JPH0459412B2 - - Google Patents

Info

Publication number
JPH0459412B2
JPH0459412B2 JP14392585A JP14392585A JPH0459412B2 JP H0459412 B2 JPH0459412 B2 JP H0459412B2 JP 14392585 A JP14392585 A JP 14392585A JP 14392585 A JP14392585 A JP 14392585A JP H0459412 B2 JPH0459412 B2 JP H0459412B2
Authority
JP
Japan
Prior art keywords
sinker
underwater
jack
girder
leg
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14392585A
Other languages
Japanese (ja)
Other versions
JPS626026A (en
Inventor
Kenji Kikuchi
Shigeyoshi Kozai
Kazuo Fujiki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP14392585A priority Critical patent/JPS626026A/en
Publication of JPS626026A publication Critical patent/JPS626026A/en
Publication of JPH0459412B2 publication Critical patent/JPH0459412B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、水中桁着底式の捨石均し装置に関
し、特に比較的簡単な操作でもつて水中桁を精度
よく水底に据付けることができるようにした水中
桁着底式の捨石均し装置に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to an underwater girder bottom-mounted rubble leveling device, and in particular, an underwater girder that can be accurately installed on the water bottom with relatively simple operation. This invention relates to an underwater girder bottom-mounted rubble leveling device.

{従来技術] 例えば海底に基礎構造物を構築するには、まず
海底の堆積物を浚渫しその浚渫底面上に砂利、砕
石等の捨石層を所定の厚みに順次形成し、その上
に構造物を構築する。このように捨石層はその上
面を敷き均して実質的に平面としなければなら
ず、このために捨石の投入工程および敷き均しの
ためのスクリード工程を必要とする。
[Prior art] For example, in order to construct a foundation structure on the seabed, first the seabed sediment is dredged, a layer of rubble such as gravel or crushed stone is sequentially formed to a predetermined thickness on the bottom of the dredged material, and then a structure is built on top of the dredged sediment. Build. In this manner, the top surface of the rubble layer must be leveled to make it substantially flat, and for this purpose, a process of introducing rubble and a screed process for leveling the layer are required.

この捨石の投入および敷き均しを行う装置とし
ては、作業船上よりラダーを吊下げて捨石の投入
および敷き均しを行う形式のものと、海底に水中
桁を据付けて捨石の投入および敷き均しを行う形
式のものとが知られている。
There are two types of equipment for loading and leveling the rubble: one is a ladder suspended from a work boat to load and level the rubble, and the other is an underwater girder installed on the seabed for loading and leveling the rubble. There are known forms that perform this.

本発明は後者の形式に属するものであり、この
形式による装置の場合は、波浪の影響を受けず捨
石の投入および敷き均しを安定して行えて好まし
いが、従来の装置による場合は水中桁の海底への
据付けに問題があつた。すなわち、 (i) 従来の装置の場合は、水中桁とシンカーが
別々で、まず4個のシンカーを単独に水深40m
前後の不陸がある捨石マウンド面に設置するの
で、据付距離、角度、レベルの誤差を生じる。
The present invention belongs to the latter type, and this type of device is preferable because it can stably load and level rubble without being affected by waves, but the conventional device uses underwater girders. There was a problem with installing it on the seabed. In other words, (i) In the case of conventional equipment, the underwater girders and sinkers are separate, and the four sinkers are first placed individually at a depth of 40 m.
Since it is installed on a rubble mound surface with uneven front and back, errors occur in installation distance, angle, and level.

(ii) 上記の誤差を吸収するための施工及び測量に
多大な時間と費用を要す。また誤差を吸収する
ため大きなジヤツキと広いスペースが必要とな
る。
(ii) Construction and surveying to absorb the above errors will require a great deal of time and expense. Also, a large amount of space and a large amount of space are required to absorb errors.

(iii) 捨石マウンド面に高低差(勾配)があるとシ
ンカーが勾配になつて着底するので、水中桁の
レベル調整が困難となる。
(iii) If there is a height difference (slope) on the rubble mound surface, the sinker will land on the bottom at a slope, making it difficult to adjust the level of the underwater girder.

(iv) 距離、角度の誤差があると水中桁の脚4点の
誤差が生じ、無理な力が水中桁に作用してスク
リード機械が作動しなくなる。
(iv) If there is an error in distance or angle, an error will occur in the four legs of the underwater girder, and unreasonable force will be applied to the underwater girder, causing the screed machine to stop working.

(v) シンカーが大きくなるのでその撤去及び移動
に時間と費用を要する。
(v) Since the sinker is large, it takes time and money to remove and move it.

[発明の目的] 本発明は従来の捨石均し装置の前記欠点を解消
すべくなされたもので、その目的とするところは
水中桁を容易にかつ精度よく据付けることのでき
る捨石均し装置を提供するにあり、また捨石マウ
ンド面に高低差(勾配)があつてシンカーが勾配
に沿つて着底しても水中桁に無理な力がかから
ず、かつ水中桁のレベル調整を容易に行うことの
できる捨石均し装置を提供するにあり、またシン
カーとして比較的小型のシンカーを用いることが
でき、したがつてシンカーの撤去及び移動の容易
な捨石均し装置を提供するにある。
[Object of the Invention] The present invention has been made to solve the above-mentioned drawbacks of conventional rubble leveling devices, and its purpose is to provide a rubble leveling device that can easily and accurately install underwater girders. In addition, even if there is a height difference (slope) on the rubble mound surface and the sinker lands on the bottom along the slope, no undue force is applied to the underwater girder, and the level of the underwater girder can be easily adjusted. To provide a rubble leveling device which can use a relatively small sinker as a sinker, and which allows the sinker to be easily removed and moved.

[発明の構成] このため本発明によれば、スクリード機械を支
持し該機械の移動をガイドする方形に組立てられ
た水中桁の各隅部に上下方向に伸縮する油圧ジヤ
ツキを備えたジヤツキアツプ脚を固定して設け
て、該ジヤツキアツプ脚の下端部から凹部を備え
たシンカーをチエーンにより吊下げ、また前記ジ
ヤツキアツプ脚の油圧ジヤツキの下端に球面軸受
を介して水平反力装置を取付け、該水平反力装置
は前記シンカーの凹部の底壁に着底すると共に左
右方向に伸縮する油圧ジヤツキを備えており、該
油圧ジヤツキはそれを伸長させることによりシン
カーの凹部の側壁に圧力をかけたシンカーと水平
反力装置とがすべらないようにするものである水
中桁着底式捨石均し装置が提供される。
[Structure of the Invention] Therefore, according to the present invention, a hydraulic jack that extends and retracts in the vertical direction is provided at each corner of an underwater girder assembled in a rectangular shape that supports a screed machine and guides the movement of the machine. A sinker having a concave portion is suspended from the lower end of the jack up leg by a chain, and a horizontal reaction force device is attached via a spherical bearing to the lower end of the hydraulic jack of the jack up leg, and the horizontal reaction force is The device is equipped with a hydraulic jack that touches the bottom wall of the recess of the sinker and expands and contracts in the left and right directions, and by extending the hydraulic jack, the hydraulic jack applies pressure to the side wall of the recess of the sinker and causes a horizontal reaction. Provided is an underwater girder bottom-mounted rubble leveling device that prevents slippage between the power device and the power device.

本発明の実施に際しては、水中桁にフロートを
設けて作業船(台船)の下に水中桁を引き込み台
船と水中桁を一体化できる構造とする。
When implementing the present invention, a structure is adopted in which a float is provided on the underwater girder and the underwater girder is pulled under the work boat (barge) to integrate the barge and the underwater girder.

[発明の作用効果] このように本発明に係る捨石均し装置は、水中
桁とシンカーが一体になつているので、水中桁を
沈設する際にシンカーも同時に沈設し、したがつ
て大水深の場合でも水中桁の脚とシンカーとの位
置がずれることがなく、水中桁の据付けの手間が
少なくなると共に精度よく据付けを行うことがで
き、かつシンカーは小型のものであつてもよく、
その撤去及び移動が容易になる。また水平反力装
置はジヤツキアツプ脚と球面軸受で連結されてい
るので、自由回転が可能であり、シンカーの勾配
に沿つて水中桁を着底させることができ、水中桁
に無理な力がかかることがなく、したがつてスク
リード機械が作動しなくなる等の不都合は解消さ
れる。また水中桁の脚は油圧ジヤツキを備えたジ
ヤツキアツプ脚であるので、捨石マウンド面の不
陸に対して水中桁の据付け高さのレベル調整が可
能であり、高精度で水中桁を据付けることができ
る。
[Operations and Effects of the Invention] As described above, in the rubble leveling device according to the present invention, the underwater girder and the sinker are integrated, so when the underwater girder is sunk, the sinker is also sunk at the same time, so that it can be used in large depths of water. The legs of the underwater girder and the sinker do not shift in position even when the girder is in the water, the effort required to install the underwater girder is reduced, and the installation can be carried out with high accuracy, and the sinker may be small.
Its removal and movement become easier. In addition, the horizontal reaction force device is connected to the jack up leg with a spherical bearing, so it can rotate freely, allowing the underwater girder to land on the bottom along the slope of the sinker, and preventing excessive force from being applied to the underwater girder. Therefore, inconveniences such as the screed machine not operating are eliminated. In addition, the legs of the underwater girder are jack-up legs equipped with hydraulic jacks, so the installation height of the underwater girder can be adjusted to the unevenness of the rubble mound surface, and the underwater girder can be installed with high precision. can.

[実施例] 以下、図面を参照して本発明の実施例につき説
明する。
[Examples] Examples of the present invention will be described below with reference to the drawings.

第1図ないし第3図において、全体を1で示す
のは作業船で、この作業船1には操船ウインチ
2、水中桁吊上げウインチ3、砕石貯蔵ホツパ
4、コンベヤ5、後述のスクリード機械11のト
レミーパイプ12に砕石を投下するための砕石ホ
ツパ6などが設けられている。全体を7で示すの
は方形に組立てられた水中桁で作業船1に設けた
前記の水中桁吊上げウインチ3によりシーブ8、
ワイヤ9を介して吊下げられて沈設される。水中
桁7にはフロート10が設けられていて浮力の増
大を計つている。11はスクリード機械で、この
スクリード機械11には前記砕石貯蔵ホツパ4か
らコンベヤ5により砕石ホツパ6に搬送された砕
石がトレミーパイプ12を経て供給され、海底A
に砕石を投下すると共に砕石を均す。このためス
クリード機械11は水中桁7に支持されて水中桁
7に沿つて水平移動する。
In FIGS. 1 to 3, the work boat is designated as a whole by 1, and this work boat 1 includes a steering winch 2, an underwater girder lifting winch 3, a crushed stone storage hopper 4, a conveyor 5, and a screed machine 11 to be described later. A crushed stone hopper 6 and the like for dropping crushed stone into the tremie pipe 12 are provided. The whole number 7 indicates an underwater girder assembled into a rectangular shape, and a sheave 8,
It is suspended and submerged via a wire 9. A float 10 is provided on the underwater girder 7 to increase buoyancy. Reference numeral 11 denotes a screed machine, to which the crushed stone conveyed from the crushed stone storage hopper 4 to the crushed stone hopper 6 by the conveyor 5 is supplied via a tremie pipe 12.
Drop crushed stones and level the crushed stones. Therefore, the screed machine 11 is supported by the underwater girder 7 and moves horizontally along the underwater girder 7.

第1図ないし第3図のほか第4図ないし第6図
を参照してさらに説明すると、水中桁7の各隅部
にはジヤツキアツプ脚13が固定して設けられて
おり、このジヤツキアツプ脚13は上下方向に伸
縮する油圧ジヤツキ14を備えている。またジヤ
ツキアツプ脚13の先端にはフロート15が設け
られている。各ジヤツキアツプ脚13の下端部か
らシンカー16がチエーン17により吊下げられ
ており、このシンカー16には凹部(凹溝)18
が形成されている。またジヤツキアツプ脚13の
油圧ジヤツキ14の下端には球面軸受19を介し
て全体20で示す水平反力装置が取付けられてい
る。この水平反力装置20はシンカー16の凹部
18の側壁18bに圧力をかけてシンカー16と
水平反力装置20とがすべらないようにする。
Further explanation will be given with reference to FIGS. 4 to 6 in addition to FIGS. 1 to 3. A jack up leg 13 is fixedly provided at each corner of the underwater girder 7. It is equipped with a hydraulic jack 14 that expands and contracts in the vertical direction. Further, a float 15 is provided at the tip of the jack up leg 13. A sinker 16 is suspended from the lower end of each jack up leg 13 by a chain 17, and this sinker 16 has a recess (groove) 18.
is formed. Further, a horizontal reaction force device generally designated 20 is attached to the lower end of the hydraulic jack 14 of the jack up leg 13 via a spherical bearing 19. The horizontal reaction device 20 applies pressure to the side wall 18b of the recess 18 of the sinker 16 to prevent the sinker 16 and the horizontal reaction device 20 from slipping.

次に主として第4図ないし第6図を参照して水
中桁を海底面に据付ける態様につき説明する。
Next, referring mainly to FIGS. 4 to 6, the manner in which the underwater girder is installed on the seabed surface will be explained.

前述のようにジヤツキアツプ脚13は水中桁7
に固定されており、またシンカー16はジヤツキ
アツプ脚13よりチエーン17で吊下げられてい
る。水中桁7の降下は作業船1上の水中桁吊上げ
ウインチ3によりシーブ8、ワイヤ9を経て行わ
れる。
As mentioned above, the jack up leg 13 is attached to the underwater girder 7.
The sinker 16 is suspended from the jack up leg 13 by a chain 17. The underwater girder 7 is lowered by the underwater girder lifting winch 3 on the work boat 1 via a sheave 8 and a wire 9.

水中桁吊上げウインチ3(4台)は等連で作動
し、このウインチ3の巻下げにより水中桁7の吊
点4か所は等速で緩やかな速度で降下する(第4
図)。
The underwater girder lifting winches 3 (4 units) operate in equal succession, and by lowering the winches 3, the four suspension points of the underwater girder 7 descend at a constant and gentle speed (the 4th
figure).

水中桁7の降下と共にシンカー16も降下す
る。シンカー16は捨石マウンド面Aの一番高い
所に当つて着底する。この時、捨石マウンド面A
に高低差(勾配)があればこの高低差に沿つて着
底する。
As the underwater girder 7 descends, the sinker 16 also descends. The sinker 16 hits the highest point of the rubble mound surface A and lands on the bottom. At this time, rubble mound surface A
If there is a difference in height (gradient), the object will land on the bottom along this difference in height.

さらに水中桁7は降下し、ジヤツキアツプ脚1
3の根元に設けた水平反力装置20がシンカー1
6の凹部18の底壁18aに着底する。
Furthermore, the underwater girder 7 descends, and the jack up leg 1
The horizontal reaction force device 20 installed at the base of 3 is the sinker 1
It bottoms out on the bottom wall 18a of the recess 18 of No.6.

水平反力装置20がシンカー16の凹部底壁1
8aに着底すると水中桁吊上げウインチ3の巻下
げをストップさせウインチ3にブレーキをかけて
水中桁7を支持する。
The horizontal reaction force device 20 is connected to the recessed bottom wall 1 of the sinker 16.
When the underwater girder 8a reaches the bottom, the lowering of the underwater girder lifting winch 3 is stopped and the brake is applied to the winch 3 to support the underwater girder 7.

次に水平反力装置20に内蔵された油圧ジヤツ
キ21を伸長させてシンカー16の凹部18の側
壁18aに圧力をかけてシンカー16と水平反力
装置20がすべらないようにする。
Next, the hydraulic jack 21 built into the horizontal reaction device 20 is extended to apply pressure to the side wall 18a of the recess 18 of the sinker 16 to prevent the sinker 16 and the horizontal reaction device 20 from slipping.

この際、水平反力装置20はジヤツキアツプ脚
13と球面軸受19で連結されているので自由回
転が可能であり、シンカー16の勾配に沿つて着
底することができる(第5図)。
At this time, since the horizontal reaction force device 20 is connected to the jack up leg 13 by a spherical bearing 19, it can rotate freely and can land on the bottom along the slope of the sinker 16 (FIG. 5).

次に捨石マウンド面Aの低い所に着底したシン
カー16の凹部底壁18aに水平反力装置20を
着底させるため、ジヤツキアツプ脚13に内蔵さ
れた油圧ジヤツキ14を伸長させる。水平反力装
置20がシンカー16の凹部底壁18aに着底す
ると水平反力装置20の油圧ジヤツキ21を伸長
させ、シンカー16の凹部側壁18bに圧力をか
けてシンカー16と水平反力装置20がすべらな
いようにする。
Next, in order to cause the horizontal reaction force device 20 to bottom out on the bottom wall 18a of the recess of the sinker 16 that has bottomed out at a low place on the rubble mound surface A, the hydraulic jack 14 built in the jack up leg 13 is extended. When the horizontal reaction device 20 touches the bottom wall 18a of the recess of the sinker 16, the hydraulic jack 21 of the horizontal reaction device 20 is extended to apply pressure to the side wall 18b of the recess of the sinker 16, causing the sinker 16 and the horizontal reaction device 20 to Avoid slipping.

このようにして順次4点のジヤツキアツプ脚1
3及び水平反力装置20を作動させて水中桁7の
据付及びレベル調整を行う。
In this way, 4 points are jacked up leg 1 in sequence.
3 and the horizontal reaction force device 20 are operated to install the underwater girder 7 and adjust the level.

最後に水中桁7の4本のレベルをトランスポン
ダ等で測定して水中桁7のレベル微調整をジヤツ
キアツプ脚13の油圧ジヤツキ14で行う。
Finally, the levels of the four underwater girders 7 are measured using a transponder or the like, and the level of the underwater girders 7 is finely adjusted using the hydraulic jacks 14 of the jack up legs 13.

なお、ジヤツキアツプ脚13の油圧ジヤツキ1
4は荷重がかかつても降下しないようにロツキン
グ装置を設ける。
In addition, the hydraulic jack 1 of the jack up leg 13
4 is provided with a locking device to prevent it from falling even when the load is applied.

[結 び] 以上説明したように本発明によれば、水中桁を
容易にかつ精度よく据付けることができ、海底や
水底に基礎構築物を構築するための捨石層を能率
よく構築することができるものである。
[Conclusion] As explained above, according to the present invention, underwater girders can be installed easily and accurately, and a rubble layer for constructing foundation structures on the seabed or underwater can be efficiently constructed. It is something.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第3図は本発明の実施例に係る水
中桁着底式捨石均し装置の全容を示し、第1図は
正面図、第2図は平面図、第3図は側面図、第4
図、第5図及び第6図は水中桁の据付け工程を示
す各正面図である。 1……作業船、2……操船ウインチ、3……水
中桁吊上げウインチ、4……砕石貯蔵ホツパ、5
……コンベヤ、6……砕石ホツパ、7……水中
桁、8……シーブ、9……ワイヤ、10……フロ
ート、11……スクリード機械、12……トレミ
ーパイプ、13……ジヤツキアツプ脚、14……
油圧ジヤツキ、15……フロート、16……シン
カー、17……チエーン、18……凹部、19…
…球面軸受、20……水平反力装置、21……油
圧ジヤツキ。
Figures 1 to 3 show the overall appearance of an underwater girder type rubble leveling device according to an embodiment of the present invention, in which Figure 1 is a front view, Figure 2 is a plan view, Figure 3 is a side view, Fourth
Figures 5 and 6 are front views showing the installation process of the underwater girder. 1... Work boat, 2... Ship operation winch, 3... Underwater girder lifting winch, 4... Crushed stone storage hopper, 5
... Conveyor, 6 ... Crushed stone hopper, 7 ... Underwater girder, 8 ... Sheave, 9 ... Wire, 10 ... Float, 11 ... Screed machine, 12 ... Tremy pipe, 13 ... Jacket leg, 14 ……
Hydraulic jack, 15...Float, 16...Sinker, 17...Chain, 18...Recess, 19...
...Spherical bearing, 20...Horizontal reaction force device, 21...Hydraulic jack.

Claims (1)

【特許請求の範囲】[Claims] 1 スクリード機械を支持し該機械の移動をガイ
ドする方形に組立てられた水中桁の各隅部に上下
方向に伸縮する油圧ジヤツキを備えたジヤツキア
ツプ脚を固定して設けて、該ジヤツキアツプ脚の
下端部から凹部を備えたシンカーをチエーンによ
り吊下げ、また前記ジヤツキアツプ脚の油圧ジヤ
ツキの下端に球面軸受を介して水平反力装置を取
付け、該水平反力装置は前記シンカーの凹部の底
壁に着底すると共に左右方向に伸縮する油圧ジヤ
ツキを備えており、該油圧ジヤツキはそれを伸長
させることによりシンカーの凹部の側壁に圧力を
かけたシンカーと水平反力装置とがすべらないよ
うにするものであることを特徴とする水中桁着底
捨石均し装置。
1. A jack up leg equipped with a hydraulic jack that expands and contracts in the vertical direction is fixedly provided at each corner of an underwater girder assembled in a rectangular shape that supports a screed machine and guides the movement of the machine, and the lower end of the jack up leg is provided. A sinker with a concave portion is suspended from the sinker by a chain, and a horizontal reaction device is attached to the lower end of the hydraulic jack of the jack up leg via a spherical bearing, and the horizontal reaction device bottoms out on the bottom wall of the concave portion of the sinker. At the same time, it is equipped with a hydraulic jack that expands and contracts in the left-right direction, and by extending the hydraulic jack, the horizontal reaction force device prevents the sinker, which applies pressure to the side wall of the sinker recess, from slipping. An underwater girder bottom rubble leveling device characterized by:
JP14392585A 1985-07-02 1985-07-02 Underwater bottom-landing ype rubble leveler Granted JPS626026A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14392585A JPS626026A (en) 1985-07-02 1985-07-02 Underwater bottom-landing ype rubble leveler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14392585A JPS626026A (en) 1985-07-02 1985-07-02 Underwater bottom-landing ype rubble leveler

Publications (2)

Publication Number Publication Date
JPS626026A JPS626026A (en) 1987-01-13
JPH0459412B2 true JPH0459412B2 (en) 1992-09-22

Family

ID=15350282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14392585A Granted JPS626026A (en) 1985-07-02 1985-07-02 Underwater bottom-landing ype rubble leveler

Country Status (1)

Country Link
JP (1) JPS626026A (en)

Also Published As

Publication number Publication date
JPS626026A (en) 1987-01-13

Similar Documents

Publication Publication Date Title
US2210408A (en) Marine working platform substructure
US3911687A (en) Foundation method for caissons
US3896628A (en) Marine structures
CA1251939A (en) Subsea foundation element and applications thereof
US4266887A (en) Self-elevating fixed platform
KR0172616B1 (en) Method and apparatus for manufacturing artificial structures in water
RU2090699C1 (en) Offshore platform and method of its construction
EA002258B1 (en) Desk installation system for offshore structures
EP0039590A2 (en) Offshore platform and method of constructing, erecting and dismantling same
CA2063380A1 (en) Jackable oil rigs and corner columns for producing legs in an oil rig
CN1020203C (en) Manufacturing method and equipment for structural parts of river port engineering
US3961489A (en) Method for placing a floating structure on the sea bed
CN110435846B (en) High-precision semi-submersible ship immersed tube base body, and prefabricating construction platform and construction method thereof
US4290716A (en) Platform resting on the bottom of a body of water, and method of manufacturing the same
JPH0459412B2 (en)
GB2085948A (en) A method of constructing a concrete offshore structure more than 200m high and stabilized on the sea bed by its own weight
US4285614A (en) Structure allowing the attainment of a precise seabed location
US2935854A (en) Offshore drilling platform
JP7050143B2 (en) Sliding device and sliding support
JP2689253B2 (en) Workboat
WO2008094573A1 (en) Offshore rig support structure
JP2630994B2 (en) Construction method of quay using caisson
CN215906728U (en) Floating type drilling construction platform
JPS6134534B2 (en)
JP2013002075A (en) Construction method of marine structure, and marine structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees