JPH0445628B2 - - Google Patents
Info
- Publication number
- JPH0445628B2 JPH0445628B2 JP58102387A JP10238783A JPH0445628B2 JP H0445628 B2 JPH0445628 B2 JP H0445628B2 JP 58102387 A JP58102387 A JP 58102387A JP 10238783 A JP10238783 A JP 10238783A JP H0445628 B2 JPH0445628 B2 JP H0445628B2
- Authority
- JP
- Japan
- Prior art keywords
- gondola
- rail
- work
- hoist
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Movable Scaffolding (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
本発明は鉄骨鉄筋コンクリート構造物の鉄骨工
事、配筋工事、型枠工事、仕上げ工事を全て一つ
の機構で連続的に行える建築工事方法に関するも
のである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method that can continuously perform steel frame work, reinforcement work, formwork work, and finishing work for a steel-framed reinforced concrete structure using one mechanism.
一般に鉄骨鉄筋コンクリート構造物、例えば高
層ビルデイングでは多数の鉄骨支柱を起立し、鉄
骨支柱間には水平方向の鉄骨梁を縦横に架設し、
支柱まわりと鉄骨梁まわりには配筋を行ない、又
鉄骨梁と配筋まわりにはコンクリートを打設して
壁及び床の躯体を成型し、この躯体成形時にはコ
ンクリート打設用の型枠を組み立て、更にコンク
リートがかたまつた後に型枠の解体及びコンクリ
ートの仕上げ工事を行つている。 Generally, in steel reinforced concrete structures, such as high-rise buildings, a large number of steel columns are erected, and horizontal steel beams are erected vertically and horizontally between the steel columns.
Reinforcement is placed around the pillars and steel beams, and concrete is poured around the steel beams and reinforcement to form the framework of walls and floors. When forming this framework, formwork for pouring concrete is assembled. After the concrete has hardened, the formwork is dismantled and concrete finishing work is carried out.
従来上記の工事を行なう場合には鉄骨工事用の
足場と、配筋、型枠の組立及び解体及び仕上げ用
の枠組足場が必要であり、支柱を順次上方に組み
付け、又躯体が上方に成形されて工事位置が高層
になるにつれて上記の足場もその都度上方に組み
立てられて行き、最上段の工事が終了した後には
これらの足場を順次解体している。この為に少な
くともビルデイングの骨組の周囲と高さに応じた
多数の枠組足場等を用意し、これらを組立、解体
しなければならないからその組立、解体作業が大
変であり、時間ががかかり、作業能率が著しく低
下する原因となつている。 Conventionally, when carrying out the above construction, scaffolding for steel construction and framework scaffolding for reinforcing, assembling and dismantling formwork, and finishing were required. As the construction site becomes higher up, the above-mentioned scaffolds are also erected upward each time, and these scaffolds are dismantled one after another after the construction on the top level is completed. For this purpose, it is necessary to prepare a large number of framework scaffolds, etc., at least according to the circumference and height of the building frame, and to assemble and dismantle these, making the assembly and dismantling work difficult, time-consuming, and This causes a significant drop in efficiency.
又部品点数が多いから経済性が悪く、地表から
相当高い位置で組立、解体作業を行う為に危険が
伴ない、これを防止する為の手段を併設しなけれ
ばならないという問題も有している。 In addition, it is not economical due to the large number of parts, and the assembly and disassembly work is carried out at a considerable height above the ground, which is dangerous, and there is also the problem that measures must be installed to prevent this. .
更に足場を上方で組立、解体する場合、一部に
はクレーン等の重機類が必要となるであろうし、
人為作業となるため、多数の小型の部材を用意し
なければならず、その組立、解体作業の能率も著
しく低下する。 Furthermore, when assembling and dismantling the scaffolding above, heavy machinery such as cranes will be required in some cases.
Since this is a manual operation, a large number of small members must be prepared, and the efficiency of assembly and disassembly work is significantly reduced.
従つて本発明の目的はユニツトレールに配設し
たゴンドラ装置とホイスト装置とからなる一つの
機構により鉄骨工事、配筋工事、型枠の組立及び
解体工事、コンクリート等の仕上げ工事等を全て
連続して行なうことによつて、クレーン等の稼動
率と、作業能率を著しく向上させ、部品点数が少
なく、経済性にすぐれ、工事の安全性が図れ、大
型のパネル等の部材でも一度に且つ簡単に搬送で
きる建築工事方法を提供することである。 Therefore, the object of the present invention is to continuously carry out all of steel construction, reinforcement work, formwork assembly and dismantling work, concrete finishing work, etc. using a single mechanism consisting of a gondola device and a hoist device arranged on a unit rail. By doing this, the operating rate of cranes, etc. and work efficiency are significantly improved, the number of parts is small, it is economical, construction safety is ensured, and even parts such as large panels can be easily processed at once. The purpose is to provide a construction method that allows transportation.
本発明はこの目的達成の為、任意の長さの足場
ゴンドラ用レールと荷役用ホイストレールとを二
つのブラケツト間に相対向して平行に結合させて
ユニツトレールを構成し、当該ユニツトレールを
多数、クレーンにより組立てられた鉄骨柱、鉄骨
梁からなる骨組の任意の位置に結合させ、足場ゴ
ンドラ用レールと荷役用ホイストレールとにそれ
ぞれ上下移動自在なゴンドラを備えたゴンドラ装
置と上下移動自在なフツクを備えたホイスト装置
とを水平方向走行自在に配設し、ゴンドラ装置と
ホイスト装置とを協働させて鉄骨工事、配筋工
事、型枠の組立及び解体工事、仕上工事等を全て
連続して行ない、且つユニツトレールとこれに配
設したゴンドラ装置とホイスト装置とを鉄骨柱の
組立てに応じて順次上方に盛替えることを特徴と
するものである。 In order to achieve this objective, the present invention constructs a unit rail by connecting a scaffold gondola rail of arbitrary length and a cargo hoist rail in parallel between two brackets, and connects a large number of the unit rails. , a gondola device that is connected to any position of a frame consisting of steel columns and steel beams assembled by a crane, and has gondolas that can be moved up and down on the scaffolding gondola rail and hoist rail for cargo handling, respectively, and a hook that can be moved up and down. A hoist device equipped with In addition, the unit rail and the gondola device and hoist device arranged thereon are sequentially rearranged upward in accordance with the assembly of the steel column.
以下本発明の実施の態様を図面について説明す
る。 Embodiments of the present invention will be described below with reference to the drawings.
第1図に示すように、地上に最下段の鉄骨柱
C1を多数起立し、この鉄骨柱C1に対して、鉄骨
柱C2をクレーンで引き上げ、鉄骨柱C1の上端と
鉄骨柱C2の下端とを仮止めする。実施例では鉄
骨柱C2とC3は一体な柱となつている。同様に上
方の鉄骨柱C4,C5,C6…Coもクレーンで引き上
げて仮止めして起立させる。他方クレーンで鉄骨
梁B1,B1を引き上げ、鉄骨梁B1の両端を鉄骨柱
C1とC1との間に仮止めする。同様に鉄骨梁B2,
B3…Boもクレーンで引き上げて鉄骨柱C2とC2の
間、C3とC3、CoとCoの間に順次仮止めし、構造
物たるビルデイングの骨組Aを構築する。 As shown in Figure 1, the lowest steel column is placed on the ground.
A large number of steel columns C 1 are erected, and a crane is used to lift the steel column C 2 to the steel column C 1 , and the upper end of the steel column C 1 and the lower end of the steel column C 2 are temporarily fixed. In the embodiment, steel columns C 2 and C 3 are integral columns. Similarly, the upper steel columns C 4 , C 5 , C 6 . On the other hand, lift up steel beams B 1 and B 1 with a crane, and connect both ends of steel beam B 1 to steel columns.
Temporarily fasten between C 1 and C 1 . Similarly, steel beam B 2 ,
B3 ... Bo is also lifted up by a crane and temporarily fixed between steel columns C2 and C2 , between C3 and C3 , and between Co and Co , to construct the frame A of the building, which is a structure.
上記の状態で、例えば鉄骨柱C3と鉄骨梁B3の
外側にユニツトレール1を固定し、このユニツト
レール1にゴンドラ装置3とホイスト装置5を横
方向走行自在に配設させ、ゴンドラ装置3とホイ
スト装置5とで鉄骨梁3より下方の位置における
主として外まわりの工事を協働して行なう。 In the above state, for example, the unit rail 1 is fixed to the outside of the steel column C 3 and the steel beam B 3 , and the gondola device 3 and the hoist device 5 are disposed on this unit rail 1 so as to be able to move laterally. The hoist device 5 and the hoist device 5 work together to carry out construction mainly around the outside at a position below the steel beam 3.
例えば、ゴンドラ装置3が備えている上下移動
自在なゴンドラ3cでは鉄骨柱C1とC2との間の
本締め作業、鉄骨柱C1と鉄骨梁B1との間の本締
め作業、鉄骨柱C1の配筋作業、床の配筋作業、
鉄骨柱C1の型枠工事、鉄骨梁B1の型枠工事、壁
や床の型枠工事等の一連の作業を行なう。 For example, in the gondola 3c that is included in the gondola device 3 and can move up and down, the final tightening work is performed between the steel columns C 1 and C 2 , the final tightening work is performed between the steel column C 1 and the steel beam B 1 , and the final tightening work is performed between the steel columns C 1 and the steel beam B 1. C 1 reinforcement work, floor reinforcement work,
A series of work will be carried out, including formwork work for steel column C 1 , formwork work for steel beam B 1 , and formwork work for walls and floors.
ホイスト装置5では、この装置が備えた上下移
動自在なフツク5cを利用して上記作業に必要な
鉄筋の引き上げ、型枠パネルの引き上げ等の作業
を行なう。 The hoist device 5 uses a vertically movable hook 5c included in the hoist device to carry out operations such as lifting reinforcing bars and formwork panels necessary for the above-mentioned operations.
コンクリートが打設されて柱、梁、壁、床の躯
体が成形されるとゴンドラ3cで型枠パネルの解
体、コンクリートの仕上げ作業を行ない、ホイス
ト装置5のフツク5cで解体された型枠パネルを
次の作業位置に移送する。 Once the concrete has been poured and the framework of columns, beams, walls, and floors have been formed, the gondola 3c dismantles the formwork panels and finishes the concrete, and the hook 5c of the hoist 5 removes the dismantled formwork panels. Transfer to next working position.
更に躯体が成形された後にはパネル等の外壁材
料、シーリング材等をフツク5cで引き上げ、ゴ
ンドラ3cで外壁作業、シーリング作業、仕上げ
作業等を行なう。上記の工事、作業が終ると、ユ
ニツトレール1を上方に盛替え、上記の作業位置
より上方の工事、作業を順次行なう。 Furthermore, after the frame is formed, external wall materials such as panels, sealing materials, etc. are pulled up using hooks 5c, and external wall work, sealing work, finishing work, etc. are performed using gondola 3c. When the above-mentioned construction work is completed, the unit rail 1 is moved upward, and the construction work above the above-mentioned work position is carried out in sequence.
ゴンドラ装置3とホイスト装置5の構造につい
て更に詳しく述べる。 The structures of the gondola device 3 and hoist device 5 will be described in more detail.
第1図、第2図及び第3図、第4図に示すよう
に鉄骨柱C1,C2…Coをクレーンを利用して起立
させた状態に於て、例えば3階に位置する各鉄骨
柱C3の上部に外方に突出する水平ブラケツト1
aの基端を固定させ、このブラケツト1aの下部
にはビルデイングの骨組Aの周囲に沿つてユニツ
ト化された平行な二本の足場ゴンドラ用レール1
bと荷役用ホイストレール1cを固定する。 As shown in Figures 1, 2, 3, and 4, when the steel columns C 1 , C 2 . . . Horizontal bracket 1 protruding outward from the top of steel column C 3
The base end of the bracket 1a is fixed, and two parallel scaffolding gondola rails 1 are unitized along the periphery of the building frame A at the bottom of the bracket 1a.
b and the cargo handling hoist rail 1c.
ブラケツト1aは鉄骨柱C3或いは鉄骨梁B3に
対して着脱自在にボルト等で固定しているが、溶
接等で固定してもよい。 The bracket 1a is detachably fixed to the steel column C3 or the steel beam B3 with bolts or the like, but it may also be fixed by welding or the like.
足場ゴンドラ用レール1bと荷役用ホイストレ
ール1cとは二つのブラケツト1a,1a間に相
対向して平行に結合させてユニツトレール1を構
成させている。 A scaffolding gondola rail 1b and a cargo handling hoist rail 1c are connected in parallel between two brackets 1a, 1a facing each other to form a unit rail 1.
即ち、足場ゴンドラ用レール1bと荷役用ホイ
ストレール1cは長手方向に沿つて非常に長いも
のであり、重量も嵩むために、ブラケツト1aと
足場ゴンドラ用レール1bと荷役用ホイストレー
ル1cとを組合せたユニツトレール1を連続的に
組み付けることによつて重量の軽量化を図り、作
業性の向上を図るものである。 That is, since the scaffolding gondola rail 1b and the cargo handling hoist rail 1c are very long in the longitudinal direction and are heavy, a unit rail that is a combination of the bracket 1a, the scaffolding gondola rail 1b, and the cargo handling hoist rail 1c is used. By assembling 1 continuously, weight is reduced and workability is improved.
この場合、相対向する二つの鉄骨柱C3とC3間
の間隔に等しい足場ゴンドラ用レール1bと荷役
用ホイストレール1cを平行に並べ、これらの足
場ゴンドラ用レール1bと荷役用ホイストレール
1cの両端部付近を二本のブラケツト1aの下部
に固定してユニツトレール1を形成し、このユニ
ツトレール1をビルデイングの骨組Aの周囲に固
定して連続したレールとするものである。(第3
図)
足場ゴンドラ用レール1bにはゴンドラ装置3
が水平方向走行自在に配設されている。荷役用ホ
イストレール1bにはホイスト装置5が水平方向
走行自在に配設されている。ゴンドラ装置3は上
下移動自在なゴンドラ3cを備え、ホイスト装置
5は上下移動自在なフツク5cを備えている。 In this case, the scaffolding gondola rail 1b and cargo handling hoist rail 1c are arranged in parallel with the same distance between the two opposing steel columns C3 and C3 , and the scaffolding gondola rail 1b and cargo handling hoist rail 1c are A unit rail 1 is formed by fixing the vicinity of both ends to the lower parts of two brackets 1a, and this unit rail 1 is fixed around a building frame A to form a continuous rail. (3rd
Figure) The gondola device 3 is installed on the scaffolding gondola rail 1b.
are arranged so that they can move freely in the horizontal direction. A hoist device 5 is disposed on the cargo handling hoist rail 1b so as to be movable in the horizontal direction. The gondola device 3 includes a gondola 3c that is vertically movable, and the hoist device 5 includes a hook 5c that is vertically movable.
足場ゴンドラ用レール1bには自走車輪2aを
介してゴンドラ走行装置2が走行自在に結合さ
れ、このゴンドラ走行装置2にはモータ2bを搭
載しており、ゴンドラ3cからの遠隔操作でこの
モータ2bを駆動し、一方向に走行させるように
なつている。 A gondola traveling device 2 is connected to the scaffolding gondola rail 1b via self-propelled wheels 2a in a freely movable manner, and this gondola traveling device 2 is equipped with a motor 2b, and the motor 2b is operated by remote control from the gondola 3c. It is designed to drive the vehicle and run in one direction.
ゴンドラ走行装置2の下部にはワイヤ3aが吊
り下げられ、このワイヤ3aの下部はゴンドラ3
cに装備されたウインチ3bと接続し、ゴンドラ
3c上でウインチ3bを駆動するとワイヤ3aが
巻かれ、又は巻き戻されてゴンドラ3cが作業位
置に沿つて昇降するようになつている。 A wire 3a is suspended from the lower part of the gondola traveling device 2, and the lower part of the wire 3a is connected to the gondola 3.
When the winch 3b is driven on the gondola 3c, the wire 3a is wound or unwound so that the gondola 3c moves up and down along the working position.
同じくホイスト装置5は自走車輪4aと荷上用
巻上部材5aとを有し、荷役用ホイストレール1
cには自走車輪4aを介してホイスト走行装置4
が走行自在に結合され、このホイスト走行装置4
には自走車輪4aとこれを走行させるためのモー
タ4bと荷上用巻上部材5aが搭載されている。
荷上用巻上部材5aにはワイヤ5bとフツク5c
が装備されており、ゴンドラ3cからの遠隔操作
によつて、走行モータ4bと荷上用巻上部材5a
の駆動が出来るようになつている。 Similarly, the hoist device 5 has self-propelled wheels 4a and a load hoisting member 5a, and has a hoist rail 1 for loading.
A hoist traveling device 4 is connected to c via self-propelled wheels 4a.
are coupled so as to be freely movable, and this hoist traveling device 4
is equipped with self-propelled wheels 4a, a motor 4b for driving the wheels, and a load hoisting member 5a.
The load hoisting member 5a has a wire 5b and a hook 5c.
The travel motor 4b and the load hoisting member 5a are controlled by remote control from the gondola 3c.
It is now possible to drive the
足場ゴンドラ用レール1bと荷役用ホイストレ
ール1cを3階の鉄骨柱C3に保持した第1図の
ような場合にはこれらの足場ゴンドラ用レール1
bと荷役用ホイストレール1cに沿つてゴンドラ
3cと、荷上用巻上部材5a及びフツク5cを任
意の位置まで走行させ、又鉄骨柱C1,C2の高さ
範囲でゴンドラ3cとフツク5cを昇降させ、鉄
骨柱C1,C2および鉄骨梁B1,B2付近の工事を行
うものである。 In the case shown in Figure 1, where the scaffolding gondola rail 1b and cargo hoist rail 1c are held on the steel column C3 on the third floor, these scaffolding gondola rails 1
The gondola 3c, hoisting member 5a and hook 5c are moved along the hoist rail 1c for cargo handling to any desired position, and the gondola 3c and hook 5c are moved along the height range of the steel columns C 1 and C 2 . The construction work will be carried out near steel columns C 1 and C 2 and steel beams B 1 and B 2 .
鉄骨柱C1,C2と鉄骨梁B1,B2付近の工事が終
了すると、この時にはすでに鉄骨柱C3の上方に
4階、5階の鉄骨柱C4,C5が起立してきており、
これにより鉄骨柱C3或いは鉄骨梁B3よりユニツ
トレール1全体を取り外しクレーンで上方に盛替
えて鉄骨柱C4、又は鉄骨C5の上部に再び固定し、
例えばユニツトレール1を鉄骨柱C5に固定した
時には3階、4階の鉄骨柱C3,C4付近の工事を
行うものである。 When the construction around steel columns C 1 and C 2 and steel beams B 1 and B 2 is completed, steel columns C 4 and C 5 on the 4th and 5th floors have already been erected above steel column C 3 . ,
As a result, the entire unit rail 1 is removed from the steel column C 3 or steel beam B 3 , moved upwards by a crane, and fixed again to the top of the steel column C 4 or steel frame C 5 .
For example, when the unit rail 1 is fixed to the steel column C5 , construction work is carried out near the steel columns C3 and C4 on the third and fourth floors.
第1図のように、例えば鉄骨柱C1付近の工事
を行なう場合について述べると、先ず足場ゴンド
ラ用レール1bと荷役用ホイストレール1cに沿
つてビルデイングの骨組Aの周囲を走行して所定
の工事位置までゴンドラ3cとフツク5cを移送
させる。この状態では、ゴンドラ3cで鉄骨柱
C1とC1の結合、鉄骨柱C1と鉄骨梁B1の連結に要
するリベツト打ち等の作業を行う。 As shown in Fig. 1, for example, when carrying out construction work near the steel frame column C1 , first, the user runs around the building frame A along the scaffold gondola rail 1b and cargo hoist rail 1c, and completes the prescribed work. The gondola 3c and hook 5c are moved to the desired position. In this state, the steel pillar is
Perform work such as riveting required to connect C 1 and C 1 and steel column C 1 and steel beam B 1 .
又地上より鉄筋をフツク5cで引き上げ、鉄骨
柱C1、まわりの配筋作業、鉄骨梁B1まわりの配
筋作業等を行う。 In addition, the reinforcing bars are pulled up from the ground using hooks 5c, and reinforcement work is carried out around the steel column C 1 and around the steel beam B 1 .
次に鉄骨柱C1に沿う壁、梁の躯体を成形する
には型枠を形成し、この型枠内にコンクリートを
打設する分けであるが、この際地上より外側の型
枠パネル7をフツク5cを介して荷上用巻上部材
5aで引き上げる。 Next, in order to form the frame of the walls and beams along the steel column C1 , formwork is formed and concrete is poured into the formwork.At this time, formwork panels 7 outside the ground are It is pulled up by the load hoisting member 5a via the hook 5c.
この場合ゴンドラ装置5を用いるため大型の巾
広いパネルでも一度に引き上げが可能となり小型
のパネルを多数用意する必要がなく大きなパネル
を使用して搬送作業と着脱作業の短縮化が図れ
る。 In this case, since the gondola device 5 is used, even large and wide panels can be pulled up at once, and there is no need to prepare a large number of small panels, and by using large panels, the transportation work and attachment/detachment work can be shortened.
型枠内にコンクリートを打設し、コンクリート
が乾いた時にはゴンドラ上3cから型枠パネル7
の解体作業を行ない、この解体された型枠パネル
7はホイスト装置5で吊り上げられ上昇或いは走
行させ順次取付作業を進める。 Concrete is poured into the formwork, and when the concrete is dry, formwork panel 7 is poured from 3c above the gondola.
The dismantled formwork panels 7 are lifted up by the hoist device 5 and moved up or traveling to proceed with the installation work one by one.
同様に第2図のようにビルデイングの工事現場
をD工区、E工区、F工区、G工区、の4ブロツ
クに区分し、これらの工区ごとに順次工事を行な
う場合、例えばE工区の工事が終了すると足場ゴ
ンドラ用レール1bと荷役用ホイストレール1c
に沿つてゴンドラ3c、フツク5cをF工区、G
工区方向に移送し、このF,G工区でE工区と同
じ作業を行ない、この時E工区で使用した型枠パ
ネル7をフツク5cでF工区、G工区方向に搬送
するものである。 Similarly, if a building construction site is divided into four blocks, D, E, F, and G, as shown in Figure 2, and construction is carried out in each of these blocks sequentially, for example, the construction in E will be completed. Then, the scaffolding gondola rail 1b and cargo handling hoist rail 1c
Gondola 3c and hook 5c along F section, G
The work is carried out in the direction of the construction zone, and the same work as in the E construction zone is carried out in the F and G construction zones. At this time, the formwork panel 7 used in the E construction zone is transported by the hook 5c in the direction of the F construction zone and the G construction zone.
上記の説明はゴンドラ装置3、ホイスト装置5
をビルデイングの骨組Aの外周に沿つて設け、特
に外まわりの工事を行なう場合について述べたも
のであるが、足場ゴンドラ用レール1bと荷役用
ホイストレール1cを内側に設け、このレールに
沿つて内側の工事に利用してもよい。又外側の工
事を行なう場合、内側の型枠の組立、解体等の工
事と並行して行なうものであり、内側の工事は昇
降自在な又自走自在な足場で利用して行なうこと
が好ましい。 The above explanation is for gondola device 3 and hoist device 5.
is installed along the outer periphery of the building frame A, and the case where construction is particularly carried out around the outside is described. However, a scaffolding gondola rail 1b and a hoist rail 1c for cargo handling are installed inside, and the inside is installed along this rail. May be used for construction purposes. In addition, when carrying out construction on the outside, it is carried out in parallel with construction work such as assembling and dismantling the inner formwork, and it is preferable that the construction on the inside is carried out using scaffolding that can be raised and lowered freely and is self-propelled.
次に最上段の鉄骨柱Co付近でこの鉄骨柱Coに
直接ユニツトレール1を取り付けてしまうと、こ
の鉄骨柱Coまわりの工事が出来なくなつてしま
う。 Next, if the unit rail 1 is attached directly to the steel column C o near the topmost steel column C o , construction work around this steel column C o will not be possible.
従つてこの場合には第5図のように、鉄骨柱
Coの上方に起立する突梁6を設け、この突梁6
の水平なアーム6aに足場ゴンドラ用レーラ1b
と荷役用ホイストレール1cを設け、このレール
にそれぞれゴンドラ装置3とホイスト装置5を走
行自在に連結するものである。突梁6にゴンドラ
装置3、ホイスト装置5を連結した場合には突梁
6のアーム6a近くまでゴンドラ等を引き上げる
ことが可能となり鉄骨柱Coの上部の工事まで行
えるものである。 Therefore, in this case, as shown in Figure 5, the steel column
A projecting beam 6 is provided that stands above C o , and this projecting beam 6
Railer 1b for scaffolding gondola is attached to horizontal arm 6a of
A hoist rail 1c for cargo handling is provided, and a gondola device 3 and a hoist device 5 are movably connected to these rails, respectively. When the gondola device 3 and the hoist device 5 are connected to the joist 6, it becomes possible to pull up the gondola etc. to near the arm 6a of the joist 6, and it is possible to carry out work on the upper part of the steel column Co.
以上のように本発明の方法によれば、次の特有
の効果が得られる。 As described above, according to the method of the present invention, the following unique effects can be obtained.
足場ゴンドラ用レールと荷役用ホイストレー
ルと二つのブラケツトとからなるユニツトレー
ル及びユニツトレールに配設したゴンドラ装置
とホイスト装置は全てユニツト化されているか
ら、ビルデイングの骨組に対する着脱、盛替え
作業が一度に行なえ、その作業性が著しく向上
し、これにより工機の短縮化を図れ、工事費の
コストダウンを達成できる。 The unit rail, which consists of a scaffolding gondola rail, a hoist rail for cargo handling, and two brackets, and the gondola device and hoist device installed on the unit rail, are all integrated into a unit, so installation, removal, and replacement work to the building frame can be done only once. The work efficiency is significantly improved, which allows the use of machine tools to be shortened and construction costs to be reduced.
工事に必要な型枠パネル、その他の建築材料
はホイスト装置が引き上げ又は引き下げ、等の
搬送を行ない、ゴンドラ装置もこれらの荷物の
搬送と同時に移動できるから送やかに、これら
の材料を利用して必要な工事を行なうことがで
きるから、工事の作業性が著しく向上する。 Formwork panels and other building materials needed for construction work are lifted or lowered by hoists, and gondolas can be moved at the same time as these items are transported, so these materials can be used quickly. Since the necessary construction work can be carried out using the same method, the work efficiency of the construction work is significantly improved.
ビルデイングの骨組の外周に沿つて任意の位
置まで自由にゴンドラ装置とホイスト装置を自
走させ、又縦方向にもゴンドラ装置のゴンドラ
とホイスト装置のフツクが任意の位置まで昇降
できるから、特別な足場や、工事別の足場を組
立てる必要がなく、ゴンドラ装置とホイスト装
置の一つの機構を協働させて鉄骨工事、配筋工
事、型枠の組立及び解体工事、コンクリートの
仕上げ工事等外周まわりの全ての工事が連続し
て行えるものである。 The gondola device and hoist device can move freely along the outer periphery of the building frame to any desired position, and the gondola device and the hoist device's hook can be raised and lowered to any desired position in the vertical direction, making it a special scaffolding. There is no need to assemble scaffolding for each work, and the gondola device and hoist device work together to perform all the work around the outside including steel frame work, reinforcement work, formwork assembly and dismantling work, concrete finishing work, etc. The construction work can be carried out continuously.
ユニツトレールの取付け、取り外し以外には
特別な足場の組立、解体作業を必要としないか
ら作業性が著しく向上し、ビルデイングの建築
作業の能率向上と工期の短縮化が図れる。 Since no special scaffold assembly or dismantling work is required other than the installation and removal of the unit rail, work efficiency is significantly improved, and the efficiency of building construction work can be improved and the construction period shortened.
部品としてはユニツトレールとゴンドラ装置
とホイスト装置だけであるから従来のような多
数の足場を組立てる必要がなく、一つの機構を
盛替え、又は水平方向に移送して使用するもの
であるから部品点数が少なく、経済性にすぐれ
ている。 Since the only parts are the unit rail, gondola device, and hoist device, there is no need to assemble many scaffolds like in the past, and the number of parts is reduced because one mechanism can be rearranged or moved horizontally. It is highly economical as it has less
構造物たるビルデイングの骨組の高さに沿つ
て足場を順次組立、解体したり、又作業時にこ
の足場を昇り降りすることが無いから、安全性
にすぐれている。 Scaffolding is not required to be sequentially assembled and dismantled along the height of the framework of the building, and there is no need to climb up and down the scaffolding during work, so safety is excellent.
第1図は工事中のビルデイングの骨組の略示正
面図、第2図は第1図の略示平面図、第3図は柱
にユニツトレールを取り付けた状態の一部切欠き
拡大平面図、第4図、第5図はユニツトレールに
ゴンドラ装置とホイスト装置を連結した状態の略
示拡大正面図である。
A…骨組、B1,B2…Bo…鉄骨梁、C1,C2…Co
…鉄骨柱、1…ユニツトレール、1a…ブラケツ
ト、1b…足場ゴンドラ用レール、1c…荷役用
ホイストレール、2…ゴンドラ走行装置、3…ゴ
ンドラ装置、3c…ゴンドラ、4…ホイスト走行
装置、5…ホイスト装置、5c…フツク、6…突
梁、7…型枠パネル。
Fig. 1 is a schematic front view of the framework of the building under construction, Fig. 2 is a schematic plan view of Fig. 1, and Fig. 3 is an enlarged partially cutaway plan view of the unit rail attached to the pillar. FIGS. 4 and 5 are schematic enlarged front views showing a state in which the gondola device and the hoist device are connected to the unit rail. A...Frame, B 1 , B 2 ...B o ... Steel beam, C 1 , C 2 ...C o
... Steel column, 1... Unit rail, 1a... Bracket, 1b... Scaffolding gondola rail, 1c... Cargo handling hoist rail, 2... Gondola traveling device, 3... Gondola device, 3c... Gondola, 4... Hoist traveling device, 5... Hoist device, 5c... Hook, 6... Projection, 7... Formwork panel.
Claims (1)
ホイストレールとを二つのブラケツト間に相対向
して平行に結合させてユニツトレールを構成し、
当該ユニツトレールを多数、クレーンにより組立
てられた鉄骨柱、鉄骨梁からなる骨組の任意の位
置に結合させ、足場ゴンドラ用レールと荷役用ホ
イストレールとにそれぞれ上下移動自在なゴンド
ラを備えたゴンドラ装置と上下移動自在なフツク
を備えたホイスト装置とを水平方向走行自在に配
設し、ゴンドラ装置とホイスト装置とを協働させ
て鉄骨工事、配筋工事、型枠の組立及び解体工
事、仕上工事等を全て連続して行ない、且つユニ
ツトレールとこれに配設したゴンドラ装置とホイ
スト装置とを鉄骨柱の組立てに応じて順次上方に
盛替えることを特徴とする建築工事方法。 2 ゴンドラ装置とホイスト装置の昇降及び走行
はゴンドラ上で遠隔操作する特許請求の範囲第1
項記載の建築工事方法。 3 ゴンドラはゴンドラ上に設けたウインチを介
してゴンドラ走行装置に昇降自在に連結され、ゴ
ンドラ走行装置は自走車輪を介して足場ゴンドラ
用レールに走行自在に連結されている特許請求の
範囲第1項記載の建築工事方法。 4 ホイスト装置は自走車輪と荷上用巻上部材と
を有し、自走車輪は荷役用ホイストレールに走行
自在に連結され、荷上用巻上部材にはフツクが上
下移動自在に結合されている特許請求の範囲第1
項記載の建築工事方法。[Scope of Claims] 1. A unit rail is constructed by connecting a scaffold gondola rail of arbitrary length and a cargo hoist rail in parallel between two brackets, facing each other;
A gondola device in which a large number of unit rails are connected to arbitrary positions of a frame consisting of steel columns and steel beams assembled by a crane, and each of a scaffold gondola rail and a cargo handling hoist rail is equipped with a gondola that can move up and down. A hoist device with a vertically movable hook is installed so that it can move freely in the horizontal direction, and the gondola device and hoist device work together to perform steel frame work, reinforcement work, formwork assembly and dismantling work, finishing work, etc. This method of construction work is characterized in that all of the steps are carried out continuously, and the unit rail and the gondola device and hoist device installed thereon are sequentially moved upward in accordance with the assembly of the steel columns. 2. Lifting, lowering and traveling of the gondola device and hoist device are remotely controlled on the gondola.
Construction method described in section. 3. The gondola is connected to a gondola traveling device so as to be able to move up and down via a winch provided on the gondola, and the gondola traveling device is connected to a scaffolding gondola rail via self-propelled wheels so that it can run freely. Construction method described in section. 4. The hoist device has self-propelled wheels and a load hoisting member, the self-propelled wheels are movably connected to a hoist rail for cargo handling, and a hook is coupled to the load hoisting member so as to be movable up and down. Claim 1
Construction method described in section.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10238783A JPS59228569A (en) | 1983-06-08 | 1983-06-08 | Construction method of building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10238783A JPS59228569A (en) | 1983-06-08 | 1983-06-08 | Construction method of building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59228569A JPS59228569A (en) | 1984-12-21 |
| JPH0445628B2 true JPH0445628B2 (en) | 1992-07-27 |
Family
ID=14326034
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10238783A Granted JPS59228569A (en) | 1983-06-08 | 1983-06-08 | Construction method of building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59228569A (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2510068B2 (en) * | 1993-03-23 | 1996-06-26 | 鹿島建設株式会社 | Building exterior work equipment |
| KR100916292B1 (en) | 2007-12-14 | 2009-09-10 | 삼지석재공업주식회사 | Temporary system for building exterior construction and building exterior construction method using the same |
| JP7256963B2 (en) * | 2019-09-27 | 2023-04-13 | 積水ハウス株式会社 | Building construction method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5411974B2 (en) * | 1973-12-31 | 1979-05-18 | ||
| JPS5552470A (en) * | 1978-10-13 | 1980-04-16 | Shimizu Construction Co Ltd | Method of facing skyscraper |
-
1983
- 1983-06-08 JP JP10238783A patent/JPS59228569A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59228569A (en) | 1984-12-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104520521B (en) | Concept of high-rise building elevation | |
| JP4886286B2 (en) | Temporary scaffolding unit | |
| JP3196043B2 (en) | Construction method of stairs and staircase, construction method of stairs, and stair members | |
| JP3579816B2 (en) | Multipurpose stage for building frame | |
| JPH09317183A (en) | Building construction method | |
| JPH0530758B2 (en) | ||
| JP6712501B2 (en) | High-rise building demolition system and demolition method | |
| JP5150313B2 (en) | Three-dimensional parking device in void and its construction method | |
| JPH0445628B2 (en) | ||
| JPH0483060A (en) | Building construction | |
| JP3220397B2 (en) | Elevating scaffold | |
| JPH0445629B2 (en) | ||
| JP3177735B2 (en) | An erect scaffold used to reinforce the perimeter of existing buildings | |
| US3435583A (en) | Method of forming buildings | |
| JP2008214932A (en) | Construction method for building | |
| KR20080099685A (en) | Construction device and method | |
| KR100539829B1 (en) | Method of pulling-up gang form for a flash board using a shaped steel | |
| JP2532116B2 (en) | Lifting scaffolding | |
| JP4065798B2 (en) | Prop work scaffold and method for constructing support work scaffold | |
| JP3240270B2 (en) | Scaffold assembling method and scaffolding device | |
| JP2843042B2 (en) | Steel framing unit scaffolding method | |
| KR20080100002A (en) | Construction device and method | |
| JP2017172262A (en) | Construction method of building | |
| JP2001240340A (en) | Method of execution for elevator tower | |
| JPH04319172A (en) | Building frame construction equipment |