JPH0365009A - Anchoring method of passing overhead wire - Google Patents
Anchoring method of passing overhead wireInfo
- Publication number
- JPH0365009A JPH0365009A JP1198717A JP19871789A JPH0365009A JP H0365009 A JPH0365009 A JP H0365009A JP 1198717 A JP1198717 A JP 1198717A JP 19871789 A JP19871789 A JP 19871789A JP H0365009 A JPH0365009 A JP H0365009A
- Authority
- JP
- Japan
- Prior art keywords
- arm
- lead
- existing
- overhead
- retaining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、引通し装柱方式の架空線を引留め装柱方式の
架空線に変更する装柱作業等を効率良く行うための引通
し架空線の引留め化工法に関するものである。[Detailed Description of the Invention] [Industrial Field of Application] The present invention is directed to a system for efficiently carrying out pole installation work, etc., in which overhead wires using a pull-in pole mounting method are changed to overhead wires using a tie-down pole mounting method. This relates to a method for retaining overhead wires.
従来の引通し装柱方式(分解式り型アームを利用して装
柱)にて袈装した架空線を引留め装柱方式による架空線
に変更する引通し架空線の引留め化工法は第3図(a)
〜(e)に示す如く、高所作業車のブーム21の先端に
装備したパケット22に搭乗した作業員が、引通し碍子
24より外した1本の架空’hlWを、他の引通し碍子
24に仮置きし、架空線Wを取り外した側の引通し碍子
24をD型アーム25より順次撤去するのであるが、こ
の撤去作業の手順は、撤去作業が活線にて行われる場合
は、先ず各架空線Wに絶縁防護カバーCを装着(同図(
b)参照)し、次に撤去すべき引通し碍子24に被せた
碍子カバー24aを外し、架空線Wを当該引通し碍子2
4から取り外して未撤去の弓通し碍子24に仮置し、最
終的に引通し碍子24のダブルナツト24bを取り外し
てD型アーム25より引通し碍子24を撤去する。The method of retaining overhead wires, which changes the overhead wires installed using the conventional pole installation method (installing poles using disassembly-type arms) into the overhead wires using the retaining pole installation method, is the first method. Figure 3 (a)
As shown in ~(e), a worker riding a packet 22 attached to the tip of the boom 21 of an aerial work vehicle removes one imaginary 'hlW from a lead-in insulator 24 and attaches it to another lead-in insulator 24. The lead-in insulator 24 on the side from which the overhead wire W has been removed is removed from the D-shaped arm 25 in sequence. Attach an insulation protection cover C to each overhead line W (see figure (
b)), then remove the insulator cover 24a covering the lead-in insulator 24 to be removed, and remove the overhead wire W from the lead-in insulator 24.
4 and temporarily placed on the unremoved bow insulator 24, and finally, the double nut 24b of the draw insulator 24 is removed and the draw insulator 24 is removed from the D-shaped arm 25.
しかして、引通し碍子24の撤去が終了すると、同図(
d)に示す如く、ストラップ28a、28a、耐張碍子
29 a s 29 a及び引留クランプ30a、30
aからなる左右一対の引留め装置31の端部に装備した
前記ストラップ28a、28aのボルト挿通穴を撤去し
た引通し碍子24の撤去後の取付穴27に合致させてボ
ルト32を挿通して取り付けた後、各架空線Wに対する
張線処理を行って既設の引通し装柱方式による架空線W
を引留め装柱方式の架空線Wに切り換えているのが実情
である。However, when the removal of the lead-in insulator 24 is completed, the same figure (
As shown in d), straps 28a, 28a, tension insulators 29a, and retaining clamps 30a, 30
The bolts 32 are inserted and installed by aligning the bolt insertion holes of the straps 28a, 28a installed at the ends of the left and right pair of retaining devices 31 consisting of a with the mounting holes 27 after the removal of the lead-in insulator 24. After that, each overhead wire W is tensioned, and the overhead wire W is
The current situation is that the overhead lines W have been switched to a tie-down pole-mounted type of overhead line W.
しかるに、従来の引通し装柱方式の架空線Wを引留め装
柱方式の架空線Wに変更する引留め化工法は、先ずパケ
ット22に搭乗した作業員が1本の引通し碍子24より
外した架空線Wを、他の引通し碍子24に仮置きするに
際し、撤去作業が活線にて行われる場合は、前述した如
く、各架空線Wに絶縁防護カバー〇を装着しなければな
らないために作業が煩わしく、しかも碍子カバー24a
を外すに当たっては、碍子カバー24aの接合部24c
に沿ってナイフ24dを当てて粘着テープ24eの切断
を行う必要があり、従って非常に危険で、かつ作業も困
難であった。又引通し碍子24から架空線Wを外す場合
は、架空線Wの保持乃至落下に十分な注意を要し、かつ
また引通し碍子24を固定したダブルナツト24bを外
す場合は、通常、パケット22を道路側に位置させて作
業を行う関係上ダブルナラ)24bを外す作業員は体を
パケット22外に相当に乗り出して行わなければダブル
ナラ)24bの位置に手が届かず、非常に危険であった
。又、ストラップ28a、28a、耐張碍子29a、2
9a及び引留クランプ30a、30aからなる左右一対
の引留め装置31は、第3図(d)に示す状態で取り付
けるのであるが、各部品毎の取付部(A、B、A’ B
’ )がフリーの状態で連結されているために取り扱い
にくく、従って通常は2人で作業を行い1人は耐張碍子
29a、29a部分を支えもう1人がD型アーム25の
ボルト穴27に対してストラップ28a、28aのボル
ト挿通穴の合致を行わなければならず作業が極めて非能
率的である。又ストラップ28a、28aをD型アーム
25に固定するためには前述したダブルナツト24bの
取り外しと同様に再び作業員はパケット22から体を乗
り出さなければならず相当困難な作業を強いられると共
に、マニピュレータ装置を装備した高所作業車を導入し
て作業を実施するには前述の如く、各作業は複雑過ぎる
ために行うことが不可能である等種々の問題を有してい
た。However, in the tie-down construction method, which changes the conventional overhead wire W of the lead-in pole installation method to the overhead wire W of the tie-down pole installation method, a worker on board the packet 22 first removes the wire from one lead-in insulator 24. When temporarily placing overhead wires W on other lead-in insulators 24, if the removal work is performed on live wires, as described above, each overhead wire W must be fitted with an insulation protection cover. The work is troublesome, and the insulator cover 24a
When removing the insulator cover 24a,
It was necessary to cut the adhesive tape 24e by applying the knife 24d along the line, which was very dangerous and difficult. Furthermore, when removing the overhead wire W from the lead-in insulator 24, sufficient care must be taken not to hold or drop the overhead wire W, and when removing the double nut 24b that fixed the lead-in insulator 24, the packet 22 is usually removed. Due to the fact that the work was carried out on the side of the road, the worker who removed the double neck 24b had to lean considerably outside the packet 22 to reach the position of the double neck 24b, which was very dangerous. Also, straps 28a, 28a, tension insulators 29a, 2
The pair of left and right retaining devices 31 consisting of the retaining clamp 9a and the retaining clamps 30a, 30a are installed in the state shown in FIG. 3(d).
) are connected in a free state, making them difficult to handle, so normally two people are required to do the work, one supporting the tension insulators 29a and 29a, and the other supporting the bolt holes 27 of the D-shaped arm 25. On the other hand, the bolt insertion holes of the straps 28a and 28a must be matched, which is extremely inefficient. In addition, in order to fix the straps 28a, 28a to the D-shaped arm 25, the operator must lean out from the packet 22 again in the same manner as in the case of removing the double nut 24b described above, and is forced to perform a considerably difficult task. As mentioned above, implementing an aerial work vehicle equipped with the equipment to carry out the work has various problems, such as the fact that each work is too complicated to carry out.
〔発明の目的及び課題を解決するための手段〕本発明は
、前述した問題点に鑑みてなされたものであり、その目
的とするところは、引通し装柱方式の架空線を引留め装
柱方式の架空線に変更する装柱作業等を効率良く行うた
めに電柱に装柱した既設の分解式り型アームの左右対象
位置に一対の腕金に対してストラップを介して耐張碍子
及び引留クランプを順次連結した引留め装置を配置する
と共に、該引留め装置の前記腕金を既設の分解式り型ア
ームを構成する上下の水平アームの側部に固定し、前記
分解式り型アームに取り付けた引通し碍子に袈装した架
空線を前記引留め装置の各引留クランプにて係止した後
、引通し碍子に袈装された架空線を各引通し碍子の左右
にて切断し、既設の分解式り型アームを構成する垂直ア
ーム部分の取り外しと同時に既設の各引通し碍子を撤去
することによって引通し装柱方式の架空線を引留め装柱
方式の架空線に変更することの出来る引通し架空線の引
留め化工法を提供することにある。[Objects of the Invention and Means for Solving the Problems] The present invention has been made in view of the above-mentioned problems, and its purpose is to connect overhead wires of the lead-through type to the poles. In order to efficiently carry out pole mounting work for changing to overhead lines, tension insulators and tie-downs are attached to a pair of arms at symmetrical positions on the left and right sides of the existing disassembly type arms attached to utility poles via straps. A retaining device in which clamps are successively connected is arranged, and the arms of the retaining device are fixed to the sides of the upper and lower horizontal arms constituting the existing disassembly type arm, and After locking the overhead wires sheathed to the installed lead-in insulators with the respective retaining clamps of the above-mentioned retaining device, the overhead wires sheathed to the lead-in insulators are cut on the left and right sides of each lead-in insulator, and the existing By removing the vertical arm part that makes up the disassembly type arm and simultaneously removing each of the existing lead-in insulators, it is possible to change the overhead wire of the lead-in pole mounting method to the overhead wire of the tie-down pole mounting method. The object of the present invention is to provide a method for retaining overhead wires.
〔作用〕
本発明は上記の引通し架空線の引留め化工法を採用して
引通し装柱方式の架空線を引留め装柱方式の架空線に変
更するものであるから、分解式り型アームに引通し装柱
方式にて配線されている既設の架空線Wを撤去する引通
し碍子から取り外して他の引通し碍子に仮置きし、撤去
した引通し碍子の取り付は穴を利用して引留め装柱方式
のストラップ、耐張碍子及び引留クランプ等を繰り返し
て順次取り付ける煩雑な作業の必要が無く、従って引通
し装柱方式より引留め装柱方式への切り換え作業が極め
て簡単となり、しかも作業にマニピュレータ装置を装備
した高所作業車を導入することが可能でるから、作業時
間の大幅な短縮と作業の十分な安全性が確保できる。[Function] The present invention employs the above-mentioned method of retaining overhead wires to change the overhead wires of the overhead line system to the overhead wires of the retaining pole system. Remove the existing overhead wire W, which is wired to the arm using the lead-in pole installation method, from the lead-in insulator to be removed and temporarily place it on another lead-in insulator, and use the hole to install the removed lead-in insulator. There is no need for the complicated work of repeatedly attaching straps, tension insulators, retaining clamps, etc. of the tie-down pole mounting method, and therefore it is extremely easy to switch from the pull-through pole mounting method to the tie-down pole mounting method. Moreover, since it is possible to introduce an aerial work vehicle equipped with a manipulator device for the work, it is possible to significantly shorten the work time and ensure sufficient safety of the work.
〔実施例]
以下、第1図及び第2図(a)〜(c)に基づいて本発
明に係る引通し架空線の引留め化工法の一実施例を詳細
に説明する。[Example] Hereinafter, an example of the method for retaining overhead wires according to the present invention will be described in detail with reference to FIG. 1 and FIGS. 2(a) to 2(c).
同図中、lはブーム2の先端にマニピュレータ操作室3
とマニピュレータ装置4を装備した高所作業車であり、
5は前記マニピュレータ操作室3の背部より同マニピュ
レータ操作室3の前方に装備したマニピュレータ装置4
の上方に臨ませることが出来る様に構成した吊り上げ装
置である。In the figure, l is a manipulator operation chamber 3 at the tip of the boom 2.
It is an aerial work vehicle equipped with a manipulator device 4,
Reference numeral 5 denotes a manipulator device 4 installed at the front of the manipulator operation chamber 3 from the back of the manipulator operation chamber 3.
This is a lifting device constructed so that it can be viewed above.
8は前記吊り上げ装置5で吊り上げ、電柱6の分解式り
型アーム(以下り型アームと略称する)7に取り付ける
べき引留め装置8であり、該引留め装置8は、垂直に配
置する一対の腕金83.8aと、左右の腕金8a、8a
に上下所定の間隔を置いて取り付けたストラップ8b、
8b、8bにそれぞれ対応させて順次耐張碍子8C18
c58Cと引留クランプ8d、8d、8dを連結するこ
とによって構成されているa8e・・・はボルト孔であ
る。Reference numeral 8 designates a retaining device 8 that is to be lifted by the lifting device 5 and attached to a disassembly type arm (hereinafter referred to as a lower type arm) 7 of the utility pole 6. Arm 83.8a and left and right arm 8a, 8a
straps 8b attached at predetermined intervals above and below,
Tension-resistant insulators 8C18 corresponding to 8b and 8b respectively
A8e... is a bolt hole formed by connecting c58C and retaining clamps 8d, 8d, 8d.
尚、本実施例に採用する前記り型アーム7は上下位置に
平行に配置する水平アーム7a、7aと、両水平アーム
7a、7a間にポル)7b・・・により垂直に取り付け
る垂直アーム7cの三部材にて構成される分解式り型ア
ーム7であり、かつ前記水平アーム7a、7aの垂直ア
ーム7Cが取り付けられる先端部寄りの側部には前記引
留め装置8を構成する左右の腕金8a、8aを取り付け
るためのボルト孔7d、7dが穿設られているものであ
る。The above-mentioned type arm 7 adopted in this embodiment has horizontal arms 7a, 7a arranged in parallel in the upper and lower positions, and a vertical arm 7c, which is attached vertically between both the horizontal arms 7a, 7a by a pole 7b... It is a removable type arm 7 composed of three members, and left and right arms constituting the retaining device 8 are attached to the sides near the tips to which the vertical arms 7C of the horizontal arms 7a and 7a are attached. Bolt holes 7d, 7d for attaching 8a, 8a are drilled.
以下、上記の構成による引留め装置8を採用して本発明
に係る引通し架空線の引留め化工法の実施要領を説明す
る。Hereinafter, the procedure for carrying out the method for retaining overhead wires according to the present invention using the retaining device 8 having the above-described configuration will be explained.
先ず、その作業手順は、引通し装柱方式によりD型アー
ム7に袈装された既設の架空線Wを引通し碍子10から
外すことなく、第2図((13〜(c)に示す如く、地
上で組み立てた引留め装置8を吊り上げ装置5によりD
型アーム7の上方へ吊り上げ、垂直に配置する左右の腕
金88及び8aの間にD型アーム7の上端を合致させ、
吊り上げ装置5を操作してD型アーム7の左右に吊り上
げた引留め装置8をゆっくりと下降させて左右の腕金8
a及び8aをD型アーム7の両脇に垂直に沿わせ、かつ
左右の腕金8a及び8aの上下に穿設したボルト孔8e
とD型アーム7の上下の水平アーム7a、7aの側部に
穿設したボルト孔7d、7dを合致させてボルト9を挿
通し、引留め装置8をD型アーム7に固定する。First, the work procedure is as shown in Fig. 2 ((13-(c)) without removing the existing overhead wire W, which is covered by the D-shaped arm 7, from the insulator 10 by the lead-in column installation method. , the restraining device 8 assembled on the ground is lifted up by the lifting device 5 D
Lift the mold arm 7 upwards, align the upper end of the D-shape arm 7 between the left and right arms 88 and 8a arranged vertically,
By operating the lifting device 5, the retaining devices 8 hoisted to the left and right sides of the D-shaped arm 7 are slowly lowered to lower the left and right arms 8.
a and 8a vertically along both sides of the D-shaped arm 7, and bolt holes 8e drilled above and below the left and right arms 8a and 8a.
The retaining device 8 is fixed to the D-shaped arm 7 by aligning the bolt holes 7d, 7d drilled in the sides of the upper and lower horizontal arms 7a, 7a of the D-shaped arm 7, and inserting the bolt 9 therethrough.
しかる後、第2図(C)に示す如く、前記引留め装置8
を構成する引留クランプ8d、8d、8dにてそれぞれ
に対応する3相の架空線Wをクランプし、既設の各引通
し碍子10の左右位1x −xXにて架空線Wを切断し
、最終的にD型アーム7の垂直アーム7Cに装着された
ままの既設の各引通し碍子lOを垂直アーム7Cを上下
の水平アーム7a、7aより取り外すことにより一体的
に取り外して本発明に係る引通し架空線の引留め化工法
による架空線の引留め作業は全て終了する。After that, as shown in FIG. 2(C), the retaining device 8
Clamp the corresponding three-phase overhead wires W with the retaining clamps 8d, 8d, and 8d that constitute the Then, by removing the vertical arm 7C from the upper and lower horizontal arms 7a, 7a, the existing lead-in insulators 1O still attached to the vertical arm 7C of the D-shaped arm 7 are removed integrally, and the lead-in insulators 10 according to the present invention are removed. All work to tie down overhead wires using the wire tie-down method has been completed.
以上の如く、既設の引通し装柱方式の架空線を引留め装
柱方式の架空線に変更するものであるから、D型アーム
マに引通し装柱方式にて配線されている既設の架空綿W
を、従来の架空線切換工法で行っていた様に既設の引通
し碍子IOに仮置きする必要も無く、しかも引留め装柱
方式に用いるストラップ8b、8b、8b、耐張碍子8
C18C18c及び引留クランプ8d、8d、8dは引
留め装置8として予め地上等に於いて組み立てられてい
るから、従来の作業の様に高所でD型アーム7に対して
−々組み立てる必要も無く、従って引通し装柱方式より
引留め装柱方式への切り換え作業が極めて簡単となり、
しかも作業には上記の実施例で説明した如く、マニピュ
レータ装置4を装備した高所作業車1を導入することが
可能であり、そのために作業時間が大幅に短縮され、か
つ作業が安全である。As mentioned above, since the existing overhead wires of the lead-in pole mounting method are to be changed to the overhead wires of the tie-down pole mounting method, the existing overhead wires that are wired in the lead-through pole mounting method to the D-type arm W
There is no need to temporarily place the insulator IO on the existing lead-in insulator IO as was done with the conventional overhead line switching method, and the straps 8b, 8b, 8b and tension insulator 8 used in the tie-down column installation method are not required.
Since the C18C18c and the retaining clamps 8d, 8d, and 8d are assembled in advance on the ground as the retaining device 8, there is no need to assemble them to the D-shaped arm 7 at a high place as in the conventional work. Therefore, it is extremely easy to switch from the lead-in pole mounting method to the tie-down pole mounting method.
Furthermore, as explained in the above embodiment, it is possible to use the aerial work vehicle 1 equipped with the manipulator device 4 for the work, which greatly reduces the work time and makes the work safer.
尚、上記の実施例では、装柱した引留め装置8の各引留
クランプ8d、8d、8dとD型アーム7に開閉器11
が装備される場合のリード線の接続についての作業は、
従来の工法と同様であるために省略した。In the above embodiment, the switch 11 is attached to each of the retaining clamps 8d, 8d, 8d of the pole-mounted retaining device 8 and the D-shaped arm 7.
For work on connecting lead wires when equipped with
This method has been omitted because it is the same as the conventional construction method.
本発明は、以上詳細に説明した如く、電柱に装柱した既
設の分解式り型アームの左右対象位置に一対の睨合に対
してストラ・ノブを介して耐張碍子及び引留クランプを
順次連結した引留め装置を配置すると共に、該引留め装
置の前記睨合を既設の分解式り型アームを構成する上下
の水平アームの側部に固定し、前記分解式り型アームに
取り付けた引通し碍子に袈装した架空線を前記引留め装
置の各引留クランプにて係止した後、引通し碍子に袈装
された架空線を各引通し碍子の左右にて切断し、各引通
し碍子を取り外すことなく既設の分解式り型アームを構
成する垂直アーム部分を取り外すことによって引通し装
柱方式の架空線を引留め装柱方式の架空線に変更するも
のであるから、分解式り型アームに引通し装柱方式にて
配線されている既設の架空線w−t−撤去する引通し碍
子から取り外して他の引通し碍子に仮置きし、撤去した
引通し碍子の取り付は穴を利用して引留め装柱方式のス
トラップ、耐張碍子及び引留クランプ等を繰り返して順
次取り付ける煩雑な作業の必要が無く、従って引通し装
柱方式より引留め装柱方式への切り換え作業が極めて簡
単となり、しかも作業にマニピュレータ装置を装備した
高所作業車を導入することが可能でるから、作業時間の
大幅な短縮と作業の十分な安全性が確保できる等種々の
優れた効果を有する。As explained in detail above, the present invention sequentially connects tension insulators and retaining clamps via strut knobs to the left and right symmetrical positions of an existing disassembleable arm mounted on a utility pole. At the same time, the eyelids of the retaining device are fixed to the sides of the upper and lower horizontal arms constituting the existing disassembly type arm, and the pull-through attached to the disassembly type arm is installed. After locking the overhead wires sheathed to the insulators with the respective retaining clamps of the retaining device, cut the overhead wires sheathed to the lead-in insulators at the left and right sides of each lead-through insulator, and then By removing the vertical arm part that makes up the existing disassembly-type arm without removing it, you can change the overhead wire of the pull-through pole-mounting method to the overhead wire of the tie-down pole-mounting method. Existing overhead wires that are wired using the lead-in pole installation method are removed from the lead-in insulator to be removed and temporarily placed on other lead-in insulators, and the removed lead-in insulators are installed using the holes. There is no need for the complicated work of repeatedly attaching straps, tension insulators, retaining clamps, etc. of the tie-down pole mounting method, and therefore it is extremely easy to switch from the pull-through pole mounting method to the tie-down pole mounting method. Moreover, since it is possible to introduce an aerial work vehicle equipped with a manipulator device to the work, it has various excellent effects such as significantly shortening the work time and ensuring sufficient safety of the work.
第1図は本発明に係る引留め装置を採用して引通し架空
線の引留め化工法をマニピュレータ装置を搭載した高所
作業車で実施する要領を示す説明図、第2図(a)はD
型アームに対し本発明に係る引通し架空線の引留め化工
法により引留め装置を取り付ける要領を示す説明図、同
図(b)はD型アームに対して引留め装置が取り付けら
れた状態を示す斜視図、同rEJ(C)は引通し架空線
の引留め化工が終了した状態を示す斜視図、第3図(a
) 、(b) 、(c) 、(d) 、(e)は従来の
架空線切換工法を示す説明図であり、同図(a)は架空
線の仮支持の様子を示す斜視図、同図(b)は従来の架
空線切換工法の第1段階を示す斜視図、同図(C)は引
通し碍子を取り外す状態を示す要部斜視図、(d)は従
来の引留め装置の取り付は状態を示す要部斜視図、(e
)は従来の架空線切換工法により装備された引留め装柱
状態を示す要部斜視図である。
1・・・高所作業車、2・・・ブーム、3・・・マニピ
ュレータ操作室、4・・・マニピュレータ装置、5・・
・吊り上げ装置、6・・・電柱、7・・・分解式り型ア
ーム、7a・・・水平アーム、7b・・・ボルト、7C
・・・垂直アーム、8・・・引留め装置、8a・・・睨
合、8b・・・ストランプ、8C・・・耐張碍子、8d
・・・引留クランプ、8e・・・ボルト孔、9・・・ボ
ルト、10・・・引通し碍子、W・・・架空線、X・・
・切断箇所。Figure 1 is an explanatory diagram showing how to implement the method of retaining overhead wires using the retaining device according to the present invention using an aerial work vehicle equipped with a manipulator device, and Figure 2 (a) is D
An explanatory diagram illustrating how to attach a retaining device to a D-type arm using the overhead wire retaining method according to the present invention. Figure (b) shows the state in which the retaining device is attached to a D-type arm. FIG.
), (b), (c), (d), and (e) are explanatory diagrams showing the conventional overhead wire switching method, and (a) is a perspective view showing how the overhead wire is temporarily supported; Figure (b) is a perspective view showing the first stage of the conventional overhead line switching method, Figure (C) is a perspective view of the main part showing the state in which the lead-in insulator is removed, and (d) is the removal of the conventional retaining device. Attached is a perspective view of the main parts showing the condition, (e
) is a perspective view of a main part showing a state in which a retaining pole is installed using the conventional overhead line switching method. 1... Aerial work vehicle, 2... Boom, 3... Manipulator operation room, 4... Manipulator device, 5...
・Lifting device, 6... Telephone pole, 7... Disassembly type arm, 7a... Horizontal arm, 7b... Bolt, 7C
... Vertical arm, 8... Retaining device, 8a... Glazing, 8b... Strump, 8C... Tension-resistant insulator, 8d
...Retaining clamp, 8e...Bolt hole, 9...Bolt, 10...Leading insulator, W...Overhead wire, X...
- Cutting point.
Claims (1)
更する架空線切換工法に於いて、電柱に装柱した既設の
分解式D型アームの左右対象位置に一対の腕金に対して
ストラップを介して耐張碍子及び引留クランプを順次連
結した引留め装置を配置すると共に、該引留め装置の前
記腕金を既設の分解式D型アームを構成する上下の水平
アームの側部に固定し、前記分解式D型アームに取り付
けた引通し碍子に袈装した架空線を前記引留め装置の各
引留クランプにて係止した後、引通し碍子に袈装された
架空線を各引通し碍子の左右にて切断し、既設の分解式
D型アームを構成する垂直アーム部分の取り外しと一体
に既設の各引通し碍子を撤去することによって引通し装
柱方式の架空線を引留め装柱方式の架空線に変更するよ
うにしたことを特徴とする引通し架空線の引留め化工法
。In the overhead line conversion method, which changes a lead-in pole-mounted overhead line to a tie-down pole-mounted overhead line, a pair of arms are attached to the left and right symmetrical positions of the existing disassembleable D-type arm attached to the utility pole. A retaining device in which a tension insulator and a retaining clamp are successively connected via a strap is arranged, and the arms of the retaining device are attached to the sides of the upper and lower horizontal arms constituting the existing disassembleable D-type arm. After securing the overhead wires sheathed to the lead-in insulators attached to the disassembleable D-shaped arm with each retaining clamp of the retaining device, each overhead wire sheathed to the lead-in insulators is By cutting the lead-in insulators on the left and right, removing the vertical arm part that makes up the existing disassembleable D-shaped arm, and removing each of the existing lead-in insulators, the overhead wires of the lead-in column mounting method are secured. A method for retaining overhead wires, characterized in that the overhead wires are changed to pole-mounted overhead wires.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1198717A JPH0365009A (en) | 1989-07-31 | 1989-07-31 | Anchoring method of passing overhead wire |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1198717A JPH0365009A (en) | 1989-07-31 | 1989-07-31 | Anchoring method of passing overhead wire |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0365009A true JPH0365009A (en) | 1991-03-20 |
Family
ID=16395837
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1198717A Pending JPH0365009A (en) | 1989-07-31 | 1989-07-31 | Anchoring method of passing overhead wire |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0365009A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6168639B1 (en) | 1997-10-09 | 2001-01-02 | Sanyo Electric Co., Ltd. | Solid electrolyte capacitor, and process and apparatus for producing same |
| CN104384118A (en) * | 2014-09-16 | 2015-03-04 | 国家电网公司 | Mechanical arm with function of electrically cleaning up foreign matters |
| CN111834765A (en) * | 2020-07-20 | 2020-10-27 | 柳州大尚科技发展有限公司 | Short circuit grounding mechanism |
-
1989
- 1989-07-31 JP JP1198717A patent/JPH0365009A/en active Pending
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6168639B1 (en) | 1997-10-09 | 2001-01-02 | Sanyo Electric Co., Ltd. | Solid electrolyte capacitor, and process and apparatus for producing same |
| US6313979B1 (en) | 1997-10-09 | 2001-11-06 | Sanyo Electric Co., Ltd. | Solid electrolyte capacitor |
| CN104384118A (en) * | 2014-09-16 | 2015-03-04 | 国家电网公司 | Mechanical arm with function of electrically cleaning up foreign matters |
| CN111834765A (en) * | 2020-07-20 | 2020-10-27 | 柳州大尚科技发展有限公司 | Short circuit grounding mechanism |
| CN111834765B (en) * | 2020-07-20 | 2021-07-13 | 柳州大尚科技发展有限公司 | Short circuit grounding mechanism |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210326920U (en) | Temporary fixing support for high-voltage cable | |
| JP2013233038A (en) | Construction method for replacing insulator set of 4 conductor power line, and replacing apparatus used for same construction method | |
| JP2003189433A (en) | Distribution line construction method and tool used therefor | |
| JPH0365009A (en) | Anchoring method of passing overhead wire | |
| JPH02262813A (en) | Separated tension insulator bracket and mounting/ dismounting method thereof | |
| JP3401751B2 (en) | How to transfer electric wires from wire-drawing wheel to suspension clamp at the time of work on tight line | |
| JPH0833169A (en) | Suspended support and method of operating overhead line to the suspended support | |
| JP5558075B2 (en) | Cable support bracket and cable connection method | |
| HU229915B1 (en) | Pole top support for aerial electric power lines | |
| JP2883474B2 (en) | How to remove overhead tracks | |
| JPH079558Y2 (en) | Overhead wire retention device | |
| JPH02307309A (en) | Distribution line supporting device for live wire work | |
| JPH05115113A (en) | Anchoring work method for aerial through cable and anchoring device | |
| JPH0510883B2 (en) | ||
| JPH01126119A (en) | Method of anchoring through wire | |
| JPH04117120A (en) | Retaining construction method and retaining device for overhead wires | |
| JPH11299068A (en) | Method and structure for branching power distribution line in air | |
| JP3479666B2 (en) | Tensile device and overhead wire work method | |
| JPH087768Y2 (en) | Temporary armor device for supporting overhead lines | |
| JP3049616U (en) | Workbench for connecting overhead optical cables | |
| SU1350725A1 (en) | Arrangement for replacing twin insulator strings and supporting hardware in power transmission lines with split insulated wires in a phase under voltage | |
| JPH07303312A (en) | Suspension device and overhead wire work method | |
| JPH02294209A (en) | Temporary support method for overhead lines | |
| JPH079557Y2 (en) | Overhead wire retention device | |
| KR100759246B1 (en) | Ductility correction device for soft and long wire |