JPH0452814B2 - - Google Patents

Info

Publication number
JPH0452814B2
JPH0452814B2 JP14610486A JP14610486A JPH0452814B2 JP H0452814 B2 JPH0452814 B2 JP H0452814B2 JP 14610486 A JP14610486 A JP 14610486A JP 14610486 A JP14610486 A JP 14610486A JP H0452814 B2 JPH0452814 B2 JP H0452814B2
Authority
JP
Japan
Prior art keywords
piles
sheet
waterproof
wooden
underground structures
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14610486A
Other languages
Japanese (ja)
Other versions
JPS634123A (en
Inventor
Hirotake Shibuya
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Astemo Ltd
Original Assignee
Nissin Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nissin Kogyo Co Ltd filed Critical Nissin Kogyo Co Ltd
Priority to JP14610486A priority Critical patent/JPS634123A/en
Publication of JPS634123A publication Critical patent/JPS634123A/en
Publication of JPH0452814B2 publication Critical patent/JPH0452814B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、例えば地下鉄,共同溝などの地下構
造築物の先やり防水工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a preliminary waterproofing method for underground structures such as subways and public ditches.

(従来の技術) 従来、地下鉄,共同溝などの地下構築物におい
ては、これら構築物の建設に先立つて防水工事が
おこなわれている。殊に都市部においては、堀削
する土量をできるだけ少なくして、工事補償の対
象となる関係の地上物件をなるべく少なくし、更
に交通上の支障を極力無くすために堀削幅をでき
るだけ狭くするのが通例である。従つて地下構築
物を建設した後、その外側から防水工事をおこな
うためには、堀削の土留面と構築物側壁との間に
1m以上の作業空間が必要であるが、前記地下構
築物の建設に先立つて防水工事をおこなう、いわ
ゆる先やり防水工法では、先づ構築物から20乃至
40cm離れた両側に一定間隔毎にH形鋼やI形鋼な
どの親杭を土留めの線に沿つて打込んでおき、堀
削と平行して木矢板を親杭の間に嵌込んで土留め
をする。また必要によつては木矢板と親杭の間に
くさびを打込み、木矢板を地山に密着させるよう
にしている。
(Prior Art) Conventionally, waterproofing work has been performed on underground structures such as subways and public ditches prior to construction of these structures. Particularly in urban areas, the amount of soil to be excavated should be minimized, the number of related above-ground properties subject to construction compensation should be minimized, and the width of the excavation should be made as narrow as possible to eliminate traffic hindrances as much as possible. It is customary. Therefore, in order to perform waterproofing work from the outside after constructing an underground structure, a work space of 1 m or more is required between the earth retaining surface of the excavation and the side wall of the structure, but it is necessary to In the so-called pre-emptive waterproofing method, waterproofing work is carried out first on the structure.
Drive main stakes such as H-beams and I-beams at regular intervals on both sides, 40 cm apart, along the earth retaining line, and fit wooden sheet piles between the main stakes in parallel with the excavation. Make a soil retainer. In addition, if necessary, wedges are driven between the wooden sheet piles and the main piles to keep the wooden sheet piles in close contact with the ground.

次いで、この土留面から湧出する水を排出する
ため、木矢板の内側10乃至15cmの距離をおき、土
留面に平行して一定間隔毎に桟木を駒によつて木
矢板に取りつけ固定して排水空間をつくるが、更
に該桟木にベニヤ合板を釘止めして、その上に防
水下地板を釘止めしてから防水シートを貼りつけ
る。更に地下構築物を建設した後、前記排水空間
にはモルタルを充填しなければならないので作業
が非常に煩雑である。
Next, in order to drain the water that gushes out from this earth retaining surface, a distance of 10 to 15 cm is placed inside the wooden sheet pile, and piers are attached to the wooden sheet pile with pieces at regular intervals parallel to the earth retaining surface and fixed to drain water. After creating a space, plywood plywood is nailed to the crosspiece, a waterproof base board is nailed on top of the plywood, and a waterproof sheet is attached. Furthermore, after constructing the underground structure, the drainage space must be filled with mortar, which makes the work very complicated.

(発明が解決しようとする問題点) 従来の先やり防水工法では、排水空間および防
水下地をつくるまでと地下構築物を建設した後に
排水空間にモルタルを充填するのに多くの時間と
費用を必要とした。また都市の過密化にともない
堀削する土量をより少なくする必要性が生じて来
ている。本発明は以上の問題点を解決するために
なされたもので、堀削する土量を最小限にすると
ともに排水機能を損なうことなく、しかも施工が
簡単な地下構築物の防水工法を提供することを目
的とする。
(Problems to be solved by the invention) In the conventional pre-emptive waterproofing method, it takes a lot of time and money to create the drainage space and waterproof foundation and to fill the drainage space with mortar after constructing the underground structure. did. Furthermore, as cities become more densely populated, there is a need to reduce the amount of soil to be excavated. The present invention has been made to solve the above problems, and aims to provide a waterproofing method for underground structures that minimizes the amount of soil to be excavated, does not impair the drainage function, and is easy to construct. purpose.

(問題点を解決するための手段) 地下鉄,共同溝などの地下構築物の外周に防水
工事をおこなうに際して、これら地下構築物の建
設に先立つて一定間隔毎にH形鋼などの親杭を打
込んでおき、堀削と平行して木矢板を親杭の間に
嵌込んで固定し、更に該木矢板の上にベニヤ合板
を釘止めして、その上に排水を容易にするための
突起付き導水シートをホツチキスなどで仮止めし
更に、その上に防水下地板を釘止めして防水シー
トを貼り付けることを特徴とする地下構築物の防
水工法である。
(Means to solve the problem) When waterproofing the outer periphery of underground structures such as subways and public ditches, it is necessary to drive parent piles such as H-beams at regular intervals prior to the construction of these underground structures. A wooden board pile is inserted and fixed between the main piles in parallel with the excavation, and a plywood plywood is nailed on top of the wooden board pile. This method of waterproofing underground structures is characterized by temporarily fixing sheets with staples, etc., and then nailing a waterproof base plate on top of the sheets and pasting the waterproof sheet.

(実施例) 本発明の実施例及び作用を図面に基づき詳細に
説明する。第2図および第4図は、それぞれ本発
明の実施例を示す斜視図および水平断面図である
が、地下構築物1の建設に先立つて1乃至1.5m
毎にH形鋼やI形鋼などの親杭2を打込んでお
き、堀削と平行して地山3を崩落させないよう
に、速やかに少なくとも30m/m以上の厚さを有
する木矢板4を、前記親杭2の間に嵌込んで固定
し土留めする。この際必要によつては木矢板と親
杭の間にくさびを打込んで、木矢板4を地山3に
密着させることをおこなう。堀削が進むにしたが
つて、木矢板4は親杭のフランジ部分2aの内側
の面に沿つて下方へさがつて行くので、順次上か
ら新しい木矢板を嵌込んで土留めする。木矢板4
には土圧がかなり加わり、該木矢板4の両端は親
杭のフランジ部分2aの面にて支えられるが、土
圧に充分耐えられるように厚みのあるものを使用
するのが好ましい。
(Example) Examples and effects of the present invention will be described in detail based on the drawings. 2 and 4 are a perspective view and a horizontal cross-sectional view, respectively, showing an embodiment of the present invention.
Drive a parent pile 2 such as an H-beam or an I-beam into each area, and immediately install wooden sheet piles 4 with a thickness of at least 30 m/m in parallel with the excavation to prevent the ground 3 from collapsing. are fitted between the main piles 2 and fixed to retain the ground. At this time, if necessary, wedges are driven between the wooden sheet piles and the main piles to bring the wooden sheet piles 4 into close contact with the ground 3. As the excavation progresses, the wooden sheet piles 4 move downward along the inner surface of the flange portion 2a of the parent pile, so new wooden sheet piles are successively fitted from above to retain the soil. Wooden pile 4
A considerable amount of earth pressure is applied to the pile, and both ends of the wooden sheet pile 4 are supported by the surfaces of the flange portions 2a of the parent pile.However, it is preferable to use a sheet pile that is thick enough to withstand the earth pressure.

次いで木矢板4のベニヤ合板5を釘止めして固
定するが、仕上がり面が平らな面を形成するよう
に該ベニヤ合板5は親杭のフランジ部分2aの厚
さとほゞ同じ厚さのものを用いる。
Next, the plywood 5 of the wooden board pile 4 is fixed with nails, but the plywood 5 should have approximately the same thickness as the flange portion 2a of the parent pile so that the finished surface forms a flat surface. use

従来は堀削した土留面から湧出す水が、木矢板
の〓間を通して内側へ滲み出て来るので、排水す
るための空間を設ける必要があり、第1図および
第3図に示すように、木矢板4を親杭2の間に嵌
込んだ後、木矢板の内側に10乃至15cmの距離をお
き、土留面に平行して一定間隔毎に桟木6を駒7
によつて、木矢板4に取り付け固定し、こん部分
が排水空間を形成していた。
Conventionally, the water that gushes out from the excavated earth retaining surface seeps inward through the gaps between the wooden sheet piles, so it is necessary to provide a space for drainage, as shown in Figures 1 and 3. After inserting the wooden sheet piles 4 between the main piles 2, place the wooden piles 6 and 7 at regular intervals parallel to the retaining surface at a distance of 10 to 15 cm inside the wooden sheet piles.
It was attached and fixed to wooden sheet piles 4, and the bottom part formed a drainage space.

しかるに、本発明の実施例によれば、ベニヤ合
板5を釘止めした仕上がり面に対して、突起付き
導水シート8、好ましくは片側全面に複数条の平
行突起を有するルーフイングを、ホツチキス等で
仮止めする。土留面から湧出した水は該突起付き
導水シート8の凹部の空間を通して排水すること
ができる。突起部分の高さが数ミリ程度のもので
も極めて容易に排水することが可能である。
However, according to the embodiment of the present invention, the water guide sheet 8 with protrusions, preferably the roofing having a plurality of parallel protrusions on the entire surface of one side, is temporarily attached with staples or the like to the finished surface to which the plywood 5 is nailed. Stop it. Water gushing out from the retaining surface can be drained through the space of the recessed portion of the water guide sheet 8 with projections. Even if the height of the protruding portion is several millimeters, it is possible to drain water extremely easily.

突起付き導水シート8の突起は形状は、上記の
複数条の平行突起に限定されるものではなく、例
えば多数の円形状または角形状のものでも差支え
ない。施工後連通空間を形成するものであれば同
じように作用する。
The shape of the protrusions of the protrusion-equipped water guide sheet 8 is not limited to the plurality of parallel protrusions described above, and may be, for example, a large number of circular or angular shapes. It works in the same way if it forms a communicating space after construction.

次いで突起付き導水シート8の上に防水下地板
9好ましくは6乃至10m/m厚さの瀝青質板を、
前記ベニヤ合板5に達する長さの釘で該ベニヤ合
板5に固定する。排水は突起付き導水シート8で
おこなわれるので、防水下地板9の表面は乾燥状
態が保たれ良好な防水下地面を与えることができ
る。この上に防水シート10を貼りつけるが、防
水下地面が濡れていたり乾燥が不充分である時
は、該防水シート10が水分の影響により、下地
面に接着しなかつたり施工後剥離したりしてトラ
ブルを起こし易い。実施例の如く防水下地面が充
分乾燥して居れば、防水シート10は粘着剤層付
きのもので剥離紙をはがしながらそのまゝ貼りつ
けてもよく、粘着剤層のないものを接着剤などで
貼りつけても何れでもよい。
Next, on top of the water guide sheet 8 with projections, a waterproof base plate 9, preferably a bituminous plate with a thickness of 6 to 10 m/m, is placed.
It is fixed to the veneer plywood 5 with nails long enough to reach the veneer plywood 5. Since drainage is carried out by the water guiding sheet 8 with projections, the surface of the waterproof base plate 9 is kept dry and a good waterproof base surface can be provided. A waterproof sheet 10 is pasted on top of this, but if the waterproof base surface is wet or not sufficiently dried, the waterproof sheet 10 may not adhere to the base surface or peel off after installation due to the influence of moisture. can easily cause trouble. As long as the waterproof base surface is sufficiently dry as in the example, the waterproof sheet 10 with an adhesive layer may be attached as is while peeling off the release paper, or the waterproof sheet 10 without an adhesive layer may be attached with an adhesive, etc. It doesn't matter if you paste it with.

(発明の効果) 本発明の地下構築物の防水工法を用いれば、木
矢板と防水下地板の間に空間を生ずることがない
ので、その分だけ堀削する土量を少なくすること
ができるとともに、従来おこなわれて来たように
桟木や駒の設置の必要がなく、また地下構築物を
建設した後に、埋戻しをおこなう際排水空間にモ
ルタルを充填する必要もなくなる。従つて大幅な
工期の短縮と経費の節減をはかることができる。
(Effects of the invention) If the waterproofing method for underground structures of the present invention is used, no space is created between the wooden sheet piles and the waterproof foundation board, so the amount of soil to be excavated can be reduced by that amount, and it is possible to reduce the amount of soil that needs to be excavated by that amount. There is no need to install piers or pieces as was previously the case, and there is no need to fill the drainage space with mortar when backfilling after constructing an underground structure. Therefore, it is possible to significantly shorten the construction period and reduce costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第3図は従来の防水施工状態を示
す斜視図および水平断面図であり、第2図および
第4図は本発明実施例の防水施工状態を示す斜視
図および水平断面図である。 1……地下構築物、2……親杭、2a……親杭
のフランジ部、3……地山、4……木矢板、5…
…ベニヤ合板、6……桟木、7……駒、8……突
起付き導水シート、9……防水下地板、10……
防水シート。
1 and 3 are a perspective view and a horizontal sectional view showing a conventional waterproof construction state, and FIGS. 2 and 4 are a perspective view and a horizontal sectional view showing a waterproof construction state according to an embodiment of the present invention. . 1... Underground structure, 2... Main pile, 2a... Flange part of main pile, 3... Earth, 4... Wood pile, 5...
...Plywood plywood, 6...Structure, 7...piece, 8...Water conductive sheet with protrusions, 9...Waterproof base plate, 10...
Tarpaulin.

Claims (1)

【特許請求の範囲】[Claims] 1 地下鉄,共同溝などの地下構築物の外周に防
水工事をおこなうに際して、これら地下構築物の
建設に先立つて一定間隔毎にH形鋼などの親杭を
打込んでおき、堀削と平行して木矢板を親杭の間
に嵌込んで固定し、更に該木矢板の上にベニヤ合
板を釘止めして、その上に排水を容易にするため
の突起付き導水シートをホツチキスなどで仮止め
し更に、その上に防水下地板を釘止めして防水シ
ートを貼り付けることを特徴とする地下構築物の
防水工法。
1. When carrying out waterproofing work around the outer periphery of underground structures such as subways and public ditches, prior to the construction of these underground structures, parent piles such as H-shaped steel are driven in at regular intervals, and wood piles are installed in parallel with the excavation. The sheet piles are fitted and fixed between the main piles, plywood is nailed on top of the wooden sheet piles, and a water guide sheet with protrusions is temporarily fastened on top of it with staples to facilitate drainage. A method of waterproofing underground structures, which is characterized by nailing a waterproof base plate and pasting a waterproof sheet thereon.
JP14610486A 1986-06-24 1986-06-24 Water-proof construction for underground structure Granted JPS634123A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14610486A JPS634123A (en) 1986-06-24 1986-06-24 Water-proof construction for underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14610486A JPS634123A (en) 1986-06-24 1986-06-24 Water-proof construction for underground structure

Publications (2)

Publication Number Publication Date
JPS634123A JPS634123A (en) 1988-01-09
JPH0452814B2 true JPH0452814B2 (en) 1992-08-24

Family

ID=15400237

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14610486A Granted JPS634123A (en) 1986-06-24 1986-06-24 Water-proof construction for underground structure

Country Status (1)

Country Link
JP (1) JPS634123A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63184620A (en) * 1987-01-28 1988-07-30 Takenaka Komuten Co Ltd Water-proofing work for underground outer wall
JPS64653U (en) * 1987-06-15 1989-01-05
CN102720217A (en) * 2012-06-12 2012-10-10 浙江城建建设集团有限公司 Basement watertightness structure and construction method thereof
JP2014101647A (en) * 2012-11-19 2014-06-05 Yamada Co Ltd Steel pile and method of application of steel pile

Also Published As

Publication number Publication date
JPS634123A (en) 1988-01-09

Similar Documents

Publication Publication Date Title
US5067289A (en) Foundation system for manufactured housing
JPH11152761A (en) Underground structure and its construction method
US2194279A (en) Skeleton framework structure and method of constructing the same
GB2235235A (en) Forming structures in ground
US6220789B1 (en) Integrated excavation shoring building foundation method
JPH0452814B2 (en)
JPH08269984A (en) Construction of basement in outside waterproofing construction method
SU868019A1 (en) Method of erecting a structure partly submerged in soil
US4205499A (en) Pool wall and deck assembly and method of assembling the same
JP2994243B2 (en) External wall construction method and external wall structure for underground structures
JPS6043500B2 (en) How to build a basement
JP3150612B2 (en) Foundation for low-rise buildings
JPS6135334B2 (en)
JPH084033A (en) Construction method of the pressure barrier against the outer perimeter of the building
JP2905625B2 (en) Half Pca plate method for underground outer wall
JPH09242089A (en) Underground outer wall using mountain retaining wall
KR200247005Y1 (en) Cast-in-site diaphragms wall with benoto method and grouting method of high pressure
CN222649128U (en) Waterproof masonry wall with external wall settlement joint
CN113513042B (en) Underground waterproof engineering construction method
JPS5919204B2 (en) Underground excavation method
CA2093708A1 (en) Prefabricated building foundation
JPS621930A (en) Foundation structure of underground structure
JPS6033160Y2 (en) Civil engineering and construction blocks
JP3307819B2 (en) Driving formwork method for underground outer wall
JPH10280434A (en) Construction method for basement under application of outside waterproofing