JPH0421792B2 - - Google Patents

Info

Publication number
JPH0421792B2
JPH0421792B2 JP3227785A JP3227785A JPH0421792B2 JP H0421792 B2 JPH0421792 B2 JP H0421792B2 JP 3227785 A JP3227785 A JP 3227785A JP 3227785 A JP3227785 A JP 3227785A JP H0421792 B2 JPH0421792 B2 JP H0421792B2
Authority
JP
Japan
Prior art keywords
old
steel tower
tower
new
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3227785A
Other languages
Japanese (ja)
Other versions
JPS61191771A (en
Inventor
Toshio Sakano
Tomoyuki Matsukura
Takahito Ito
Juichi Takehara
Yasuhiko Myagawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Cable Industries Ltd
Kansai Electric Power Co Inc
Original Assignee
Mitsubishi Cable Industries Ltd
Kansai Denryoku KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Cable Industries Ltd, Kansai Denryoku KK filed Critical Mitsubishi Cable Industries Ltd
Priority to JP3227785A priority Critical patent/JPS61191771A/en
Publication of JPS61191771A publication Critical patent/JPS61191771A/en
Publication of JPH0421792B2 publication Critical patent/JPH0421792B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は既設送電線を仮工事することなく、ま
た既設鉄塔をそのまま使用した状態で旧地盤から
新地盤に継脚する既設鉄塔の継脚工法に関する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is a method for connecting legs of an existing steel tower from old ground to new ground without performing temporary construction on existing power transmission lines, and while using the existing tower as it is. Regarding construction methods.

(従来技術) 第8図Aのように丘綾1上に既設鉄塔2がある
場合、最近の宅地造成や土地改良などにより、旧
鉄塔ルートが鉄塔移設を余儀なくされることが多
い。しかし土地の造成よりも鉄塔の移設が遅れ、
第8図Bのように、他の切り取られた地盤3より
も鉄塔2付近の地盤だけが小高い丘4のように残
される。ところが鉄塔の移設には用地買収を要
し、経費と時間が嵩む。この対策として丘4を削
り、新地盤3上に鉄塔建替工事を行つている。そ
の手順は、第8図Cのように既設鉄塔2の横に鉄
塔5を仮設し、一次的に停電させた後旧鉄塔2か
ら新鉄塔5へ移線し、Dのように旧鉄塔2を解体
し、次にEのように地盤カツトにより丘4を除
き、丘4のあつた位置にFのように新鉄塔6を構
築して再び停電状態で鉄塔5から移線し、次に仮
鉄塔5を解体しているG。ところがこの場合も線
路の一次的停電に伴う複雑な調整と、仮鉄塔5を
設けるための煩しい用地業務が避けられない。
(Prior Art) When there is an existing steel tower 2 on a hill 1 as shown in FIG. 8A, the old steel tower route often has to be relocated due to recent housing development or land improvement. However, the relocation of the steel tower was delayed compared to the land preparation.
As shown in FIG. 8B, only the ground near the steel tower 2 is left as a slightly elevated hill 4 compared to the other ground 3 that has been cut out. However, relocating the tower requires land acquisition, which increases costs and time. As a countermeasure, Hill 4 has been removed and the steel tower is being rebuilt on new ground 3. The procedure is to temporarily install a steel tower 5 next to the existing steel tower 2 as shown in Figure 8C, temporarily cut off the power, then transfer the line from the old steel tower 2 to the new tower 5, and then move the old steel tower 2 to the new tower 5 as shown in D. Demolish it, then remove hill 4 by cutting the ground as shown in E, build a new tower 6 at the location of hill 4 as shown in F, transfer the line from tower 5 again under power outage, and then install a temporary tower. G dismantling 5. However, in this case as well, complicated adjustments due to a temporary power outage on the line and troublesome land work for installing the temporary tower 5 are unavoidable.

(発明の目的) 本発明は既設送電線を仮工事することなく、ま
た既設鉄塔をそのまま使用した状態で旧地盤から
新地盤へ継脚できるようにすることを目的として
いる。
(Objective of the Invention) The object of the present invention is to enable the legs to be connected from the old ground to the new ground without performing temporary construction on the existing power transmission line and while using the existing steel tower as it is.

(発明の構成) 本発明は旧鉄塔の下方に深礎掘削を行ない、そ
こに旧基礎より上方へ突出した鉄筋コンクリート
の杭を設け、杭の上端に台部を配筋しかつ旧塔脚
にアンカー加工を施して台部に巻込むようにコン
クリートを打設し、引続き旧基礎の徹去を含めて
新地盤まで切土徹去する既設鉄塔の継脚工法であ
る。
(Structure of the Invention) The present invention involves excavating a deep foundation below the old steel tower, installing reinforced concrete piles that protrude upwards from the old foundation, reinforcing the base at the top of the pile, and anchoring it to the legs of the old tower. This is a method of connecting the legs of an existing steel tower, in which concrete is placed so that it wraps around the base of the tower, and then the old foundation is removed and the earth is cut and removed to the new ground.

(実施例) 第1図は1本のコンクリート杭11を使用する
例、第2図は複数本のコンクリート杭12を使用
する例を示している。まず第1図Aに示すよう
に、丘綾1上に鉄塔2が設けられていて、鉄塔2
の周辺が宅地造成等により削られて鉄塔2がBの
ように小高い丘4上に取り残された場合、Cのよ
うに既設鉄塔2にコンクリート杭11を接続した
後、杭11の周囲の丘4を切り取り、将来の地盤
3上に新しい鉄塔6を形成している。新鉄塔6の
上半部は旧鉄塔2でできており、旧鉄塔2の位置
には全く変更がない。
(Example) FIG. 1 shows an example in which one concrete pile 11 is used, and FIG. 2 shows an example in which a plurality of concrete piles 12 are used. First, as shown in Figure 1A, a steel tower 2 is installed on top of the hill 1.
If the area around the steel tower 2 is removed due to construction of a residential area and the steel tower 2 is left on a small hill 4 as shown in B, after connecting the concrete pile 11 to the existing steel tower 2 as shown in C, the hill 4 around the pile 11 is removed. is cut out and a new steel tower 6 is formed on the future ground 3. The upper half of the new steel tower 6 is made up of the old steel tower 2, and the position of the old steel tower 2 has not changed at all.

第1図の新工法の詳細を第3図以下に示す。第
3図、第4図は深礎掘削工程を示しており、旧鉄
塔2の塔脚2aと旧基礎16で囲まれた区域の中
央部に土留材例えば鋼矢板15を使用して穴17
が掘削され、穴17の下端部分18に拡底掘削が
施される。
Details of the new construction method shown in Figure 1 are shown in Figures 3 and below. Figures 3 and 4 show the deep foundation excavation process, in which a hole 17 is created using earth retaining material, such as steel sheet pile 15, in the center of the area surrounded by the pedestal 2a of the old steel tower 2 and the old foundation 16.
is excavated, and the bottom end portion 18 of the hole 17 is expanded.

第5図は配筋コンクリート工程を示しており、
穴内に杭11の配筋とコンクリート打設を行う。
12は杭11の鉄筋である。
Figure 5 shows the reinforced concrete process.
Reinforce the piles 11 and place concrete in the hole.
12 is a reinforcing bar of the pile 11.

第6図は旧塔脚のアンカー加工と台部の配筋コ
ンクリート工程を示している。即ち杭11の上端
部に突出した鉄筋12を中心に、台部13のため
の配筋が行われ、同時に旧塔脚2aにアンカー1
4が加工され、アンカー14が台部13内に巻き
込まれるように台部13にコンクリートを打設す
る。
Figure 6 shows the anchoring process for the old tower pedestal and the reinforcing concrete process for the base. That is, reinforcement for the platform 13 is placed around the reinforcing bars 12 protruding from the upper end of the pile 11, and at the same time anchors 1 are placed on the old tower pedestals 2a.
4 is processed, and concrete is poured into the base part 13 so that the anchor 14 is rolled into the base part 13.

第7図は旧基礎の徹去と切土工程を示してい
る。まず台部13の配筋、コンクリート打設の
後、台部13より上方の旧鉄塔2内に腹材改造を
施す。22は改造材(腹材)である。次に旧基礎
16の徹去を含めて、新地盤3まで切土を行ない
土を徹去する。切り取りレベルに応じて杭11の
表面仕上げを施す。これにより新鉄塔6が得られ
る。新鉄塔6の上半部は、前述の如く旧鉄塔2で
形成されており、旧鉄塔2の位置には全く変更が
生じない。
Figure 7 shows the removal of the old foundation and the cutting process. First, after reinforcing the base part 13 and pouring concrete, the interior of the old steel tower 2 above the base part 13 is remodeled. 22 is a modified material (belly material). Next, including the removal of the old foundation 16, the earth is cut to the new ground 3 and the soil is removed. The surface of the pile 11 is finished according to the cutting level. As a result, a new steel tower 6 is obtained. The upper half of the new steel tower 6 is formed by the old steel tower 2 as described above, and the position of the old steel tower 2 will not change at all.

第2図のようにコンクリート杭12を複数本設
ける場合も、第3図〜第7図と同様の工法を採用
することができる。
Even when a plurality of concrete piles 12 are provided as shown in FIG. 2, the same construction method as shown in FIGS. 3 to 7 can be employed.

(発明の効果) 本発明によると仮工事なしに旧鉄塔の塔脚を現
状のまま地中へ継脚して、新地盤上に新鉄塔を設
けることができ、旧鉄塔の横に移線用の仮鉄塔
等、大掛かりな仮設備を要することなく、又狭少
な工事範囲で、既鉄塔の元位置に、将来の地盤
(切り取り後)から見れば嵩上げされた新鉄塔を
構築し得る。このため複雑な停電の調整と、煩わ
しい用地業務が軽減されるメリツトがあり、工事
費の面も大幅に軽減する余地がある。これにより
仮工事(停電)なしの元位置建替が可能となる。
(Effects of the Invention) According to the present invention, the legs of the old steel tower can be connected underground as they are without temporary construction, and a new steel tower can be installed on the new ground, and the new tower can be installed next to the old steel tower for transfer purposes. It is possible to construct a new steel tower, which will be raised from the future ground (after cutting), at the original location of the existing steel tower, without requiring large-scale temporary equipment such as a temporary steel tower, and within a narrow construction area. This has the advantage of reducing complex power outage adjustments and cumbersome land management work, and there is also room to significantly reduce construction costs. This makes it possible to rebuild at the original location without temporary construction (power outages).

【図面の簡単な説明】[Brief explanation of drawings]

第1図、第2図は本発明による新工法2種類を
示す正面略図、第3図〜第7図は第1図に示す新
工法の詳細図、第8図は従来工法を示す正面略図
である。2…旧鉄塔、2a…旧塔脚、3…新地
盤、11…コンクリート杭、13…台部、14…
アンカー、16…旧基礎。
Figures 1 and 2 are schematic front views showing two types of new construction methods according to the present invention, Figures 3 to 7 are detailed views of the new construction method shown in Figure 1, and Figure 8 is a schematic front view showing the conventional construction method. be. 2... Old steel tower, 2a... Old tower foot, 3... New ground, 11... Concrete pile, 13... Base, 14...
Anchor, 16...old foundation.

Claims (1)

【特許請求の範囲】[Claims] 1 旧鉄塔の下方に深礎掘削を行ない、そこに旧
基礎より上方へ突出した鉄筋コンクリートの杭を
設け、杭の上端に台部を配筋しかつ旧塔脚にアン
カー加工を施して台部に巻込むようにコンクリー
トを打設し、引続き旧基礎の徹去を含めて新地盤
まで切土徹去する既設鉄塔の継脚工法。
1. We excavated a deep foundation below the old steel tower, installed reinforced concrete piles that protruded upwards from the old foundation, placed reinforcements on the tops of the piles, and anchored the old tower legs to attach them to the base. A method of connecting the legs of an existing steel tower, in which concrete is placed in a rolling manner, and then the old foundation is removed and the cutting is removed to the new ground.
JP3227785A 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower Granted JPS61191771A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3227785A JPS61191771A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3227785A JPS61191771A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Publications (2)

Publication Number Publication Date
JPS61191771A JPS61191771A (en) 1986-08-26
JPH0421792B2 true JPH0421792B2 (en) 1992-04-13

Family

ID=12354481

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3227785A Granted JPS61191771A (en) 1985-02-20 1985-02-20 Leg connection construction method of existing iron tower

Country Status (1)

Country Link
JP (1) JPS61191771A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6834226B2 (en) * 2016-08-02 2021-02-24 東京電力ホールディングス株式会社 Pile foundation and tower rebuilding method

Also Published As

Publication number Publication date
JPS61191771A (en) 1986-08-26

Similar Documents

Publication Publication Date Title
CN108867692A (en) The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
US5433557A (en) Method for underpinning an existing footing
JP3516391B2 (en) Ground excavation method
JP2868651B2 (en) Earth retaining method above existing underground structure
CN208604588U (en) Underground power house partition wall rock mass pays protection structure and underground power house partition wall rock mass structure in advance
JPS62288269A (en) Method for extending underground stair of building
CN216193926U (en) Construction site trestle structure
DK152442B (en) PROCEDURE FOR MAKING FOUNDATIONS FOR A CONSTRUCTION AND FOUNDATION BLOCK FOR USING THE PROCEDURE
JPS61191771A (en) Leg connection construction method of existing iron tower
GB2067623A (en) Method for supporting buildings
JPH0721196B2 (en) Reverse construction method of underground structure
JPH06341154A (en) Construction of underground building frame
JPH0421791B2 (en)
JP3700119B2 (en) Pillar construction method
CN221422007U (en) Existing rubble retaining wall high side slope supporting construction adjacent to deep foundation pit
JPH04194277A (en) Building demolition method
JPS59233028A (en) Residential land formation work on sloped ground
RU2105100C1 (en) Method for strengthening of strip foundations
JP2001131962A (en) Installation of cage
JP2838019B2 (en) Caisson blade framing method
JP3567387B2 (en) How to build an underground skeleton
JPH0654015B2 (en) How to build the foundation
JPS6178927A (en) Construction of retaining wall
JPH0765313B2 (en) Underground construction method