JPH0421871Y2 - - Google Patents

Info

Publication number
JPH0421871Y2
JPH0421871Y2 JP7075387U JP7075387U JPH0421871Y2 JP H0421871 Y2 JPH0421871 Y2 JP H0421871Y2 JP 7075387 U JP7075387 U JP 7075387U JP 7075387 U JP7075387 U JP 7075387U JP H0421871 Y2 JPH0421871 Y2 JP H0421871Y2
Authority
JP
Japan
Prior art keywords
loop
wall
reinforcement
longitudinal
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP7075387U
Other languages
Japanese (ja)
Other versions
JPS63181630U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP7075387U priority Critical patent/JPH0421871Y2/ja
Publication of JPS63181630U publication Critical patent/JPS63181630U/ja
Application granted granted Critical
Publication of JPH0421871Y2 publication Critical patent/JPH0421871Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【考案の詳細な説明】 《産業上の利用分野》 本考案は地下に打設したコンクリートによる単
位壁を、順次相互に連設していくことで地下連続
壁を本設構造物として構築していく際、上記単位
壁間に埋設して使用し、単位壁相互を強固に連設
するのに用いられている壁間継手の改良に関す
る。
[Detailed explanation of the invention] <Industrial application field> This invention constructs an underground continuous wall as a permanent structure by sequentially connecting unit walls made of concrete poured underground. The present invention relates to improvements in wall-to-wall joints that are used by being buried between the unit walls to firmly connect the unit walls.

《従来の技術》 既知の如く地下連続壁を構築しようとするとき
は、第7図に例示する通り、先ず同図aの先行エ
レメント溝孔Aを掘削して、その端部Aeにロツ
キングパイプBとジヨイントボツクスCを建込
み、さらに、これと隣接させて壁間継手Dを建込
んだ後、先行エレメント鉄筋かごEを建込むか、
D,Eを一体として同時に建込み、然る後先行す
るエレメントのコンクリートを打設して、単位壁
Fを形成する。
<<Prior Art>> When attempting to construct an underground continuous wall as is known in the art, as illustrated in Fig. 7, the preceding element groove A shown in Fig. After erecting B and joint box C, and erecting inter-wall joint D adjacent to this, either erecting the preceding element reinforcing bar E, or
D and E are erected at the same time as one unit, and then the concrete of the preceding element is poured to form the unit wall F.

ところで、上記の壁間継手Dとして従来用いら
れているものは、第5図の正面図によつても知ら
れる通り、縦長基板D1の表裏両面から直交状に
各一対宛の縦走フランジ板D2を植立させること
で、横断面キ字状とした仕切鋼板D3が形成さ
れ、さらに上記各縦走フランジ板D2の内側面
に、基端部D4が溶接手段により固着されたコ字
状等のループ筋D5,D5……を、所要多数個だ
け縦走平面内にて列設し、計4列のループ筋群を
形成したものである。
By the way, in the conventional wall-to-wall joint D, as can be seen from the front view of FIG. By planting, a partition steel plate D3 having a square cross section is formed, and furthermore, on the inner surface of each of the longitudinal flange plates D2, a loop striation having a U shape or the like is formed, the base end D4 of which is fixed by welding means. A required number of D5, D5, .

従つて、前記の如く単位壁Fが形成された後
に、第7図fの如くロツキングパイプBを引き抜
き、さらに後行するエレメント溝孔A1を掘削し
終つたならば、ジヨイントボツクスCを引き抜く
ことで、当該壁間継手Dの片面側である一対のル
ープ筋群を、上記のエレメント溝孔A1側に露呈
させ、同上溝孔A1に後行エレメント鉄筋かごE
1を建込んだ後、後行するエレメントのコンクリ
ート打設を行つて後行単位壁F1を連続させるこ
とになる。
Therefore, after the unit wall F is formed as described above, the locking pipe B is pulled out as shown in FIG. By doing so, the pair of loop reinforcements on one side of the wall-to-wall joint D are exposed on the element slot A1 side, and the trailing element reinforcing bar cage E is placed in the same slot A1.
1, the succeeding unit wall F1 will be made continuous by placing concrete for the succeeding element.

ところが、上記従来の壁間継手によるときは、
ループ筋D5,D5……が縦走フランジ板D2に
溶接されただけのものであるため、何れも単体と
して格別に固着されているループ筋の強度が充分
でないという問題がある。
However, when using the above conventional wall joint,
Since the loop reinforcements D5, D5, .

そこで、上記の難点を解消するために、第6図
に示すものも用いられているが、その構成は縦走
フランジ板D2の外側面と内側面とに、夫々ルー
プ筋D5,D5……の基端部D4を溶接すると共
に、列設されたこれらのループ筋D5,D5……
が順次相互に、壁厚方向にあつて重なり合うよう
に配設されたものである。
Therefore, in order to solve the above-mentioned difficulties, the one shown in Fig. 6 is also used, but its configuration is such that loop reinforcements D5, D5... are provided on the outer and inner surfaces of the longitudinal flange plate D2, respectively. While welding the end portion D4, these loop reinforcements D5, D5...
are arranged one after another so as to overlap each other in the wall thickness direction.

これによるときは、上記の如くループ筋D5の
溶接位置と重ね合わせ構成により、確かにその強
度は第5図のものより改善されるのであるが、ま
だ満足すべき強度が得られたとはいえないだけで
なく、基端部の溶接位置の関係から、ループ筋の
列設状態が一平面内に収まらず、このことがコン
クリートの充填を阻害することとなつて、地下連
続壁としての強度を低下させてしまうことにもな
る。
In this case, the strength is certainly improved compared to the one in Figure 5 due to the welding position and overlapping configuration of the loop muscle D5 as described above, but it cannot be said that a satisfactory strength has been obtained yet. In addition, due to the welding position of the base end, the loop reinforcements cannot be arranged in one plane, which impedes concrete filling and reduces the strength of the underground continuous wall. It may also cause you to do so.

《考案が解決しようとする問題点》 本考案は上記従来の問題点に鑑み、前記の列設
されたループ筋の適所に縦鉄筋を固着して、これ
らを一体的に連設することにより、ループ筋の強
度を大幅に向上すると共に、コンクリートの充填
を阻害しないようにし、さらに建込みに際しジヨ
イントボツクスCに引掛けたり、またエレメント
鉄筋かごの建込みに際し、ループ筋と衝当すると
いつたことによる破損、変形を防止しようとする
のが、その目的である。
<<Problems to be solved by the invention>> In view of the above-mentioned conventional problems, the present invention fixes vertical reinforcing bars at appropriate positions of the above-mentioned rows of loop bars and connects them in an integral manner. In addition to greatly improving the strength of the loop bars, it also prevents them from interfering with concrete filling, and also prevents them from getting caught in the joint box C during erection, and from colliding with the loop bars when erecting element reinforcing bars. The purpose is to prevent damage and deformation caused by

《問題点を解決するための手段》 本考案は上記の目的を達成するために、縦長基
板の表裏両面から直交状に各一対宛の縦走フラン
ジ板を植立した仕切鋼板にあつて、上記各縦走フ
ランジ板の一側面に、基端部が固着されたループ
筋を、所要多数個だけ、縦走平面内にて列設する
ことでループ筋群を形成し、これら夫々のループ
筋群における各ループ筋の先端部を、縦鉄筋の固
着により一体に連設してなる地下連続壁の壁間継
手を提供しようとするものである。
<Means for Solving the Problems> In order to achieve the above-mentioned object, the present invention provides a partition steel plate in which each pair of longitudinal flange plates is installed perpendicularly from both the front and back sides of a vertically long board. A loop muscle group is formed by arranging a required number of loop muscles whose proximal ends are fixed in a row in a longitudinal plane on one side of the longitudinal flange plate, and each loop in each of these loop muscle groups The purpose of the present invention is to provide a wall-to-wall joint for an underground continuous wall in which the tips of the bars are integrally connected by fixing vertical reinforcing bars.

《作用》 個々のループ筋が縦鉄筋によつて一体に連設さ
れることとなり、しかもその連設位置が、ループ
筋の先端部であるため、外力に対してループ筋群
全体が、これを受承することとなつて強度が大幅
に増強され、しかもループ筋は縦走−平面内に収
められることとなるので、コンクリートの打設に
支障なく、また縦鉄筋の縦設によつて、建込みに
際しループ筋が他部材に引掛けたり衝当し難くな
つて、建込作業の能率が向上し、当該衝当等によ
り破損、変形などといつたことも生じないことと
なる。
《Effect》 The individual loop reinforcements are connected together by the longitudinal reinforcing bars, and since the connection position is the tip of the loop reinforcement, the entire loop muscle group resists external force. The strength of the reinforcement is greatly increased, and since the loop bars are placed within the vertical running plane, there is no problem with concrete pouring, and the vertical installation of the vertical reinforcing bars allows for easy construction. During this process, the loop reinforcements are less likely to catch or collide with other members, improving the efficiency of construction work, and preventing damage, deformation, etc. due to such collisions.

《実施例》 本考案を図示の実施例によつて詳記すれば、第
1図乃至第3図に示す如く、鉄板等により形成さ
れた仕切鋼板1は、縦長基板1aと、その表裏両
面から直交状に各一対宛植立させた縦走フランジ
板1b,1b,1b,1bによつて横断面キ字状
に形成されており、ループ筋2,2……の基端部
2aが、上記各縦走フランジ板1b,1b,1
b,1bの一側面に溶接手段にて固着され、これ
により、これらループ筋2,2……が縦走平面内
にて順次隣装状態にて列設されたループ筋群3
a,3b,3c,3dが形成されているのは従来
のものと同じである。
《Example》 To describe the present invention in detail with reference to an illustrated example, as shown in Figs. 1 to 3, a partition steel plate 1 formed of an iron plate or the like has a vertically elongated substrate 1a and both sides thereof. The longitudinal flange plates 1b, 1b, 1b, 1b are set perpendicularly to each other in pairs to form a V-shaped cross section, and the base ends 2a of the loop reinforcements 2, 2... are connected to each longitudinal flange plate. Board 1b, 1b, 1
A loop reinforcement group 3 is fixed to one side surface of b, 1b by welding means, whereby these loop reinforcements 2, 2... are successively arranged in a row next to each other in a longitudinal plane.
The formation of a, 3b, 3c, and 3d is the same as in the conventional one.

ここで第1図のループ筋2,2……は何れも放
物線状に形成され、その先端部2bが円弧状とな
つているが、第2図のものでは山形となつてい
て、先端部2bは縦向きの直線状としてあり、第
3図のループ筋2,2……はコ字状で、もちろん
その先端部は第2図のものよりも長い縦向きの線
状となつており、基端部2aは図示例の如く縦走
フランジ板1b,1b,1b,1bの外側面より
も内側面に溶接するのがよい。
Here, the loop lines 2, 2, . is a vertical straight line, and the loops 2, 2, etc. in Figure 3 are U-shaped, and of course their tips are longer vertical lines than those in Figure 2, and the base The end portions 2a are preferably welded to the inner surfaces of the longitudinal flange plates 1b, 1b, 1b, 1b rather than the outer surfaces as shown in the illustrated example.

本考案では、上記のループ筋群3a,3b,3
c,3dにあつて、その上下配置であるループ筋
2,2……の先端部2bを、直線状である縦鉄筋
4a,4b,4c,4dの溶接手段による固着に
より、一体に連設するのである。
In the present invention, the above loop muscle groups 3a, 3b, 3
c, 3d, the tips 2b of the loop reinforcements 2, 2, etc., which are arranged above and below, are integrally connected by fixing the vertical reinforcing bars 4a, 4b, 4c, and 4d, which are straight, by welding means. It is.

この際、上記先端部2bの外側に沿つて溶接す
るのが望ましく、かつ第1図にあつては先端部2
bである円弧状部分に、第2図では山頂部分に、
第3図では長寸の直線部分において充分に溶接す
るのがよいが、先端部2bであればその他の部分
でもよく、例えば先端部2bの突端面に沿わせて
溶接するとか、これとは逆に上記円弧部や直線状
部よりも、少しく基端部2a寄りに溶接すること
もできる。
At this time, it is desirable to weld along the outside of the tip 2b, and in the case of FIG.
In the arc-shaped part shown in b, and in the mountaintop part in Figure 2,
In Fig. 3, it is preferable to fully weld the long straight part, but other parts may be used as long as it is the tip 2b. It is also possible to weld a little closer to the proximal end 2a than the arcuate portion or linear portion.

そこで、上記の壁間継手を使用するには、第4
図によつて示される通り、第7図につき前述した
一般工法に従うこととなるのであり、同図a,b
の如く先行エレメント溝孔Aに、ロツキングパイ
プBとジヨイントボツクスCを建込んだ後、本案
壁間継手を建込むこととなる。
Therefore, in order to use the above-mentioned wall joint, the fourth
As shown in the figure, the general construction method described above in Figure 7 will be followed, and
After installing the locking pipe B and the joint box C in the preceding element slot A, the wall-to-wall joint will be installed.

この際ジヨイントボツクスCの切込溝内にルー
プ筋2,2……が降下挿入されていくこととなる
が、縦鉄筋4a,4bがあるため、ループ筋2,
2……がジヨイントボツクスCに引掛つて、当該
降下が阻害されたり、衝当によるシヨツクによつ
て損傷、変形するといつたこともなく、円滑な作
業を助勢することとなり、このことは同図dの如
く先行エレメント鉄筋かごEを建込む際にも縦鉄
筋4c,4dが同様の降下を発揮することとなる
だけでなく、同図fにおけるジヨイントボツクス
Cの引き抜き、同図gの後行エレメント鉄筋かご
E1建込み時にあつても同じである。
At this time, the loop bars 2, 2... will be inserted downward into the cut grooves of the joint box C, but since there are longitudinal reinforcing bars 4a, 4b, the loop bars 2, 2...
2... will not get caught in the joint box C and hinder its descent, nor will it be damaged or deformed by the shock caused by impact, and this will help the work to be carried out smoothly. Not only will the vertical reinforcing bars 4c and 4d exert a similar downward movement when the preceding element reinforcing bar basket E is erected as shown in d, but also when the joint box C is pulled out in the figure f, and when the joint box C is pulled out in the same way as shown in the figure g, The same applies when the element reinforcing cage E1 is erected.

《考案の効果》 本考案は上記のようにして構成されたものであ
り、縦鉄筋4a,4b,4c,4dにより、ルー
プ筋2,2……の先端部2bが連設されたループ
筋群3a,3b,3c,3dを形成したから、あ
たかもトラス状に一体化されることとなり、外力
に対して各々の単体であるループ筋が抵抗するの
ではなく、全ループ筋が縦鉄筋と共に一体となつ
て抵抗でき、この結果継手強度を大幅に向上させ
ることができる。
<<Effect of the invention>> The present invention is constructed as described above, and includes a loop muscle group in which the tip portions 2b of the loop muscles 2, 2... are connected by vertical reinforcing bars 4a, 4b, 4c, and 4d. Since 3a, 3b, 3c, and 3d are formed, it is as if they were integrated into a truss shape, and instead of each individual loop reinforcement resisting external force, all the loop reinforcements are integrated together with the longitudinal reinforcement. As a result, the strength of the joint can be greatly improved.

また、形状が単純でループ筋は縦装平面内に配
在されているから、コンクリートの充填が円滑に
行われ、コンクリート充填不十分による継手強度
の低下を防ぐことができる。
In addition, since the shape is simple and the loop reinforcements are arranged within the vertical installation plane, concrete filling is performed smoothly, and a decrease in joint strength due to insufficient concrete filling can be prevented.

さらに本考案では建込みと引き抜きに際し、縦
鉄筋が一種のガイド作用を果し、当該作業が迅速
に行い得ると共に、ループ筋がジヨイントボツク
スや鉄筋カゴに引掛つて、ループ筋が破損したり
変形するといつたことも解消される。
Furthermore, with this invention, the vertical reinforcing bars act as a kind of guide during erection and pulling out, allowing the work to be carried out quickly. Then the problem will disappear.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案に係る壁間継手の使用状態を示
す一実施例の部分斜視図、第2図と第3図は同上
継手の異種例を示した部分斜視図、第4図a〜h
は同上継手を用いて地下連続壁を構築する場合の
工程順を示す平面説明図、第5図と第6図は従来
の壁間継手を示した別異例の各部分側面部、第7
図a〜hは第5図の壁間継手を用いて地下連続壁
を構築するときの工程手順平面説明図である。 1……仕切鋼板、1a……縦長基板、1b……
縦走フランジ板、2……ループ筋、2a……基端
部、2b……先端部、3a,3b,3c,3d…
…ループ筋群、4a,4b,4c,4d……縦鉄
筋。
FIG. 1 is a partial perspective view of one embodiment of the wall-to-wall joint according to the present invention showing how it is used; FIGS. 2 and 3 are partial perspective views showing different examples of the same joint; FIGS. 4 a to h
1 is an explanatory plan view showing the process order when constructing an underground continuous wall using the same joint as above, FIG. 5 and FIG.
Figures a to h are explanatory plan views of process steps when constructing an underground continuous wall using the wall-to-wall joint in Figure 5. 1...Partition steel plate, 1a...Vertical board, 1b...
Longitudinal flange plate, 2...Loop muscle, 2a...Proximal end, 2b...Tip, 3a, 3b, 3c, 3d...
...Loop muscle group, 4a, 4b, 4c, 4d... Vertical reinforcing bars.

Claims (1)

【実用新案登録請求の範囲】 (1) 縦長基板の表裏両面から直交状に各一対宛の
縦走フランジ板を植立した仕切鋼板にあつて、
上記各縦走フランジ板の一側面に、基端部が固
着されたループ筋を、所要多数個だけ、縦走平
面内にて列設することでループ筋群を形成し、
これら夫々のループ筋群における各ループ筋の
先端部を、縦鉄筋の固着により一体に連設して
なる地下連続壁の壁間継手。 (2) ループ筋の基端部が、仕切鋼板の縦走フラン
ジ板における内側面に固着され、縦鉄筋がルー
プ筋の先端部における外側面に固着されている
実用新案登録請求の範囲第1項記載の地下連続
壁の壁間継手。 (3) ループ筋の基端部が、仕切鋼板の縦走フラン
ジ板における内側面に固着され、縦鉄筋がルー
プ筋の先端部における突端面に固着されている
実用新案登録請求の範囲第1項記載の地下連続
壁の壁間継手。
[Scope of Claim for Utility Model Registration] (1) Regarding a partition steel plate in which a pair of longitudinal flange plates are planted perpendicularly from both the front and back sides of a vertically long board,
A loop muscle group is formed by arranging a required number of loop muscles whose proximal ends are fixed on one side of each of the longitudinal flange plates in a longitudinal plane,
A wall-to-wall joint for an underground continuous wall in which the tips of each loop reinforcement in each of these loop reinforcement groups are connected together by fixing vertical reinforcing bars. (2) The base end of the loop reinforcement is fixed to the inner surface of the longitudinal flange plate of the partition steel plate, and the longitudinal reinforcement is fixed to the outer surface of the tip of the loop reinforcement, as described in claim 1 of the utility model registration. Inter-wall joints for underground continuous walls. (3) The base end of the loop reinforcement is fixed to the inner surface of the longitudinal flange plate of the partition steel plate, and the longitudinal reinforcement is fixed to the tip end surface of the tip of the loop reinforcement, as stated in claim 1 of the utility model registration claim. Inter-wall joints for underground continuous walls.
JP7075387U 1987-05-12 1987-05-12 Expired JPH0421871Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7075387U JPH0421871Y2 (en) 1987-05-12 1987-05-12

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7075387U JPH0421871Y2 (en) 1987-05-12 1987-05-12

Publications (2)

Publication Number Publication Date
JPS63181630U JPS63181630U (en) 1988-11-24
JPH0421871Y2 true JPH0421871Y2 (en) 1992-05-19

Family

ID=30912675

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7075387U Expired JPH0421871Y2 (en) 1987-05-12 1987-05-12

Country Status (1)

Country Link
JP (1) JPH0421871Y2 (en)

Also Published As

Publication number Publication date
JPS63181630U (en) 1988-11-24

Similar Documents

Publication Publication Date Title
US4320888A (en) Concrete form systems and components thereof
JPH0421871Y2 (en)
US4145024A (en) Form for reinforced concrete wall
JPS6146606B2 (en)
JPS62280414A (en) Construction work of underground continuous wall
JPH073749A (en) Hybrid structure slit dam
JPH0868113A (en) Joint structure of steel beam and reinforced concrete beam
JPH0118229B2 (en)
JPH0439954Y2 (en)
JPS5817055Y2 (en) Spiral stirrup for beams
JPH0586663A (en) How to join precast concrete wall columns
JPH0437129Y2 (en)
JPH0135873Y2 (en)
JPH0542538B2 (en)
JP3019326U (en) Legal framework
JPH0449254Y2 (en)
JPH0738517Y2 (en) Reinforcing bar connection structure
JPS6340521Y2 (en)
WO1983001975A1 (en) A method of erecting a building construction and a reinforcing element for use in the method
JP2575792Y2 (en) Jig for returning bending
JP2000303552A (en) How to build a reinforced cage
JPS6219712Y2 (en)
JPH0716843Y2 (en) Girder steel frame with supporting piece of girder reinforcing bar
JPS6019859Y2 (en) Main reinforcement holding bracket
JPS601461B2 (en) Flexible formwork device