JPH04189934A - Jointing method between house units in unit type construction - Google Patents
Jointing method between house units in unit type constructionInfo
- Publication number
- JPH04189934A JPH04189934A JP31582390A JP31582390A JPH04189934A JP H04189934 A JPH04189934 A JP H04189934A JP 31582390 A JP31582390 A JP 31582390A JP 31582390 A JP31582390 A JP 31582390A JP H04189934 A JPH04189934 A JP H04189934A
- Authority
- JP
- Japan
- Prior art keywords
- cement paste
- bolt
- column
- unit
- housing unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 14
- 238000010276 construction Methods 0.000 title abstract description 8
- 239000004568 cement Substances 0.000 claims abstract description 34
- 239000011440 grout Substances 0.000 claims description 4
- 239000000463 material Substances 0.000 claims description 4
- 230000008878 coupling Effects 0.000 abstract 1
- 238000010168 coupling process Methods 0.000 abstract 1
- 238000005859 coupling reaction Methods 0.000 abstract 1
- 238000003780 insertion Methods 0.000 description 16
- 230000037431 insertion Effects 0.000 description 16
- 230000000694 effects Effects 0.000 description 4
- 238000011065 in-situ storage Methods 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- 230000001934 delay Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001879 gelation Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
本発明は、ユニ・ソト式建築における住宅ユニット相互
間の接合方法に関する。TECHNICAL FIELD The present invention relates to a method for joining housing units together in Uni-Sotho architecture.
従来、住宅ユニット相h:間の接合は、接合部を当接し
、位置合わせをした後、ボルトにより接合していた。Conventionally, the housing unit phase h: was joined by bolts after the joint parts were brought into contact and aligned.
しかし、かかる方法では、住宅ユニットの接合部に穿設
されるボルト孔の位置が正確でないと接合不能となるの
で、精度の要求が厳格になるという欠点があった。そし
て、通常ボルト挿入孔の位置は相互にずれている場合が
多く、現場での調整作業に多くの時間と手間を要してい
た。
また、従来は接合部の構造が繁雑であったため、工場に
おける仕上率(いわゆるプレハブ化率)が低かった。こ
の結果、現場での作業がか増太し、今後益々懸念される
職人不足に対応し難くく、工期の不安定、遅延等の問題
が惹起されていた。
本発明は、上記欠貨を解消し、高精度でかつ高強度の接
合を迅速かつ容易に行ない、工期短縮、安定に資するユ
ニット式建築における住宅ユニット相互間の接合方法を
供することを目的とする。However, this method has the disadvantage that the requirements for accuracy are strict, as the bolt holes drilled in the joints of the housing units must be placed in accurate positions to make the joints possible. Further, the positions of the bolt insertion holes are often shifted from each other, and a lot of time and effort are required for adjustment work on site. Furthermore, because the structure of the joints was conventionally complicated, the finishing rate in factories (so-called prefabrication rate) was low. As a result, the amount of work on-site has increased, making it difficult to cope with the shortage of skilled workers that will become a growing concern in the future, and causing problems such as unstable construction schedules and delays. The present invention aims to eliminate the above-mentioned shortage, quickly and easily perform high-precision and high-strength joining, and provide a method for joining housing units in a unit-type building that contributes to shortening construction time and stability. .
上記目的達成のため、本発明は、下層階住宅ユニットの
柱の頭部に現場にてセメント・ペーストが注入され、上
層階住宅ユニットの柱の下端部に固着されたナツトプレ
ートに現場にてボルトが嵌着され、該ボルトの下方部分
を下層階住宅ユニットの柱の頭部に注入されたセメント
・ペースト中に埋め込み固定することを特徴とするユニ
ット式建築における住宅ユニット相互間の接合方法を供
する。
このユニット式建築における住宅ユニット相互間の接合
方法は、上記セメント・ペーストに急硬性グラウト材が
用いられる点をも特徴とする。To achieve the above object, the present invention provides that cement paste is injected in-situ into the head of the column of the lower-story housing unit, and bolts are applied in-situ to the nut plate fixed to the lower end of the column of the upper-story housing unit. Provided is a method for joining housing units in a unit building, characterized in that the lower part of the bolt is embedded and fixed in cement paste injected into the head of a column of a lower floor housing unit. . This method of joining housing units in a unit-type building is also characterized in that a rapidly hardening grout material is used in the cement paste.
まず、設置固定された下層階住宅ユニットの柱の頭部に
現場にてセメント・ペーストが注入される。
一方、上層階住宅ユニットの柱の下端部に固着されたナ
ツトプレートに現場にてボルトが嵌着される。
しかる後、上記ボルトの下方部分を下層階住宅ユニット
の柱の頭部に注入されたセメント・ペースト中に埋め込
み固定する。
所定時間が経過し、セメント・ペーストが固化すれば、
そこに埋め込まれたボルトは固定され、下層階住宅ユニ
ットと上層階住宅ユニットが接合される。
柱の頭部を構成する第1ダイヤフラム、第2ダイヤフラ
ムの孔はセメント・ペースト及びボルトの挿入するため
のものであるから、ボルトの外径より相当程度大として
も接合精度及び固定に影響がない。したがって、ボルト
の埋め込み挿入に当たって、位置ズレによる調整作業を
省略することができる。
また、ボルトはセメント・ペーストが付着して固化、固
定されるから、接合部の強度がボルトの破断強度より大
となる。このため、住宅ユニット相互間の接合の強度か
増強される。
さらに、柱の頭部及び下端部は予め工場内で所定の構造
に仕上げておくことができるので、現場での接合をセメ
ント・ペーストの注入、ボルトの嵌着並びに埋め込みと
いった単純な作業にすることができる。このため、未熟
練な作業員でも、住宅ユニット相互間の接合を高精度、
高強度でかつ迅速に行なうことが可能である。First, cement paste is injected on-site into the column heads of the fixed lower floor housing units. Meanwhile, bolts are fitted on-site to nut plates fixed to the lower ends of the pillars of the upper floor housing units. Thereafter, the lower part of the bolt is embedded and fixed in cement paste poured into the head of the column of the lower floor housing unit. Once the specified time has passed and the cement paste has solidified,
The bolts embedded there are fixed and connect the lower floor residential unit and the upper floor residential unit. The holes in the first diaphragm and second diaphragm that make up the head of the column are for inserting cement paste and bolts, so even if they are considerably larger than the outside diameter of the bolts, there is no effect on joining accuracy and fixation. . Therefore, adjustment work due to positional deviation can be omitted when inserting the bolt into the embedding. Further, since the cement paste adheres to the bolts and solidifies and fixes them, the strength of the joint is greater than the breaking strength of the bolts. Therefore, the strength of the bond between housing units is increased. Furthermore, since the head and bottom ends of the columns can be pre-finished into a predetermined structure in the factory, on-site joining can be as simple as pouring cement paste, fitting bolts, and embedding. I can do it. Therefore, even unskilled workers can connect housing units with high precision.
It can be performed quickly and with high intensity.
次に、本発明にかかるユニット式建築における住宅ユニ
ット相互間の接合方法を実施例を示す図面に基すいて詳
細に説明する。
1は下層階住宅ユニット、例えば1階住宅ユニットを示
す。該下層階住宅ユニット1の柱】lの接合部となる頭
部12には、セメント・ペースト受具13、ダイヤフラ
ム、14.15が取付けられる。セメント・ペースト受
具13には孔がおいておらず、頭部12の底部となって
いる。第1ダイヤフラム14及び第2ダイヤフラム15
は、裏当板16.17を介して、柱1】に内設され、ボ
ルト3より径大の挿入孔141.15]が設けられる。
+6]、17+は裏当板16.17に開けられたボルト
の挿入孔である。第2ダイヤフラム15には、セメント
・ペースト注入のためのエア抜き孔152が設けられ、
また上面に、柱11の上端と面一にするため、ギャップ
プレート153が固着される。18は吊り上げ用ボルト
の取付はナツト、19は1階の梁である。
2は上層階住宅ユニット、例えば2階住宅ユニットを示
す。該上層階住宅ユニット2の柱21の接合部となる下
端部22には、裏当板23.24を介して、ダイヤフラ
ム25.26が取り付けられる。第1ダイヤフラム25
には孔がおいておらず、下端部22の天板となっている
。第2ダイヤフラム26には、ボルト3より径大の挿入
孔261.262が設けられる。第2ダイヤフラム26
には、ナツトプレート27が固着されている。28は2
階の下梁である。
挿入孔+4]、+5]の内径は、施工クリアランスが約
8mmとなるようボルト3の外径より径大に設定される
。図示例では、挿入孔】4】は直径約40mm、挿入孔
151は直径約26mmであるのに対し、ボルト3は外
径16mmである。
本発明方法による建築は、第4図に示す如く行なう。
即ち、取付はナツト18に治具(図示省略)を引掛け、
クレーン等にて吊り上げ移動し、基礎(図示省略)上に
下層階住宅ユニット1を設置、固定する。下層階住宅ユ
ニット1の設置後、取付はナツト18は取り外す。
次に、ギャッププレート153から下層階住宅ユニット
1の柱11の頭部12に、現場にて、急硬性グラウト材
からなるセメント・ペースト4が注入される。本実施例
では、急硬性グラウト材として、例えば、デンカハイタ
スコンセメントを水で練りあげたものを用いている。セ
メント・ペースト4は、頭部12のギャッププレート1
53までいっばいに充填される。
一方、現場にて、上層階住宅ユニット2の柱21の下端
部22に固着されたナツトプレート27に、ボルト3が
ナツト32にて嵌着される。
しかる後、クレーン等により上層階住宅ユニット2を下
層階住宅ユニッH上に移動し、ボルト3の下方部分31
を下層階住宅ユニット1の柱11の頭部12に注入され
たセメント・ペースト4中に埋め込む。セメント・ペー
スト4のゲル化時間は、例えば、60分乃至80分程度
である。
セメント・ペースト4が硬化すると、そこに埋め込まれ
たボルト3は柱11の頭部12内に完全に固定される。
セメント・ペースト4の硬化時間は、例えば、80分乃
至100分程度である。
本例では、挿入孔14]は直径約40mm、挿入孔15
1は直径約26mmであるのに対し、ボルト3は外径1
6mmであり、施工クリアランスに適度な余裕があるの
で、位置ズレによる調整作業をする必要がない。
また、ボルトはセメント・ペーストが付着して同化、固
定されるから、接合部の強度がボルトの破断強度より犬
となる。このため、住宅ユニット相互間の接合の強度が
増強される。
さらに、柱11の頭部12及び柱21の下端部22は、
上記の如き構成に予め工場内で所定の構造に仕1げてお
くことができる。したがって、現場での接合をセメント
・ペーストの注入、ボルトの嵌着並びに埋め込みといっ
た単純な作業にすることができる。このため、未熟練な
作業員でも、住宅ユニット相互間の接合を高精度、高強
度でかつ迅速に行なうことが可能である。
本発明にかかるユニット式建築における住宅ユニット相
互間の接合方法は、上記実施例に限定されない。例えば
、柱の頭部あるいは柱の下端部を構成するダイヤフラム
の個数、形状は任意であり、開口される挿入孔の太きさ
もボルトとの関係で適宜に決定される。
なお、本発明方法が適用される住宅ユニットの柱の本数
は任意であり、1箇所に複数の柱があってもよい。Next, a method for joining housing units in a unit-type building according to the present invention will be explained in detail based on drawings showing embodiments. 1 indicates a lower floor housing unit, for example a first floor housing unit. A cement paste receiver 13, a diaphragm, and 14.15 are attached to the head 12, which is the joint of the pillar 1 of the lower floor housing unit 1. The cement paste receiver 13 has no holes and is the bottom of the head 12. First diaphragm 14 and second diaphragm 15
is installed inside the column 1] through a backing plate 16.17, and is provided with an insertion hole 141.15] having a larger diameter than the bolt 3. +6], 17+ are bolt insertion holes drilled in the backing plate 16 and 17. The second diaphragm 15 is provided with an air vent hole 152 for cement paste injection,
Further, a gap plate 153 is fixed to the upper surface so as to be flush with the upper end of the pillar 11. Numeral 18 is a nut for mounting a lifting bolt, and numeral 19 is a beam on the first floor. 2 indicates an upper floor housing unit, for example, a second floor housing unit. A diaphragm 25.26 is attached to the lower end portion 22 of the upper floor residential unit 2, which is the joint portion of the column 21, via a backing plate 23.24. First diaphragm 25
has no holes and serves as a top plate for the lower end 22. The second diaphragm 26 is provided with insertion holes 261 and 262 having a larger diameter than the bolt 3. Second diaphragm 26
A nut plate 27 is fixed to the. 28 is 2
This is the lower beam of the floor. The inner diameters of the insertion holes +4] and +5] are set larger than the outer diameter of the bolt 3 so that the construction clearance is approximately 8 mm. In the illustrated example, the insertion hole [4] has a diameter of about 40 mm, the insertion hole 151 has a diameter of about 26 mm, while the bolt 3 has an outer diameter of 16 mm. Construction according to the method of the present invention is carried out as shown in FIG. That is, the installation is done by hooking a jig (not shown) on the nut 18,
The lower floor housing unit 1 is lifted and moved using a crane or the like, and the lower floor housing unit 1 is installed and fixed on the foundation (not shown). After installing the lower floor housing unit 1, the nuts 18 are removed. Next, a cement paste 4 made of a rapidly hardening grout material is injected into the head 12 of the column 11 of the lower floor housing unit 1 from the gap plate 153 on-site. In this embodiment, as the rapidly hardening grout material, for example, Denka Hytascon cement kneaded with water is used. The cement paste 4 is applied to the gap plate 1 of the head 12.
It is filled up to 53 at once. On the other hand, the bolt 3 is fitted with a nut 32 into the nut plate 27 fixed to the lower end 22 of the column 21 of the upper floor housing unit 2 at the site. After that, the upper floor housing unit 2 is moved onto the lower floor housing unit H using a crane or the like, and the lower part 31 of the bolt 3 is moved.
is embedded in the cement paste 4 poured into the head 12 of the column 11 of the lower floor housing unit 1. The gelation time of the cement paste 4 is, for example, about 60 to 80 minutes. When the cement paste 4 hardens, the bolt 3 embedded therein is completely fixed in the head 12 of the column 11. The hardening time of the cement paste 4 is, for example, about 80 minutes to 100 minutes. In this example, the insertion hole 14] is approximately 40 mm in diameter, and the insertion hole 15 is approximately 40 mm in diameter.
1 has a diameter of approximately 26 mm, while bolt 3 has an outer diameter of 1
6mm, and there is a reasonable amount of construction clearance, so there is no need to make adjustments due to misalignment. Also, since the cement paste adheres to the bolts and assimilates and fixes them, the strength of the joint is greater than the breaking strength of the bolts. Therefore, the strength of the connection between housing units is enhanced. Furthermore, the head 12 of the column 11 and the lower end 22 of the column 21 are
The above-mentioned configuration can be prefabricated into a predetermined structure in a factory. Therefore, on-site joining can be a simple operation of pouring cement paste, fitting bolts and embedding. Therefore, even unskilled workers can join housing units with high precision, high strength, and quickly. The method of joining housing units in a unit-type building according to the present invention is not limited to the above embodiment. For example, the number and shape of the diaphragms constituting the head of the column or the lower end of the column are arbitrary, and the thickness of the insertion hole to be opened is also appropriately determined in relation to the bolt. Note that the number of columns in a housing unit to which the method of the present invention is applied is arbitrary, and there may be a plurality of columns at one location.
このように、本発明にかかるユニット式建築における住
宅ユニット相互間の接合方法によれば、下層階住宅ユニ
ットの柱の頭部に現場にてセメント・ペーストが注入さ
れ、上層階住宅ユニットの柱の下端部に固着されたナツ
トプレートに現場にてボルトが嵌着され、該ボルトの下
方部分を下層階住宅ユニットの柱の頭部に注入されたセ
メント・ペースト中に埋め込み固定するから、高精度で
かつ高強度の接合を迅速かつ容易に行ない、工期短縮に
資する効果がある。As described above, according to the method of joining housing units in a modular building according to the present invention, cement paste is injected on-site into the column heads of the lower floor housing units, and the cement paste is injected into the column heads of the upper floor housing units. Bolts are fitted on-site to nut plates fixed to the lower ends, and the lower parts of the bolts are embedded and fixed in cement paste injected into the heads of the pillars of the lower floor housing units, so they can be fixed with high precision. In addition, high-strength bonding can be quickly and easily performed, which has the effect of contributing to shortening the construction period.
第1図は本発明にかかるユニット式建築における住宅ユ
ニット相互間の接合方法の実施例を示す要部断面図、第
2図は第1図のA−A矢視図、第3図はボルトの取付け
を説明する図である。
l・・・下層階住宅ユニッl−(]階住宅ユニット)、
11・・・柱、12・−・頭部、13・・・セメント・
ペースト、I4・・・第1ダイヤフラム、14+・・・
挿入孔、]5・・・第2タイヤフラム、152・・・エ
ア抜き孔、153・・・ギャッププレート、16・・・
裏当板、161・・・挿入孔、17・・・裏当板、17
+・・・挿入孔、I18・・・取付はナツト、19・・
・梁、2・・・上層階住宅ユニット(2階住宅ユニット
)、21・・・柱、22・・・下端部、23・・・裏当
板、24・・・裏当板、241・・・挿入孔、25・・
・第1ダイヤフラム、26・・・第2ダイヤフラム、2
61・・・挿入孔、262・・・挿入孔、27・・・ナ
ツトプレート28・・・下梁、3・・・ポル1−.31
・・・下方部分、32・・・ナツト4・・・セメント・
ペースト
特許出願人 株式会社エムデイアイ
代理人 弁理士 浅 野 勝 美
第1図
第2図
手続補正書
平成2年12月21日Fig. 1 is a sectional view of main parts showing an embodiment of the method of joining housing units in a unit type building according to the present invention, Fig. 2 is a view taken along arrow A-A in Fig. 1, and Fig. 3 is a cross-sectional view of a bolt. It is a figure explaining attachment. l...lower floor housing unit l-(] floor housing unit),
11...Column, 12...Head, 13...Cement
Paste, I4...first diaphragm, 14+...
Insertion hole,] 5... Second tire flam, 152... Air vent hole, 153... Gap plate, 16...
Backing plate, 161... Insertion hole, 17... Backing plate, 17
+...insertion hole, I18...mounting with nut, 19...
- Beam, 2... Upper floor housing unit (second floor housing unit), 21... Column, 22... Lower end, 23... Backing plate, 24... Backing plate, 241...・Insertion hole, 25...
・First diaphragm, 26...Second diaphragm, 2
61...Insertion hole, 262...Insertion hole, 27...Nut plate 28...Lower beam, 3...Pol 1-. 31
...Lower part, 32...Nut 4...Cement
Paste patent applicant Katsumi Asano Patent attorney MDA Co., Ltd. Figure 1 Figure 2 Procedural amendment December 21, 1990
Claims (1)
・ペーストが注入され、上層階住宅ユニットの柱の下端
部に固着されたナットプレートに現場にてボルトが嵌着
され、該ボルトの下方部分を下層階住宅ユニットの柱の
頭部に注入されたセメント・ペースト中に埋め込み固定
することを特徴とするユニット式建築における住宅ユニ
ット相互間の接合方法。 2、請求項1記載のユニット式建築における住宅ユニッ
ト相互間の接合方法において、上記セメント・ペースト
に急硬性グラウト材が用いられるユニット式建築におけ
る住宅ユニット相互間の接合方法。[Claims] 1. Cement paste is injected into the head of the column of the lower floor housing unit on site, and bolts are fitted on site to the nut plate fixed to the lower end of the column of the upper floor housing unit. 1. A method for joining housing units in a modular building, characterized in that the lower part of the bolt is embedded and fixed in cement paste injected into the head of a column of a lower floor housing unit. 2. The method for joining housing units in a unit-type building according to claim 1, wherein a rapidly hardening grout material is used in the cement paste.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31582390A JPH04189934A (en) | 1990-11-22 | 1990-11-22 | Jointing method between house units in unit type construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31582390A JPH04189934A (en) | 1990-11-22 | 1990-11-22 | Jointing method between house units in unit type construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH04189934A true JPH04189934A (en) | 1992-07-08 |
Family
ID=18069992
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP31582390A Pending JPH04189934A (en) | 1990-11-22 | 1990-11-22 | Jointing method between house units in unit type construction |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH04189934A (en) |
-
1990
- 1990-11-22 JP JP31582390A patent/JPH04189934A/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3160748B2 (en) | Precast structural member composed of reinforced concrete columns and steel beams, and method of constructing structure using the same | |
| JP2001073453A (en) | Building construction method | |
| JPH07292783A (en) | Connective structure of prestressed concrete members | |
| JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
| US8627623B2 (en) | Modular foundation system and method | |
| JP4026510B2 (en) | Rapid construction method for PCa structures | |
| JPH04189934A (en) | Jointing method between house units in unit type construction | |
| JPH08120790A (en) | Coupling fitting for construction member | |
| JPH0790933A (en) | Construction method of structure | |
| JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
| JP3771177B2 (en) | Joining structure of reinforced concrete column and steel column, and joining method thereof | |
| TW202432928A (en) | Method for constructing building structure | |
| JPH04189935A (en) | Jointing method for foundation and house unit in unit type construction | |
| JPH03244733A (en) | Exterior wall connection structure | |
| JPH0434161A (en) | Centrifugally molded hollow pc concrete column and column construction method | |
| JPS61233131A (en) | Foundation structure of pole | |
| JP7463331B2 (en) | Temporary jig and method for constructing artificial ground using said temporary jig | |
| JPH0892965A (en) | How to build a tubular structure | |
| JP2759361B2 (en) | Pillar support members for building reinforced concrete buildings | |
| JPH0462249A (en) | Joint structure of floor with wall and jointing method | |
| JPH0749681B2 (en) | Steel frame / reinforced concrete composite construction method | |
| JP2000096576A (en) | Joint structure of steel column base and construction method | |
| JP2025143982A (en) | Joint structure of the bottom end of a wooden pillar to the concrete surface | |
| JPH0453223B2 (en) | ||
| JPH06212645A (en) | Use of existing concrete for architectural foundation |