JPH0432170B2 - - Google Patents
Info
- Publication number
- JPH0432170B2 JPH0432170B2 JP13618387A JP13618387A JPH0432170B2 JP H0432170 B2 JPH0432170 B2 JP H0432170B2 JP 13618387 A JP13618387 A JP 13618387A JP 13618387 A JP13618387 A JP 13618387A JP H0432170 B2 JPH0432170 B2 JP H0432170B2
- Authority
- JP
- Japan
- Prior art keywords
- wall
- walls
- beams
- reinforcing bar
- columns
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は地中連続壁による地下構造物の構築
方法に関する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method for constructing an underground structure using an underground continuous wall.
(従来の技術)
地中連続壁は仮設的な止水壁および山留壁とし
てのみならず、地下構造物として利用されてい
る。(Prior Art) Underground continuous walls are used not only as temporary water-stop walls and retaining walls, but also as underground structures.
地中連続壁を地下構造物として利用する場合、
従来地中連続壁の構築後、その内方を掘削し、連
続壁内面に柱、梁、床版等の後打ち躯体を構築
し、連続壁と接合して一体化を図つている。 When using a diaphragm wall as an underground structure,
Conventionally, after constructing an underground continuous wall, the inside of the wall is excavated, and post-cast structures such as columns, beams, and floor slabs are constructed on the inner surface of the continuous wall, and these are joined to the continuous wall to integrate them.
これは次のような理由によるものである。すな
わち地中連続壁は単位壁体ごとに構築されるため
単位壁体間に接合部が生じるが、接合部において
は先行壁における鉄筋篭の横筋を継手部材として
仕切板から後行壁に突出させ、後行壁における鉄
筋篭の横筋と重ね合せている。この重ね部分にお
いては横筋どうしの一体的な接合も、また拘束筋
による拘束もすることができないので、接合部に
おいては掘削後に地盤側から作用する面外せん断
力に対して弱く、このため接合部内面に後打ち躯
体として特に柱および梁を構築し、この柱および
梁によつて面外せん断力を負担させている。 This is due to the following reasons. In other words, since the underground continuous wall is constructed for each unit wall, there are joints between the unit walls, but at the joint, the horizontal reinforcement of the reinforcing bar cage in the leading wall is used as a joint member to protrude from the partition plate to the trailing wall. , overlaps with the horizontal reinforcement of the reinforcing bar cage on the trailing wall. In this overlapped part, the transverse bars cannot be integrally connected to each other, nor can they be restrained by restraint bars, so the joint is vulnerable to out-of-plane shear forces that act from the ground side after excavation. Columns and beams are constructed on the inner surface as a post-cast framework, and the out-of-plane shear force is borne by these columns and beams.
(発明が解決しようとする問題点)
しかしながら、連続壁の構築後に後打ち躯体を
接合する従来工法は、(1)壁付きの柱、梁が壁面か
ら内方に突出するため、内部の有効空間を著しく
制約すること、(2)連続壁の杭、壁付きの柱、梁が
偏心するため、接合用のシヤーコネクタを多量に
必要とし、工費が高くなるだけでなく工期も長く
なること、(3)後打ち柱や梁と連続壁との接合部は
コンクリート、鉄筋等が二重投資となつていて、
不経済であること等種々の問題点を有していた。(Problems to be Solved by the Invention) However, the conventional construction method of joining the post-casting frame after constructing a continuous wall does not allow for: (2) Since the continuous wall piles, wall columns, and beams are eccentric, a large number of shear connectors are required for joining, which not only increases the construction cost but also lengthens the construction period. 3) The joints between post-cast columns and beams and continuous walls are double-invested with concrete, reinforcing bars, etc.
It had various problems such as being uneconomical.
この発明は上記のような種々の問題点を解決す
ることができる工法を提供することを目的とす
る。 The object of the present invention is to provide a construction method that can solve the various problems mentioned above.
(問題点を解決するための手段)
この発明は連続壁の単位壁どうしの接合部にお
いて、先行壁の鉄筋篭の横筋と後行壁の鉄筋篭の
横筋とを一体的に接合する手法を見出した。この
発明はこのような手法に基づくもので、掘削した
第1溝孔に柱用の鉄筋篭を挿入設置したうえ、コ
ンクリートを打設硬化させて柱を構築する工程
と、前記第1溝孔と連続する第2溝孔に梁および
壁用の鉄筋篭を挿入設置して該第2溝孔にコンク
リートを打設硬化させて梁および壁を構築し、さ
らに柱用の鉄筋篭の端部と梁および壁用の鉄筋篭
の端部とを一体的に接合する工程とを備えてなる
ことを特徴とするものである。この発明によれ
ば、連続壁それ自体が柱および梁を形成するの
で、上記問題点は解決される。(Means for Solving the Problems) This invention has discovered a method of integrally joining the horizontal reinforcement of the reinforcing bar cage of the leading wall and the horizontal reinforcement of the reinforcing bar cage of the trailing wall at the joint between unit walls of a continuous wall. Ta. This invention is based on such a method, and includes the steps of inserting and installing a reinforcing bar cage for a column into an excavated first groove, and then constructing a column by pouring and hardening concrete. Reinforcement cages for beams and walls are inserted into the continuous second slots, concrete is poured into the second slots and hardened to construct the beams and walls, and the ends of the reinforcing bar cages for columns and the beams are placed. and a step of integrally joining the ends of the reinforcing bar cage for the wall. According to the present invention, the above-mentioned problem is solved because the continuous wall itself forms columns and beams.
(実施例)
第1図は地中連続壁による地下構造物の平面図
であり、Aは柱となる先行壁、Bは梁および壁と
なる後行壁を示す。(Example) FIG. 1 is a plan view of an underground structure with underground continuous walls, where A shows a leading wall that becomes a column, and B shows a trailing wall that becomes a beam and a wall.
第2図には柱用の鉄筋篭組立体1が示されこの
組立体は1対の仕切板2,2および鉄筋篭3を具
えている。仕切板2は溝孔の巾方向に1対配置さ
れる端部仕切板2a、溝孔の長さ方向に1対配置
される波形の中央仕切板2bとを含み、端部仕切
板2aの中央仕切板2bとの間に断面コ字形の縦
向きに延びるスリーブ4が固着されている。この
スリーブ4は下端が閉鎖し、側部の開口端にフラ
ンジ5が設けられている。20はスリーブ内面に
設けた突条、21はスリーブ4間に固着されたコ
ツタ筋、22はコンクリート漏洩防止シートを示
す。 FIG. 2 shows a reinforcing bar cage assembly 1 for a column, which assembly comprises a pair of partition plates 2, 2 and a reinforcing bar cage 3. As shown in FIG. The partition plate 2 includes a pair of end partition plates 2a arranged in the width direction of the slot, and a pair of corrugated central partition plates 2b arranged in the length direction of the slot. A vertically extending sleeve 4 having a U-shaped cross section is fixed between the partition plate 2b and the partition plate 2b. The sleeve 4 is closed at its lower end and has a flange 5 at its open side end. Reference numeral 20 indicates a protrusion provided on the inner surface of the sleeve, 21 indicates a rib fixed between the sleeves 4, and 22 indicates a concrete leakage prevention sheet.
柱用鉄筋篭3は柱主筋3aの周囲をフープ筋3
bで囲み、内側に梁主筋6を設けて構成され、梁
主筋6の端部はスリーブ4の奥壁に固着されたね
じ式カプラー7に固着されている。上記組立体1
は施工前にあらかじめ組立てられる。 The column reinforcement cage 3 has hoop reinforcements 3 around the column main reinforcement 3a.
b, and a main beam reinforcement 6 is provided inside, and the end of the main beam reinforcement 6 is fixed to a screw type coupler 7 fixed to the back wall of the sleeve 4. Above assembly 1
will be pre-assembled before construction.
施工時において、第2図に示すように安定液を
満たしながら先行溝孔8を掘削し、その際溝孔8
の下部は支持層9まで達するようにする(第5図
参照)。次に溝孔8内に上記柱用鉄筋篭組立体1
を挿入設置し、1対の仕切板2,2間にコンクリ
ートを打設して硬化させ、上部において柱10、
下部において杭11が形成される(第5図参照)。 During construction, as shown in FIG.
The lower part of the support layer 9 is made to reach the support layer 9 (see FIG. 5). Next, insert the reinforcing bar cage assembly 1 for the column into the slot 8.
are inserted and installed, concrete is poured between the pair of partition plates 2, 2 and hardened, and the columns 10,
A pile 11 is formed in the lower part (see Figure 5).
次に先行溝孔8に連続する後行溝孔12を掘削
し、この溝孔12に第3〜5図に示すように梁お
よび壁用の鉄筋篭13を挿入設置する。鉄筋篭1
3は上下部の梁主筋14、それを囲むフープ筋1
5、縦筋16および壁用の横筋17によつて構成
され、鉄筋篭13の挿入時に梁主筋14および横
筋17の端部がスリーブ4にその上部開口から挿
入される。その際、梁主筋14の端部に設けた開
き止め板18がフランジ5に嵌め込まれて該フラ
ンジを拘束する。18aはシール材を示す。 Next, a trailing slot 12 continuous with the leading slot 8 is excavated, and a reinforcing bar cage 13 for beams and walls is inserted into this slot 12 as shown in FIGS. 3 to 5. Rebar cage 1
3 is the upper and lower main beam reinforcement 14, and the hoop reinforcement 1 surrounding it
5. It is composed of vertical reinforcements 16 and horizontal reinforcements 17 for walls, and when the reinforcing bar basket 13 is inserted, the ends of the main beam reinforcement 14 and the horizontal reinforcement 17 are inserted into the sleeve 4 from its upper opening. At this time, the stopper plate 18 provided at the end of the beam main reinforcement 14 is fitted into the flange 5 to restrain the flange. 18a indicates a sealing material.
以上のようにして壁および梁用の鉄筋篭13を
建込んだら、後行溝孔12にコンクリートを打設
して硬化させる。またスリーブ4内は安定液が充
満しているので、高圧水を用いて清掃を兼ねて安
定液と置換し、その後スリーブ4内に高強度無収
縮注入材19を注入し硬化させ、この注入材19
を介して柱用鉄筋篭3の梁主筋6と梁および壁用
鉄篭13の梁主筋14とを一体的に接合し、この
ようにして梁23および壁24を形成する(第5
図参照)。注入材としてセメント系あるいはエポ
キシ系等のもの、例えば(株)日曹マスターズ製マス
ターフオローを使用することができる。 After the reinforcing bar baskets 13 for the walls and beams are erected as described above, concrete is poured into the trailing grooves 12 and hardened. In addition, since the sleeve 4 is filled with stabilizing liquid, high-pressure water is used to clean it and replace it with the stabilizing liquid, and then a high-strength non-shrinkable injection material 19 is injected into the sleeve 4 and hardened. 19
The beam main reinforcements 6 of the column reinforcement cages 3 and the beam main reinforcements 14 of the beam and wall reinforcement cages 13 are integrally joined through the
(see figure). As the injection material, cement-based or epoxy-based materials, such as Master Follow manufactured by Nisso Masters Co., Ltd., can be used.
なお連続壁の内方の地盤を掘削し、柱に接合さ
れる壁と直角方向の中央部の梁主筋は、図示しな
いが柱用の鉄筋篭にあらかじめ取付けたカプラー
を介して該鉄筋篭に接合され、床版筋は曲げ伸ば
しにより接合される。 The ground inside the continuous wall was excavated, and the main beam reinforcement at the center perpendicular to the wall to be connected to the column was connected to the reinforcing bar cage for the column via a coupler that was pre-attached to the reinforcing bar cage (not shown). The slab reinforcements are then joined by bending and stretching.
上記のような連続壁において、該連続壁の長さ
方向に作用する面内せん断力は、波形の中央仕切
板2bの支圧とコツタ筋21とによつて伝達さ
れ、また従来問題となつていた面外せん断力によ
り梁主筋6,14に作用する引張り応力は、スリ
ーブ4、注入材19、カプラー7を介して伝達さ
れ、梁主筋6,14が注入材によつて一体化され
ているので面外せん断力に対して十分に対抗でき
る。 In the continuous wall as described above, the in-plane shear force acting in the longitudinal direction of the continuous wall is transmitted by the bearing pressure of the corrugated central partition plate 2b and the cotter reinforcements 21, which has been a problem in the past. The tensile stress acting on the beam main reinforcements 6, 14 due to the out-of-plane shear force is transmitted via the sleeve 4, the injection material 19, and the coupler 7, and the beam main reinforcements 6, 14 are integrated by the injection material. Can sufficiently resist out-of-plane shear forces.
上記実施例では柱を先行壁、梁および壁を後行
壁としたが、その逆にしてもよい、この場合梁お
よび壁用の鉄筋篭に仕切板およびスリーブを設け
てもよい。仕切板、スリーブおよび注入材等を用
いる鉄筋篭どうしの接合構造は、上記実施例以外
にも従来の連続壁の接合部すなわち単位壁を壁に
のみ使用する場合にも適用できる。 In the above embodiment, the columns are the leading walls, and the beams and walls are the trailing walls, but the reverse may be used. In this case, the reinforcing bars for the beams and walls may be provided with partition plates and sleeves. The structure of connecting reinforcing bar cages using partition plates, sleeves, injection materials, etc. can be applied not only to the above-mentioned embodiments but also to cases where conventional continuous wall joints, that is, unit walls are used only for walls.
(発明の効果)
以上のようにこの発明によれば、連続壁それ自
体によつて柱および梁を形成するので、柱、梁が
壁面から突出することなく、あるいは大巾に減少
させることができ、内部空間を有効に利用でき
る。また杭、柱、梁の中心線が一致するため、部
材間の偏心荷重がなく、簡単な構造となり、また
シヤーコネクターが不要となるので、工費、工期
を低減できる。さらにコンクリート、鉄筋等の二
重投資を避けることが可能となり、経済的であ
る。(Effects of the Invention) As described above, according to the present invention, the columns and beams are formed by the continuous wall itself, so the columns and beams do not protrude from the wall surface or can be reduced in width. , the interior space can be used effectively. In addition, since the center lines of the piles, columns, and beams coincide, there is no eccentric load between the members, resulting in a simple structure, and since shear connectors are not required, construction costs and construction times can be reduced. Furthermore, it is possible to avoid double investment in concrete, reinforcing bars, etc., which is economical.
第1図はこの発明の一実施例を示す全体平面
図、第2図は柱用鉄筋篭組立体の平面図、第3図
は第1図のイ部分の拡大平面図、第4図は同上の
側面図、第5図は全体配筋を示す側面図、第6図
は開き止め板を示す斜視図。
1……柱用鉄筋篭組立体、2……仕切板、3…
…柱用鉄筋篭、4……スリーブ、6……梁主筋、
8……先行溝孔、10……柱、11……杭、12
……後行溝孔、13……梁および壁用鉄筋篭、1
4……梁主筋、19……注入材、23……梁、2
4……壁。
Fig. 1 is an overall plan view showing one embodiment of the present invention, Fig. 2 is a plan view of a reinforcing bar cage assembly for columns, Fig. 3 is an enlarged plan view of part A in Fig. 1, and Fig. 4 is the same as above. FIG. 5 is a side view showing the entire reinforcement arrangement, and FIG. 6 is a perspective view showing the opening stop plate. 1... Rebar cage assembly for pillars, 2... Partition plate, 3...
...Reinforcing bar cage for columns, 4...Sleeve, 6...Beam main reinforcement,
8... Leading trench, 10... Pillar, 11... Pile, 12
... Trailing groove, 13 ... Rebar cage for beams and walls, 1
4... Beam main reinforcement, 19... Injection material, 23... Beam, 2
4...Wall.
Claims (1)
したうえ、コンクリートを打設硬化させて柱を構
築する工程と、前記第1溝孔と連続する第2溝孔
に梁および壁用の鉄筋篭を挿入設置して該第2溝
孔にコンクリートを打設硬化させて梁および壁を
構築し、さらに柱用の鉄筋篭の端部と梁および壁
用の鉄筋篭の端部とを一体的に接合する工程とを
備えてなることを特徴とする地中連続壁による地
下構造物の構築方法。1. A process of inserting and installing reinforcing bar cages for columns into the excavated first groove, and then pouring and hardening concrete to construct columns, and installing reinforcement cages for beams and walls into second grooves that are continuous with the first groove. Reinforcement cages are inserted and installed, and concrete is cast and hardened in the second groove to construct beams and walls, and the ends of the reinforcing bar cages for columns and the ends of the reinforcing bar cages for beams and walls are connected. A method for constructing an underground structure using an underground continuous wall, comprising the step of integrally joining the wall.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13618387A JPS63300111A (en) | 1987-05-30 | 1987-05-30 | Construction of underground structure by underground continuous wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13618387A JPS63300111A (en) | 1987-05-30 | 1987-05-30 | Construction of underground structure by underground continuous wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63300111A JPS63300111A (en) | 1988-12-07 |
| JPH0432170B2 true JPH0432170B2 (en) | 1992-05-28 |
Family
ID=15169284
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13618387A Granted JPS63300111A (en) | 1987-05-30 | 1987-05-30 | Construction of underground structure by underground continuous wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS63300111A (en) |
-
1987
- 1987-05-30 JP JP13618387A patent/JPS63300111A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63300111A (en) | 1988-12-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
| JP2004027609A (en) | Construction method of underground structure and underground structure | |
| JP2009046829A (en) | Seismic reinforcement wall | |
| JP3929006B2 (en) | Construction method for expanded seismic walls | |
| JPS61122320A (en) | Method of coupling continuous underground wall with underground structure | |
| JPH10252187A (en) | Seismic structure of building structure and its construction method | |
| JPH0480444A (en) | Connection unit of reinforced concrete pole and steel framed beam | |
| KR102482690B1 (en) | Bridge foundation construction method using formwork integrated PC panels | |
| JPS63300111A (en) | Construction of underground structure by underground continuous wall | |
| JP2579120B2 (en) | garage | |
| JP2001146756A (en) | Earth retaining wall / RC composite structure | |
| JP2002081058A (en) | Joining structure between wall body and sheet pile member | |
| JP3114141B2 (en) | Basement | |
| JPH0432171B2 (en) | ||
| JPH116162A (en) | Construction method for reinforced concrete underground external wall | |
| JPH11181807A (en) | Construction method for underground story | |
| JP7610953B2 (en) | Beam and slab joint structure | |
| JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
| JP2922731B2 (en) | How to connect slabs and concrete columns | |
| JPS6322216Y2 (en) | ||
| JPH09256515A (en) | Precast wall slab and constructing method of building using the wall slab | |
| JP2002206238A (en) | Coupling tool for strut in strut earth-retaining method | |
| JPS6343239Y2 (en) | ||
| KR102482691B1 (en) | Foundation structures using strut-tie reinforcement and its construction method | |
| JP2671754B2 (en) | Construction method of steel reinforced concrete structure |