JPH0363717B2 - - Google Patents
Info
- Publication number
- JPH0363717B2 JPH0363717B2 JP58121486A JP12148683A JPH0363717B2 JP H0363717 B2 JPH0363717 B2 JP H0363717B2 JP 58121486 A JP58121486 A JP 58121486A JP 12148683 A JP12148683 A JP 12148683A JP H0363717 B2 JPH0363717 B2 JP H0363717B2
- Authority
- JP
- Japan
- Prior art keywords
- containment vessel
- reactor containment
- grout
- course
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000011440 grout Substances 0.000 claims description 33
- 239000004576 sand Substances 0.000 claims description 28
- 238000009434 installation Methods 0.000 claims description 13
- 238000000034 method Methods 0.000 claims description 10
- 238000003466 welding Methods 0.000 description 16
- 238000010276 construction Methods 0.000 description 5
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 238000011900 installation process Methods 0.000 description 4
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 3
- 235000011613 Pinus brutia Nutrition 0.000 description 3
- 241000018646 Pinus brutia Species 0.000 description 3
- 230000003111 delayed effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 238000009835 boiling Methods 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 230000001629 suppression Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Monitoring And Testing Of Nuclear Reactors (AREA)
Description
【発明の詳細な説明】
〔発明の技術分野〕
この発明は、原子炉格納容器の据付方法に関す
る。DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method for installing a nuclear reactor containment vessel.
第1図は従来の沸騰水型原子炉を示すものであ
つて、原子炉格納容器が原子炉建屋に据え付けら
れた状態を示す一部切欠側面図である。
FIG. 1 shows a conventional boiling water nuclear reactor, and is a partially cutaway side view showing a reactor containment vessel installed in a reactor building.
原子炉格納容器1は原子炉建屋3内に据え付け
られる。この原子炉建屋3は、マツト5と、マツ
ト5の上部に設けられて、原子炉格納容器1を囲
撓する遮蔽壁7と、マツト5の上部で、遮蔽壁7
の外側に設けられる円周壁9等から成り、前記遮
蔽壁7と原子炉格納容器1との間にはグラウト1
1が充填される。 The reactor containment vessel 1 is installed within the reactor building 3. This reactor building 3 includes a mat 5, a shield wall 7 provided above the mat 5 and surrounding the reactor containment vessel 1, and a shield wall 7 provided above the mat 5 to surround the reactor containment vessel 1.
A grout 1 is provided between the shielding wall 7 and the reactor containment vessel 1.
1 is filled.
原子炉格納容器1は、下方から上方に向つてボ
トムコース13、下部球殻1段15、下部球殻2
段17およびベントコース19が順次溶接にて組
み付けられ、さらにベントコース19の上部に円
筒部21、上部球殻23がそれぞれ順位溶接さ
れ、この上部球殻23の上部に原子炉格納容器ヘ
ツド25が取り外し可能に配設される。これら、
円筒部21、上部球殻23および原子炉格納容器
25を「原子炉格納容器の上部エレメント」とす
る。また、原子炉格納容器1には、ベント管27
を介してトーラス29が建設される。このトーラ
ス29は原子炉格納容器1の下方に設置され、内
部にサプレツシヨンチヤンバを形成している。 The reactor containment vessel 1 includes, from the bottom to the top, a bottom course 13, a lower spherical shell 1 stage 15, and a lower spherical shell 2.
The stage 17 and the vent course 19 are sequentially assembled by welding, and the cylindrical part 21 and the upper spherical shell 23 are sequentially welded to the upper part of the vent course 19, and the reactor containment vessel head 25 is attached to the upper part of the upper spherical shell 23. Detachably arranged. these,
The cylindrical portion 21, the upper spherical shell 23, and the reactor containment vessel 25 are referred to as the "upper element of the reactor containment vessel." In addition, the reactor containment vessel 1 includes a vent pipe 27.
A torus 29 is constructed via. This torus 29 is installed below the reactor containment vessel 1 and forms a suppression chamber inside.
また、原子炉格納容器1の内部には原子炉圧力
容器31が設けられ、この原子炉圧力容器31は
ペデスタル33に支持されている。ペデスタル3
3は、原子炉格納容器1の内部に立設され、内部
コンクリート37によつて補強され、強固に保持
される。 Further, a reactor pressure vessel 31 is provided inside the reactor containment vessel 1, and this reactor pressure vessel 31 is supported by a pedestal 33. Pedestal 3
3 is erected inside the reactor containment vessel 1, reinforced with internal concrete 37, and held firmly.
前記グラウト11は、第2図に示される如く、
マツト5の上部から、下部球殻2段17とベント
コース19との水平方向溶接線41Aの下方近傍
位置までの高さを有し、その上部にサンドクツシ
ヨン39が設けられる。このサンドクツシヨン3
9は溶接線41Aの外側に当接し、溶接線41A
に沿つて環状に設けられる。また、サンドクツシ
ヨン39は、下部遮蔽壁7aの上部に形成される
上部遮蔽壁7bによつて、コンクリート固定され
る。これら下部および上部遮蔽壁7a,7bによ
り、遮蔽壁7が構成される。 The grout 11, as shown in FIG.
It has a height from the top of the mat 5 to a position near the bottom of the horizontal weld line 41A between the two lower spherical shells 17 and the vent course 19, and a sand cushion 39 is provided above the height. This sandwich 3
9 is in contact with the outside of the welding line 41A, and the welding line 41A
It is provided in an annular shape along the Furthermore, the sand cushion 39 is fixed to concrete by an upper shielding wall 7b formed above the lower shielding wall 7a. A shielding wall 7 is constituted by these lower and upper shielding walls 7a and 7b.
また、前記内部コンクリート37は、ボトムコ
ース13の底部から溶接線41Aの上方近傍まで
打設される。このうち、溶接線41Aの内側に当
接する環状部分は内部コンクリート残部43とさ
れる。尚、符号41Bはボトムコース13、下部
球殻1段15、同2段17の溶接箇所である。 Further, the internal concrete 37 is placed from the bottom of the bottom course 13 to near the upper part of the weld line 41A. Of these, the annular portion that contacts the inside of the weld line 41A is the internal concrete remainder 43. Incidentally, reference numeral 41B is a welding point of the bottom course 13, the first stage 15 of the lower spherical shell, and the second stage 17 of the lower spherical shell.
次に、原子炉格納容器の据付工程を、第6図A
を参照して説明する。まず、原子炉建屋3のマツ
ト5を配筋作業およびコンクリート打設作業によ
り形成する。次に、遮蔽壁7の下部7aおよび円
周壁9のコンクリート打設作業を開始すると同時
に、マツト5上でボトムコース13を組立てる。
ボトムコース13の組立後、ボトムコース13の
上部に下部球殻1段15を、さらに下部球殻1段
15の上部に下部球殻2段17を順次溶接して組
み付ける。下部球殻2段17の組付後、この下部
球殻2段17の上部にベントコース19を組み付
けるとともに、ボトムコース13下部球殻1段・
2段15,17の溶接箇所41Bの局所リークテ
スト45を行なう。 Next, the installation process of the reactor containment vessel is shown in Figure 6A.
Explain with reference to. First, the pine 5 of the reactor building 3 is formed by reinforcement work and concrete pouring work. Next, the bottom course 13 is assembled on the mat 5 at the same time as the concrete placement work for the lower part 7a of the shielding wall 7 and the circumferential wall 9 is started.
After assembling the bottom course 13, one stage of lower spherical shells 15 is sequentially welded to the upper part of the bottom course 13, and further, two stages of lower spherical shells 17 are sequentially welded to the upper part of the first stage of lower spherical shells 15. After assembling the lower spherical shell 2 stage 17, the vent course 19 is assembled to the upper part of the lower spherical shell 2 stage 17, and the bottom course 13 lower spherical shell 1 stage.
A local leak test 45 is performed on the welding points 41B of the second stage 15 and 17.
この局部リークテスト45は、溶接箇所41B
をテストチヤネルによつて覆い、そのテストチヤ
ネル内部を所定圧力に加圧して行なわれるもので
ある。これにより、溶接箇所41Bの耐圧および
漏洩が検査される。 This local leak test 45 is performed at the welding location 41B.
The test is carried out by covering the test channel with a test channel and pressurizing the inside of the test channel to a predetermined pressure. As a result, the pressure resistance and leakage of the welded portion 41B are inspected.
ベントコース19の組付後、このベントコース
19の上部に円筒部21、円筒部21の上部に上
部球殻23を溶接して組み付け、更に上部球殻2
3の上部に原子炉格納容器ヘツド25の上部エレ
メントを順次取り付けて、原子炉格納容器1の上
部を形成する。この原子炉格納容器1の上部エレ
メントの組付作業と並行して、局所リークテスト
45の終了後、原子炉格納容器の下部にグラウト
11を注入し充填する。グラウト11の固化とと
もに、ペデスタル33の組立作業や内部コンクリ
ート37の打設(内部コンクリート残部43を除
く。)作業を行なう。 After assembling the vent course 19, the cylindrical part 21 is welded to the upper part of the vent course 19, the upper spherical shell 23 is welded to the upper part of the cylindrical part 21, and then the upper spherical shell 2 is welded to the upper part of the cylindrical part 21.
The upper elements of the reactor containment vessel head 25 are sequentially attached to the upper part of the reactor containment vessel 1 to form the upper part of the reactor containment vessel 1. In parallel with the assembly work of the upper element of the reactor containment vessel 1, after the local leak test 45 is completed, grout 11 is injected and filled into the lower part of the reactor containment vessel. As the grout 11 hardens, the pedestal 33 is assembled and the internal concrete 37 is poured (excluding the remaining internal concrete 43).
これら原子炉格納容器1の上部エレメント組立
21,23,25の組立、グラウト11の充填、
およびペデスタル33の組立作業、並びに内部コ
ンクリート37の打設作業の後に、全体リークテ
スト47を行なう。この全体リークテスト47
は、溶接箇所41Bを除いて全ての溶接箇所につ
いて行なわれる。 Assembling the upper element assemblies 21, 23, 25 of the reactor containment vessel 1, filling the grout 11,
After assembling the pedestal 33 and placing the internal concrete 37, an overall leak test 47 is conducted. This whole leak test 47
is performed for all welding locations except for welding location 41B.
全体リークテスト47の後、原子炉格納容器1
に外面塗装49を施すとともに、内部コンクリー
ト残部43にコンクリートを打設する。このコン
クリート打設後、原子炉格納容器内工事51(原
子炉圧力容器31の配設等)を行なう。また、前
記外面塗装49の後、サンドクツシヨン39を設
け、遮蔽壁7の上部遮蔽壁7bを形成する。 After the overall leak test 47, reactor containment vessel 1
The exterior surface is painted 49, and concrete is poured into the remaining internal concrete portion 43. After this concrete pouring, work 51 inside the reactor containment vessel (installation of the reactor pressure vessel 31, etc.) is performed. Further, after the outer surface painting 49, a sand cushion 39 is provided to form the upper shielding wall 7b of the shielding wall 7.
ところが、上記のような従来の原子炉格納容器
1の据付方法においては、全体リークテスト47
の後にサンドクツシヨン39を設け、その後上部
遮蔽壁7bのコンクリート打設作業を行なつてい
る。そして、上記全体リークテストは、原子炉格
納容器1の組付終了後に行なわれる。したがつ
て、サンドクツシヨン39の設置作業の開始時期
が遅くなり、遮蔽壁7の完成が遅延化して、原子
炉建屋3の建設期間が長期化するという問題を生
ずる。
However, in the conventional installation method of the reactor containment vessel 1 as described above, the overall leak test 47
After that, a sand cushion 39 is installed, and then concrete pouring work for the upper shielding wall 7b is performed. The above-mentioned overall leak test is performed after the assembly of the reactor containment vessel 1 is completed. Therefore, the start time of the sand cushion 39 installation work is delayed, the completion of the shielding wall 7 is delayed, and the construction period of the reactor building 3 is prolonged.
また、サンドクツシヨン39の設置作業はグラ
ウト11の完成後行なわれるため、サンドクツシ
ヨン39の設置が狭隘な場所で行なれわれること
になる。故に、サンドクツシヨン39の設置作業
が複雑かつ煩雑となり、作業性および作業安全性
が低下するという短所もある。 Furthermore, since the sand cushion 39 is installed after the grout 11 is completed, the sand cushion 39 must be installed in a narrow space. Therefore, the work of installing the sand cushion 39 becomes complicated and complicated, and there is also a disadvantage that work efficiency and work safety are reduced.
この発明は、上記の事実を考慮してなされたも
のであり、原子炉建屋の建設工期を短縮すること
ができる原子炉格納容器の据付方法を提供するこ
とを目的とする。
The present invention has been made in consideration of the above facts, and an object of the present invention is to provide a method for installing a reactor containment vessel that can shorten the construction period of a reactor building.
上記目的を達成するために、この発明に係る原
子炉格納容器の据付方法はボトムコース、下部球
殻1段、下部球殻2段、およびベントコースを下
方から順次組み付けて原子炉格納容器下部を組み
立てた後、上記ベントコースの上方に原子炉格納
容器の上部エレメントを順次組み付ける作業と並
行して、前記ベントコースと下部球殻2段との溶
接部のリークテストを行ないかつこのリークテス
ト後に上記溶接部へサンドクツシヨンを取付ける
作業を行なうものであり、前記リークテストおよ
びサンドクツシヨン取付作業を原子炉格納容器の
上部組付中に完了することにより、原子炉格納容
器の組付完了後早期に、原子炉建屋の遮蔽壁を完
成するものである。
In order to achieve the above object, the method for installing a reactor containment vessel according to the present invention is to assemble the bottom course, one stage of lower spherical shell, two stages of lower spherical shell, and vent course from below in order to install the lower part of the reactor containment vessel. After assembly, in parallel with the work of sequentially assembling the upper elements of the reactor containment vessel above the vent course, a leak test of the welded part between the vent course and the two lower spherical shells was performed, and after this leak test, the above This involves attaching the sand cushion to the welded part, and by completing the leak test and sand cushion installation work during the assembly of the upper part of the reactor containment vessel, it is possible to perform the work at an early stage after the assembly of the reactor containment vessel is completed. Finally, the shielding wall of the reactor building will be completed.
第3図および第4図は、この発明に係る原子炉
格納容器の据付方法を適用して完成した原子炉格
納容器および原子炉建屋を示す図である。これら
両図において前記従来例と同様な部分は同一の符
号を附すことにより説明を省略する。
3 and 4 are diagrams showing a reactor containment vessel and a reactor building completed by applying the reactor containment vessel installation method according to the present invention. In both of these figures, the same parts as those in the conventional example are designated by the same reference numerals, and the explanation thereof will be omitted.
グラウト61は内側グラウト61aと外側グラ
ウト61bとから構成される。内側グラウト61
aは、ボトムコース13および下部球殻15の外
側を覆い、その半径方向外側の最大高さはマツト
5から下部球殻1段15と同2段17との溶接線
の下方近傍までの距離である。また、外側グラウ
ト61bは、内側グラウト61aに接してその外
周側に位置し、断面略台形状で、原子炉格納容器
1に沿つて円筒状またはトーラス状に形成され
る。また、この外側グラウト61bは下部球殻2
段17の外側を覆い、その高さは、マツト5から
溶接線41Aの下方近傍までの距離である。 The grout 61 is composed of an inner grout 61a and an outer grout 61b. Inside grout 61
a covers the outside of the bottom course 13 and the lower spherical shell 15, and its maximum height in the radial direction is the distance from the pine 5 to the vicinity below the welding line between the first stage 15 and the second stage 17 of the lower spherical shell. be. Further, the outer grout 61b is located on the outer peripheral side of the inner grout 61a in contact with the inner grout 61a, has a substantially trapezoidal cross section, and is formed in a cylindrical or toroidal shape along the reactor containment vessel 1. Moreover, this outer grout 61b is connected to the lower spherical shell 2.
It covers the outside of the step 17, and its height is the distance from the mat 5 to the vicinity below the weld line 41A.
この外側クラウド61bの上方で、原子炉格納
容器1における溶接線41Aの外側に、サンドク
ツシヨン39が設けられる。このサンドクツシヨ
ン39の取付を第5図に基づいて説明する。 A sand cushion 39 is provided above the outer cloud 61b and outside the weld line 41A in the reactor containment vessel 1. The installation of this sand cushion 39 will be explained based on FIG. 5.
下部球殻2段の外面には周方向適宜位置にパツ
ト63が固着され、このパツト63に支持部材6
5が固定される支持部材65には、サポート67
を介して枠体69が支持される。この枠体69は
断面略L字形状で溶接線41Aの外側に対向し、
この溶接線41Aに沿つて環状に形成されてい
る。枠体69と下部球殻2段17およびベントコ
ース19とにより囲まれる空間内に砂70が充填
されて、サンドクツシヨン39の取付は完了す
る。支持部材65およびサポート67の一部は、
その後にコンクリート打設される外側グラウト6
1bに埋没され、また枠体69およびサポート6
7の残部も上部遮蔽壁7bに埋没されてコンクリ
ート固定される。 Pats 63 are fixed to the outer surface of the second stage of the lower spherical shell at appropriate positions in the circumferential direction, and the support members 6 are attached to the parts 63.
The support member 65 to which 5 is fixed has a support 67
The frame body 69 is supported via. This frame body 69 has a substantially L-shaped cross section and faces the outside of the welding line 41A.
It is formed in an annular shape along this weld line 41A. Sand 70 is filled into the space surrounded by the frame body 69, the two lower spherical shells 17, and the vent course 19, and the installation of the sand cushion 39 is completed. A portion of the support member 65 and the support 67 are
External grout 6 to be concreted afterwards
1b, and the frame body 69 and the support 6
The remaining part of 7 is also buried in the upper shielding wall 7b and fixed in concrete.
次に、原子炉格納容器の据付工法を第6図Bに
基づいて説明する。同図Aと同様な工程は同一の
符号を用いる。 Next, the installation method of the reactor containment vessel will be explained based on FIG. 6B. The same reference numerals are used for steps similar to those in FIG.
まず、原子炉建屋3のマツトをを、配筋作業お
よびコンクリート打設作業により形成する。その
後、下部遮蔽壁7aおよび円周壁9のコンクリー
ト打設を開始する。このコンクリート打設と並行
して、マツト5上でボトムコース13を組立て
る。ボトムコース13の組立後、ボトムコース1
3の上部に下部球殻1段15を、さらにこの下部
球殻1段15の上部に下部球殻2段17を順次溶
接して組み付ける。下部球殻2段17の組付後、
その上部にベントコース19を組み付けるととも
に、ボトムコース13、下部球殻1段15、同2
段17の溶接箇所41Bの局所リークテスト45
を行なう。前記下部遮蔽壁7aは局所リークテス
ト45の終了時には終了している。 First, the pine of the reactor building 3 is formed by reinforcement work and concrete pouring work. Thereafter, concrete placement of the lower shielding wall 7a and the circumferential wall 9 is started. In parallel with this concrete pouring, the bottom course 13 is assembled on the mat 5. After assembling bottom course 13, bottom course 1
A first stage of lower spherical shells 15 is sequentially welded to the upper part of the lower spherical shell 15, and two stages of lower spherical shells 17 are sequentially welded to the upper part of the first stage of lower spherical shells 15. After assembling the lower spherical shell two stages 17,
In addition to assembling the vent course 19 on the upper part, the bottom course 13, the lower spherical shell 1 stage 15, and the
Local leak test 45 of welding point 41B of stage 17
Do this. The lower shielding wall 7a is finished at the end of the local leak test 45.
上記局所リークテスト45の終了後ペデスタル
33の組立作業および内部コンクリート37の打
設作業(内部コンクリート残部43を除く。)を
行なうとともに、内側グラウト61aを形成す
る。 After the local leak test 45 is completed, the pedestal 33 is assembled and the internal concrete 37 is placed (excluding the remaining internal concrete 43), and the internal grout 61a is formed.
一方、ベントコース19の組み付け後、このベ
ントコース19の上部に円筒部21を、この円筒
部21の上部に上部球殻23を組み付け、更に上
部球殻23の上部に原子炉格納容器ヘツド25を
取り付けて、原子炉格納容器1の上部を組み立て
る。この原子炉格納容器1の上部エレメント組立
を順次組み付けていく組立作業と並行して、溶接
線41Aの局部リークテスト71を行なう。この
局部リークテスト71は局部リークテスト45と
同様にして行なう。局部リークテスト71の終了
後で原子炉格納容器の上部エレメントの組立中
に、内部コンクリート残部43を打設するととも
に、サンドクツシヨン39を原子炉格納容器1の
外周に取り付ける。原子炉格納容器の上部エレメ
ント組立中で、上記サンドクツシヨン39の取付
後に、外側グラウト61bを充填する。サンドク
ツシヨン39の取付用のサポート67の一部およ
び支持部材65は上記外側グラウト61bの充填
時にこれを埋没される。 On the other hand, after assembling the vent course 19, the cylindrical part 21 is assembled to the upper part of this vent course 19, the upper spherical shell 23 is assembled to the upper part of this cylindrical part 21, and the reactor containment vessel head 25 is further installed to the upper part of the upper spherical shell 23. Attach it and assemble the upper part of the reactor containment vessel 1. In parallel with the assembly work of sequentially assembling the upper elements of the reactor containment vessel 1, a local leak test 71 of the weld line 41A is performed. This local leak test 71 is performed in the same manner as the local leak test 45. After the local leak test 71 is completed and during the assembly of the upper element of the reactor containment vessel, the remaining internal concrete 43 is poured and the sand cushion 39 is attached to the outer periphery of the reactor containment vessel 1. During assembly of the upper element of the reactor containment vessel, after the sand cushion 39 is installed, the outer grout 61b is filled. A part of the support 67 for mounting the sand cushion 39 and the support member 65 are buried in the outer grout 61b when it is filled.
原子炉格納容器の上部組立完了後、並びに内部
コンクリートの残部43のコンクリート打設完了
後、更に外側グラウト61bの充填作業後全体リ
ークテスト73を行なう。この全体リークテスト
73は、すでにリークテスト済みの溶接線41
A、および溶接箇所41Bを除いた全ての溶接箇
所について行なわれる。 After completing the assembly of the upper part of the reactor containment vessel, after completing the pouring of the remaining internal concrete 43, and after filling the outer grout 61b, an overall leak test 73 is performed. This entire leak test 73 is performed on the weld line 41 which has already been leak tested.
This is done for all welding locations except for welding location A and welding location 41B.
全体リークテスト73の終了後、原子炉格納容
器内工事51(原子炉圧力容器31の配設等)を
行なうとともに、原子炉格納容器1の外面塗装4
9を行なう。この外面塗装49の後に上部遮蔽壁
7bを形成する。前記サンドクツシヨン39、サ
ポート67の残部および枠体69は、上記の上部
遮蔽壁7bに埋没されて、コンクリート固着さ
れ、一体構造物となる。 After completion of the overall leak test 73, work inside the reactor containment vessel 51 (installation of the reactor pressure vessel 31, etc.) is carried out, and the outer surface of the reactor containment vessel 1 is painted 4.
Do 9. After this outer surface coating 49, the upper shielding wall 7b is formed. The sand cushion 39, the remainder of the support 67, and the frame 69 are buried in the upper shielding wall 7b and fixed to concrete to form an integral structure.
上記実施例によれば、原子炉格納容器の上部2
1,23,25の組立中に、溶接線41Aの局部
リークテスト71を行ない、更にサンドクツシヨ
ン39を取り付けることから、原子炉格納容器1
を組み立て全体リークテスト73を行なつた後、
迅速に遮蔽壁7を完成することができる。したが
つて、原子炉建屋の建設工期を短縮することがで
きる。 According to the above embodiment, the upper part 2 of the reactor containment vessel
1, 23, and 25, a local leak test 71 of the weld line 41A is performed, and the sand cushion 39 is installed, so the reactor containment vessel 1
After assembling and performing a leak test 73,
The shielding wall 7 can be completed quickly. Therefore, the construction period for the reactor building can be shortened.
また、グラウト61を、中央部の内側グラウト
61aと、サンドクツシヨン39の取付位置下方
に形成される外側グラウト61bとに分け、内側
グラウト61aの充填後サンドクツシヨン39を
取付け、その後外側グラウト61bを充填するこ
とから、サンドクツシヨン39の取付作業を広い
空間内で行なうことができ、この取付作業性およ
び作業安全性を向上させることができる。 Further, the grout 61 is divided into an inner grout 61a in the center and an outer grout 61b formed below the mounting position of the sand cushion 39, and after filling the inner grout 61a, the sand cushion 39 is attached, and then the outer grout 61b is Since the sand cushion 39 is filled with , the installation work of the sand cushion 39 can be carried out in a wide space, and the workability and safety of the installation work can be improved.
さらに、溶接線41Aの局所リークテスト71
を原子炉格納容器の上部組立中に行なうことか
ら、内部コンクリート残部43のコンクリート打
設を原子炉格納容器の上部組立中に完了すること
ができ、原子炉圧力容器31の配設等の原子炉格
納容器2内の工事を全体リークテスト73の直後
に、早期に着工することができる。 Furthermore, local leak test 71 of weld line 41A
Since this is performed during the assembly of the upper part of the reactor containment vessel, the concrete placement of the remaining internal concrete 43 can be completed during the assembly of the upper part of the reactor containment vessel, and the reactor pressure vessel 31 arrangement etc. Construction inside the containment vessel 2 can be started immediately after the overall leak test 73.
以上のように、この発明に係る原子炉、格納容
器の据付方法によれば、原子炉格納容器の上部エ
レメント組立の順次組付作業と並行して、ベント
コースと下部球殻2段との溶接部のリークテスト
およびこのリークテスト後の上記溶接部へのサン
ドクツシヨン取付作業を行なうことから、原子炉
格納容器の組付完了後早期に原子炉建屋の遮蔽壁
を完成することができ、故に原子炉建屋の建設工
期を短縮することができるという効果を有する。
As described above, according to the method for installing a nuclear reactor and containment vessel according to the present invention, welding of the vent course and the two lower spherical shells is performed in parallel with the sequential assembly work of the upper element assembly of the reactor containment vessel. By performing a leak test on the welded part and installing the sand cushion on the welded part after the leak test, the shielding wall of the reactor building can be completed early after the assembly of the reactor containment vessel is completed. This has the effect of shortening the construction period for the reactor building.
第1図は従来の原子炉格納容器が原子炉建屋に
据え付けられた状態を示す一部切欠側面図、第2
図は原子炉格納容器の下部を拡大して示す断面
図、第3図はこの発明に係る原子炉格納容器の据
付方法を適用して完成した原子炉格納容器および
原子炉建屋を示す一部切欠側面図、第4図は第3
図の原子炉格納容器の下部を拡大して示す断面
図、第5図はサンドクツシヨンを原子炉格納容器
へ取り付けた状態を示す側面図、第6図は原子炉
格納容器の据付工程を示すものであり、同図Bは
この発明による原子炉格納容器の据付工程を、同
図Aは従来の原子炉格納容器の据付工程を、それ
ぞれ示すシーケンス図である。
1……原子炉格納容器、3……原子炉建屋、1
3……ボトムコース、15……下部球殻1段、1
7……下部球殻2段、19……ベントコース、2
1……円筒部、23……上部球殻、25……原子
炉格納容器ヘツド、39……サンドクツシヨン、
41A……溶接線、43……内部コンクリート残
部、61……グラウト、61a……内側グラウ
ト、61b……外側グラウト、71……局部リー
クテスト。
Figure 1 is a partially cutaway side view showing a conventional reactor containment vessel installed in a reactor building;
The figure is an enlarged sectional view of the lower part of the reactor containment vessel, and Fig. 3 is a partial cutaway showing the reactor containment vessel and reactor building completed by applying the reactor containment vessel installation method according to the present invention. Side view, Figure 4 is the 3rd
Figure 5 is a side view showing the sand cushion attached to the reactor containment vessel; Figure 6 is a diagram showing the installation process of the reactor containment vessel. Figure B is a sequence diagram showing the installation process of a reactor containment vessel according to the present invention, and Figure A is a sequence diagram showing the installation process of a conventional reactor containment vessel. 1...Reactor containment vessel, 3...Reactor building, 1
3...Bottom course, 15...Lower spherical shell 1 stage, 1
7...2 lower spherical shells, 19...Bent course, 2
1... Cylindrical part, 23... Upper spherical shell, 25... Reactor containment vessel head, 39... Sand cushion,
41A... Welding line, 43... Internal concrete remainder, 61... Grout, 61a... Inner grout, 61b... Outer grout, 71... Local leak test.
Claims (1)
およびベントコースを下方から順次組み付けて原
子炉格納容器下部を組み立てた後、上記ベントコ
ースの上方に原子炉格納容器の上部エレメントを
順次組み付ける作業と並行して、前記ベントコー
スと下部球殻2段との溶接部のリークテストを行
ないかつこのリークテスト後に上記溶接部へサン
ドクツシヨンを取付ける作業を行なうことを特徴
とする原子炉格納容器の据付方法。 2 前記原子炉格納容器の外側下方で前記溶接線
の下方近傍までのグラウト充填作業を、前記原子
炉格納容器の上部エレメント組立作業と並行して
行ない、そのグラウトの充填作業は、前記ボトム
コースおよび下部球殻1段の下方に形成される内
側グラウトと、下部球殻2段の下方に形成される
外側グラウトとに分けられ、前記内側グラウトの
充填後、前記サンドクツシヨンを取り付け、その
後に前記外側グラウトを充填する特許請求の範囲
第1項記載の原子炉格納容器の据付方法。 3 前記原子炉格納容器の内部下方で前設溶接線
の上方近傍まで打設される内部コンクリートの打
設作業を、前記原子炉格納容器の上部エレメント
組立作業と並行して行ない、その内部コンクリー
トの打設作業は、前記溶接部に当接する内部コン
クリート残部の打設作業が前記リークテストの終
了後に開始され、前記原子炉格納容器の上部エレ
メント組立終了までに完了している特許請求の範
囲第1項記載の原子炉格納容器の据付方法。[Claims] 1. After assembling the lower part of the reactor containment vessel by sequentially assembling the bottom course, the first stage of lower spherical shell, the second stage of lower spherical shell, and the vent course from below, the reactor containment vessel is installed above the vent course. In parallel with the work of sequentially assembling the upper elements of the invention, a leak test is performed on the welded part between the vent course and the two lower spherical shells, and after this leak test, the work of installing a sand cushion to the welded part is performed. How to install a reactor containment vessel. 2. A grout filling operation is performed below the outside of the reactor containment vessel up to the vicinity of the lower part of the weld line in parallel with the upper element assembly operation of the reactor containment vessel, and the grout filling operation is performed on the bottom course and the vicinity of the weld line. It is divided into an inner grout formed below the first stage of the lower spherical shell and an outer grout formed below the second stage of the lower spherical shell. After filling the inner grout, the sand cushion is attached, and then the A method for installing a nuclear reactor containment vessel according to claim 1, which comprises filling the outer grout. 3. The work of placing internal concrete, which is placed in the lower part of the reactor containment vessel up to the vicinity above the front weld line, is carried out in parallel with the work of assembling the upper element of the reactor containment vessel, and According to the first aspect of the present invention, the pouring work is such that the pouring work of the remaining internal concrete that comes into contact with the welded portion is started after the end of the leak test and is completed by the end of the assembly of the upper element of the reactor containment vessel. Installation method of reactor containment vessel described in Section 1.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58121486A JPS6014197A (en) | 1983-07-06 | 1983-07-06 | Method of installing nuclear reactor containing vessel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58121486A JPS6014197A (en) | 1983-07-06 | 1983-07-06 | Method of installing nuclear reactor containing vessel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6014197A JPS6014197A (en) | 1985-01-24 |
| JPH0363717B2 true JPH0363717B2 (en) | 1991-10-02 |
Family
ID=14812347
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP58121486A Granted JPS6014197A (en) | 1983-07-06 | 1983-07-06 | Method of installing nuclear reactor containing vessel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6014197A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5260268B2 (en) * | 2008-12-26 | 2013-08-14 | 日立Geニュークリア・エナジー株式会社 | Manufacturing method of core shroud for nuclear power plant and nuclear power plant structure |
-
1983
- 1983-07-06 JP JP58121486A patent/JPS6014197A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6014197A (en) | 1985-01-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0363717B2 (en) | ||
| JP3283735B2 (en) | Method for constructing upper dry well of reactor containment vessel and module used for the method | |
| JPS63755B2 (en) | ||
| JPS62310B2 (en) | ||
| JPH05264772A (en) | Method for constructing diaphragm floor | |
| JPS6322278B2 (en) | ||
| JPH0672940B2 (en) | Construction method of reactor containment superstructure | |
| JPS6323355Y2 (en) | ||
| JP2005189013A (en) | Reactor containment vessel, reactor containment facility having the reactor containment vessel, and methods of construction thereof | |
| JP3345537B2 (en) | Diaphragm floor of reinforced concrete containment vessel | |
| JP2862049B2 (en) | Concrete casting jig for concrete outer tube | |
| JPH04265898A (en) | Method for constructing reactor container of nuclear power station | |
| JPS6315832Y2 (en) | ||
| JPS646426B2 (en) | ||
| JPH03295496A (en) | Reactor containment vessel top slab construction method and reactor containment vessel | |
| JPS6331069B2 (en) | ||
| JPS6219596Y2 (en) | ||
| JPS6244634B2 (en) | ||
| JPS6410795B2 (en) | ||
| JPS61120091A (en) | Installation method for the bottom of the reactor containment vessel | |
| JPS60108791A (en) | Reactor containment vessel bottom liner installation method | |
| JPS63756B2 (en) | ||
| JPH09166685A (en) | Construction method of reinforced concrete reactor containment vessel | |
| JPH0213757B2 (en) | ||
| JPS5952787A (en) | Method of building reactor container |