JPH0421791B2 - - Google Patents

Info

Publication number
JPH0421791B2
JPH0421791B2 JP3227685A JP3227685A JPH0421791B2 JP H0421791 B2 JPH0421791 B2 JP H0421791B2 JP 3227685 A JP3227685 A JP 3227685A JP 3227685 A JP3227685 A JP 3227685A JP H0421791 B2 JPH0421791 B2 JP H0421791B2
Authority
JP
Japan
Prior art keywords
old
tower
new
ground
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3227685A
Other languages
Japanese (ja)
Other versions
JPS61191770A (en
Inventor
Toshio Sakano
Tomoyuki Matsukura
Takahito Ito
Juichi Takehara
Yasuhiko Myagawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Cable Industries Ltd
Kansai Electric Power Co Inc
Original Assignee
Mitsubishi Cable Industries Ltd
Kansai Denryoku KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Cable Industries Ltd, Kansai Denryoku KK filed Critical Mitsubishi Cable Industries Ltd
Priority to JP3227685A priority Critical patent/JPS61191770A/en
Publication of JPS61191770A publication Critical patent/JPS61191770A/en
Publication of JPH0421791B2 publication Critical patent/JPH0421791B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は既設送電線を仮工事することなく、ま
た既設鉄塔を送電状態で旧地盤から新地盤に継脚
する既設鉄塔の継脚工法に関する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention relates to a method for connecting an existing tower to a new ground without performing temporary construction on an existing power transmission line, and in which the existing tower is connected from the old ground to the new ground while power is being transmitted. .

(従来技術) 第12図Aのように丘綾1上に既設鉄塔2があ
る場合、最近の宅地造成や土地改良などにより、
旧鉄塔ルートが鉄塔移設を余儀なくされることが
多い。しかし土地の造成よりも鉄塔の移設が遅
れ、第12図Bのように、他の切り取られた地盤
3よりも鉄塔2付近の地盤だけが小高い丘4のよ
うに残される。ところが鉄塔の移設には用地買収
を要し、経費と時間が嵩む。この対策として丘4
を削り、新地盤3上に鉄塔建替工事を行つてい
る。その手順は、第12図Cのように既設鉄塔2
の横に鉄塔5を仮設し、一次的に停電させた後旧
鉄塔2から新鉄塔5へ移線し、Dのように旧鉄塔
2を解体し、次にEのように地盤カツトにより丘
4を除き、丘4のあつた位置にFのように新鉄塔
6を構築して再び停電状態で鉄塔5から移線し、
次に仮鉄塔5を解体しているG。ところがこの場
合も線路の一次的停電に伴う複雑な調整と、仮鉄
塔5を設けるための煩しい用地業務が避けられな
い。
(Prior art) When there is an existing steel tower 2 on the hill 1 as shown in Fig. 12A, due to recent residential land development and land improvement, etc.
Old steel tower routes often have to be relocated. However, the relocation of the tower was delayed compared to the land preparation, and as shown in Figure 12B, only the ground near the tower 2 was left behind, like a small hill 4, compared to the other ground 3 that had been cut out. However, relocating the tower requires land acquisition, which increases costs and time. As a countermeasure for this, hill 4
The steel tower is being reconstructed on new ground 3. The procedure is as shown in Figure 12C.
A steel tower 5 was temporarily constructed next to the hill, and after a temporary power outage, the line was transferred from the old steel tower 2 to the new steel tower 5. The old steel tower 2 was dismantled as shown in D, and then the hill 4 was built by cutting the ground as shown in E. Except for this, a new steel tower 6 was built at the location where hill 4 was located as shown in F, and the line was transferred from tower 5 again under power outage.
Next, G is dismantling temporary steel tower 5. However, in this case as well, complicated adjustments due to a temporary power outage on the line and troublesome land work for installing the temporary tower 5 are unavoidable.

(発明の目的) 本発明は既設送電線を仮工事することなく、ま
た既設鉄塔を送電状態で旧地盤から新地盤へ継脚
できるようにすることを目的としている。
(Objective of the Invention) An object of the present invention is to make it possible to connect an existing steel tower from an old ground to a new ground while transmitting power without having to perform temporary construction on an existing power transmission line.

(発明の構成) 本発明は旧鉄塔の各塔脚を旧地盤上に仮受けし
た後、旧塔脚の下方延長部に土留材を用いて旧基
礎の徹去を含めて深礎掘削を行い、掘削完了後新
基礎を設けて将来の地盤まで埋戻し、新基盤と旧
塔脚を主柱材で連結し、座屈防止用の支保工を施
こした後仮受材を除いて主柱材に荷重をかけ、土
留材と支保工の除去を含め順次腹材を組み立てな
がら新地盤まで切土徹去する既設鉄塔の継脚工法
である。
(Structure of the Invention) The present invention involves temporarily supporting each tower leg of a former steel tower on the old ground, and then excavating a deep foundation, including removing the old foundation, using earth retaining material at the lower extension of the old tower leg. After the excavation was completed, a new foundation was installed and backfilled to the future ground level, the new foundation and the old tower base were connected with main pillar materials, and after providing support to prevent buckling, the main pillar was removed, excluding the temporary support material. This is a method of connecting the legs of an existing steel tower, in which a load is applied to the timber, the earth retaining material and shoring are removed, and the upper material is assembled in sequence, while the earth is cut and removed to the new ground.

(実施例) 第1図は本発明工法の概要を示しており、Aの
ように丘綾1上に既設鉄塔2がある状態から、周
辺の宅地造成等により鉄塔2付近の地盤だけが小
高い丘4に残された場合B,Cのように塔脚2a
を1本ずつ地上にて仮受けしながら深礎掘にて将
来の地盤3に新基礎10を施工し、新基礎10と
旧塔脚2aを主柱材11によりつなぎ、その後丘
4を切り取りD、実質的に旧鉄塔に塔脚を継ぎ足
して新鉄塔6を得る方法である。
(Example) Figure 1 shows an outline of the construction method of the present invention. From a state where the existing steel tower 2 is on top of the hill Aya 1 as shown in A, to a situation where only the ground near the steel tower 2 is a slightly elevated hill due to surrounding housing land development etc. If left in 4, tower pedestal 2a like B and C
A new foundation 10 is constructed on the future ground 3 by deep foundation digging while temporary supporting one by one on the ground, and the new foundation 10 and the old tower pedestal 2a are connected with the main pillar material 11, and then the hill 4 is cut out. This is a method to obtain a new steel tower 6 by essentially adding tower legs to the old steel tower.

次に第1図の新工法を工程順に詳述する。第2
図は塔脚仮受工程を示しており、施工は一脚ずつ
行う。まず塔脚2aの地面4a(地盤)付近にH
形鋼等からなる補強材又は仮受材12をジヤツキ
13により仮止めし、ジヤツキアツプによりその
塔脚2aの荷重を仮受けさせる(圧縮脚の場合)。
引揚脚の場合は仮支線を併用する。
Next, the new construction method shown in Figure 1 will be explained in detail in the order of the steps. Second
The figure shows the temporary mounting process for tower legs, and construction will be carried out one leg at a time. First, place H near the ground 4a (ground) of the tower pedestal 2a.
A reinforcing material or temporary support material 12 made of shaped steel or the like is temporarily fixed with jacks 13, and the load of the column leg 2a is temporarily supported by the jack up (in the case of a compression leg).
In the case of a towing leg, a temporary branch line is also used.

第3図、第4図は深礎掘削工程を示しており、
第3図のように旧塔脚2aの下方に例えば鋼矢
板、デツキプレート或は軽みぞ形鋼等よりなる土
留材15を使用して旧基礎16の徹去を含めて穴
17を掘削する。この場合、土留材15には円周
方向並びに上下方向に分解可能な多数個の分割片
によるボルト組立方式のものを使用するのが作業
上有利である。
Figures 3 and 4 show the deep foundation excavation process.
As shown in FIG. 3, a hole 17 is excavated below the old tower pedestal 2a, including the removal of the old foundation 16, using earth retaining material 15 made of, for example, steel sheet piles, deck plates, or light groove steel. In this case, it is advantageous for the work to use a bolt assembly system for the retaining material 15, which is made up of a large number of divided pieces that can be disassembled in the circumferential direction and the vertical direction.

補強仮受材12は第4図に示す如く穴17を横
切るように配置されており、従つてジヤツキ13
は穴17の外方に位置している。仮受材12の他
に別の仮受材12aを追加することもできる。
The reinforcing temporary support material 12 is arranged so as to cross the hole 17 as shown in FIG.
is located outside the hole 17. In addition to the temporary receiving material 12, another temporary receiving material 12a can also be added.

第5図は深礎掘削末期の工程を示している。即
ち掘削を進め、将来の新地盤3を想定して新基礎
の根入れを決定し、部分18に拡底掘削を施す。
なお土留材15の裏込めにはモルタルは使用しな
いので(土留材15は後程除去するので)、土留
材15の周部に当接させて鋼管ぐい或はH形鋼ぐ
い等の補強材15aを複数本打ち込み、土留材1
5をより強固に立設させておくことが望ましい。
Figure 5 shows the process at the final stage of deep foundation excavation. That is, the excavation is proceeded, the new foundation is determined based on the future new ground 3, and the bottom expansion excavation is performed in the portion 18.
Since mortar is not used to backfill the earth retaining material 15 (the earth retaining material 15 will be removed later), a reinforcing material 15a such as a steel pipe pile or H-shaped steel pile is placed in contact with the circumference of the earth retaining material 15. Driving multiple pieces, earth retaining material 1
It is desirable to have 5 more firmly erected.

第6図は基礎コンクリート工程を示しており、
穴17の掘削完了後、新基礎10のための据付配
筋コンクリート施工を施し、引き続き新地盤3ま
で埋戻土19により埋戻しておく。
Figure 6 shows the basic concrete process.
After completing the excavation of the hole 17, installation reinforcement concrete work is performed for the new foundation 10, and the new ground 3 is subsequently backfilled with backfill soil 19.

第7図、第8図は主材組立工程を示しており、
ジヤツキアツプしている旧塔脚2a(旧ポスト)
と新基礎10を主柱材11により連結する。この
場合、旧塔脚2aの荷重による主柱材11の座屈
を防ぐため、土留材15の内壁から等辺山形鋼或
はみぞ形鋼等よりなる支保工21を例えば第8図
に示すように十字状に多数個施しておく。なお、
上記支保工21は、土留材15の内壁に固定させ
る以外に、土留材15の内壁近傍に別途支保工固
定用の支柱P(第8図に二点鎖線で示す)を設け
て取付固定してもよい。支保工完了後ジヤツキ1
3と仮受材12を取外し、旧塔脚2aの荷重を主
柱材11を介して新基礎10にかける。
Figures 7 and 8 show the main material assembly process.
The old tower foot 2a (old post) is jacked up
and the new foundation 10 are connected by the main pillar material 11. In this case, in order to prevent buckling of the main column 11 due to the load of the old tower pedestal 2a, a support 21 made of equilateral angle steel or groove steel is installed from the inner wall of the earth retaining material 15, for example, as shown in FIG. Apply many pieces in a cross shape. In addition,
The above-mentioned shoring 21 is not only fixed to the inner wall of the earth retaining material 15, but also installed and fixed by separately providing a pillar P for securing the shoring (indicated by a two-dot chain line in Fig. 8) near the inner wall of the earth retaining material 15. Good too. Jacking after shoring completion 1
3 and the temporary supporting material 12 are removed, and the load of the old tower pedestal 2a is applied to the new foundation 10 via the main pillar material 11.

第9図は四脚施工の状態を示しており、四脚式
の鉄塔の場合第2〜第8図に示す工事を四脚に対
し行う。
Figure 9 shows the state of four-legged construction; in the case of a four-legged steel tower, the construction shown in Figures 2 to 8 is performed on the four legs.

第10図は切り取り組立工程を示しており、四
脚新基礎完成後、新地盤3まで切土徹去を行う。
この際に順次腹材22の組立と、土留材15(お
よび補強材15a)の徹去作業を行う。23は切
取面である。なお、上記切り取り組立工程を実施
する場合には、ラーメン構造の組立式櫓R(第1
0図に二点鎖線で示す)を四本の主柱材11を囲
むように立設し、この櫓Rにて旧塔脚2aの荷重
を一時的に分担支承させておくのが安全作業上好
ましい。
Figure 10 shows the cutting and erection process, and after the new four-legged foundation is completed, cutting and removal will be carried out up to the new ground level 3.
At this time, the work of assembling the belly material 22 and removing the earth retaining material 15 (and reinforcing material 15a) is performed in sequence. 23 is a cut surface. In addition, when carrying out the above-mentioned cutting and assembling process, it is necessary to
For safety reasons, it is recommended to erect a column (indicated by a two-dot chain line in Fig. preferable.

第11図は主地盤3上に継脚された新鉄塔6を
示しており、新鉄塔6の上半部は旧鉄塔2の主要
部で構成されており、旧鉄塔2の位置は全く変更
していない。
Figure 11 shows the new steel tower 6 with legs attached to the main ground 3. The upper half of the new steel tower 6 is made up of the main part of the old steel tower 2, and the position of the old steel tower 2 has not changed at all. Not yet.

(発明の効果) 本発明によると仮工事なしに旧鉄塔の塔脚を現
状のまま地中へ継脚して、新地盤上に新鉄塔を設
けることができ、旧鉄塔の横に移線用の仮鉄塔
等、大掛かりな仮設備を要することなく、又狭少
な工事範囲で、既鉄塔の元位置に、将来の地盤
(切り取り後)から見れば嵩上げされた新鉄塔を
構築し得る。このため複雑な停電の調整と、煩わ
しい用地業務が軽減されるメリツトがあり、工事
費の面も大幅に軽減する余地がある。これにより
仮工事(停電)なしの元位置建替が可能となる。
(Effects of the Invention) According to the present invention, the legs of the old steel tower can be connected underground as they are without temporary construction, and a new steel tower can be installed on the new ground, and the new tower can be installed next to the old steel tower for transfer purposes. It is possible to construct a new steel tower, which will be raised from the future ground (after cutting), at the original location of the existing steel tower, without requiring large-scale temporary equipment such as a temporary steel tower, and within a narrow construction area. This has the advantage of reducing complex power outage adjustments and cumbersome land management work, and there is also room to significantly reduce construction costs. This makes it possible to rebuild at the original location without temporary construction (power outages).

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明による新工法を示す正面略図、
第2図〜第11図は本発明の工法を具体的に示す
詳細図、第12図は従来工法を示す正面略図であ
る。1…丘綾(旧地盤)、2…旧鉄塔、2a…塔
脚、3…新地盤、10…新基礎、11…主柱材、
12…仮受材、15…土留材、16…旧基礎、2
1…支保工、22…腹材。
Figure 1 is a schematic front view showing the new construction method according to the present invention;
2 to 11 are detailed views specifically showing the construction method of the present invention, and FIG. 12 is a schematic front view showing the conventional construction method. 1...Okaaya (old ground), 2...Old steel tower, 2a...Tower base, 3...New ground, 10...New foundation, 11...Main pillar material,
12...Temporary retaining material, 15...Earth retaining material, 16...Old foundation, 2
1... Shoring, 22... Belly material.

Claims (1)

【特許請求の範囲】[Claims] 1 旧鉄塔の各塔脚を旧地盤上に仮受けした後、
旧塔脚の下方延長部に土留材を用いて旧基礎の徹
去を含めて深礎掘削を行い、掘削完了後新基礎を
設けて将来の地盤まで埋戻し、新基盤と旧塔脚を
主柱材で連結し、座屈防止用の支保工を施こした
後仮受材を除いて主柱材に荷重をかけ、土留材と
支保工の除去を含め順次腹材を組み立てながら新
地盤まで切土徹去する既設鉄塔の継脚工法。
1 After temporarily supporting each tower leg of the old steel tower on the old ground,
A deep foundation excavation was performed using earth retaining material on the lower extension of the old tower foot, including the removal of the old foundation. After the excavation was completed, a new foundation was installed and backfilled to the future ground, and the new foundation and old tower foot were mainly removed. After connecting with pillars and installing shoring to prevent buckling, load is applied to the main pillars with the temporary support materials removed, and the earth retaining materials and shoring are removed, and the main pillars are assembled sequentially until the new ground is reached. A method of connecting legs to existing steel towers by cutting and removing soil.
JP3227685A 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower Granted JPS61191770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3227685A JPS61191770A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3227685A JPS61191770A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Publications (2)

Publication Number Publication Date
JPS61191770A JPS61191770A (en) 1986-08-26
JPH0421791B2 true JPH0421791B2 (en) 1992-04-13

Family

ID=12354454

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3227685A Granted JPS61191770A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Country Status (1)

Country Link
JP (1) JPS61191770A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Existing foundation reinforced steel tower foundation and its construction method
JP4950146B2 (en) * 2007-08-20 2012-06-13 三菱重工鉄構エンジニアリング株式会社 Coral growing device and coral growing method

Also Published As

Publication number Publication date
JPS61191770A (en) 1986-08-26

Similar Documents

Publication Publication Date Title
US3184893A (en) Contact foundation method
CN210288419U (en) An anti-column diagonal bracing reinforcement system for large-span inverse foundation pits
US20040071511A1 (en) Apparatus and method of supporting a structure with a pier
CN214832716U (en) Soft soil property of municipal construction takes underground structure
CN112832248B (en) Urban tunnel subway station construction method and deep and large foundation pit group construction dynamic monitoring and measuring method
JP2001520340A (en) Arch support structure
JP3724320B2 (en) Construction method for underground structures
JP2012112121A (en) Excavation method of ground under spread foundation and base-isolating method of existing building
JP2596798B2 (en) Existing building seismic isolation method
JP4465571B2 (en) Seismic isolation system for existing buildings
JPH0220768A (en) Basement extension method for existing building
JPH0421791B2 (en)
JPH11209996A (en) Footing structure of cylindrical towery structure
JPS62288269A (en) Method for extending underground stair of building
CN216193926U (en) Construction site trestle structure
JPH0559728A (en) Sheathing work above underground structure
JPH11310928A (en) Seismic isolation reinforcement method for existing structures
KR20240071652A (en) basement floor connection construction method
DK152442B (en) PROCEDURE FOR MAKING FOUNDATIONS FOR A CONSTRUCTION AND FOUNDATION BLOCK FOR USING THE PROCEDURE
JP3809618B2 (en) Foundation pile and construction method of foundation pile
JP2566050B2 (en) How to construct a vertical structure below an existing building
JPH0742179A (en) Modified inversion placing construction method
JP4589506B2 (en) Pre-installation method of large steel columns for constructing buildings with superstructure structure by the reverse driving method
JPH0421792B2 (en)
JPH1130053A (en) Construction method of seismic isolation building

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees