FIGS. 1 and 2, the temporary lid 3 is locked in a state that almost blocks the filling sand inlet of each compartment 2a, and the caisson 2 is closed.
The installation work is temporarily suspended after the system is set in place. Since this temporary lid body 3 has enough weight to keep the caisson 2 in a fixed state even when sand for filling the caisson 2 has not been put into the caisson 2 as shown in FIG. If the filler sand is added halfway, its fixation will be even better. In this way, the dead weight of the caisson 2 and the temporary lid body 3 are
The total weight of the caisson 2 and the additional weight of the filler sand 4, which may be added, anchors the caisson 2 on the installation foundation 1, even under adverse sea conditions.
Movement of the caisson 2 and wall destruction will not occur, and filling sand 4 will not escape from the filling sand input port which is almost blocked. In order to facilitate the work of locking the temporary lid body 3 to the caisson 2, the third
As shown in Figures to Figures 5, a hanging fitting 3a for hanging the crane is embedded in the upper surface of the temporary lid 3, and its head is exposed inside the concave box cutout 3b, and a sand inlet for filling is provided. Fluid vent hole 3 for making it easier for air or water to escape from each compartment 2a when it is almost closed
It is preferable to drill a hole c.

上記の如く仮蓋体3をケーソン2に係止せしめ
た状態でケーソン2の据付工事を一旦中断し、海
象の回復を待つて据付工事を再開する。据付工事
を再開してからは、仮蓋体3をクレーン等で撤去
し、開口された中詰め用砂投入口から中詰め用砂
を投入する工法によつても良く、また、第6図〜
第8図の如く第3図〜第5図の仮蓋体3に外側の
端部にフランジを有する中詰め用砂投入管5を設
けておき、据付工事を再開してから仮蓋体3を係
止させたままこの砂投入管5に砂輸送管を連結し
てサンドポンプ等により水−砂スラリーを圧送し
て各区画室2aに圧入して中詰め用砂を投入する
工法によつてもよい。この場合、水−砂スラリー
が区画室2aに圧入されるに従つて水が流体抜き
孔3cから強制的に排出されることを容易にする
ため、第6図〜第8図に示す如く流体抜き孔3c
の径を大きくしておくことが好ましい。このよう
に仮蓋体3を撤去しないで据付工事を再開する工
法によれば、据付工事再開後中詰め用砂投入未完
のうちに再び海象が急変して据付工事を再び中断
する場合に便利であり、そして中詰め用砂の投入
が完了した後に仮蓋体3を撤去すれば良い。この
ようにケーソン2の据付工事再開後にいずれの上
記工法を採る場合でも仮蓋体3の撤去と中詰め用
砂の投入とを蓋コンクリートの載置までに行つ
て、その後に蓋コンクリートを中詰め砂4の上部
に載置し、更にその上部に上部コンクリートを打
設することは従来工法と同様である。
The installation work of the caisson 2 is temporarily suspended with the temporary lid body 3 locked to the caisson 2 as described above, and the installation work is restarted after waiting for the sea conditions to recover. After restarting the installation work, the temporary cover body 3 may be removed using a crane or the like, and filling sand may be introduced through the opened filling sand inlet.
As shown in FIG. 8, a filling sand input pipe 5 having a flange at the outer end is provided in the temporary lid 3 shown in FIGS. 3 to 5, and the temporary lid 3 is installed after restarting the installation work. It is also possible to use a construction method in which a sand transport pipe is connected to the sand input pipe 5 while the sand is locked, and a water-sand slurry is pumped using a sand pump or the like, and the sand for filling is poured into each compartment 2a. . In this case, in order to make it easier for the water to be forcibly discharged from the fluid drainage hole 3c as the water-sand slurry is pressurized into the compartment 2a, the fluid drainage hole 3c is shown in FIGS. 6 to 8. Hole 3c
It is preferable to keep the diameter of the diameter large. According to this method of restarting the installation work without removing the temporary cover body 3, it is convenient in the case where the sea conditions suddenly change again and the installation work is interrupted again before the sand filling for filling has been completed after the installation work has been restarted. Yes, and the temporary lid body 3 may be removed after the filling sand is completely inserted. In this way, when any of the above construction methods is adopted after the installation work of caisson 2 is resumed, the temporary cover body 3 must be removed and filling sand must be added before the cover concrete is placed, and then the cover concrete is filled. Placing it on top of the sand 4 and placing the upper concrete on top of it is the same as in the conventional construction method.

本発明工法によれば、据付基礎1上の所定位置
にケーソン2を載置しさえすれば、中詰め用砂の
投入が未完のうちに海象が悪化しても上記の如く
仮蓋体3を係止せしめることにより安全に据付工
事を一旦中断することができる。そしてこのよう
なケーソン2の載置に1〜1.5日と仮蓋体3の係
止作業に0.5日との合計1.5〜2日が連続して静穏
であればケーソン2の載置から仮蓋体3の係止ま
で実施できる。従つて本発明工法によれば静穏な
海象が1.5〜2日連続すると予知されたときはケ
ーソン2の据付工事を開始することができるので
ある。そしてこの程度の日数の静穏な海象状態は
従来の据付工法による場合に要求される静穏に連
続する2〜3日と言う日数に比べてその出現率は
遥かに高いのである。実際に、仮蓋体3の係止作
業は、本発明工法によれば海象の悪化が予知され
たとき或いは悪化の兆しが認められた初期段階で
直ちに着手すれば、殆んどの場合海象が本格的に
悪化するまでに完了するものである。従つて、ケ
ーソン2が据付基礎1に載置された後は海象が何
時悪化しても据付工事を安全に一時中断すること
ができ、海象回復後は直ちに据付工事を再開する
ことができる。
According to the construction method of the present invention, as long as the caisson 2 is placed at a predetermined position on the installation foundation 1, even if the sea conditions worsen before filling with sand is completed, the temporary cover 3 can be installed as described above. By locking it, the installation work can be temporarily interrupted safely. If the caisson 2 is placed for 1 to 1.5 days and the temporary lid body 3 is locked for 0.5 days, the total of 1.5 to 2 consecutive days is calm, then the temporary lid body is removed from the installation of the caisson 2. This can be done with 3 locks. Therefore, according to the construction method of the present invention, installation work for the caisson 2 can be started when it is predicted that calm sea conditions will continue for 1.5 to 2 consecutive days. The occurrence rate of such a number of days of calm sea conditions is much higher than the number of consecutive calm days of 2 to 3 days required in the case of conventional installation methods. In fact, according to the construction method of the present invention, if the work of locking the temporary lid body 3 is started immediately when a deterioration of the sea conditions is predicted or at an early stage when signs of deterioration are recognized, in most cases, the sea conditions will be in full swing. It is completed by the time the situation worsens. Therefore, after the caisson 2 is placed on the installation foundation 1, the installation work can be safely temporarily suspended even if the sea conditions worsen at any time, and the installation work can be restarted immediately after the sea conditions recover.

本発明工法によれば、上記説明の如く、ケーソ
ンの据付工事は出現率の比較的高い海象が連続し
て1.5〜2日静穏と予想される日に着工すること
ができ、そして据付工事途中で海象が悪化しても
その悪化期間と言う最小限の日数しか工期は延び
ない。このようにして本発明工法は、海象には余
り影響されないでケーソンの据付を実施すること
を可能にして完成時期を早め、それにより構築物
構築の全工期の遅延を防止することのできる価値
あるものである。
According to the construction method of the present invention, as explained above, the caisson installation work can be started on a day when the sea conditions with a relatively high occurrence rate are expected to be calm for 1.5 to 2 consecutive days, and the construction work can be started during the installation work. Even if the sea conditions deteriorate, the construction period will only be extended by the minimum number of days during which the sea conditions worsen. In this way, the construction method of the present invention is valuable because it enables the installation of caissons to be carried out without much influence from sea conditions, hastens the completion time, and thereby prevents delays in the overall construction period of the structure. It is.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明工法の1実施例において中詰め
用砂未投入のまま仮蓋体を係止せしめた状態を示
す縦断面説明図、第2図は本発明工法の他の実施
例において中詰め用砂投入未完の状態で仮蓋体を
係止せしめた状態を示す縦断面説明図、第3図,
第4図及び第5図は仮蓋体の1例を示すそれぞれ
の斜視図,平面図及び正面図、第6図,第7図及
び第8図は仮蓋体の他の1例を示すそれぞれの斜
視図,平面図及び正面図である。 1…据付基礎、2…ケーソン、2a…区画室、
3…仮蓋体、3a…吊り金具、3b…箱抜き、3
c…流体抜き孔、4…中詰め砂、5…中詰め用砂
投入管。
Fig. 1 is a vertical cross-sectional explanatory diagram showing a state in which the temporary lid is locked without filling sand in one embodiment of the method of the present invention, and Fig. 2 is an explanatory longitudinal cross-sectional view showing a state in which the temporary lid is locked without filling sand in one embodiment of the method of the present invention. Fig. 3 is an explanatory longitudinal cross-sectional view showing a state in which the temporary lid is locked in a state in which filling sand has not been completely inserted;
Figures 4 and 5 are perspective views, plan views, and front views of one example of a temporary lid, and Figures 6, 7, and 8 are views of another example of a temporary lid. They are a perspective view, a plan view, and a front view. 1... Installation foundation, 2... Caisson, 2a... Compartment room,
3...temporary lid body, 3a...hanging metal fittings, 3b...box cutter, 3
c...Fluid vent hole, 4...filling sand, 5...filling sand input pipe.

Claims (1)

【特許請求の範囲】 1 ケーソンを水中に設けられた据付基礎上に載
置した後に中詰め用砂の投入、蓋コンクリートの
載置及び上部コンクリート打ちを行なつてケーソ
ンを据え付けるに当り、該ケーソンの区画室の中
詰め用砂投入口をほぼ閉塞する状態に係止される
形状を有し且つ施工時に予想され得る波力に対し
て中詰め用砂未投入の状態のケーソンを前記据付
基礎上の所定位置に定着せしめる重量を分担して
有する仮蓋体を予め区画室の数だけ準備し、ケー
ソンの据付工事中に変化する海象に応じて前記据
付基礎上に載置されたケーソンへの中詰め用砂の
投入未完の状態で一旦上記仮蓋体をケーソンの各
区画室の中詰め用砂投入口をほぼ閉塞する状態に
係止せしめてケーソンを定着状態ににして据付工
事を中断し、海象の回復を待つて据付工事を再開
して仮蓋体の撤去と中詰め用砂の投入とを蓋コン
クリートの載置までに行なうことを特徴とする海
象悪化時におけるケーソン据付工法。 2 ケーソン据付工事を再開してから仮蓋体を撤
去した後に中詰め用砂の投入を行なう特許請求の
範囲第1項に記載の海象悪化時におけるケーソン
の据付工法。 3 ケーソンの据付工事を再開してから仮蓋体を
係止させたまま中詰め用砂を投入した後に仮蓋体
を撤去する特許請求の範囲第1項に記載の海象悪
化時におけるケーソンの据付工法。
[Scope of Claims] 1. When installing the caisson by placing filler sand, placing cover concrete, and pouring the upper concrete after placing the caisson on the installation foundation provided in the water, The caisson has a shape that is locked in a state that almost closes the filling sand inlet of the compartment, and the caisson without filling sand is placed on the installation foundation against the wave force that can be expected during construction. Temporary lids are prepared in advance for the number of compartments, which share the weight of fixing the caisson in a predetermined position. While the filling sand has not been completely inserted, the temporary lid is locked to almost block the filling sand inlet in each compartment of the caisson, the caisson is fixed, and the installation work is interrupted. This method of installing a caisson during deterioration of sea conditions is characterized by restarting the installation work after waiting for the recovery of the water, removing the temporary cover body, and inserting filling sand before placing the cover concrete. 2. The method for installing a caisson during deterioration in sea conditions as set forth in claim 1, in which filling sand is introduced after the temporary lid is removed after restarting the caisson installation work. 3 Installation of a caisson during deterioration of sea conditions as set forth in claim 1, in which the temporary lid is removed after the caisson installation work is resumed and filler sand is put in with the temporary lid locked. Construction method.
JP14647983A 1983-08-12 1983-08-12 Installing method of caisson at worsening of marine climate Granted JPS6040740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14647983A JPS6040740A (en) 1983-08-12 1983-08-12 Installing method of caisson at worsening of marine climate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14647983A JPS6040740A (en) 1983-08-12 1983-08-12 Installing method of caisson at worsening of marine climate

Publications (2)

Publication Number Publication Date
JPS6040740A JPS6040740A (en) 1985-03-04
JPH0363604B2 true JPH0363604B2 (en) 1991-10-01

Family

ID=15408567

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14647983A Granted JPS6040740A (en) 1983-08-12 1983-08-12 Installing method of caisson at worsening of marine climate

Country Status (1)

Country Link
JP (1) JPS6040740A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3864398B2 (en) * 2004-10-07 2006-12-27 潔 斎藤 Submerged rubble foundation and its consolidation method
KR102411918B1 (en) * 2020-05-27 2022-06-22 한국해양과학기술원 Single Cell Caisson for Concrete Block Replacement and Port Construction Method Using Same

Also Published As

Publication number Publication date
JPS6040740A (en) 1985-03-04

Similar Documents

Publication Publication Date Title
CN109780325A (en) A kind of water factory's water intaking tunnel submarine pipeline installation method
JP3599431B2 (en) Construction method of temporary deadline
AU2019203298B2 (en) A method and system for underwater scour prevention
JPH0363604B2 (en)
JP2000290936A (en) Construction method of pier footing and caisson for pier footing construction
JPH11140893A (en) Manufacture and launching method for sinking box
GB2121854A (en) Marine structure constructing method
JP2745097B2 (en) Construction method of low temperature liquefied gas underground tank
JPH052774B2 (en)
JP2655322B2 (en) Construction method of revetment structure
JP4688099B2 (en) Top slope slit embankment and upper slope slit towing method and upper slope slit bank construction method
JP3294118B2 (en) How to build an environmentally friendly submerged levee
KR200341453Y1 (en) A box for construction on the sea
JPS6226371B2 (en)
JPH0323689B2 (en)
JPH0132335B2 (en)
JP2581602B2 (en) Waste treatment method
JPS6131515A (en) Method of installing hull type caisson
JPS6040404A (en) Construction of breakwater structure
JPS5950809B2 (en) Artificial islands and their construction methods
JPS6018776B2 (en) Hull caisson construction method
JPH06272423A (en) Construction work for underground tank
JPH03110218A (en) Installation of caisson
Wibisono An alternative structural system for an offshore airport
JPS6133095B2 (en)