JPS626026A - Underwater bottom-landing ype rubble leveler - Google Patents
Underwater bottom-landing ype rubble levelerInfo
- Publication number
- JPS626026A JPS626026A JP14392585A JP14392585A JPS626026A JP S626026 A JPS626026 A JP S626026A JP 14392585 A JP14392585 A JP 14392585A JP 14392585 A JP14392585 A JP 14392585A JP S626026 A JPS626026 A JP S626026A
- Authority
- JP
- Japan
- Prior art keywords
- sinker
- jack
- underwater
- leg
- rubble
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は、水中桁着底式の捨石均し装置に関し、特に比
較的簡単な操作でもって水中桁を精度よく水底に据付け
ることができるようにした水中桁着底式の捨石均し装置
に関する。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to an underwater girder bottom-mounted rubble leveling device, and in particular, an underwater girder that can be accurately installed on the water bottom with relatively simple operations. This invention relates to an underwater girder bottom-mounted rubble leveling device.
(従来技術]
例えば海底に基礎構造物を構築するには、まず゛海底の
堆積物を1渫しその没渫底面上に砂利、砕石等の捨石層
を所定の厚みに順次形成し、その上に構造物を構築する
。このように捨石層はその上面を敷き均して実質的に平
面としなければならず、このために捨石の投入工程およ
び敷き均しのため ・ ]のスクリード工程を必要
とする。(Prior art) For example, in order to construct a foundation structure on the seabed, first ``one layer of seabed sediment is deposited, a layer of rubble such as gravel or crushed stone is sequentially formed to a predetermined thickness on the bottom of the sediment, and then In this way, the top surface of the rubble layer must be leveled to make it substantially flat, which requires the process of adding rubble and screeding for leveling. shall be.
この捨石の投入および敷き均しを行う装置としでは、作
業船上よりラダーを吊下げて捨石の投入および散き均し
を行う形式のものと、海底に水中桁を据付けて捨石の投
入および敷き均しを行う形式のものとが知られている。There are two types of equipment for loading and leveling the rubble: one is a ladder suspended from a work boat to load and level the rubble, and the other is an underwater girder installed on the seabed for loading and leveling the rubble. It is known that there is a type that performs
本発明は後者の形式に屈するものであり、この形式によ
る装置の場合は、波浪の影響を受けず捨石の投入および
敷き均しを安定して行えて好ましいが、従来の装ぽによ
る場合は水中桁の海底への据付けに問題があった。すな
わち、
(1) 従来の装置の場合は、水中桁とシンカーが別
々で、まず4個のシンカーを単独に水深40m前後の不
陸がある捨石マウンド面に設置するので、据付距離、角
度、レベルの誤差を生じる。The present invention succumbs to the latter type of equipment, and while this type of equipment is preferable because it allows stable loading and leveling of rubble without being affected by waves, the conventional equipment allows for stable loading and leveling of rubble without being affected by waves. There was a problem with installing the girder on the seabed. In other words, (1) In the case of conventional equipment, the underwater girders and sinkers are separate, and the four sinkers are first installed individually on the surface of an uneven rubble mound at a depth of about 40 m, so the installation distance, angle, and level are different. This results in an error of
(11) 上記の誤差を吸収するための施工及びWs
量に多大な時間と費用を要す。また誤差を吸収するため
大きなジヤツキと広いスペースが必要となる。(11) Construction and Ws to absorb the above errors
It takes a huge amount of time and money. Also, a large amount of space and a large amount of space are required to absorb errors.
(lii ) 捨石マウンド面に高低差(勾配)があ
るとシンカーが勾配に沿って着底するので、水中桁のレ
ベル調整が困難となる。(lii) If there is a height difference (slope) on the surface of the rubble mound, the sinker will land on the bottom along the slope, making it difficult to adjust the level of the underwater girder.
(1v) 距離、角度の誤差があると水中桁の脚4点
の誤差が生じ、無理な力が水中桁に作用してスクリード
機械が作動しなくなる。(1v) If there is an error in distance or angle, there will be an error in the four legs of the underwater girder, and unreasonable force will act on the underwater girder, making the screed machine inoperable.
(V) シンカーが大きくなるのでその撤去及び移動
に時間と費用を要する。(V) Since the sinker is large, it takes time and money to remove and move it.
[発明の目的]
本発明は従来の捨石均し装置の前記欠点を解消すべくな
されたもので、その目的とするところは水中桁を容易に
かつ精度よく据付けることのできる捨石均し装置を提供
するにあり、また捨石マウンド面に高低差(勾配)があ
ってシンカーが勾配に沿って着底しても水中桁に無理な
力がかからず、かつ水中桁のレベル調整を容易に行うこ
とのできる捨石均し装置を提供するにあり、またシンカ
ーとして比較的小型のシンカーを用いることができ、し
たがってシンカーの撤去及び移動の容易な捨石均し装置
を提供するにある。[Object of the Invention] The present invention has been made to solve the above-mentioned drawbacks of conventional rubble leveling devices, and its purpose is to provide a rubble leveling device that can easily and accurately install underwater girders. In addition, even if the rubble mound surface has a height difference (slope) and the sinker lands on the bottom along the slope, no undue force is applied to the underwater girder, and the level of the underwater girder can be easily adjusted. To provide a rubble leveling device which can use a relatively small sinker as a sinker, and which allows the sinker to be easily removed and moved.
[発明の構成]
このため本発明によれば、スクリード機械を支持し該機
械の移動をガイドする方形に組立てられた水中桁の各隅
部に上下方向に伸縮する油圧ジヤツキを備えたジヤツキ
アップ脚を固定して設けて、該ジヤツキアップ脚の下端
部から凹部を備えたシンカーをチェーンにより吊下げ、
また前記ジヤツキアップ脚の油圧ジヤツキの下端に球面
軸受を介して水平反力装置を取付け、該水平反力装置は
前記シンカーの凹部の底壁に着底すると共に左右方向に
伸縮する油圧ジヤツキを備えており、該油圧ジヤツキは
それを伸長させることによりシンカーの四部の側壁に圧
力をかけてシンカーと水平反力装置とがすべらないよう
にするものである水中桁着底式捨石均し装置が提供され
る。[Structure of the Invention] Therefore, according to the present invention, a jack-up leg is provided at each corner of an underwater girder assembled in a rectangular shape that supports a screed machine and guides the movement of the machine, and is equipped with a hydraulic jack that extends and contracts in the vertical direction. fixedly provided, and a sinker having a recess is suspended from the lower end of the jack-up leg by a chain;
Further, a horizontal reaction force device is attached to the lower end of the hydraulic jack of the jack up leg via a spherical bearing, and the horizontal reaction force device is provided with a hydraulic jack that touches the bottom wall of the recess of the sinker and expands and contracts in the left and right direction. and the hydraulic jack extends pressure on the side walls of the four parts of the sinker to prevent the sinker and the horizontal reaction device from slipping. Ru.
本発明の実施に際しては、水中桁にフロートを設けて作
業船(台船)の下に水中桁を引き込み台船と水中桁を一
体化できる構造とする。When implementing the present invention, a structure is adopted in which a float is provided on the underwater girder and the underwater girder is pulled under the work boat (barge) to integrate the barge and the underwater girder.
[発明の作用効果]
このように本発明に係る捨石均し装置は、水中桁とシン
カーが一体になっているので、水中桁を沈設する際にシ
ンカーも同時に沈設し、したがって大水深の場合でも水
中桁の脚とシンカーとの位置がずれることがなく、水中
桁の据付けの手間が少なくなると共に精度よく据付けを
行うことができ、かつシンカーは小型のものであっても
よく、その撤去及び移動が容易になる。また水平反力装
置はジヤツキアップ脚と球面軸受で連結されているので
、自由回転が可能であり、シンカーの勾配に沿って水中
桁を着底させることができ、水中桁に無理な力がかかる
ことがなく、したがってスクリード機械が作動しなくな
る等の不都合は解消される。また水中桁の脚は油圧ジヤ
ツキを備えたジヤツキアップ脚であるので、捨石マウン
ド面の不陸に対して水中桁の据付は高さのレベル調整が
可−能であり、高精度で水中桁を据付けることができる
。[Operation and Effect of the Invention] As described above, in the rubble leveling device according to the present invention, the underwater girder and the sinker are integrated, so when the underwater girder is sunk, the sinker is also sunk at the same time, so even in the case of deep water. The positions of the legs of the underwater girder and the sinker do not shift, reducing the effort required to install the underwater girder and allowing for accurate installation, and the sinker may be small, making it easy to remove and move it. becomes easier. In addition, the horizontal reaction force device is connected to the jack-up leg with a spherical bearing, so it can rotate freely, allowing the underwater girder to land on the bottom along the slope of the sinker, and preventing excessive force from being applied to the underwater girder. Therefore, inconveniences such as the screed machine not operating are eliminated. In addition, the legs of the underwater girder are jack-up legs equipped with hydraulic jacks, so it is possible to adjust the height level when installing the underwater girder against uneven surfaces of the rubble mound, and the underwater girder can be installed with high precision. Can be attached.
[実施例] 以下、図面を参照して本発明の実施例につき説明する。[Example] Embodiments of the present invention will be described below with reference to the drawings.
第1図ないし第3図において、全体を1で示すのは作業
船で、この作業船1には操船ウィンチ2、水中桁吊上げ
ウィンチ3、砕石貯蔵ホッパ4、コ □ンベヤ
5、後述のスクリード機械11のトレミーパイプ12に
砕石を投下するための砕石ホッパ6などが設けられてい
る。全体を7で示すのは方形に組立てられた水中桁で作
業船1に設けた前記の水中桁吊上げウィンチ3によりシ
ーブ8、ワイヤ9を介して吊下げられて沈設される。水
中桁7にはフロート10が設けられていて浮力の増大を
計りている。11はスクリード機械で、このスクリード
機械11には前記砕石貯蔵ホッパ4からコンベヤ5によ
り砕石ホッパ6に搬送された砕石がトレミーパイプ12
を経て供給され、海底Aに砕石を投下すると共に投下さ
れた砕石を均す。このためスクリード機械11は水中桁
7に支持されて水中桁7に沿って水平移動する。In Figures 1 to 3, the reference numeral 1 indicates a work boat, and the work boat 1 includes a steering winch 2, an underwater girder lifting winch 3, a crushed stone storage hopper 4, a conveyor 5, and a screed machine to be described later. A crushed stone hopper 6 for dropping crushed stone into the 11 tremie pipes 12 is provided. The overall designation 7 is an underwater girder assembled into a rectangular shape, which is suspended and submerged via a sheave 8 and wire 9 by the underwater girder lifting winch 3 provided on the work boat 1. A float 10 is provided on the underwater girder 7 to increase buoyancy. Reference numeral 11 denotes a screed machine, and the screed machine 11 carries crushed stone conveyed from the crushed stone storage hopper 4 to the crushed stone hopper 6 by the conveyor 5 through a tremie pipe 12.
The crushed stones are supplied to the seabed A and are then leveled. Therefore, the screed machine 11 is supported by the underwater girder 7 and moves horizontally along the underwater girder 7.
第1図ないし第3図のばか第4図ないし第6図を参照し
てさらに説明すると、水中桁7の各隅部にはジヤツキア
ップl1113が固定して設けられており、このジッヤ
キアップ脚13は上下方向に伸縮する油圧ジヤツキ14
を備えている。またジヤツキアップ脚13の先端にはフ
ロート15が設けられている。各ジヤツキアップ脚13
の下端部からシンカー16がチェーン17により吊下げ
られており、このシンカー16には凹部(凹溝)18が
形成されている。またジヤツキアップ脚13の油圧ジヤ
ツキ14の下端には球面軸受19を介して全体20で示
す水平反力装置が取付けられている。この水平反力装f
it 20はシンカー16の凹部18の側壁18bに圧
力をかけてシンカー16と水平反力装置20とがすべら
ないようにする。To explain further with reference to FIGS. 1 to 3 and FIGS. 4 to 6, a jack-up leg 1113 is fixedly provided at each corner of the underwater girder 7, and this jack-up leg 13 is attached to the top and bottom. Hydraulic jack 14 that expands and contracts in the direction
It is equipped with Further, a float 15 is provided at the tip of the jack-up leg 13. Each jack up leg 13
A sinker 16 is suspended by a chain 17 from the lower end of the sinker 16, and a recess (groove) 18 is formed in the sinker 16. Further, a horizontal reaction force device generally designated 20 is attached to the lower end of the hydraulic jack 14 of the jack-up leg 13 via a spherical bearing 19. This horizontal reaction force f
It 20 applies pressure to the side wall 18b of the recess 18 of the sinker 16 to prevent the sinker 16 and the horizontal reaction device 20 from slipping.
次に主として第4図ないし第6図を参照して水中桁を海
底面に据付ける態様につき説明する。Next, referring mainly to FIGS. 4 to 6, the manner in which the underwater girder is installed on the seabed surface will be explained.
前述のようにジヤツキアップ脚13は水中桁7に固定さ
れており、またシンカー16はジヤツキアップ脚13よ
りチェーン17で吊下げられている。水中桁7の降下は
作業船1上の水中桁吊上げウィンチ3によりシーブ8、
ワイヤ9を経て行われる。As mentioned above, the jack-up leg 13 is fixed to the underwater beam 7, and the sinker 16 is suspended from the jack-up leg 13 by a chain 17. The underwater girder 7 is lowered by the sheave 8,
This is done via wire 9.
水中桁吊上げウィンチ3(4台)は等連で作動し、この
ウィンチ3の巻下げにより水中桁7の量産4か所は等速
で緩やかな速度で降下する(第4図)。The underwater girder lifting winches 3 (four units) operate in equal sequence, and by lowering the winches 3, the four mass-produced underwater girders 7 are lowered at a uniform and gentle speed (Figure 4).
水中桁7の降下と共にシンカー16も降下する。As the underwater girder 7 descends, the sinker 16 also descends.
シンカー16は捨石マウンド面Aの一番高い所に当って
着底する。この時、捨石マウンド而Aに高低差(勾配)
があればこの高低差に沿って着底する。The sinker 16 hits the highest point of the rubble mound surface A and lands on the bottom. At this time, there is a difference in height (gradient) on the rubble mound A.
If there is, it will touch the bottom along this height difference.
さらに水中桁7は降下し、ジヤツキアップ脚13の根元
に設けた水平反力装@20がシンカー1.6の凹部18
の底壁18aに着底する。Further, the underwater girder 7 descends, and the horizontal reaction force device @20 provided at the base of the jack-up leg 13 moves into the recess 18 of the sinker 1.6.
It lands on the bottom wall 18a of.
水平反力装置20がシンカー16の凹部底壁18aに着
底すると水中桁吊上げウィンチ3の巻下げをストップさ
せウィンチ3にブレーキをかけて水中桁7を支持する。When the horizontal reaction force device 20 reaches the bottom of the recessed bottom wall 18a of the sinker 16, the lowering of the underwater spar lifting winch 3 is stopped and the winch 3 is braked to support the underwater spar 7.
次に水平反力装置20に内蔵された油圧ジヤツキ21を
伸長させてシンカー16の凹部18の側壁18aに圧力
をかけてシンカー16と水平反力装置20がすべらない
ようにする。Next, the hydraulic jack 21 built into the horizontal reaction device 20 is extended to apply pressure to the side wall 18a of the recess 18 of the sinker 16 to prevent the sinker 16 and the horizontal reaction device 20 from slipping.
この際、水平反力装置20はジ↑・ツキアップ脚13と
球面軸受19で連結されているので自由回転が可能であ
り、シンカー16の勾配に沿って着底することができる
(第5図)。At this time, since the horizontal reaction force device 20 is connected to the j↑/tsuki-up leg 13 by a spherical bearing 19, it can rotate freely and can land on the bottom along the slope of the sinker 16 (Fig. 5). .
次に捨石マウンド面Aの低い所に着底したシンカー16
の凹部底壁18aに水平反力装置20を着底させるため
、ジヤツキアップ1I113に内蔵された油圧ジヤツキ
14を伸長させる。水平反力装置20がシンカー16の
四部底壁18aに着底すると水平反力装置20の油圧ジ
ヤツキ21を伸長させ、シンカー16の凹部側壁18b
に圧力をかけてシンカー16と水平反力装置20がすべ
らないようにする。Next, sinker 16 landed on the bottom of the rubble mound surface A.
In order to place the horizontal reaction force device 20 on the bottom wall 18a of the concave portion, the hydraulic jack 14 built in the jack up 1I113 is extended. When the horizontal reaction force device 20 bottoms out on the four-part bottom wall 18a of the sinker 16, the hydraulic jack 21 of the horizontal reaction force device 20 is extended, and the concave side wall 18b of the sinker 16 is extended.
Pressure is applied to prevent the sinker 16 and the horizontal reaction device 20 from slipping.
このようにして順次4点のジヤツキアップ脚13及び水
平反力装置20を作動さぽて水平桁7の据付及びレベル
微調整を行う。In this way, the four jack-up legs 13 and the horizontal reaction force device 20 are operated one after another, and the horizontal girder 7 is installed and the level is finely adjusted.
最後に水平桁7の4本のレベルをトランスポンダ等で測
定して水平桁7のレベル微調整をジヤツキアップ脚13
の油圧シリンダ14で行う。Finally, measure the level of the four horizontal beams 7 using a transponder, etc., and fine-tune the level of the horizontal beam 7 by adjusting the jack-up leg 13.
This is done using the hydraulic cylinder 14.
なお、ジヤツキ・アップ脚13の油圧ジヤツキ14は荷
重がかかっても降下しないようにロッキング装置を設け
る。Note that a locking device is provided for the hydraulic jack 14 of the jack up leg 13 so that it does not fall even when a load is applied.
[結び]
以上説明したように本発明によれば、水中桁を容易にか
つ精度よく据付けることができ、海底や水底に基礎構築
物を構築するための捨石層を能率よく構築することがで
きるものである。[Conclusion] As explained above, according to the present invention, an underwater girder can be installed easily and accurately, and a rubble layer for constructing a foundation structure on the seabed or under water can be efficiently constructed. It is.
第1図ないしM3図は本発明の実施例に係る水中桁着底
式捨石均し装置の全容を示し、第1図は正面図、第2図
は手簡図、第3図は側面図、第4図、第5図及び第6図
は水中桁の据付は工程を示す各正面図である。
1・・・作業船 2・・・操船ウィンチ3・・・水中
桁吊上げウィンチ 4・・・砕石貯蔵ホッパ 5・
・・コンベヤ 6・・・砕石ホッパ 7・・・水中
桁 8・・・シーブ9・・・ワイヤ −0・・・フ
ロート11・・・スクリード機械 12・・・トレミ
ーパイプ 13・・・ジヤツキアップ脚 14・・
・油圧ジヤツキ 15・・・フロート16・働・シン
カー 17・・・チェーン18・・・凹部 19・
・◆球面軸受 20・・・水平反力装@ 21・・
・油圧ジヤツキ
第3図
l115vA
第6図Figures 1 to M3 show the entire structure of the underwater girder type rubble leveling device according to the embodiment of the present invention, in which Figure 1 is a front view, Figure 2 is a simplified diagram, Figure 3 is a side view, FIGS. 4, 5, and 6 are front views showing the installation process of the underwater girder. 1... Work boat 2... Ship operation winch 3... Underwater girder lifting winch 4... Crushed stone storage hopper 5.
... Conveyor 6 ... Crushed stone hopper 7 ... Underwater girder 8 ... Sheave 9 ... Wire -0 ... Float 11 ... Screed machine 12 ... Tremy pipe 13 ... Jack up leg 14・・・
・Hydraulic jack 15...Float 16・Working・Sinker 17...Chain 18...Concavity 19・
・◆Spherical bearing 20...Horizontal reaction device @ 21...
・Hydraulic jack Fig. 3 l115vA Fig. 6
Claims (1)
に組立てられた水中桁の各隅部に上下方向に伸縮する油
圧ジャッキを備えたジャッキアップ脚を固定して設けて
、該ジャッキアップ脚の下端部から凹部を備えたシンカ
ーをチェーンにより吊下げ、また前記ジャッキアップ脚
の油圧ジャッキの下端に球面軸受を介して水平反力装置
を取付け、該水平反力装置は前記シンカーの凹部の底壁
に着底すると共に左右方向に伸縮する油圧ジャッキを備
えており、該油圧ジャッキはそれを伸長させることによ
りシンカーの凹部の側壁に圧力をかけたシンカーと水平
反力装置とがすべらないようにするものであることを特
徴とする水中桁着底捨石均し装置。A jack-up leg equipped with a hydraulic jack that extends and retracts in the vertical direction is fixedly provided at each corner of an underwater girder assembled in a rectangular shape that supports the screed machine and guides the movement of the machine, and the lower end of the jack-up leg is provided. A sinker with a concave portion is suspended from the bottom wall of the sinker by a chain, and a horizontal reaction device is attached to the lower end of the hydraulic jack of the jack-up leg via a spherical bearing, and the horizontal reaction device is attached to the bottom wall of the concave portion of the sinker. It is equipped with a hydraulic jack that expands and contracts in the left and right directions when it hits the bottom, and by extending the hydraulic jack, the horizontal reaction device prevents the sinker, which applies pressure to the side wall of the recess of the sinker, from slipping. An underwater girder-bottom rubble leveling device characterized by:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14392585A JPS626026A (en) | 1985-07-02 | 1985-07-02 | Underwater bottom-landing ype rubble leveler |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14392585A JPS626026A (en) | 1985-07-02 | 1985-07-02 | Underwater bottom-landing ype rubble leveler |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS626026A true JPS626026A (en) | 1987-01-13 |
| JPH0459412B2 JPH0459412B2 (en) | 1992-09-22 |
Family
ID=15350282
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14392585A Granted JPS626026A (en) | 1985-07-02 | 1985-07-02 | Underwater bottom-landing ype rubble leveler |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS626026A (en) |
-
1985
- 1985-07-02 JP JP14392585A patent/JPS626026A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0459412B2 (en) | 1992-09-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210482355U (en) | Offshore wind power jacket foundation pile sinking retainer | |
| EP0039590A2 (en) | Offshore platform and method of constructing, erecting and dismantling same | |
| CN101806053B (en) | Integral installation method of cantilever beams of self lifting type well drilling platform | |
| CN101392521A (en) | Rock-socketed steel dock structure and construction method thereof | |
| CN109706987B (en) | A method for internal jacking and rectification of frame structure buildings | |
| US3283516A (en) | Walking work barge | |
| RU2057845C1 (en) | Method for installation of marine stationary platform with flat bottom and marine stationary platform | |
| CN116289963A (en) | A leveling device and construction method for paving gravel cushion of a 100-meter deep-water bridge | |
| CN110435846B (en) | High-precision semi-submersible ship immersed tube base body, and prefabricating construction platform and construction method thereof | |
| JP6681225B2 (en) | How to install a gravity type structure on the bottom of the water | |
| JPS63502842A (en) | Casing and its arrangement method | |
| US4290716A (en) | Platform resting on the bottom of a body of water, and method of manufacturing the same | |
| CN1036611A (en) | Manufacturing method and equipment for structural parts of river port engineering | |
| US4285614A (en) | Structure allowing the attainment of a precise seabed location | |
| JPH0459412B2 (en) | ||
| JP7050143B2 (en) | Sliding device and sliding support | |
| CN215105262U (en) | Pile forming structure of cast-in-situ bored pile | |
| JP7274705B2 (en) | SHAPE IDENTIFICATION DEVICE AND SHAPE IDENTIFICATION METHOD OF EXCAVATED GROUND SIDE | |
| JP4699320B2 (en) | Construction method of pedestal concrete | |
| JPS6134534B2 (en) | ||
| JPH04250216A (en) | Leveler for rubble mound | |
| JPH0326734B2 (en) | ||
| JPS6022108Y2 (en) | Rubble foundation leveling machine | |
| JPS641916Y2 (en) | ||
| CN118727810A (en) | Foundation leveling device and leveling method suitable for rock foundation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |