JPH0442495B2 - - Google Patents

Info

Publication number
JPH0442495B2
JPH0442495B2 JP1514888A JP1514888A JPH0442495B2 JP H0442495 B2 JPH0442495 B2 JP H0442495B2 JP 1514888 A JP1514888 A JP 1514888A JP 1514888 A JP1514888 A JP 1514888A JP H0442495 B2 JPH0442495 B2 JP H0442495B2
Authority
JP
Japan
Prior art keywords
water
sheet
trench
shielding
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1514888A
Other languages
Japanese (ja)
Other versions
JPH01190819A (en
Inventor
Tadashi Yoshikawa
Mine Ishizaka
Yoshiaki Ikeuchi
Noboru Sakata
Tetsuo Kuramasu
Nariaki Shimazu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Ube Corp
Original Assignee
Kajima Corp
Ube Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Ube Industries Ltd filed Critical Kajima Corp
Priority to JP1514888A priority Critical patent/JPH01190819A/en
Publication of JPH01190819A publication Critical patent/JPH01190819A/en
Publication of JPH0442495B2 publication Critical patent/JPH0442495B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は地中連続遮水壁の施工法に関するも
のである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a construction method for an underground continuous impermeable wall.

〔この発明が解決すべき問題点〕[Problems to be solved by this invention]

地下構造物を施工中の地下水の湧水を防ぎ、或
いはダム工事における地下水の止水等を目的とし
て地中連続壁を構築するか、シートパイルを打設
してジヨイント部に注入を行う等の工法が採用さ
れている。
To prevent groundwater from springing up during construction of underground structures, or to stop groundwater during dam construction, it is necessary to construct an underground continuous wall, or to pour sheet piles into joints. construction method has been adopted.

これら従来の工法を止水のみを目的として構築
する場合、以下のような問題がある。
When these conventional construction methods are used for construction purposes only to stop water, the following problems arise.

(イ) 地中連続壁は必要以上の壁厚を施工するのが
通常であり、施工が不必要に大がかりとなると
ともに余分なコンクリートを大量に使用して施
工費が高価である。
(b) Underground walls are usually constructed with a wall thickness greater than necessary, making the construction unnecessarily large-scale and requiring a large amount of excess concrete, resulting in high construction costs.

(ロ) シートパイルを打設してジヨイント部に注入
を行う工法も同じく施工が大がかりであり、材
料費が高価である。
(b) The construction method of driving sheet piles and pouring into the joints also requires extensive construction and is expensive in material cost.

(ハ) 地中連続壁において施工費を安価にするため
に壁厚を薄く造ることも考えられるが、狭巾の
溝を掘削し得る機械もなく、例え狭巾の溝が掘
れたとしてもコンクリートの流動性が損われて
均質な地中壁は完成できない。
(c) It is possible to build thinner underground continuous walls to reduce construction costs, but there are no machines that can excavate narrow trenches, and even if a narrow trench could be dug, the wall thickness would be reduced. A homogeneous underground wall cannot be completed due to the loss of fluidity.

(ニ) また止水の確実性及び信頼性の点で見れば、
コンクリート壁は地震時のクラツクが止水性を
損わせ、プレキヤストコンクリートパネルやシ
ートパイルを使用した工法ではジヨイント部に
夾雑物、ベントナイト等を挟み込み充分な止水
性能を得ることができなかつた。
(d) Also, from the point of view of water stoppage certainty and reliability,
Cracks during earthquakes impair the water-stopping properties of concrete walls, and construction methods using precast concrete panels or sheet piles were unable to obtain sufficient water-stopping performance due to contaminants, bentonite, etc. being trapped in the joints.

この発明は、施工が容易であつて施工費が安
価となり、且つ止水の確実性、信頼性の高い遮
水壁を構築可能な地中連続遮水工法を提供する
ことを目的とする。
An object of the present invention is to provide an underground continuous water-blocking construction method that is easy to construct, has low construction costs, and can construct a water-blocking wall that is highly reliable and reliable.

〔問題点を解決するための手段〕[Means for solving problems]

この発明にかかる地中連続遮水壁の施工法は、
左右に隣り合う遮水シートを繋ぎシートによつて
連続させ、溝を巾方向左右に仕切るものである。
The method of constructing an underground continuous impermeable wall according to this invention is as follows:
Adjacent water-shielding sheets on the left and right are connected by a connecting sheet, and the grooves are partitioned into left and right sides in the width direction.

地盤に溝を掘削する。左右端部の少なくともい
ずれか一方の端部の上下方向に連続して接着部を
設けた遮水シートを隣り合わせて溝内に吊り降ろ
す。この隣り合う遮水シート間に両端部の上下方
向に連続して接着部を設けた繋ぎシートを配設す
る。溝内に配設したパツカーを膨らませて遮水シ
ートと繋ぎシートの接着部を圧着して連結した遮
水シートによつて溝内を巾方向左右に仕切るよう
にする。この遮水シートを内蔵した遮水壁を溝内
にて構築する。
Dig a trench in the ground. Water-shielding sheets, each having an adhesive portion continuously provided in the vertical direction on at least one of the right and left ends, are suspended into the groove so as to be adjacent to each other. A connecting sheet is provided between the adjacent water-shielding sheets, with adhesive portions provided continuously in the vertical direction at both ends. The inside of the groove is partitioned into right and left sides in the width direction by the connected water-shielding sheets by inflating a pack car arranged in the groove and pressing the adhesive parts of the water-shielding sheet and the connecting sheet. A water-shielding wall incorporating this water-shielding sheet will be constructed inside the trench.

〔実施例〕〔Example〕

以下、図に示す一実施例に基づきこの発明を詳
細に説明する。
Hereinafter, the present invention will be explained in detail based on an embodiment shown in the drawings.

(1) 溝掘削 地盤に溝1を不透水層まで掘削する。溝1は広
巾でなくともよく、その分施工が容易となる。溝
1の掘削には安定液である泥水を充填しながら行
う。地盤が良好で崩壊の可能性が低い場合には無
水で掘削を行う。
(1) Trench excavation A trench 1 is excavated in the ground up to the impermeable layer. The groove 1 does not have to be wide, which makes construction easier. Trench 1 is excavated while being filled with muddy water, which is a stabilizing liquid. If the ground is good and the possibility of collapse is low, excavation will be carried out without water.

(2) 遮水シート 遮水シート2としてはポリエチレンシートや、
ゴムアスフアルト防水シート等が採用できる。遮
水シート2の下端には全長に棒状の重り材3が取
付けられている。遮水シート2は複数枚順次前記
1内に配設するものであつて、先行して配設する
遮水シート2の一表面の左右両側端部には上下方
向に連続する接着部4が設けられている。
(2) Water-shielding sheet The water-shielding sheet 2 is a polyethylene sheet,
Rubber asphalt waterproof sheets, etc. can be used. A bar-shaped weight member 3 is attached to the lower end of the water-shielding sheet 2 along its entire length. A plurality of water-shielding sheets 2 are arranged one after another in the above-mentioned 1, and adhesive parts 4 that are continuous in the vertical direction are provided at both left and right end portions of one surface of the water-shielding sheet 2 that is arranged in advance. It is being

接着部4を構成する接着剤としては、少なくと
もアスフアルトとゴム物質とを含む配合物であつ
て、軟化温度が60℃以上、針入度が60〜400、好
ましくは150〜300である変性アスフアルトが好適
である。
The adhesive constituting the adhesive part 4 is modified asphalt, which is a compound containing at least asphalt and a rubber substance, and has a softening temperature of 60°C or higher and a penetration of 60 to 400, preferably 150 to 300. suitable.

(3) 遮水シート配設 遮水シート2は地上に配設したロール5から繰
り出して溝1内に沈下する。遮水シート2は複数
枚を隣り合わせて溝1の長手(深さ)方向に配設
する。
(3) Arranging the water-shielding sheet The water-shielding sheet 2 is rolled out from the roll 5 placed on the ground and sinks into the groove 1. A plurality of water shielding sheets 2 are arranged next to each other in the longitudinal (depth) direction of the groove 1.

(4) 繋ぎシート配設 繋ぎシート6もポリエチレンシートやゴムアス
フアルト防水シート等が採用できる。繋ぎシート
6は巾遮水シート2と同様なシートであつて、下
端に重り材3が取付けられている。また繋ぎシー
ト6の一表面の左右両端部にも上下方向に連続す
る接着部4,4が設けられている。
(4) Arrangement of connecting sheet The connecting sheet 6 can also be made of polyethylene sheet, rubber asphalt waterproof sheet, etc. The connecting sheet 6 is a sheet similar to the width water-shielding sheet 2, and has a weight member 3 attached to its lower end. Adhesive portions 4, 4 that are continuous in the vertical direction are also provided at both left and right ends of one surface of the connecting sheet 6.

この繋ぎシート6をやはり地上に載せたロール
7から引出して、溝1内に沈下する。繋ぎシート
6は横方向に隣り合う遮水シート2,2間の隙間
に対向して配設し、遮水シート2,2間の端部の
接着部4,4と繋ぎシート6の左右両端部の接着
部4,4を向き合せる。
This connecting sheet 6 is pulled out from a roll 7 which is also placed on the ground and is lowered into the groove 1. The connecting sheet 6 is disposed to face the gap between the water-blocking sheets 2, 2 adjacent to each other in the horizontal direction, and the bonded portions 4, 4 at the ends between the water-blocking sheets 2, 2 and both left and right ends of the connecting sheet 6 are connected to each other. The adhesive parts 4, 4 of the two are faced to each other.

(5) パツカー沈下 溝1内にパツカー8を沈下する。パツカー8は
ポリエチレンシート等によつて長尺の袋状に形成
したものであつて、長尺の補強材9に沿わせて、
この補強材9とともに溝1内に沈設する。パツカ
ー8,8は繋ぎシート6の左右両端部に対応する
位置に配設する。
(5) Patsucar sinking Patsucar 8 is lowered into trench 1. The packer 8 is formed into a long bag shape from polyethylene sheet or the like, and is placed along the long reinforcing material 9.
This reinforcing material 9 is sunk into the groove 1. The packers 8, 8 are arranged at positions corresponding to both left and right ends of the connecting sheet 6.

(6) 遮水シートの繋ぎ 以上のような状態でパツカー8,8内に水や空
気を注入してパツカー8,8を膨張させる。パツ
カー8,8が膨張して繋ぎシート6の左右両端部
の接着部6,6を遮水シート2,2の接着部6,
6に圧着し、接着させる。このようにして遮水シ
ート2,2を繋ぎシート6によつて連続させ、溝
1内を巾方向左右に仕切る。
(6) Connecting the water-shielding sheets In the above state, water and air are injected into the pack cars 8, 8 to inflate them. The packers 8, 8 expand and connect the adhesive parts 6, 6 of the left and right ends of the connecting sheet 6 to the adhesive parts 6, 6 of the water-blocking sheets 2, 2,
6 and adhere. In this way, the water-blocking sheets 2, 2 are connected by the connecting sheet 6, and the inside of the groove 1 is partitioned into left and right sides in the width direction.

(7) 間詰め 溝1の泥水内にモルタル、コンクリート等の硬
化材を注入して泥水を固化し、遮水壁を構築す
る。
(7) Filling Inject hardening materials such as mortar and concrete into the muddy water in trench 1 to solidify the muddy water and construct an impermeable wall.

地盤が竪固な場合は無水により掘削するが、こ
の場合はソイルモルタルを溝1内に打設して硬化
する。
If the ground is vertical and hard, excavation is performed without water, but in this case, soil mortar is poured into the trench 1 and hardened.

遮水が目的である為、いずれの場合も遮水シー
トを押える間詰め材として、ジン性のある、低強
度の材料でよい。
Since the purpose is to block water, in either case, a low-strength material with strong properties can be used as a filler to hold down the water-blocking sheet.

〔発明の効果〕〔Effect of the invention〕

この発明は以上のような構成を有し、以下のよ
うな効果を得ることができる。
The present invention has the above configuration and can obtain the following effects.

(イ) 溝を掘削し、遮水シートを配設し、泥水を固
化するだけであるため、施工が容易となり、大
がかりな施工は不要で施工費は安価となる。
(b) Construction is easy because it only involves digging a trench, placing a water-blocking sheet, and solidifying the muddy water, and there is no need for large-scale construction, making the construction cost low.

(ロ) 完成した遮水壁は内側に遮水シートを挟み込
むため、地震等によるクラツクが発生しても止
水性が損われることがなく、確実性、信頼性が
高くなる。
(b) Since the completed water-shielding wall has a water-shielding sheet sandwiched inside, its water-stopping properties will not be impaired even if cracks occur due to earthquakes, etc., making it more reliable and reliable.

(ハ) 泥水を固化、あるいはソイルモルタルを充填
して構築するため、地中壁全体を均一な地中壁
とすることができる。また例え強度の低下する
部分が生じても上記のように遮水シートによつ
て止水性は確保される。
(c) Because it is constructed by solidifying muddy water or filling it with soil mortar, the entire underground wall can be made into a uniform underground wall. Furthermore, even if there is a portion where the strength is reduced, water-stopping properties are ensured by the water-blocking sheet as described above.

(ニ) 遮水シート端部に接着部を設けておき、隣り
合う遮水シート間の隙間に対応して左右両端部
に接着部を設けた繋ぎシートを配設し、溝内に
配設したパツカーを膨らませて接着部を圧着し
溝内に連続的に配設するものである。従つて、
遮水シートの溝内への配設が容易であり、施工
が容易である。
(d) Adhesive parts were provided at the ends of the water-shielding sheets, and connecting sheets with adhesive parts at both left and right ends were placed in correspondence with the gaps between adjacent water-shielding sheets, and the sheets were placed in the grooves. The packer is inflated and the adhesive portion is pressed and placed continuously in the groove. Therefore,
The water-blocking sheet can be easily placed in the groove, and construction is easy.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第5図はこの発明の施工順序平面図、
第6図〜第9図はこの発明の施工順序断面図であ
る。 1……溝、2……遮水シート、3……重り材、
4……接着部、5……ロール、6……繋ぎシー
ト、7……ロール、8……パツカー、9……補強
材。
Figures 1 to 5 are plan views of the construction sequence of this invention;
6 to 9 are sectional views showing the construction sequence of the present invention. 1...Groove, 2...Waterproof sheet, 3...Weight material,
4... Adhesive part, 5... Roll, 6... Connecting sheet, 7... Roll, 8... Packer, 9... Reinforcement material.

Claims (1)

【特許請求の範囲】[Claims] 1 地盤に溝を掘削し、左右端部の少なくともい
ずれか一方の端部の上下方向に連続して接着部を
設けた遮水シートを隣り合わせて溝内に吊り降
し、この隣り合う遮水シート間に両端部の上下方
向に連続して接着部を設けた繋ぎシートを配設
し、溝内に配設したパツカーを膨らませて遮水シ
ートと繋ぎシートの接着部を圧着して連結した遮
水シートによつて溝内を巾方向左右に仕切るよう
にし、この遮水シートを内蔵した遮水壁を溝内に
て構築して成ることを特徴とする地中連続遮水壁
の施工法。
1. A trench is excavated in the ground, and water-shielding sheets with continuous adhesive parts provided in the vertical direction on at least one of the left and right ends are suspended into the groove next to each other, and the adjacent water-shielding sheets are A connecting sheet with a continuous adhesive section in the vertical direction on both ends is placed in between, and a patch car placed in the groove is inflated to connect the waterproof sheet and the adhesive section of the connecting sheet by pressing and bonding. A construction method for an underground continuous impermeable wall characterized by partitioning the inside of the trench from side to side in the width direction with a sheet, and constructing an impermeable wall containing the impermeable sheet inside the trench.
JP1514888A 1988-01-26 1988-01-26 Method for constructing under-ground continuous impervious wall Granted JPH01190819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1514888A JPH01190819A (en) 1988-01-26 1988-01-26 Method for constructing under-ground continuous impervious wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1514888A JPH01190819A (en) 1988-01-26 1988-01-26 Method for constructing under-ground continuous impervious wall

Publications (2)

Publication Number Publication Date
JPH01190819A JPH01190819A (en) 1989-07-31
JPH0442495B2 true JPH0442495B2 (en) 1992-07-13

Family

ID=11880719

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1514888A Granted JPH01190819A (en) 1988-01-26 1988-01-26 Method for constructing under-ground continuous impervious wall

Country Status (1)

Country Link
JP (1) JPH01190819A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010242318A (en) * 2009-04-01 2010-10-28 Ohbayashi Corp Placing joint implement, and method for constructing placing joint portion of underground wall

Also Published As

Publication number Publication date
JPH01190819A (en) 1989-07-31

Similar Documents

Publication Publication Date Title
US4741644A (en) Environmental cut-off and drain
CN103958780B (en) Methods of forming cemented retaining walls
US5106233A (en) Hazardous waste containment system
US5240348A (en) Methods of hazardous waste containment
KR102153902B1 (en) Slurry wall, construction method for the same and wire mesh assembly
IT8419864A1 (en) METHOD AND APPARATUS FOR THE CONSTRUCTION OF REINFORCED CONCRETE WALLS IN THE GROUND
CA1185441A (en) Process of forming a continuous wall in the ground
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
JP2004204581A (en) Water-blocking method for managed revetment
JPH0442495B2 (en)
JPH11217824A (en) Execution method of underground impervious wall
CN212130501U (en) Foam concrete transition structure for bridge-tunnel connection in high and steep terrain
JPS63304821A (en) Construction work of underground continuous cut-off wall
JPH01235715A (en) Underground continuous impermeable wall method
JP2764482B2 (en) Construction method of large depth human hole
KR20210119710A (en) Slurry wall, construction method for the same and wire mesh assembly
CN116988484B (en) Water-blocking support structure and construction method in water-rich soft soil area
CN120401540B (en) Flexible composite impermeable thin wall system and construction method thereof
JP4081659B2 (en) Impervious plate, connection structure of impermeable plate, and construction method of impermeable wall
JPH0786229B2 (en) Impermeable wall using impermeable sheet, construction method thereof, and impermeable sheet used for impermeable wall
JP3424117B2 (en) Construction method of continuous underground wall
JPS6313487B2 (en)
JPS63308112A (en) Construction of underground continuous cut-off wall
JPH0122410B2 (en)
JP3023236B2 (en) How to construct a suspended water wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees