JPH04194227A - Earth reinforcing method with tubular reinforcement - Google Patents
Earth reinforcing method with tubular reinforcementInfo
- Publication number
- JPH04194227A JPH04194227A JP32632090A JP32632090A JPH04194227A JP H04194227 A JPH04194227 A JP H04194227A JP 32632090 A JP32632090 A JP 32632090A JP 32632090 A JP32632090 A JP 32632090A JP H04194227 A JPH04194227 A JP H04194227A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing material
- ground
- pipe
- reinforcing
- reinforced
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は補強土工法に係り、特に斜面安定のための地山
補強に際し、補強材として小口径管を地山に設置する管
状補強材による補強土工法に関する。[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a reinforced earthwork method, and in particular, when reinforcing the ground for slope stabilization, a method using a tubular reinforcing material in which small-diameter pipes are installed in the ground as a reinforcing material is used. Regarding reinforced earth construction methods.
補強土工法のうち自然地山の補強として補強材を設置す
る方法には、プレボーリング方式と直接打込み方式との
二種がある。プレボーリング方式は、地山を削孔した後
補強材を挿入し、その後グラウトを注入して補強材を全
面接着するものである。直接打込み方式では、補強材を
地山に打設したのち中空孔からグラウトを注入し、全面
接着する方法が多く用いられている。Among the reinforced earthwork methods, there are two types of methods for installing reinforcing materials to reinforce natural ground: the pre-boring method and the direct driving method. The pre-boring method involves inserting reinforcing material after drilling a hole in the ground, and then injecting grout to bond the reinforcing material to the entire surface. In the direct casting method, a method is often used in which the reinforcing material is cast into the ground, then grout is injected through a hollow hole and the entire surface is bonded.
これらの方法は、補強材と地山との一体化にグラウト材
を用いるため、一体化するまでに数日間が必要となる。These methods use grout to integrate the reinforcing material and the ground, so it takes several days to integrate the reinforcing material and the ground.
また、そのような補強材に補強効果が生じるのは、地山
が変形してからのこととなる。Moreover, such reinforcing materials will only have a reinforcing effect after the ground is deformed.
しかしながら、この種の補強土工法の施工手順は、各工
程毎に遂次施工されるのが通常で、設置された補強材が
地山と一体化した後に次段階の掘削へと進む。そして補
強材設置後グラウトが硬化するまでに要する日数は、普
通セメントで7日間程度、早強セメントを用いても3日
間はかかるという問題があった。However, in the construction procedure of this type of reinforced earthwork method, each step is usually constructed one after another, and the next step of excavation is carried out after the installed reinforcement material is integrated with the ground. There was a problem in that the number of days required for the grout to harden after installing the reinforcing material was about 7 days with ordinary cement, and 3 days even with early strength cement.
本発明の目的は、上記問題点を解消するためになされた
もので、補強材の設置直後から地山と補強材とが一体化
し、有効的且つ効果的に補強機能を発揮する管状補強材
による補強土工法を提供することである。The purpose of the present invention has been made to solve the above-mentioned problems, and uses a tubular reinforcing material that integrates the ground and the reinforcing material immediately after the reinforcing material is installed, and effectively and effectively exerts the reinforcing function. The purpose is to provide a reinforced earth construction method.
上記の目的を達成するために本発明は、地山に管状の補
強材を直接打設する管状補強材による補強土工法におい
て、前記補強材を地中に貫入した後、該補強材の基端部
を前記地山の斜面に固定し、該補強材にプレストレスを
導入することを特徴とするものである。In order to achieve the above object, the present invention provides a reinforced earthwork method using a tubular reinforcing material in which a tubular reinforcing material is directly cast into the ground. The reinforcing member is fixed to the slope of the ground, and prestress is introduced into the reinforcing material.
そして、前記補強材を地中に貫入した後、該補強材の基
端部を前記地山の斜面に固定し、次いで該補強材の先端
部を外周方向に拡径することにより、該補強材にプレス
トレスを導入することを特徴とするものである。After penetrating the reinforcing material into the ground, the base end of the reinforcing material is fixed to the slope of the ground, and then the diameter of the distal end of the reinforcing material is expanded in the outer circumferential direction. This is characterized by the introduction of prestress.
上記構成によれば、管状補強材に導入されたプレストレ
スにより、地山と管状補強材とをより強固に一体化させ
ることができる。このようなプレストレスの導入は、補
強管の先端を拡径した場合に、補強材後端の連結固定部
と拡径した突出部との間で発生する。この作用により、
その間の地山は拘束力を受けて強固となり、変形をおさ
えることが可能となるのである。そして、このような管
状補強材を複数本打設することによって、補強材局面の
摩擦抵抗及び拡径部の支圧抵抗により、地山に強固な擬
似擁壁を造成することができる。According to the above configuration, the prestress introduced into the tubular reinforcing material allows the ground and the tubular reinforcing material to be more firmly integrated. When the diameter of the distal end of the reinforcing tube is expanded, such prestress is introduced between the connecting and fixing portion at the rear end of the reinforcing material and the protruding portion whose diameter has been expanded. Due to this effect,
The ground in between becomes stronger due to the restraining force, making it possible to suppress deformation. By casting a plurality of such tubular reinforcing materials, a strong pseudo-retaining wall can be constructed in the ground due to the frictional resistance of the reinforcing material surface and the bearing pressure resistance of the enlarged diameter portion.
以下、本発明のいくつかの実施例を、図面を参照して説
明する。Hereinafter, some embodiments of the present invention will be described with reference to the drawings.
第1図は本実施例の工法を説明するためのもので、地山
2を順次切り下げてできた斜面に、直接打込み方式によ
り、管状補強材である補強管4を水平もしくはやや上向
に打設する。補強管4の打設によって、基端部の連結固
定部8を予め施工した表面保護工12に連結固定する。Fig. 1 is for explaining the construction method of this embodiment, in which reinforcing pipes 4, which are tubular reinforcing materials, are driven horizontally or slightly upward into the slope created by successively cutting down the ground 2, using the direct driving method. Set up By driving the reinforcing pipe 4, the connecting and fixing part 8 at the proximal end is connected and fixed to the surface protection work 12 that has been constructed in advance.
その後、先端の拡径部を拡径する。拡径部6が補強管4
と直交方向に拡径することにより、拡径部6と連結固定
部8との間の管周面の地盤が圧縮されるとともに補強管
4に引張力が生じ、地山と補強管とがより緊密となり、
補強管4の摩擦抵抗及び拡径部6の支圧抵抗によって、
地山2と補強管4とが一体化する。このような補強管4
を上下左右に打設することにより、強固な擬似擁壁が造
成される。After that, the diameter of the enlarged diameter portion at the tip is enlarged. The expanded diameter portion 6 is the reinforcing tube 4
By expanding the diameter in a direction perpendicular to the diameter, the ground on the pipe peripheral surface between the expanded diameter part 6 and the connecting fixing part 8 is compressed, and a tensile force is generated in the reinforcing pipe 4, so that the ground and the reinforcing pipe become more become closer,
Due to the frictional resistance of the reinforcing pipe 4 and the bearing pressure resistance of the enlarged diameter part 6,
The earth 2 and the reinforcing pipe 4 are integrated. Such reinforcement pipe 4
A strong pseudo-retaining wall is created by pouring the walls vertically, horizontally, and horizontally.
第2図は直接打込み方式による補強管4の打設の手順を
説明するためのものである。FIG. 2 is for explaining the procedure for driving the reinforcing pipe 4 by the direct driving method.
第2図(A)に示すように、地山斜面に予め表面保護工
12を施工した後、補強管4の後部に衝撃式削進機24
を接続し、打撃によって地山に貫入させる。補強管4と
表面保護工12との間には連結プレート18及びテーパ
ワッシャ20を介在させ、衝撃式削進機24にはコンプ
レッサ26に連結した反力体を必要としないエアハンマ
を用いている。As shown in FIG. 2(A), after a surface protection work 12 has been previously constructed on the slope of the ground, an impact type excavator 24 is installed at the rear of the reinforcing pipe 4.
connect and penetrate the ground by blowing. A connecting plate 18 and a taper washer 20 are interposed between the reinforcing pipe 4 and the surface protection work 12, and an air hammer that does not require a reaction force connected to a compressor 26 is used as the impact type cutting machine 24.
補強管4の打設終了時には、第2図(B)に示すように
、補強管4と表面保護工12とは連結固定部8により連
結固定される。When the reinforcing pipe 4 is finished being cast, the reinforcing pipe 4 and the surface protection work 12 are connected and fixed by the connecting fixing part 8, as shown in FIG. 2(B).
次に、第2図(C)に示すように、補強管4の先端の拡
径部6を拡径すると、拡径部6の管外周が補強管4の軸
方向と直交する方向に突出するため、根元を固定された
補強管4には軸方向に引張力が働き、管周面の地山には
圧縮力が働いた状態で定着する。Next, as shown in FIG. 2(C), when the expanded diameter portion 6 at the tip of the reinforcing tube 4 is expanded, the tube outer periphery of the expanded diameter portion 6 protrudes in a direction perpendicular to the axial direction of the reinforcing tube 4. Therefore, a tensile force acts in the axial direction on the reinforcing pipe 4 whose root is fixed, and the reinforcing pipe 4 is fixed with a compressive force acting on the ground around the pipe.
第3図は本実施例に用いた補強管4の先端拡径部6の詳
細を示すもので、第3図(A)に示すように、先端部材
30は変形し易いように周方向に溝が形成され、長手方
向にはスリット(図示せず)の形成されたパイプから′
なり、頭部内周面にはネジ32が切られている。第3図
(B)は先端部材3oが周方向に突出した状態を示すも
ので、ネジ32に棒鋼34の先端のネジを係合させて引
っ張ることにより提燈状に拡径することができる。FIG. 3 shows details of the enlarged diameter portion 6 at the tip of the reinforcing tube 4 used in this example. As shown in FIG. is formed, and a slit (not shown) is formed in the longitudinal direction of the pipe.
A screw 32 is cut on the inner peripheral surface of the head. FIG. 3(B) shows a state in which the tip member 3o protrudes in the circumferential direction, and can be expanded in diameter into a lantern shape by engaging the screw at the tip of the steel bar 34 with the screw 32 and pulling it.
このように補強管へのプレストレスの導入は、補強管の
先端を拡径した場合に発生するもので、管後部に地山に
密着して設置した連結プレートと拡径した突出部との間
で生じる。この作用により、その間の地山は拘束力を受
けて強固となり、変形をおさえることが可能となるので
ある。In this way, prestress is introduced into the reinforcing pipe when the diameter of the tip of the reinforcing pipe is expanded. occurs in As a result of this action, the ground between them receives a restraining force and becomes stronger, making it possible to suppress deformation.
因に、長さ3m、外径48.6mmの補強管の先端を、
外径150mmまで拡径すると、約30m程度地盤を圧
縮することになり、N値が約10の砂地盤で打設実験を
行ったところ、1を程度のプレストレスが導入されるこ
とが確認できた。Incidentally, the tip of a reinforcing tube with a length of 3 m and an outer diameter of 48.6 mm is
Expanding the outer diameter to 150 mm will compress the ground by about 30 m, and when we conducted a casting experiment on sandy ground with an N value of about 10, it was confirmed that a prestress of about 1 was introduced. Ta.
第5図は本実施例の実験結果を示したもので、補強材の
打設長 1=3.0m、打設地盤はN=8の細砂地盤で
、プレボーリング方式、直接打込み方式、直接打込み方
弐十先端拡径の本実施例方式、の3方式により実験した
。Figure 5 shows the experimental results of this example, where the reinforcing material casting length was 3.0 m, the casting ground was N=8 fine sand, and the pre-boring method, direct driving method, and direct driving method were used. Experiments were conducted using three methods: the method of this embodiment, which has a diameter enlargement at the tip, and the method of this embodiment.
プレボーリング方式は電動オーガーにより削孔しく削孔
径φ=48mm)、孔内にグラウトを注入した後鉄筋を
挿入して補強材としたものである(仕上り径φ= 50
mm)。In the pre-boring method, a hole is drilled using an electric auger (diameter φ = 48 mm), and after grout is injected into the hole, reinforcing bars are inserted to serve as reinforcement (finished diameter φ = 50 mm).
mm).
直接打込み方式は補強管(φ=48.6mm)を衝撃式
削進機により打設したものである。In the direct driving method, a reinforcing tube (φ=48.6 mm) is driven using an impact type cutting machine.
本実施例方式は、直接打込み方式に加えて補強管の先端
を拡径したものである(拡径φ=148mm)。In this embodiment method, in addition to the direct driving method, the tip of the reinforcing tube is expanded in diameter (expanded diameter φ=148 mm).
実験の結果、図示するように、直接打込み方式では補強
材の周面摩擦抵抗が8tf/rrr以下となり基準値を
超えず、プレボーリング方式でもせいぜい10 t f
/ mであった。これに対して本実施例方式によれば
、10 t f / rrI 前後から11.7t f
/ mとなり、他の2方式に比較して大幅に摩擦抵抗
が増加することが明らかとなった。As a result of the experiment, as shown in the figure, the peripheral surface friction resistance of the reinforcing material is 8 tf/rrr or less in the direct driving method, which does not exceed the standard value, and even in the pre-boring method, it is at most 10 tf/rrr.
/ m. On the other hand, according to the method of this embodiment, from around 10 t f /rrI to 11.7 t f
/ m, and it became clear that the frictional resistance increased significantly compared to the other two methods.
先端部の拡径は、補強管と地山との一体化をより確実な
ものとするために実施するもので、本実施例のように先
端を引っ張って提燈状に拡径する方法の他に、第4図に
示すように、スリットを設けたインナーパイプ36の後
部から楔38を打撃してインナーパイプ36を拡開し、
スリット(図示せず)の形成された先端部を拡径するこ
とも可能である。Expanding the diameter of the tip is done to ensure the integration of the reinforcing pipe with the ground, and other than the method of expanding the diameter into a lantern shape by pulling the tip as in this example. Then, as shown in FIG. 4, the wedge 38 is struck from the rear of the inner pipe 36 provided with the slit to expand the inner pipe 36.
It is also possible to enlarge the diameter of the tip portion in which the slit (not shown) is formed.
第6図は本実施例に用いた補強管4の一例を示すもので
、有孔部14と鋼管部16とからなり、先端に拡径部6
、基端に連結固定部8を備えている。有孔部14は地盤
浸透水を排水して地山を安定させるために設けたもので
、本例では、長手方向に複数本の鉄筋を円形に配列し、
その周囲に線材を巻回して線材間に僅かな間隙を設けて
固着し。FIG. 6 shows an example of the reinforcing pipe 4 used in this embodiment, which is composed of a perforated part 14 and a steel pipe part 16, and has an enlarged diameter part 6 at the tip.
, is provided with a connecting fixing part 8 at the base end. The perforated part 14 is provided to drain water that seeps into the ground and stabilize the ground, and in this example, a plurality of reinforcing bars are arranged in a circular manner in the longitudinal direction,
Wrap the wire around it and fix it with a small gap between the wires.
その間隙をスリット孔にしたものである。巻回した線材
による外周面の凹凸によって補強管長手方向の摩擦抵抗
が増大する効果がある。勿論、管壁に水抜き孔を散在さ
せた有孔鋼管を使用してもよい。排水効果のある補強管
を使用する場合、地山斜面に緑化保護工を施工すると植
物の育成に好適である。The gap is made into a slit hole. The unevenness of the outer peripheral surface caused by the wound wire rod has the effect of increasing the frictional resistance in the longitudinal direction of the reinforcing tube. Of course, a perforated steel pipe with drainage holes scattered in the pipe wall may also be used. When using reinforcing pipes with drainage effects, it is suitable for growing plants if green protection works are constructed on the slopes of the ground.
第7図は補強管の根元の連結固定部8を示したものであ
る。錆管部16の基端にはフランジ22が形成され、テ
ーパワッシャ20、連結プレート18を介して地山に密
着固定されている。FIG. 7 shows the connecting and fixing part 8 at the base of the reinforcing pipe. A flange 22 is formed at the base end of the rust pipe portion 16, and is tightly fixed to the earth via a taper washer 20 and a connecting plate 18.
このように、グラウト注入を伴わない即効性のある補強
材設置方法で地山と補強材とを一体化する方法として、
直接打込み方式による打設と管状補強材先端部の拡径及
び管状補強材へのプレストレスの導入を行うことにより
、補強効果が増大し、より強固に地山と一体化させるこ
とができる。In this way, as a method for integrating the ground and reinforcing material with a quick-acting reinforcing material installation method that does not involve grouting,
By using the direct driving method, expanding the diameter of the tip of the tubular reinforcing material, and applying prestress to the tubular reinforcing material, the reinforcing effect can be increased and it can be more firmly integrated with the ground.
上述のとおり本発明によれば、即効性のある補強材の設
置が可能となり、施工性に優れた補強土工法を提供する
ことができる。As described above, according to the present invention, it is possible to install reinforcing materials with immediate effect, and it is possible to provide a reinforced earth construction method with excellent workability.
第1図は本発明の一実施例を示す説明図、第2図は本実
施例の施工手順を示す説明図、第3図は本実施例に用い
た補強材の一例を示す要部断面図、第4図は同じく補強
材の他の例を示す要部断面図、第5図は本実施例の効果
を示す実験データを記載した図、第6図は本実施例に用
いた補強材の側面図、第7図は本実施例に用いた補強材
の固定方法を示す説明図である。Fig. 1 is an explanatory diagram showing one embodiment of the present invention, Fig. 2 is an explanatory diagram showing the construction procedure of this embodiment, and Fig. 3 is a cross-sectional view of essential parts showing an example of the reinforcing material used in this embodiment. , FIG. 4 is a cross-sectional view of the main part showing another example of the reinforcing material, FIG. 5 is a diagram showing experimental data showing the effect of this example, and FIG. 6 is a diagram of the reinforcing material used in this example. The side view and FIG. 7 are explanatory diagrams showing a method of fixing the reinforcing material used in this example.
Claims (1)
る補強土工法において、 前記補強材を地中に貫入した後、該補強材の基端部を前
記地山の斜面に固定し、該補強材にプレストレスを導入
することを特徴とする管状補強材による補強土工法。 2、地山に管状の補強材を直接打設する管状補強材によ
る補強土工法において、 前記補強材を地中に貫入した後、該補強材の基端部を前
記地山の斜面に固定し、次いで該補強材の先端部を外周
方向に拡径することにより、該補強材にプレストレスを
導入することを特徴とする管状補強材による補強土工法
。 3、請求項2記載の補強土工法において、 前記補強材の先端部は、先端を引っ張ることにより拡径
することを特徴とする管状補強材による補強土工法。 4、請求項2記載の補強土工法において、 前記補強材の先端部は、長手方向に溝を有するインナー
パイプを内部に具備し、該インナーパイプの後部から楔
を打撃することにより拡張させて、前記先端部を拡径す
ることを特徴とする管状補強材による補強土工法。 5、請求項1又は2記載の補強土工法において、前記地
山の斜面にあらかじめ表面保護工を施工し、該表面保護
工に前記補強材の基端部を固定することを特徴とする管
状補強材による補強土工法。 6、請求項1又は2記載の補強土工法において、前記補
強材は、通水孔を有することを特徴とする管状補強材に
よる補強土工法。 7、請求項1又は2記載の補強土工法において、前記地
山の斜面にあらかじめ緑化保護工を施工し、該緑化保護
工に前記補強材の基端部を固定すると共に、該補強材は
通水孔を有することを特徴とする管状補強材による補強
土工法。 8、請求項1ないし7のうちのいずれかに記載の補強土
工法を、地山の切下げ毎に順次施工する管状補強材によ
る補強土工法。 9、請求項1ないし8のうちのいずれかに記載の補強土
工法に用いられた管状補強材。[Claims] 1. In a reinforced earthwork method using a tubular reinforcing material in which a tubular reinforcing material is directly cast into the ground, after the reinforcing material is penetrated into the ground, the base end of the reinforcing material is inserted into the ground. A reinforced earthwork method using a tubular reinforcing material, which is fixed to a mountain slope and is characterized by introducing prestress into the reinforcing material. 2. In the reinforced earthwork method using tubular reinforcing materials in which tubular reinforcing materials are directly cast into the ground, after the reinforcing material has penetrated into the ground, the base end of the reinforcing material is fixed to the slope of the ground. A reinforced earthwork method using a tubular reinforcing material, characterized in that prestress is introduced into the reinforcing material by subsequently expanding the diameter of the tip end of the reinforcing material in the outer circumferential direction. 3. The reinforced earthwork method using a tubular reinforcing material according to claim 2, wherein the diameter of the tip of the reinforcing material is expanded by pulling the tip. 4. The reinforced earth construction method according to claim 2, wherein the tip of the reinforcing material is provided with an inner pipe having a groove in the longitudinal direction, and is expanded by hitting a wedge from the rear of the inner pipe, A reinforced earthwork method using a tubular reinforcing material, characterized by expanding the diameter of the tip. 5. The reinforced earthwork method according to claim 1 or 2, characterized in that a surface protection work is previously constructed on the slope of the ground, and the base end of the reinforcing material is fixed to the surface protection work. Reinforced earth construction method using materials. 6. A reinforced earthwork method using a tubular reinforcing material according to claim 1 or 2, wherein the reinforcing material has water holes. 7. In the reinforced earthwork method according to claim 1 or 2, a greening protection work is constructed in advance on the slope of the ground, the base end of the reinforcing material is fixed to the greening protection work, and the reinforcing material is A reinforced earthwork method using tubular reinforcing materials that are characterized by having water holes. 8. A reinforced earth construction method using tubular reinforcing materials, in which the reinforced earth construction method according to any one of claims 1 to 7 is sequentially applied each time a ground is cut down. 9. A tubular reinforcing material used in the reinforced earth construction method according to any one of claims 1 to 8.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2326320A JPH0730562B2 (en) | 1990-11-28 | 1990-11-28 | Reinforced earth method with tubular reinforcement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2326320A JPH0730562B2 (en) | 1990-11-28 | 1990-11-28 | Reinforced earth method with tubular reinforcement |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04194227A true JPH04194227A (en) | 1992-07-14 |
| JPH0730562B2 JPH0730562B2 (en) | 1995-04-05 |
Family
ID=18186452
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2326320A Expired - Fee Related JPH0730562B2 (en) | 1990-11-28 | 1990-11-28 | Reinforced earth method with tubular reinforcement |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0730562B2 (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006291498A (en) * | 2005-04-07 | 2006-10-26 | Okumura Corp | Drilling machine |
| JP2011252319A (en) * | 2010-06-02 | 2011-12-15 | Central Japan Railway Co | Reinforcement material for natural ground reinforcement earth method and natural ground reinforcement earth method |
| JP2013036216A (en) * | 2011-08-08 | 2013-02-21 | Sun Quest:Kk | Reinforcement method of retaining wall |
| JP2013221330A (en) * | 2012-04-17 | 2013-10-28 | Nippo Corp | Construction method of paved road and reinforcing structure of paved road |
| WO2016002700A1 (en) * | 2014-06-30 | 2016-01-07 | 株式会社三喜工務店 | Foundation pile |
| JP2018096132A (en) * | 2016-12-14 | 2018-06-21 | 日鐵住金建材株式会社 | Bearing jig for multistage pipe and method of penetration of multistage pipe |
| JP2022127221A (en) * | 2021-02-19 | 2022-08-31 | 日鉄建材株式会社 | Reinforcement structure and reinforcement method of masonry wall, and tubular reinforcement member |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS608732U (en) * | 1983-06-27 | 1985-01-22 | 株式会社 佐藤工業所 | wall reinforcement device |
| JPS6128624A (en) * | 1984-07-16 | 1986-02-08 | Kajima Corp | Slope-stabilizing construction |
| JPS6397721A (en) * | 1986-10-15 | 1988-04-28 | Nippon Soiru Kogyo Kk | Slope frame construction work |
| JPH02147723A (en) * | 1988-11-30 | 1990-06-06 | Fujita Corp | Cut slope stabilization structure and stabilization method |
-
1990
- 1990-11-28 JP JP2326320A patent/JPH0730562B2/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS608732U (en) * | 1983-06-27 | 1985-01-22 | 株式会社 佐藤工業所 | wall reinforcement device |
| JPS6128624A (en) * | 1984-07-16 | 1986-02-08 | Kajima Corp | Slope-stabilizing construction |
| JPS6397721A (en) * | 1986-10-15 | 1988-04-28 | Nippon Soiru Kogyo Kk | Slope frame construction work |
| JPH02147723A (en) * | 1988-11-30 | 1990-06-06 | Fujita Corp | Cut slope stabilization structure and stabilization method |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006291498A (en) * | 2005-04-07 | 2006-10-26 | Okumura Corp | Drilling machine |
| JP2011252319A (en) * | 2010-06-02 | 2011-12-15 | Central Japan Railway Co | Reinforcement material for natural ground reinforcement earth method and natural ground reinforcement earth method |
| JP2013036216A (en) * | 2011-08-08 | 2013-02-21 | Sun Quest:Kk | Reinforcement method of retaining wall |
| JP2013221330A (en) * | 2012-04-17 | 2013-10-28 | Nippo Corp | Construction method of paved road and reinforcing structure of paved road |
| WO2016002700A1 (en) * | 2014-06-30 | 2016-01-07 | 株式会社三喜工務店 | Foundation pile |
| JP2018096132A (en) * | 2016-12-14 | 2018-06-21 | 日鐵住金建材株式会社 | Bearing jig for multistage pipe and method of penetration of multistage pipe |
| JP2022127221A (en) * | 2021-02-19 | 2022-08-31 | 日鉄建材株式会社 | Reinforcement structure and reinforcement method of masonry wall, and tubular reinforcement member |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0730562B2 (en) | 1995-04-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101696916B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
| JP2009041335A (en) | Repair method for existing lining | |
| KR101041362B1 (en) | Permanent anchor body for slope reinforcement and slope stabilization method using the same | |
| JP6634219B2 (en) | Ground anchor installation method | |
| KR20130108218A (en) | Method of reinforcement and construction of pillar of neighboring tunnel | |
| JPH09217594A (en) | How to support the tunnel | |
| JP2017186801A (en) | Rock bolt | |
| JP7211779B2 (en) | Shield start-side shaft wall and shield start-side shaft wall construction method | |
| KR102185255B1 (en) | Construction method of composite pile with extensioned tip | |
| JPH1054031A (en) | Pre-stress concrete pile and its positioning method of pile | |
| JPH0730562B2 (en) | Reinforced earth method with tubular reinforcement | |
| KR100632977B1 (en) | Plasma anchor method | |
| KR100696309B1 (en) | Slope reinforcement nail anchor | |
| JP5504463B2 (en) | Reinforcing method of concrete frame | |
| JP4884276B2 (en) | Rotating press pile construction method and slope construction equipment | |
| KR100717252B1 (en) | Earth anchor installation method and device | |
| KR100869369B1 (en) | Ground reinforcement device of grouting method using bundle steel pipe and ground reinforcement method through it | |
| JP4689448B2 (en) | Anchor structure and anchor method | |
| KR102458224B1 (en) | Anchor with front-end expansion parts and construction method using the same | |
| JP2984728B2 (en) | Construction method of cast-in-place concrete pile | |
| JP7398768B1 (en) | Embedded method | |
| KR100505330B1 (en) | Tension nail of construction | |
| KR100999911B1 (en) | Pack anchor | |
| KR100721605B1 (en) | Structure of the front pressure plate of the soil nail | |
| JPH0325120A (en) | Rock anchor method in widened borehole wall type |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |