JPH0385491A - Controlling device for nuclear reactor output - Google Patents
Controlling device for nuclear reactor outputInfo
- Publication number
- JPH0385491A JPH0385491A JP1221561A JP22156189A JPH0385491A JP H0385491 A JPH0385491 A JP H0385491A JP 1221561 A JP1221561 A JP 1221561A JP 22156189 A JP22156189 A JP 22156189A JP H0385491 A JPH0385491 A JP H0385491A
- Authority
- JP
- Japan
- Prior art keywords
- temperature
- reactor
- control rod
- fuzzy
- control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Monitoring And Testing Of Nuclear Reactors (AREA)
- Feedback Control In General (AREA)
Abstract
Description
【発明の詳細な説明】
〔発明の目的〕
(産業上の利用分野)
本発明は原子炉出力制御装置に係り、特に制御棒の位置
を操作し、原子炉出口温度を所定の値に制御する原子炉
出力制御装置に関する。[Detailed Description of the Invention] [Objective of the Invention] (Industrial Application Field) The present invention relates to a nuclear reactor power control device, and in particular, a device for controlling the reactor outlet temperature to a predetermined value by manipulating the position of control rods. Regarding nuclear reactor power control equipment.
(従来の技術)
従来の原子炉出力制御装置について第17図を参照して
説明する。(Prior Art) A conventional nuclear reactor power control device will be described with reference to FIG. 17.
原子炉1には炉心1aが収容され、この炉心1aは核分
裂連鎖反応により発熱して炉内を流れる1次冷却材を加
熱する。加熱された1次冷却材は高温側配管2を経て中
間熱交換器3へ送り込まれ、熱交換により2次冷却材へ
熱を伝達する。熱交換により温度降下した1次冷却材は
、低温側配管4を通って原子炉1へ還流される。このよ
うな1次冷却材の循環は、低温側配管4に介装された循
環ポンプ5により行われる。A nuclear reactor 1 houses a reactor core 1a, which generates heat due to a nuclear fission chain reaction and heats a primary coolant flowing within the reactor. The heated primary coolant is sent to the intermediate heat exchanger 3 via the high temperature side pipe 2, and transfers heat to the secondary coolant through heat exchange. The primary coolant whose temperature has been lowered by heat exchange is returned to the reactor 1 through the low temperature side pipe 4. Such circulation of the primary coolant is performed by a circulation pump 5 interposed in the low temperature side piping 4.
一方、中間熱交換器3で熱交換により温度上昇した2次
冷却材は、高温側配管6を通って負荷熱交換器である蒸
気発生器7へ送り込まれる。ここでは負荷熱交換器の一
例として蒸気発生器フを用いた場合について説明するが
、空気冷却器その他でも同様の冷却系構成となる。蒸気
発生器7で熱交換により温度降下した2次冷却材は、低
温側配管8を通って中間熱交換器3へ還流される。この
ような2次冷却材の循環は、低温側配管8に介装された
循環ポンプ9により行われる。On the other hand, the secondary coolant whose temperature has been increased by heat exchange in the intermediate heat exchanger 3 is sent through the high temperature side pipe 6 to the steam generator 7 which is a load heat exchanger. Here, a case will be described in which a steam generator fan is used as an example of a load heat exchanger, but an air cooler and other cooling systems have a similar cooling system configuration. The secondary coolant whose temperature has been lowered by heat exchange in the steam generator 7 is returned to the intermediate heat exchanger 3 through the low temperature side pipe 8. Such circulation of the secondary coolant is performed by a circulation pump 9 interposed in the low temperature side piping 8.
原子炉出力の制御は、出力設定器10からの出力設定値
と、温度検出器11からの原子炉出口温度および中性子
束検出器12からの中性子束レベルを用いて、原子炉出
力制御装置13により行われる。原子炉出力制御装置1
3は、温度検出器11からの原子炉出口温度をフィード
バック信号とし、中性子束検出器12からの中性子束レ
ベルを補助信号として演算処理し、その結果得られる制
御棒駆動速度指令信号を制御棒駆動機構14へ出力する
。制御棒駆動速度指令信号を入力した制御棒駆動機構1
4は、制御棒15を炉心1aに挿抜することにより原子
炉出力を調整する。The reactor output is controlled by the reactor output control device 13 using the output setting value from the output setting device 10, the reactor outlet temperature from the temperature detector 11, and the neutron flux level from the neutron flux detector 12. It will be done. Reactor power control device 1
3 uses the reactor exit temperature from the temperature detector 11 as a feedback signal, processes the neutron flux level from the neutron flux detector 12 as an auxiliary signal, and uses the control rod drive speed command signal obtained as a result to drive the control rods. Output to mechanism 14. Control rod drive mechanism 1 into which the control rod drive speed command signal is input
4 adjusts the reactor output by inserting and removing the control rods 15 into and from the reactor core 1a.
(発明が解決しようとする課題)
従来の原子炉出力制御装置13では、臨界から低出力運
転の間、特に制御棒操作に対する原子炉出口温度の応答
が遅い系統昇温時の原子炉出口温度を運転状態に応じた
所定の値に自動制御することが困難であった。このため
、臨界から低出力運転の間は運転員が手動により制御棒
15の操作を行っていた。しかしながら、運転員の経験
および技量により操作内容が左右されるため、臨界から
低出力運転の間は運転員の技量等により出力制御特性が
左右されるという問題があった。(Problems to be Solved by the Invention) In the conventional reactor power control device 13, during critical to low power operation, the reactor exit temperature is controlled particularly during system temperature rise, where the response of the reactor exit temperature to control rod operations is slow. It was difficult to automatically control to a predetermined value depending on the operating state. For this reason, the operator manually operated the control rods 15 during the critical to low output operation. However, since the content of the operation is influenced by the experience and skill of the operator, there is a problem in that the output control characteristics are influenced by the operator's skill and the like from critical to low output operation.
本発明は上記の事情を考慮してなされたもので、慎界か
ら低出力運転を含め原子炉出力の自動制御を安定的に行
うことができる原子炉出力制御装置を提供することを目
的とする。The present invention has been made in consideration of the above circumstances, and an object of the present invention is to provide a nuclear reactor power control device capable of stably automatically controlling the reactor power, including low power operation. .
(課題を解決するための手段)
本発明は、制御棒駆動機構へ制御棒駆動速度指令信号を
出力して原子炉の出力を制御する原子炉出力制御装置に
おいて、原子炉出口温度を入力して原子炉出口温度の制
御目標値と制御目標変化率を比較し、ファジー推論によ
り制御棒の引き抜きあるいは挿入の速度を設定する規定
ファジー制御部と、原子炉入口温度、中性子束レベル、
冷却材配管温度等の原子炉回りの各種プロセス量を入力
してそれらプロセス量の制約条件と比較し、ファジー推
論により上記規定ファジー制御部で設定された制御棒の
引き抜きあるいは挿入の速度を補正する制約ファジー制
御部とを具備したものである。(Means for Solving the Problems) The present invention provides a reactor power control device that outputs a control rod drive speed command signal to a control rod drive mechanism to control the output of a nuclear reactor, in which a reactor outlet temperature is input. A prescribed fuzzy control unit that compares the control target value and control target change rate of the reactor exit temperature and sets the control rod withdrawal or insertion speed by fuzzy reasoning, and the reactor inlet temperature, neutron flux level,
Various process quantities related to the reactor, such as coolant piping temperature, are input and compared with the constraint conditions of these process quantities, and the control rod withdrawal or insertion speed set by the above-mentioned prescribed fuzzy control unit is corrected by fuzzy reasoning. The system is equipped with a constraint fuzzy control section.
(作用)
本発明は、規定ファジー制御部が原子炉出口温度を入力
して原子炉出口温度の制御目標値と制御目標変化率を比
較し、ファジー推論により制御棒の引き抜きあるいは挿
入の速度を設定し、制約ファジー制御部が原子炉入口温
度、中性子束レベル、冷却材配管温度等の原子炉回りの
各種プロセス量を入力してそれらプロセス量の制約条件
と比較し、ファジー推論により規定ファジー制御部で設
定された制御棒の引き抜きあるいは挿入の速度を補正し
、その結果得られた制御棒駆動速度指令信号を制御棒駆
動機構へ出力する。したがって、原子炉の臨界から高出
力運転まで原子炉出口温度を運転状態に応じた所定の値
に安定的に制御することができる。(Operation) In the present invention, the predetermined fuzzy control unit inputs the reactor outlet temperature, compares the control target value of the reactor outlet temperature with the control target change rate, and sets the control rod withdrawal or insertion speed by fuzzy reasoning. Then, the constraint fuzzy control unit inputs various process quantities surrounding the reactor, such as reactor inlet temperature, neutron flux level, and coolant piping temperature, compares them with the constraint conditions of these process quantities, and uses fuzzy reasoning to create a prescribed fuzzy control unit. Corrects the control rod withdrawal or insertion speed set in , and outputs the control rod drive speed command signal obtained as a result to the control rod drive mechanism. Therefore, the reactor outlet temperature can be stably controlled to a predetermined value depending on the operating state from the critical state to high power operation of the reactor.
(実施例)
本発明に係る原子炉出力制御装置の一実施例について添
付図面を参照して説明する。(Embodiment) An embodiment of the nuclear reactor power control device according to the present invention will be described with reference to the accompanying drawings.
第1図において第17図と同一部分については同一の符
号を付して重複説明を省略する。原子炉1には炉心1a
が収容され、この炉心1aに制御棒15が制御棒駆動機
構14によって挿抜可能に設けられる。原子炉1に接続
される1次冷却材高温側配管2には原子炉出口温度を測
定する温度検出器11と配管温度を測定する温度検出器
17とが接続される。1次冷却材低温側配管4には原子
炉入口温度を測定する温度検出器18が接続される。な
お、符号12は中性子束レベルを測定する中性子束検出
器を示しており、この中性子束検出器12は原子炉1の
周辺に配置される。In FIG. 1, the same parts as in FIG. 17 are given the same reference numerals, and redundant explanation will be omitted. Reactor 1 has core 1a.
A control rod 15 is provided in the reactor core 1a so that it can be inserted and removed by a control rod drive mechanism 14. A temperature detector 11 for measuring the reactor outlet temperature and a temperature detector 17 for measuring the pipe temperature are connected to the primary coolant high temperature side pipe 2 connected to the reactor 1. A temperature detector 18 for measuring the reactor inlet temperature is connected to the primary coolant low temperature side pipe 4. Note that reference numeral 12 indicates a neutron flux detector that measures the neutron flux level, and this neutron flux detector 12 is arranged around the nuclear reactor 1.
原子炉出力制御装置19は温度検出器11からの原子炉
出口温度、温度検出器17からの配管温度、温度検出器
18からの原子炉入口温度、中性子束検出器12からの
中性子束レベルおよび出力設定器10からの原子炉出口
温度目標値と原子炉出口温度変化率目標値を入力し、演
算処理を行った後、制御棒駆動速度指令信号を制御棒駆
動機構14へ出力し、原子炉出力を制御するようになっ
ている。The reactor power control device 19 receives the reactor outlet temperature from the temperature detector 11, the piping temperature from the temperature detector 17, the reactor inlet temperature from the temperature detector 18, and the neutron flux level and output from the neutron flux detector 12. After inputting the reactor outlet temperature target value and the reactor outlet temperature change rate target value from the setting device 10 and performing arithmetic processing, a control rod drive speed command signal is output to the control rod drive mechanism 14 to adjust the reactor output. is designed to be controlled.
第2図は原子炉出力制御装置19のブロック図を示すも
ので原子炉出力制御装置19は規定ファジー制御部19
aと制約ファジー制御部19bとから構成される。規定
ファジー制御部19aは、原子炉出口温度T1、原子炉
出口温度目標値T8および原子炉出口温度変化率目標値
DT8を入力し、ファジー推論により制御棒15の引き
抜きあるいは挿入の速度VRを設定する。制約ファジー
制御部19bは、原子炉入口温度Tl、中性子束レベル
Nおよび冷却材配管温度THPのプロセス量を入力し、
ファジー推論により規定ファジー制御部19aで設定さ
れた制御棒15の引き抜きあるいは挿入の速度を補正し
て、その結果得られた制御棒駆動速度指令■を制御棒駆
動機構14へ出力する。FIG. 2 shows a block diagram of the reactor power control device 19. The reactor power control device 19 is a prescribed fuzzy control section 19
a and a constraint fuzzy control section 19b. The specified fuzzy control unit 19a inputs the reactor outlet temperature T1, the reactor outlet temperature target value T8, and the reactor outlet temperature change rate target value DT8, and sets the withdrawal or insertion speed VR of the control rod 15 by fuzzy reasoning. . The constraint fuzzy control unit 19b inputs the process variables of the reactor inlet temperature Tl, the neutron flux level N, and the coolant pipe temperature THP,
The speed of withdrawal or insertion of the control rod 15 set by the prescribed fuzzy control section 19a is corrected by fuzzy reasoning, and the control rod drive speed command (2) obtained as a result is output to the control rod drive mechanism 14.
次に、規定ファジー制御部19aにおける処理を第3図
に従って説明する。Next, the processing in the prescribed fuzzy control section 19a will be explained with reference to FIG.
まず、原子炉出口温度T1、原子炉出口温度目標値T8
および原子炉出口温度変化率目標値DT、を読み込み、
これらに基づいて原子炉出口温度変化率DT、を算出す
る。次に原子炉出口温度目標値T8と原子炉出口温度T
、との偏差T8TP (温度偏差)を算出し、その偏差
を第4図に示すメンバシップ関数に代入し、正で大きい
(PB)グレード、正で小さい(P S)グレード、零
(ZO)のグレード、負で小さい(NS)グレードおよ
び負で大きい(NB)グレードを求める。First, reactor outlet temperature T1, reactor outlet temperature target value T8
and reactor outlet temperature change rate target value DT,
Based on these, the reactor outlet temperature change rate DT is calculated. Next, reactor outlet temperature target value T8 and reactor outlet temperature T
Calculate the deviation T8TP (temperature deviation) between Determine the grade, negative less (NS) grade and negative greater (NB) grade.
次に原子炉出口温度変化率目標値DT、と原子炉出口温
度変化率DT、との偏差DT8−DT。Next, the deviation DT8-DT between the reactor outlet temperature change rate target value DT and the reactor outlet temperature change rate DT.
(温度変化率偏差)を算出し、その偏差を第5図に示す
メンバシップ関数に代入し、正で大きい(P B)グレ
ード、正で小さい(ps)グレード、零(ZO)のグレ
ード、負で小さい(NS)グレードおよび負で大きい(
NB)グレードを求める。(Temperature change rate deviation) and substituted the deviation into the membership function shown in Figure 5, positive and large (P B) grade, positive and small (ps) grade, zero (ZO) grade, negative small (NS) grade and negative large (
NB) Find the grade.
そして第6図に示すファジー制御規則を実行し、制御棒
速度の変更幅DVとそれに対応したメンバシップ関数を
定める。なお、制御棒速度の変化幅DVの正で大きい(
P B)ファジー集合、正で小さい(p s)ファジー
集合、零(zO)のファジー集合、負で小さい(NS)
ファジー集合および負で大きい(NB)ファジー集合は
第7図に示すメンバシップ関数により定義されるとする
。次に各ファジー・ルールの実行により得られた各制御
棒速度の変化幅DVのメンバシップ関数を合成し、その
重心を制御棒速度の変化幅DvRとする。たとえば、温
度偏差が0.7のグレードでPBで温度変化率偏差が0
. 4のグレードでPSの場合は、制御棒速度の変化幅
DVを正で小さい値(P S)とし、そのメンバシップ
関数は温度偏差がPHのグレードと温度変化率がPSの
グレードの最小値0.4を最大とする第8図に示す関数
形とする。Then, the fuzzy control rule shown in FIG. 6 is executed to determine the change width DV of control rod speed and the membership function corresponding thereto. Note that if the control rod speed change width DV is positive and large (
P B) Fuzzy set, positive and small (p s) fuzzy set, fuzzy set of zero (zO), negative and small (NS)
It is assumed that the fuzzy set and the negative large (NB) fuzzy set are defined by the membership functions shown in FIG. Next, the membership functions of each control rod speed change width DV obtained by executing each fuzzy rule are synthesized, and the center of gravity is set as the control rod speed change width DvR. For example, in a grade with a temperature deviation of 0.7, the temperature change rate deviation is 0 in PB.
.. In the case of PS with grade 4, the change width DV of control rod speed is a positive and small value (PS), and its membership function is the minimum value 0 of the grade with temperature deviation PH and the grade with temperature change rate PS. The function form shown in Fig. 8 has a maximum value of .4.
また、温度偏差が0.3のグレードでPSで温度変化率
偏差が0.6のグレードでzOの場合は、制御棒速度の
変更幅DVを零(20)とし、そのメンバシップ関数は
温度偏差がPSのグレードと温度変化率がzOのグレー
ドの最小値0. 3を最大とする。第9図に示す関数形
とする。そこで、第10図に示すように第8図のメンバ
シップ関数と第9図のメンバシップ関数を合成して、そ
の重心DvRを制御棒速度の変更幅とする。そして、現
在の制御棒速度■1に得られた制御棒速度の変更幅Dv
Rを加え、制御棒速度VRを設定する。In addition, if the temperature deviation is 0.3 in the grade PS and the temperature change rate deviation is 0.6 in the grade zO, the control rod speed change range DV is set to zero (20), and its membership function is the temperature deviation is the minimum value of the PS grade and the temperature change rate is the minimum value of the zO grade. 3 is the maximum. The function form shown in FIG. 9 is assumed. Therefore, as shown in FIG. 10, the membership function in FIG. 8 and the membership function in FIG. 9 are combined, and the center of gravity DvR is set as the range of change in control rod speed. Then, the change width Dv of the control rod speed obtained for the current control rod speed ■1
Add R and set the control rod speed VR.
次に、制約ファジー制御部19bの処理について第11
図に従って説明する。Next, regarding the processing of the constraint fuzzy control unit 19b, the 11th
This will be explained according to the diagram.
まず、規定ファジー制御部19aにより得られた制御棒
速度■1、原子炉入口温度T1、高温側配管温度TII
Pおよび中性子束レベルNを読み込む。First, the control rod speed ■1 obtained by the prescribed fuzzy control unit 19a, the reactor inlet temperature T1, and the high temperature side piping temperature TII
Read P and neutron flux level N.
ここで、制御棒速度■2は第12図に示すメンバシップ
関数により定義されるファジー集合とする。Here, the control rod speed 2 is assumed to be a fuzzy set defined by the membership function shown in FIG.
次に原子炉入口温度T1、高温側配管温度TH−よび中
性子束レベルNを第13図(A)、(B)。Next, the reactor inlet temperature T1, high temperature side piping temperature TH-, and neutron flux level N are shown in FIGS. 13(A) and 13(B).
(C)に示すメンバシップ関数によりちょうど良い(M
EDIUM)か、大き過ぎる(B I G)か判定する
。第13図(A)から(C)におけるTIL、THPL
” Lは、それぞれ原子炉入口温度T11高温側配管
温度THP’中性子東レベルNの運転上の制限条件であ
り、あらかじめ定められたものである。The membership function shown in (C) is just right (M
EDIUM) or too large (BIG). TIL and THPL in Figures 13 (A) to (C)
”L are operational limit conditions for the reactor inlet temperature T11, high temperature side piping temperature THP', and neutron east level N, respectively, and are determined in advance.
そして、第14図に示すファジー制御規則を実行し、第
15図に示すように新たなりRのメンバシップ関数とv
zのメンバシップ関数を定める。Then, the fuzzy control rule shown in FIG. 14 is executed, and as shown in FIG. 15, the new membership function of R and v
Define the membership function of z.
ここで、vzは第15図に示す通り0.0を中心とする
メンバシップ関数により定義されるファジー集合とする
。つまりvRのメンバシップ関数は、各プロセスのME
DIUMであるグレードの最小値(LM)を最大とする
形となる。またv2のメンバシップ関数は、各プロセス
のBIGであるグレードの最大値(LB)を最大とする
形となる。Here, vz is a fuzzy set defined by a membership function centered at 0.0, as shown in FIG. In other words, the membership function of vR is
The minimum value (LM) of the grade, which is DIUM, is maximized. Further, the membership function of v2 has a form in which the maximum value (LB) of the grade, which is the BIG of each process, is maximized.
そこで、第16図に示すようにvRのメンバシップ関数
とv2のメンバシップ関数を合成してその重心Vを制御
棒速度指令とする。Therefore, as shown in FIG. 16, the membership function of vR and the membership function of v2 are combined and their center of gravity V is used as the control rod speed command.
このように上記実施例によれば、制御棒操作を実施した
後の原子炉出口温度の挙動をもって適切な制御方法を設
定するため、制御棒操作に対する原子炉出口温度の応答
が遅い系統昇温時においても、原子炉出口温度を運転状
態に応じた所定の値に自動制御することが可能となり、
臨界から高出力運転までの原子炉出力の自動制御を安定
に行うことができる。また、運転員の負担が軽減され、
運転員の経験や技量により出力制御特性が左右されると
いう問題を解決し、運転制御性の向上を図ることができ
る。In this way, according to the above embodiment, an appropriate control method is set based on the behavior of the reactor outlet temperature after the control rod operation is performed. Also, it is now possible to automatically control the reactor outlet temperature to a predetermined value depending on the operating status.
Automatic control of reactor output from criticality to high-power operation can be performed stably. In addition, the burden on the operator is reduced,
This solves the problem that output control characteristics are influenced by the experience and skill of the operator, and improves operational controllability.
本発明は、原子炉出口温度を入力して原子炉出口温度の
制御目標値と制御目標変化率を比較し、ファジー推論に
より制御棒の引き抜きあるいは挿入の速度を設定する規
定ファジー制御部と、原子炉入口温度、中性子束レベル
、冷却材配管温度等の原子炉回りの各種プロセス量を入
力してそれらプロセス量の制約条件と比較し、ファジー
推論により上記規定ファジー制御部で設定された制御棒
の引き抜きあるいは挿入の速度を補正する制約ファジー
制御部とを具備したから、原子炉の臨界から高出力運転
まで原子炉出力を安定的に制御することが可能となり、
プラントの運転制御性の向上を図ることができる。The present invention provides a predetermined fuzzy control unit that inputs the reactor outlet temperature, compares the control target value and control target change rate of the reactor outlet temperature, and sets the control rod withdrawal or insertion speed by fuzzy reasoning; By inputting various process quantities surrounding the reactor, such as the reactor inlet temperature, neutron flux level, and coolant piping temperature, and comparing them with the constraint conditions of these process quantities, the control rods set in the above-mentioned fuzzy control section are determined by fuzzy reasoning. Equipped with a constraint fuzzy control unit that corrects the withdrawal or insertion speed, it is possible to stably control the reactor output from the reactor criticality to high power operation.
It is possible to improve plant operation controllability.
第1図は本発明に係る原子炉出力制御装置の一実施例を
備えた原子炉設備を示す構成図、第2図は上記実施例を
示すブロック図、第3図は上記実施例における規定ファ
ジー制御部の処理フロー図、第4図は上記実施例におけ
る原子炉出口温度と原子炉出口温度目標値との偏差の判
定基準となるメンバシップ関数を示す図、第5図は上記
実施例における原子炉出口温度変化率目標値との偏差の
判定基準となるメンバシップ関数を示す図、第6図は上
記実施例における規定ファジー制御部に備えられたファ
ジー制御規則を示す図、第7図は上記実施例における制
御棒速度の変化幅の判定のためのメンバシップ関数を示
す図、第8図は上記実施例における制御棒速度の変化幅
が正で小さい値のメンバシップ関数の一例を示す図、第
9図は上記実施例における制御棒速度の変化幅が零のメ
ンバシップ関数の一例を示す図、第10図は上記実施例
における制御棒速度の変化幅のメンバシップ関数の合成
例を示す図、第11図は上記実施例における制約ファジ
ー制御部の処理フロー図、第12施例における制御棒速
度、原子炉入口温度、高温側配管温度および中性子束レ
ベルの判定のためのメンバシップ関数を示す図、第14
図は上記実施例における制約ファジー制御部に備えられ
たファジー制御規則を示す図、第15図は上記実施例に
おける制約ファジー制御部におけるファジー制御規則実
行後の制御速度のメンバシップ関数例および制御速度の
メンバシップ関数例を示す図、第16図は上記実施例に
おける制御棒速度のメンバシップ関数の合成例を示す図
、第17図は従来の原子炉出力制御装置を備えた原子炉
設備を示す構成図である。
l・・・原子炉、1a・・・炉心、10・・・出力設定
器、11・・・温度検出器、12・・・中性子束検出器
、14・・・制御棒駆動機構、15・・・制御棒、17
.18・・・温度検出器、19・・・原子炉出力制御装
置、19a・・・規定ファジー制御部、19b・・・制
約ファジー制御部。Fig. 1 is a block diagram showing a nuclear reactor equipment equipped with an embodiment of the reactor power control device according to the present invention, Fig. 2 is a block diagram showing the above embodiment, and Fig. 3 is a prescribed fuzzy diagram in the above embodiment. A processing flow diagram of the control unit, FIG. 4 is a diagram showing the membership function serving as a criterion for the deviation between the reactor outlet temperature and the reactor outlet temperature target value in the above embodiment, and FIG. FIG. 6 is a diagram showing the membership function that serves as a criterion for determining the deviation from the furnace outlet temperature change rate target value. FIG. 6 is a diagram showing the fuzzy control rules provided in the prescribed fuzzy control section in the above embodiment. FIG. A diagram showing a membership function for determining the range of change in control rod speed in the embodiment, FIG. 8 is a diagram showing an example of a membership function in which the range of change in control rod speed is a positive and small value in the above embodiment, FIG. 9 is a diagram showing an example of a membership function in which the width of change in control rod speed is zero in the above embodiment, and FIG. 10 is a diagram showing an example of composition of membership functions with a width of change in control rod speed in the above embodiment. , FIG. 11 shows a processing flow diagram of the constrained fuzzy control unit in the above embodiment, and membership functions for determining the control rod speed, reactor inlet temperature, high temperature side piping temperature, and neutron flux level in the twelfth embodiment. Figure, 14th
The figure shows fuzzy control rules provided in the constrained fuzzy control section in the above embodiment, and FIG. FIG. 16 is a diagram showing an example of the composition of the membership function of control rod speed in the above embodiment. FIG. 17 is a diagram showing a nuclear reactor equipment equipped with a conventional reactor power control device. FIG. l... Nuclear reactor, 1a... Core, 10... Output setting device, 11... Temperature detector, 12... Neutron flux detector, 14... Control rod drive mechanism, 15...・Control rod, 17
.. 18... Temperature detector, 19... Nuclear reactor power control device, 19a... Regulation fuzzy control section, 19b... Constraint fuzzy control section.
Claims (1)
子炉の出力を制御する原子炉出力制御装置において、原
子炉出口温度を入力して原子炉出口温度の制御目標値と
制御目標変化率を比較し、ファジー推論により制御棒の
引き抜きあるいは挿入の速度を設定する規定ファジー制
御部と、原子炉入口温度、中性子束レベル、冷却材配管
温度等の原子炉回りの各種プロセス量を入力してそれら
プロセス量の制約条件と比較し、ファジー推論により上
記規定ファジー制御部で設定された制御棒の引き抜きあ
るいは挿入の速度を補正する制約ファジー制御部とを具
備したことを特徴とする原子炉出力制御装置。In a reactor power control device that outputs a control rod drive speed command signal to the control rod drive mechanism to control the reactor output, the reactor outlet temperature is input and the control target value and control target change rate of the reactor outlet temperature are calculated. A predefined fuzzy control unit that sets the control rod withdrawal or insertion speed using fuzzy reasoning, and inputs various process variables around the reactor such as reactor inlet temperature, neutron flux level, and coolant piping temperature. Reactor power control characterized by comprising a constraint fuzzy control unit that compares with the process quantity constraint conditions and corrects the control rod withdrawal or insertion speed set by the prescribed fuzzy control unit based on fuzzy reasoning. Device.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1221561A JP2647206B2 (en) | 1989-08-30 | 1989-08-30 | Reactor power control device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1221561A JP2647206B2 (en) | 1989-08-30 | 1989-08-30 | Reactor power control device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0385491A true JPH0385491A (en) | 1991-04-10 |
| JP2647206B2 JP2647206B2 (en) | 1997-08-27 |
Family
ID=16768658
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1221561A Expired - Lifetime JP2647206B2 (en) | 1989-08-30 | 1989-08-30 | Reactor power control device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2647206B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2666043A1 (en) * | 1990-08-27 | 1992-02-28 | Nissei Plastics Ind Co | TEMPERATURE REGULATION METHOD FOR AN INJECTION MOLDING MACHINE. |
| FR2668097A1 (en) * | 1990-10-18 | 1992-04-24 | Nissei Plastics Ind Co | TEMPERATURE CONTROL METHOD FOR INJECTION MOLDING MACHINE. |
-
1989
- 1989-08-30 JP JP1221561A patent/JP2647206B2/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2666043A1 (en) * | 1990-08-27 | 1992-02-28 | Nissei Plastics Ind Co | TEMPERATURE REGULATION METHOD FOR AN INJECTION MOLDING MACHINE. |
| FR2668097A1 (en) * | 1990-10-18 | 1992-04-24 | Nissei Plastics Ind Co | TEMPERATURE CONTROL METHOD FOR INJECTION MOLDING MACHINE. |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2647206B2 (en) | 1997-08-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS5830560B2 (en) | Water supply control equipment for nuclear reactor power plants | |
| CN104776416A (en) | Method and system for controlling main steam temperature of drum type boiler | |
| JPH0566601B2 (en) | ||
| JP2647206B2 (en) | Reactor power control device | |
| JP2664822B2 (en) | Reactor operation monitoring and control device | |
| CN104566352B (en) | CFBB primary air fan control method and system with demand regulator | |
| JPH04115190A (en) | Controlling apparatus for output of reactor | |
| CN116466570A (en) | Simulation method for steam temperature control system of high temperature gas-cooled reactor | |
| JPS63247592A (en) | Condenser cooling water flow control device | |
| JPS639194B2 (en) | ||
| JPS6219719B2 (en) | ||
| JPH01230903A (en) | Boiler forced cooling control method | |
| JP2507516B2 (en) | Reactor control device | |
| KR100415487B1 (en) | Nuclear heating method for integral reactor | |
| CN116466569A (en) | Simulation method for output thermal power control system of high temperature gas-cooled reactor | |
| JP2723310B2 (en) | Reactor power control device | |
| JPH047960B2 (en) | ||
| JPS581398B2 (en) | Nuclear power plant reactor power distribution control method and device | |
| JPS5819608A (en) | Self-controller for boiler | |
| JP2931152B2 (en) | Boiler reheat steam temperature control method | |
| JPH01314998A (en) | Apparatus and method for controlling output of nuclear reactor | |
| CN118352104A (en) | High temperature gas-cooled reactor feed water flow control method and system | |
| JPH03255399A (en) | Controlling device of nuclear reactor output | |
| JPS6327676B2 (en) | ||
| JPS61274297A (en) | Reactor pressure controller |