JPH0446433Y2 JP1987013657U JP1365787U JPH0446433Y2 JP H0446433 Y2 JPH0446433 Y2 JP H0446433Y2 JP 1987013657 U JP1987013657 U JP 1987013657U JP 1365787 U JP1365787 U JP 1365787U JP H0446433 Y2 JPH0446433 Y2 JP H0446433Y2
Authority
JP
Japan
Prior art keywords
concrete
concrete pouring
shape
rail
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1987013657U
Other languages
Japanese (ja)
Other versions
JPS63122540U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1987013657U priority Critical patent/JPH0446433Y2/ja
Publication of JPS63122540U publication Critical patent/JPS63122540U/ja
Application granted granted Critical
Publication of JPH0446433Y2 publication Critical patent/JPH0446433Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【考案の詳細な説明】 産業上の利用分野 本考案は、土木工事、建築工事の型枠部や土間
等にコンクリートを打設するコンクリート打設装
置に関する。
[Detailed Description of the Invention] Industrial Application Field The present invention relates to a concrete pouring device for pouring concrete into formwork, dirt floors, etc. in civil engineering and architectural works.

従来の技術 従来、土木工事や建築工事のコンクリート打設
作業は、コンクリートポンプ車等からフレキシブ
ルホースを介して送給されるコンクリートを作業
員がフレキシブルホースの筒先部をもつて、所要
の打設部に移動しながら打設しているものであつ
た。
Conventional technology Conventionally, in concrete pouring work for civil engineering and construction work, a worker holds the tip of a flexible hose to place concrete delivered from a concrete pump truck or the like through a flexible hose to the desired pouring area. The concrete was being poured while moving from place to place.

考案が解決しようとする問題点 しかし、配筋処理をした型枠や土間部をコンク
リート打設する場合には、数十Kg/cm2の圧送圧が
かかつたフレキシブルホースが配筋上をとびはね
て配筋を乱し、その手直し作業をしなければなら
ないとともにフレキシブルホースの移動が簡単に
行なえず、多数の作業員が苦渋して筒先部の移動
を行なつているものであつた。
Problems that the invention aims to solve However, when pouring concrete into formwork or earthen floors that have been treated with reinforcement, flexible hoses that are under pressure of several tens of kilograms/ cm2 jump over the reinforcement. This disturbs the reinforcing arrangement, necessitating rework, and the flexible hose cannot be moved easily, requiring many workers to move the tube tip with great difficulty.

そのため、ブーム付コンクリートポンプ車やタ
ワークレーンでコンクリートを打設する装置が知
られているが、搬送距離が制約されるうえ高所か
らコンクリートを流出して打設するため、コンク
リート骨材が分離して品質が悪くなり、またコン
クリートの落下で衝撃が大きく、危険な打設とな
るものであつた。
For this reason, devices that use boom-equipped concrete pump trucks or tower cranes to place concrete are known, but they limit the conveyance distance, and because the concrete is poured from a high place and placed, the concrete aggregate may separate. This resulted in poor quality, and the falling concrete caused a large impact, making pouring dangerous.

なお、特開昭57−71962号公報には、デリベリ
パイプの先端を巻揚ウインチにより遠隔操作する
自走式スラリー吐出機が提案されているが、巻揚
ウインチを作動するモーターや電力設置などを必
要として、所定場所に簡単に、かつ確実にコンク
リート打設することが難しいものであつた。
In addition, Japanese Patent Application Laid-open No. 57-71962 proposes a self-propelled slurry discharge machine in which the tip of the delivery pipe is remotely controlled by a hoisting winch, but it requires a motor to operate the hoisting winch, electric power installation, etc. Therefore, it was difficult to easily and reliably place concrete in a predetermined location.

また、特開昭61−87060号公報には、ガイドレ
ールに沿つて走行するデイストリビユータ装置に
よるコンクリート打設方法が提案されている。し
かし、ガイドレールをローラで挟んで走行するも
ので、デイストリビユータ装置は直線方向しか走
行することができず、コンクリート打設現場に合
わせてL字状やT字状等にガイドレールを配置し
てコンクリート打設することができず、作業効率
が悪いものであつた。
Further, Japanese Patent Application Laid-Open No. 61-87060 proposes a method of placing concrete using a distributor device that runs along a guide rail. However, because the distributor runs with a guide rail sandwiched between rollers, it can only run in a straight line, and the guide rails are arranged in an L-shape, T-shape, etc. to suit the concrete placement site. It was not possible to pour concrete using the concrete, and the work efficiency was poor.

問題点を解決するための手段 本考案は上記のような点に鑑みたもので、上記
の問題を解決するために、コンクリート打設本体
にコンクリート打設用パイプを折曲可能に側方に
突設して、コンクリート打設部にコンクリートを
打設するようにしたコンクリート打設装置におい
て、上記折曲可能としたコンクリート打設用パイ
プの先端側に手動ウインチを装着して、コンクリ
ート打設用パイプの先端側を昇降可能に手動ウイ
ンチのワイヤーをコンクリート打設用パイプの支
持側に係止し、上記コンクリート打設用パイプの
先端部を下方に折曲して筒先部を形成するととも
に、この先端部に操作ハンドルを取着し、打設準
備をしたコンクリート打設部にコンクリート打設
本体走行用の建設枠組足場にチヤンネル状のレー
ルを搭載した枠組方式の走行レールをコンクリー
ト打設面よりやや上部の高さとして、L字状、T
字状、E字状、F字状、コ字状等の配列に敷設し
て、上記走行用レールにキヤスターのように旋回
可能に軸着した車輪を嵌挿してコンクリート打設
本体を上記走行用レールにそつて搭載するように
したことを特徴とするコンクリート打設装置を提
供するにある。
Means for Solving the Problems The present invention was developed in view of the above-mentioned problems.In order to solve the above-mentioned problems, a concrete pouring pipe is provided with bendable side protrusions in the concrete pouring body. In a concrete pouring device that is configured to place concrete in a concrete pouring section, a manual winch is attached to the tip side of the bendable concrete pouring pipe. The wire of a manual winch is fixed to the support side of the concrete pouring pipe so that the tip side of the concrete pouring pipe can be raised and lowered, and the tip of the concrete pouring pipe is bent downward to form a cylindrical tip. Attach an operating handle to the concrete pouring section, and install a frame-type running rail with a channel-shaped rail mounted on the construction framework scaffolding for the concrete pouring body to run on the concrete pouring section, which is prepared for pouring. As the height of L-shape, T
Concrete is laid in a shape such as a letter shape, an E shape, an F shape, a U shape, etc., and wheels rotatably pivoted like casters are inserted into the above-mentioned running rail to make the concrete pouring body for the above-mentioned running. To provide a concrete placing device characterized in that it is mounted along a rail.

作 用 本考案によれば、走行用レールのレール部材が
簡素化できてコンクリート打設部にコンクリート
打設本体走行用の走行用レールを簡単に敷設でき
る。また、この走行用レールにコンクリート打設
本体を安定よく走行でき、所要の型枠部や土間部
に最少限の作業員が筒先部を簡単に操作してコン
クリートを順次打設できる。コンクリート打設用
パイプの筒先部を手動ウインチで手動操作して筒
先部を簡単に操作でき、コンクリート打設用パイ
プの筒先部を簡単に昇降してコンクリートを打設
でき、油圧装置やモーター等の高価な設備費を必
要とせずに施工できる。さらに、上記の手動ウイ
ンチと相まつてコンクリート打設用パイプの筒先
部を操作ハンドルによつて操作できて、たとえ側
枠部や手すりシユート部の流し込みにくい場所で
あつても、所定場所に筒先部を向けられて確実に
コンクリートを流し込んでコンクリートを打設で
きる。
Effects According to the present invention, the rail members of the running rail can be simplified, and the running rail for running the concrete pouring body can be easily laid in the concrete pouring part. In addition, the concrete pouring body can run stably on this traveling rail, and a minimum number of workers can easily operate the tube tip and pour concrete one by one into the required formwork or dirt floor area. The tip of the concrete pouring pipe can be manually operated with a manual winch to easily operate the tip, and the tip of the concrete pouring pipe can be easily raised and lowered to place concrete. It can be constructed without requiring expensive equipment costs. Furthermore, in conjunction with the above-mentioned manual winch, the tip of the concrete pouring pipe can be operated using the operating handle, allowing the tip to be placed in a predetermined location, even in areas where pouring is difficult, such as the side frame or handrail chute. Concrete can be placed by pointing the concrete accurately.

実施例 以下、本考案を実施例に基づいて説明する。Example Hereinafter, the present invention will be explained based on examples.

第1図以下は、本考案の一実施例である。コン
クリート打設装置1は、4トントラツク等で搬送
可能に分割組立てできるようにしていて、第1
図、第2図ようにコンクリート打設本体2を走行
用レール3に搭載自在として走行可能に形成して
いる。コンクリート打設本体2は、四角形状に骨
組したそれぞれの角部にキヤスターのように旋回
可能に軸着した車輪4をそれぞれ下側方に突設し
て走行自在とし、四角形状に骨組した中央部には
やや大径の旋回用軸受5を設けてコンクリート打
設用パイプ架設部6を枢着し、コンクリート打設
用パイプ7を旋回自在に側方に突設してコンクリ
ートを広範囲にわたつて打設できるように支着し
ている。コンクリート打設用パイプ架設部6は、
第1図、第2図のように中心部をやや大径に円板
状として安定よく旋回用軸受5に軸着していて、
その上部に逆T形状のパイプ支持部8を配設し、
長尺とした方の水平なパイプ支持部8にコンクリ
ート打設用パイプ7を支持台9を介してベンド1
0で固定して搭載している。
FIG. 1 and subsequent figures show an embodiment of the present invention. The concrete pouring device 1 is designed to be able to be assembled in parts so that it can be transported by a 4-ton truck, etc.
As shown in FIGS. 2 and 2, the concrete casting body 2 is configured to be freely mounted on a running rail 3 so that it can run. The concrete casting body 2 has a square frame, and wheels 4 rotatably pivoted like casters are provided at each corner of the frame so that it can run freely, and wheels 4 are rotatably mounted on the corners of the frame. A swing bearing 5 with a slightly larger diameter is provided to pivotally connect a concrete pouring pipe installation part 6, and a concrete pouring pipe 7 is rotatably protruded from the side to allow concrete to be poured over a wide area. It is supported so that it can be set up. The pipe construction part 6 for concrete pouring is
As shown in FIGS. 1 and 2, the center portion is shaped like a disk with a slightly larger diameter and is stably attached to the swing bearing 5.
An inverted T-shaped pipe support part 8 is arranged on the upper part,
Bend 1 the concrete pouring pipe 7 to the long horizontal pipe support 8 via the support stand 9.
It is installed fixed at 0.

コンクリート打設用パイプ7は、パイプ支持部
8の先端部で図のように下方に折曲するとともに
側方に折曲し、その折曲部分に水平回転接続具1
1および垂直回転接続具12をそれぞれ接続して
段落した段落部13を第2図のように水平方向に
旋回自在に、かつ第1図のように垂直方向に傾け
て昇降自在に移動できるようにしている。この段
落部13には、図のように小型の手動のウインチ
14を固着していて、そのワイヤー15の一端を
段落したパイプ支持部8の上方に設けた吊設部1
6に係止し、ウインチ14の巻回によつて筒先部
17を容易に昇降駆動して一定の高さに位置でき
るようにしている。また、段落部13の端部側お
よび先端の下方に折曲した筒先部17には、操作
ハンドル18,19をそれぞれ配設していて、筒
先部17より少し離れて、また筒先部17のすぐ
側で操作ハンドル18,19を操作してコンクリ
ートを所定場所に打設できるようにしている。ま
た、コンクリート打設用パイプ架設部6の逆T字
状の水平パイプ支持部8の反対側の端部には、図
のようにバランスウエイト20を適宜量積層して
平衡を保つようにしている。21,22はそれぞ
れパイプ支持部8を支持するための支持具であ
る。
The concrete pouring pipe 7 is bent downward and sideways at the tip of the pipe support 8 as shown in the figure, and a horizontal rotation connector 1 is attached to the bent part.
1 and the vertical rotation connector 12, respectively, so that the stepped section 13 can be rotated horizontally as shown in FIG. 2, and tilted vertically as shown in FIG. 1, so that it can be moved up and down. ing. As shown in the figure, a small manual winch 14 is fixed to this stepped portion 13, and one end of the wire 15 is attached to a hanging portion 1 provided above the stepped pipe support portion 8.
6, and by winding the winch 14, the cylinder tip 17 can be easily moved up and down to be positioned at a constant height. In addition, operating handles 18 and 19 are respectively provided on the end side of the stepped portion 13 and on the tube tip 17 bent downward at the tip. By operating operation handles 18 and 19 on the side, concrete can be poured into a predetermined location. In addition, as shown in the figure, an appropriate amount of balance weights 20 are stacked on the opposite end of the inverted T-shaped horizontal pipe support section 8 of the concrete placement pipe installation section 6 to maintain balance. . 21 and 22 are supports for supporting the pipe support section 8, respectively.

一方、走行用レール3は、第1図、第2図のよ
うにベース24,レール受け25,26、レール
27を組み合せて、レール27をコンクリート打
設面よりやや上部に突き出して敷設できるように
構成している。できれば、レール27をできるだ
け低く敷設するのが好ましい。ベース24は、第
3図、第4図のように所定の大きさのプレート2
8に100〜300mm位(好ましくは100〜150mm位)の
短い支持パイプ29を垂設し、プレート28に開
孔した固定孔30を介してコンクリート打設面に
釘で固定するようにして、走行用レール3を確実
にコンクリート打設面に固定できるようにしてい
る。レール27は、第5図、第6図のようにチヤ
ンネル材を1100〜1800mm位の持ち運び容易な所定
の寸法に形成しているもので、下面に補強材31
を突設するとともに両端部にレール受け25,2
6に簡単に着脱できるように係止用突起32をそ
れぞれ突設している。レール受け25,26は、
第7図〜第10図のように走行用とコーナー用と
を設けていて、それぞれ1600〜2000mm位の長さに
コンクリート打設本体2の車輪4の間隔を合わせ
ており、パイプ材33で接合した両端部に上記し
たベース24の支持パイプ29に嵌合する架設用
パイプ34を垂設し、その上面に上記したレール
27の係止用突起32を着脱自在に係止孔35に
嵌着して架設するレール架設部36をレール27
の厚みだけ端部を段落して、図のように走行用の
ものは対向して、コーナー用のものは180度ごと
に対向して設けて、簡単かつ迅速に走行用レール
3を組み立て、分解できるように形成している。
なお、コーナー用のものは、パイプ材33の中間
部分に第9図、第10図のようにブレース留め具
37を突設して、第11図のような両端が折曲し
て係止自在の水平ブレース38を斜め状に懸架し
て補強できるようにしている。第12図、第13
図は、コーナー部のレール受け25,26間に架
設するための布枠受け39で、所定の長さのパイ
プ材40の両端にレール架設材41を取着し、レ
ール架設材41の下面に係止用突起42を突設し
て、レール受け26の係止孔35に着脱自在に架
設できるようにして、布枠受け39間に上記と同
様にしてレール27を架設できるようにしている
ものである。
On the other hand, the traveling rail 3 can be laid by combining the base 24, rail receivers 25, 26, and rail 27 as shown in Figures 1 and 2, with the rail 27 protruding slightly above the concrete pouring surface. It consists of If possible, it is preferable to lay the rail 27 as low as possible. The base 24 has a plate 2 of a predetermined size as shown in FIGS. 3 and 4.
8, a short support pipe 29 of about 100 to 300 mm (preferably about 100 to 150 mm) is installed vertically, and is fixed to the concrete pouring surface with nails through the fixing hole 30 drilled in the plate 28. The rail 3 can be securely fixed to the concrete pouring surface. As shown in Figs. 5 and 6, the rail 27 is made of channel material formed into a predetermined size of about 1100 to 1800 mm for easy portability, and has a reinforcing material 31 on the bottom surface.
rail receivers 25, 2 at both ends.
A locking protrusion 32 is provided in a protruding manner so as to be easily attached to and detached from the holder 6. The rail receivers 25 and 26 are
As shown in Figures 7 to 10, there are wheels for running and wheels for corners, each with a length of about 1,600 to 2,000 mm, and the intervals between the wheels 4 of the concrete pouring body 2 are matched, and they are joined with pipe material 33. An erection pipe 34 that fits into the support pipe 29 of the base 24 described above is installed vertically at both ends thereof, and the locking protrusion 32 of the rail 27 described above is removably fitted into the locking hole 35 on the upper surface thereof. The rail erecting section 36 to be erected is connected to the rail 27.
Assemble and disassemble the running rail 3 easily and quickly by arranging the ends by a thickness of It is designed so that it can be done.
In addition, for the corner type, a brace fastener 37 is provided protruding from the middle part of the pipe material 33 as shown in Figs. 9 and 10, and both ends can be bent and locked as shown in Fig. 11. The horizontal brace 38 is suspended diagonally so that it can be reinforced. Figures 12 and 13
The figure shows a cloth frame receiver 39 to be installed between the rail receivers 25 and 26 at the corner, and a rail construction material 41 is attached to both ends of a pipe material 40 of a predetermined length, and the rail construction material 41 is attached to the bottom surface of the rail construction material 41. A locking protrusion 42 is provided in a protruding manner so that the rail 27 can be removably installed in the locking hole 35 of the rail receiver 26, and the rail 27 can be installed between the cloth frame receivers 39 in the same manner as above. It is.

しかして、建設工事において、配筋等の処理を
施す型枠部や土間部にコンクリートを打設するに
は、たとえば第14図のようにコンクリート打設
部である土間部の中央部に上記のベース24を一
定間隔に釘で固着して、配筋処理後または配筋処
理と同時にレール受け25,26をそれぞれベー
ス24に嵌装して架設し、レール27、布枠受け
39をレール受け25,26に適宜に架設して走
行用レール3を組み立てて敷設していく。そし
て、組み立てた走行用レール3のレール27にコ
ンクリート打設本体2の車輪4を嵌装してコンク
リート打設本体2を搭載し、コンクリートポンプ
車(図示せず)のコンクリート送給ホース43を
必要によりコンクリート送給パイプ(図示せず)
を介してコンクリート打設用パイプ7の端部に接
続し、図のようにコンクリート打設本体2を走行
用レール3の前部へ走行して、コンクリートを送
給する。コンクリート打設用パイプ7の先端部に
取着した操作ハンドル18,19を適宜に操作し
てコンクリート打設用パイプ7を図のように適宜
に折曲し、土間であるコンクリート打設部にコン
クリートを打設していくものである。打設の際、
第15図のように段落部13のウインチ14を巻
回して筒先部17をできるだけ低くすれば、コン
クリートを衝撃なく打設できる。必要に応じて、
ウインチ14を巻回して、第16図のように筒先
部17を所定の高さに位置し、側枠部や下階への
シユート部へコンクリートを流し込んでいくもの
である。
In construction work, when placing concrete in the formwork or earthen floor area where reinforcement is to be placed, for example, as shown in Figure 14, it is necessary to place the above-mentioned The base 24 is fixed with nails at regular intervals, and the rail receivers 25 and 26 are fitted to the base 24 after or at the same time as the reinforcement treatment, and the rail 27 and the cloth frame receiver 39 are installed on the rail receiver 25. , 26 as appropriate, and the running rail 3 is assembled and laid. Then, the wheels 4 of the concrete pouring main body 2 are fitted onto the rails 27 of the assembled traveling rail 3, and the concrete pouring main body 2 is mounted, and a concrete feed hose 43 of a concrete pump vehicle (not shown) is required. Concrete feed pipe (not shown)
The concrete casting main body 2 is connected to the end of the concrete pouring pipe 7 via the concrete pouring pipe 7, and as shown in the figure, the concrete pouring main body 2 is run to the front of the running rail 3 to feed concrete. By appropriately operating the operation handles 18 and 19 attached to the tip of the concrete pouring pipe 7, bend the concrete pouring pipe 7 appropriately as shown in the figure, and place the concrete in the concrete pouring area, which is an earthen floor. We will continue to pour the concrete. During pouring,
As shown in FIG. 15, by winding the winch 14 of the stepped portion 13 to lower the tube tip portion 17 as much as possible, concrete can be poured without impact. as needed,
By winding the winch 14, the tube end 17 is positioned at a predetermined height as shown in FIG. 16, and concrete is poured into the side frame and the chute toward the lower floor.

このようにコンクリート打設本体を容易に走行
できるとともに、筒先部を最少限の作業者で簡単
に操作できるため、コンクリート打設の省力化が
はかれ、作業員の削減もはかれて、作業の効率化
がはかれるものであり、従来のようにフレキシブ
ルホースを配筋上に敷設して配筋を乱すことな
く、配筋の手直しの必要もなくなり、しかも30
Kg/cm2もの高圧力がかかつてコンクリートを圧送
するフレキシブルホースを多数の作業員が苦渋す
ることも解消できるものである。また、油圧装置
やモーター等の動力を一切使用しないで、筒先部
を簡単に振り回せるため、設備費も安価なもので
ある。
In this way, the concrete pouring body can be moved easily, and the tip of the tube can be easily operated by a minimum number of workers, which saves labor in concrete pouring and reduces the number of workers. This improves efficiency, eliminates the need to disturb the reinforcement by laying flexible hoses on top of the reinforcement, and eliminates the need to modify the reinforcement.
This eliminates the need for many workers to use flexible hoses to pump concrete, which is subject to high pressures of kg/ cm2 . In addition, the equipment cost is low because the cylinder tip can be easily swung without using any power such as a hydraulic device or a motor.

また、走行用レールをコンクリート打設面に対
してやや高い程度の高さに敷設しているため、コ
ンクリート打設本体を安定性よく走行でき、また
作業者が走行用レールを容易に上り、下りでき
て、疲労少なく作業ができるものである。しか
も、上記のようにレール部材をできるだけ少な
く、嵌合状態によつて結合できるようにしている
ため、走行用レールの組み立てや分解を迅速にか
つ簡単に行なえるものである。
In addition, since the running rail is installed at a slightly higher height than the concrete pouring surface, the concrete casting body can run with good stability, and workers can easily climb up and down the running rail. It is easy to use and allows you to work with less fatigue. Moreover, since the number of rail members is as small as possible and can be connected in a fitted state as described above, the traveling rail can be quickly and easily assembled and disassembled.

なお、上記説明では、走行用レールをL字状に
敷設してコンクリートを打設する例を示したが、
上記のレール部材を適宜に組み合わせることによ
つて、I字状、T字状、E字状、F字状、コ字状
等の打設現場に対応した最適な状態に敷設するこ
とができるものである。また、敷設した走行用レ
ールに、建設現場の足場板のような作業足場板を
支持枠間に架設することもでき、施工現場での作
業を安全にかつ容易に行なえるようにできるもの
である。
In addition, in the above explanation, an example was shown in which running rails are laid in an L-shape and concrete is poured.
By appropriately combining the above-mentioned rail members, it is possible to lay the rails in the optimal condition corresponding to the pouring site, such as I-shape, T-shape, E-shape, F-shape, U-shape, etc. It is. In addition, work scaffolding boards, similar to scaffolding boards at construction sites, can be erected between the support frames on the running rails that have been laid, allowing work at the construction site to be carried out safely and easily. .

考案の効果 以上のように本考案にあつては、コンクリート
打設用パイプの筒先部を手動ウインチで手動操作
して筒先部を簡単に操作でき、コンクリート打設
用パイプの筒先部を簡単に昇降してコンクリート
を打設でき、油圧装置やモーター等の高価な設備
費を必要とせずに施工できる。そして、上記の手
動ウインチと相まつてコンクリート打設用パイプ
の筒先部を操作ハンドルによつて操作できて、た
とえ側枠部や手すりシユート部の流し込みにくい
場所であつても、所定場所に筒先部を向けられて
確実にコンクリートを流し込んでコンクリートを
打設できる。そしてまた、コンクリート打設部に
走行用レールを、I字状、T字状、E字状、F字
状、コ字状等の適宜な状態に迅速かつ簡単に敷設
できる。特に、キヤスターのように旋回可能に軸
着した車輪を90度回転することによつて、コンク
リート打設本体を旋回移動できるため、走行用レ
ールに直角方向にも走行させることができ、上記
したようにL字状、T字状、E字状、F字状、コ
字状等の適宜の形状の配列に敷設した走行用レー
ル上を折曲して走行できて、効率よくコンクリー
ト打設が行える。
Effects of the invention As described above, with the present invention, the tip of the concrete pouring pipe can be easily operated by manually operating the tip with a manual winch, and the tip of the concrete pouring pipe can be easily raised and lowered. Concrete can be poured using the concrete method, and the construction can be done without requiring expensive equipment such as hydraulic equipment or motors. In conjunction with the above-mentioned manual winch, the tip of the concrete pouring pipe can be operated using the operating handle, allowing the tip to be placed in a predetermined location, even if it is difficult to pour into the side frame or handrail chute. Concrete can be placed by pointing the concrete accurately. Further, the running rail can be quickly and easily laid in an appropriate shape such as an I-shape, a T-shape, an E-shape, an F-shape, or a U-shape in the concrete placement area. In particular, by rotating the rotatably pivoted wheels like casters by 90 degrees, the concrete pouring body can be moved in a swiveling manner, making it possible to travel in a direction perpendicular to the running rail, as described above. Concrete can be placed efficiently by bending and running on running rails laid in an appropriate shape such as L-shape, T-shape, E-shape, F-shape, U-shape, etc. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図は本考案の一実施例の一側面図
および平面図、第3図、第4図は同上の走行用レ
ールのベースの側面図および平面図、第5図、第
6図は同上のレールの一部省略した側面図および
平面図、第7図〜第10図はそれぞれ同上のレー
ル受けの側面図および平面図、第11図は同上の
水平ブレースの側面図、第12図、第13図は同
上の布枠受けの一部省略した側面図および平面
図、第14図〜第16図はそれぞれ同上の一施工
例の説明用図である。 1……コンクリート打設装置、2……コンクリ
ート打設本体、3……走行用レール、14……ウ
インチ、17……筒先部。
1 and 2 are a side view and a plan view of an embodiment of the present invention, FIGS. 3 and 4 are a side view and a plan view of the base of the same running rail, and FIGS. 5 and 6 are The figures are a partially omitted side view and a plan view of the same rail, FIGS. 7 to 10 are a side view and a plan view of the same rail receiver, respectively, and FIG. Figures 13 and 13 are partially omitted side and plan views of the cloth frame holder shown above, and Figures 14 to 16 are explanatory views of one construction example of the same. DESCRIPTION OF SYMBOLS 1... Concrete placement device, 2... Concrete placement main body, 3... Running rail, 14... Winch, 17... Tube tip.

Claims (1)

【実用新案登録請求の範囲】 コンクリート打設本体にコンクリート打設用パ
イプを折曲可能に側方に突設して、コンクリート
打設部にコンクリートを打設するようにしたコン
クリート打設装置において、 上記折曲可能としたコンクリート打設用パイプ
の先端側に手動ウインチを装着して、コンクリー
ト打設用パイプの先端側を昇降可能に手動ウイン
チのワイヤーをコンクリート打設用パイプの支持
側に係止し、 上記コンクリート打設用パイプの先端部を下方
に折曲して筒先部を形成するとともに、この先端
部に操作ハンドルを取着し、 打設準備をしたコンクリート打設部にコンクリ
ート打設本体走行用の建設枠組足場にチヤンネル
状のレールを搭載した枠組方式の走行用レールを
コンクリート打設面よりやや上部の高さとして、
L字状、T字状、E字状、F字状、コ字状等の配
列に敷設して、上記走行用レールにキヤスターの
ように旋回可能に軸着した車輪を嵌挿してコンク
リート打設本体を上記走行用レールにそつて搭載
するようにしたことを特徴とするコンクリート打
設装置。
[Scope of Claim for Utility Model Registration] A concrete pouring device in which a concrete pouring pipe is bendably protruded from the side of the concrete pouring body to pour concrete into the concrete pouring portion, A manual winch is attached to the tip side of the bendable concrete pouring pipe, and the wire of the manual winch is locked to the support side of the concrete pouring pipe so that the tip side of the concrete pouring pipe can be raised and lowered. Then, bend the tip of the above-mentioned concrete pouring pipe downward to form a tube tip, attach an operating handle to this tip, and place the concrete pouring body in the concrete pouring area prepared for pouring. A framework-type running rail with a channel-shaped rail mounted on a running construction framework scaffold is set at a height slightly above the concrete pouring surface.
The concrete is laid in an L-shape, T-shape, E-shape, F-shape, U-shape, etc., and wheels rotatably pivoted like casters are inserted into the above-mentioned running rail and concrete is poured. A concrete placing device characterized in that the main body is mounted along the traveling rail.
JP1987013657U 1987-01-30 1987-01-30 Expired JPH0446433Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1987013657U JPH0446433Y2 (en) 1987-01-30 1987-01-30

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1987013657U JPH0446433Y2 (en) 1987-01-30 1987-01-30

Publications (2)

Publication Number Publication Date
JPS63122540U JPS63122540U (en) 1988-08-09
JPH0446433Y2 true JPH0446433Y2 (en) 1992-10-30

Family

ID=30802925

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1987013657U Expired JPH0446433Y2 (en) 1987-01-30 1987-01-30

Country Status (1)

Country Link
JP (1) JPH0446433Y2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100367518B1 (en) * 2000-01-13 2003-01-15 주식회사 수성 Concrete transfer and distributor
KR100387988B1 (en) * 2000-01-24 2003-07-12 (주) 희림종합건축사사무소 Circular distributer and an apparatus for reducing pulse of the distributing pipe

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5771962A (en) * 1980-10-20 1982-05-06 Daiwa Kiko Self-propelling slurry discharger
JPS6187060A (en) * 1984-10-04 1986-05-02 極東開発工業株式会社 Distributor apparatus

Also Published As

Publication number Publication date
JPS63122540U (en) 1988-08-09

Similar Documents

Publication Publication Date Title
CN101124379A (en) Clamps for Construction Equipment
US3689019A (en) Apparatus for shuttering poured concrete structures
US4942940A (en) Scaffold jack
CN113636466A (en) Portal frame for building demolition and demolition method
JPH0446433Y2 (en)
KR20040097542A (en) Carrier for curtain-wall panel establishing use and curtain-wall establishing method using the same
CN212532065U (en) A gantry crane that can be used in different height difference sites
JP2563762B2 (en) Bridge girder uplifting method, uplifting machine and vent member
JPH0390777A (en) Concrete placement method and equipment
JPH0447100B2 (en)
CN213233354U (en) Special large-gradient sliding form device with arc lining bottom plate
CN107792802A (en) A kind of small members movement and mounting system and method
KR100387987B1 (en) Circular distributer
KR200294830Y1 (en) Supporting structure of scaffold for mold
CN114875955A (en) Installation device for overlong concrete linear retaining wall template and construction method thereof
CN114737750A (en) Construction method for reinforced concrete silo top plate template
CN114991462A (en) Cloth and creeping formwork integrated equipment for construction building
KR20080099685A (en) Construction device and method
US4648518A (en) Self-lifting gantry crane and boom therefor
JPH0577448U (en) Construction equipment for concrete construction
CN111979991A (en) Special large-gradient sliding form device with arc lining bottom plate and construction method
CN223269097U (en) T-beam construction device and T-beam construction system
JP7771484B2 (en) Concrete pouring equipment and pouring methods
CN213538977U (en) Concrete construction device for lower side wall of complex terrain
CN214399453U (en) Construction elevator footboard that can overturn