JPH0460060A - Building method for multi-story steel structure - Google Patents
Building method for multi-story steel structureInfo
- Publication number
- JPH0460060A JPH0460060A JP16940890A JP16940890A JPH0460060A JP H0460060 A JPH0460060 A JP H0460060A JP 16940890 A JP16940890 A JP 16940890A JP 16940890 A JP16940890 A JP 16940890A JP H0460060 A JPH0460060 A JP H0460060A
- Authority
- JP
- Japan
- Prior art keywords
- steel frame
- rise
- permanent steel
- steel
- permanent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 78
- 239000010959 steel Substances 0.000 title claims abstract description 78
- 238000000034 method Methods 0.000 title description 6
- 238000010276 construction Methods 0.000 claims description 5
- 230000005484 gravity Effects 0.000 claims description 4
- 238000004873 anchoring Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 abstract description 6
- 208000031481 Pathologic Constriction Diseases 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 2
- 239000000872 buffer Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000037433 frameshift Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 210000004894 snout Anatomy 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【発明の詳細な説明】 「産業上の利用分野」 本発明は、高層鉄骨の鉄骨建方法に関する。[Detailed description of the invention] "Industrial application field" The present invention relates to a method for constructing a high-rise steel frame.
「従来の技術」 従来の高層鉄骨の鉄骨建方は、骨組架構の形状。"Conventional technology" The conventional method of constructing high-rise steel frames is a frame structure.
重量が運搬上の制約を大きく受けることから、単材の形
で現場に運搬したのち、タワークレーンあるいは移動式
クレーンによる積上げ方式でもって立体的に骨組架構を
組立てている。Since weight is a major constraint on transportation, materials are transported to the site in single pieces and then assembled into three-dimensional frameworks using tower cranes or mobile cranes.
叙上クレーンは、単材の重量及び作業半径、鉄骨構築物
の高さ等から選定される。The cranes mentioned above are selected based on the weight and working radius of the single material, the height of the steel structure, etc.
「発明が解決しようとする課題」
しかし、従来の建方では、
(1)作業の大部分が高所で行われることとなるため、
作業が困難で作業能率が低い上に危険が多く工期も長く
かかるが、高所で組立て作業を行なうとび職の技能は一
般的に低下してきており、また高所作業に要求される仮
設安全対策はより厳しくなってきているという難点があ
る。``Problems to be solved by the invention'' However, in conventional construction, (1) most of the work is done at high places;
The work is difficult, has low work efficiency, is dangerous, and takes a long time, but the skills of jumpers who perform assembly work at heights are generally declining, and the temporary safety measures required for work at heights are decreasing. The problem is that it is becoming more difficult.
(2)構築物が高くなれば大型のクレーンを使用しなけ
ればならないため、その輸送費や稼働費は膨大なものと
なり、更にトラッククレーンはもちろんのこと、クライ
ミングクレーンを用いる場合にも、構造物の外側に設置
しなければならず、クレーン据付のためのかなり広い余
分なスペースとクレーン設備のための基礎工事または地
盤の養生を要するが、はとんどの現場は、周囲に建物が
密集していることが多いことなどにより、材料の搬入、
取扱い、足場の確保などが難かしいこと、または障害物
があって、クレーンの搬入が不可能な現場には対応し得
ない。(2) If the structure becomes taller, a larger crane must be used, resulting in huge transportation and operating costs. It must be installed outside and requires considerable extra space for the crane installation and foundation work or soil curing for the crane equipment, but most sites are surrounded by buildings. Due to frequent occurrences, the delivery of materials,
It cannot be applied to sites where it is difficult to handle or secure scaffolding, or where there are obstacles that make it impossible to bring in a crane.
等の問題点がある。There are other problems.
本発明は、側段大型のクレーンを必要とすることなくし
て僅かな高所作業のみでもって建方がし得る、従来手段
の難点の起因である大型クレーンを必要とする高所作業
での単材の組立てという常識から脱した新規な鉄骨建方
法を提供することを目的としている。The present invention enables construction to be carried out with only a small amount of work at height without requiring a large side crane. The aim is to provide a new method of steel frame construction that departs from the common sense of assembling materials.
「課題を解決するための手段」
上記目的を達成するために、本発明の鉄骨建方法は、高
層鉄骨における低層部の鉄骨を小型クレーン、低層足場
でもって建方し、一方、高層部の鉄骨を小型クレーンで
もって地組みしたうえ当該高層部の鉄骨を逆立ちさせて
該低層部の鉄骨に寄り添わし、次いで相接した態様にあ
る両鉄骨の継ぎ足しされるべき一方の側端間をヒンジ結
合すると共に高層部の鉄骨の他方の側端にはガントリー
を突設し、地上に設置したウィンチのワイヤーロープを
低層部の鉄骨の上端、該ガントリー、高層部の鉄骨の上
端に架け渡して巻きとって高層部の鉄骨を該ヒンジを枢
点として回動引き上げし、高層部の鉄骨の重心が引き上
げ方向に偏位する寸前にて引き上げを停止して低層部の
鉄骨と高層部の鉄骨間に架設の油圧ジヤツキに盛り替え
し、当該油圧ジヤツキで衝撃を緩衝しつつ高層部の鉄骨
の定着をし、本結合をして高層鉄骨を建方するとしたも
のである。"Means for Solving the Problems" In order to achieve the above object, the steel frame erection method of the present invention involves erecting the steel frames in the lower part of a high-rise steel frame using a small crane and low-rise scaffolding, while The steel frames of the high-rise section were assembled on the ground using a small crane, and the steel frames of the high-rise section were turned upside down and nestled against the steel frames of the low-rise section, and then the two side edges of the two adjacent steel frames to be joined were joined by hinges. At the same time, a gantry was installed protruding from the other end of the steel frame in the high-rise section, and the wire rope from a winch installed on the ground was passed over the upper end of the steel frame in the low-rise section, the gantry, and the upper end of the steel frame in the high-rise section, and then wound around it. The high-rise steel frame is pivoted about the hinge, and the lifting is stopped just before the center of gravity of the high-rise steel frame shifts in the lifting direction, and the steel frame is erected between the low-rise steel frame and the high-rise steel frame. The hydraulic jacks will be used to cushion the impact while anchoring the high-rise steel frame, which will then be fully connected and the high-rise steel frame will be erected.
「作用」
上記のように構成された本発明の建方法によるならば、
高層部の本設鉄骨は、地組みにより高品質、迅速に仕上
げられ、組立てに際しては小型のクレーンがあれば済む
。仕上げられた高層部の本設鉄骨は基端がピン止めされ
ているので、ウィンチによって簡単に起立され、クレー
ンによることなくして一気に高層架橋が立ち上がること
となる。"Operation" According to the construction method of the present invention configured as described above,
The permanent steel frame for the high-rise section will be constructed quickly and with high quality through ground assembly, and only requires a small crane to assemble it. Since the base end of the finished steel frame for the high-rise section is pinned, it can be easily erected with a winch, and the high-rise bridge can be erected all at once without the need for a crane.
高層部の本設鉄骨が一気に立ち上がるものであるため、
高所作業は存在しなくなり、単に低層部の本設鉄骨の上
端レベルでの結合作業があるのみとなる。Since the permanent steel frame of the high-rise section will be erected all at once,
There will be no work at heights, and there will only be work to connect the permanent steel beams at the top level of the lower floors.
「実施例」
実施例について図面を参照して説明すると、第1図、第
2図において、高層鉄骨における低層部の本設鉄骨1は
、比較的低層の足場(図示省略)と小型のクレーンとで
もって基礎打ちを完了した基盤2上に建方されるので、
はぼ地組みと同じ感覚で仕上げることができる。これに
対し、高層鉄骨における高層部の本設鉄骨3は、近傍で
地組みされる。地組みであるので、小型クレーンで済む
。"Example" To explain the example with reference to the drawings, in Figs. 1 and 2, the permanent steel frame 1 in the low-rise part of the high-rise steel frame has a relatively low-rise scaffold (not shown) and a small crane. Since it will be erected on the foundation 2 which has completed the foundation pouring,
It can be finished in the same way as Habochi-gumi. On the other hand, the permanent steel frame 3 in the high-rise section of the high-rise steel frame is assembled into the ground nearby. Since it is built on the ground, only a small crane is required.
当該本設鉄骨3は逆立ち、つまり、基端を上にした姿勢
にして、第2図aに示される如く、該本設鉄骨lに寄り
添わせる。これにより、継ぎ足しされるべき両鉄骨1,
3の一方の側端同志が相接するが、この側端間を仮設の
ブラケット4を介してヒンジ結合5させる。The permanent steel frame 3 is placed upside down, that is, with its base end facing upward, and is placed close to the permanent steel frame 1, as shown in FIG. 2a. As a result, both steel frames 1 to be added,
3 are in contact with each other, and a hinge connection 5 is made between the side ends via a temporary bracket 4.
本設鉄骨3の当該ヒンジ結合5と反対側には、ガントリ
ー6を仮設する。本設鉄骨lの該ヒンジ結合5と反対側
の地上に設置したウィンチ7からのワイヤーロープ8を
、本設鉄骨1のヒンジ結合5と反対側上端に配設の滑車
9、該ガントリー6先端に配設の滑車10を介して本設
鉄骨3の上端に止着11する。該ウィンチ7の巻き取り
で、本設鉄骨3をヒンジ結合5を枢点として回動引き上
げする。この引き上げは、終極までしてはならない。A gantry 6 is temporarily installed on the side of the permanent steel frame 3 opposite to the hinge connection 5. A wire rope 8 from a winch 7 installed on the ground on the opposite side of the hinge connection 5 of the permanent steel frame 1 is connected to a pulley 9 installed at the upper end of the permanent steel frame 1 on the opposite side to the hinge connection 5, and to the tip of the gantry 6. It is fastened 11 to the upper end of the main steel frame 3 via the provided pulley 10. By winding up the winch 7, the permanent steel frame 3 is rotated and pulled up about the hinge connection 5. This increase must not be final.
何故ならば、ヒンジ結合5を支点として立姿勢にある本
設鉄骨3は、重心が該支点より引き上げ側に偏位したと
ころでもってウィンチ7のコントロールから脱し、−気
に傾倒してしまうので、ワイヤーロープ8の引張りを受
けて加速されて大きな衝撃をもって本設鉄骨1に対して
衝突することとなるからである。This is because the permanent steel frame 3, which is in an upright position with the hinge connection 5 as a fulcrum, loses control of the winch 7 when its center of gravity deviates from the fulcrum to the pulling side, and tilts upward. This is because it is accelerated by the tension of the rope 8 and collides with the main steel frame 1 with a large impact.
かかる事態を避けるため、ウィンチ7により弓き上げは
、上記の重心の偏位がおこる寸前で停止する。この状態
を保持して、本設鉄骨1と本設鉄骨3との間に油圧ジヤ
ツキ12を両端根止のもと架設し、これに、本設鉄骨3
の回動制御を盛り替える。In order to avoid such a situation, the winch 7 stops the bow raising just before the above-mentioned deviation of the center of gravity occurs. While maintaining this state, a hydraulic jack 12 is erected between the permanent steel frame 1 and the main steel frame 3, with both ends anchored, and the hydraulic jack 12 is attached to the main steel frame 3.
Rearrange the rotation control.
しかして、当該油圧ジヤツキ12は、既述の本設鉄骨3
の一気の傾倒動を受止緩衝し、ゆるやかに本設鉄骨1上
に突き合わせて定着させる。定着部の本結合とブラケッ
ト4、ガン)!J−6、油圧ジヤツキ12等の引き上げ
回動のために付設された仮設材の撤去とをとり行なうと
、高層鉄骨が完成する。However, the hydraulic jack 12 is
It absorbs and buffers the sudden tilting movement of the steel frame 1, and gently butts it against the main steel frame 1 and fixes it. Final connection of the fixing section and bracket 4, gun)! The high-rise steel frame will be completed after removing the temporary materials installed for lifting and rotating the J-6, hydraulic jack 12, etc.
「発明の効果」
本発明は、以上説明したように構成されているので、以
下に記載されるような効果を奏する。"Effects of the Invention" Since the present invention is configured as described above, it produces the effects described below.
(1)高層鉄骨を大型クレーンを用いることなくして建
方出来るので、クレーンの費用の低減ができる。(1) Since high-rise steel frames can be erected without using large cranes, crane costs can be reduced.
(2)障害物あるいは大型クレーンが入れないとか設置
できない狭い場所での建方が可能である。(2) It can be erected in narrow spaces where obstacles or large cranes cannot enter or install.
(3)高所作業を少なくすることで安全性が向上する。(3) Safety is improved by reducing work at heights.
第1図は本発明方法の概略図、第2図a、bは本発明要
領を詳示した正、側面図である。
1・・・本設鉄骨、 2・・・基盤、 3・・・本設鉄
骨、4・・・ブラケット、 5・・・ヒンジ結合、
6・・・ガントリー、 7・・・ウィンチ、 8
・・・ワイヤーロープ、9・・・滑車、 10・・・滑
車、 11・・・止着、 12・・・油圧ジヤツキ。
プラクZθ
/り2吻FIG. 1 is a schematic diagram of the method of the present invention, and FIGS. 2a and 2b are front and side views showing the details of the method of the present invention. 1...Permanent steel frame, 2...Foundation, 3...Permanent steel frame, 4...Bracket, 5...Hinge connection,
6... Gantry, 7... Winch, 8
... wire rope, 9 ... pulley, 10 ... pulley, 11 ... anchoring, 12 ... hydraulic jack. Plaque Zθ /ri2 snout
Claims (1)
低層足場でもって建方し、一方、高層部の鉄骨を小型ク
レーンでもって地組みしたうえ当該高層部の鉄骨を逆立
ちさせて該低層部の鉄骨に寄り添わし、次いで相接した
態様にある両鉄骨の継ぎ足しされるべき一方の側端間を
ヒンジ結合すると共に高層部の鉄骨の他方の側端にはガ
ントリーを突設し、地上に設置したウインチのワイヤー
ロープを低層部の鉄骨の上端、該ガントリー、高層部の
鉄骨の上端に架け渡して巻きとって高層部の鉄骨を該ヒ
ンジを枢点として回動引き上げし、高層部の鉄骨の重心
が引き上げ方向に偏位する寸前にて引き上げを停止して
低層部の鉄骨と高層部の鉄骨間に架設の油圧ジャッキに
盛り替えし、当該油圧ジャッキで衝撃を緩衝しつつ高層
部の鉄骨の定着をし、本結合をして高層鉄骨を建方する
としたことを特徴とする高層鉄骨の鉄骨建方法。(1) Use a small crane to remove the lower steel frame of a high-rise steel frame.
The structure was erected using low-rise scaffolding, and the steel frames of the high-rise sections were erected on the ground using small cranes, and the steel frames of the high-rise sections were turned upside down and nestled against the steel frames of the low-rise sections, and then the steel frames of the high-rise sections were erected on the ground using small cranes. One side of the steel frame to be added is connected by a hinge, and a gantry is installed protruding from the other side of the steel frame in the high-rise section, and the wire rope of the winch installed on the ground is connected to the upper end of the steel frame in the low-rise section. The gantry is stretched around the upper end of the steel frame in the high-rise area, and the steel frame in the high-rise area is rotated and pulled up using the hinge, and the lifting is stopped just before the center of gravity of the steel frame in the high-rise area shifts in the lifting direction. Then, a hydraulic jack was installed between the steel frame of the low-rise section and the steel frame of the high-rise section, and the hydraulic jack cushioned the impact while anchoring the steel frame of the high-rise section.The final connection was made, and the high-rise steel frame was erected. A steel frame construction method for high-rise steel frames that is characterized by the following.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16940890A JP2818754B2 (en) | 1990-06-27 | 1990-06-27 | High-rise steel frame construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16940890A JP2818754B2 (en) | 1990-06-27 | 1990-06-27 | High-rise steel frame construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0460060A true JPH0460060A (en) | 1992-02-26 |
| JP2818754B2 JP2818754B2 (en) | 1998-10-30 |
Family
ID=15886047
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16940890A Expired - Fee Related JP2818754B2 (en) | 1990-06-27 | 1990-06-27 | High-rise steel frame construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2818754B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103388405A (en) * | 2013-08-02 | 2013-11-13 | 武汉钢铁(集团)公司 | Large-sized overhang steel structure mounting method |
| CN105971292A (en) * | 2016-05-31 | 2016-09-28 | 上海宝冶集团有限公司 | Synchronous slippage construction technique for double-span net rack with middle column |
-
1990
- 1990-06-27 JP JP16940890A patent/JP2818754B2/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103388405A (en) * | 2013-08-02 | 2013-11-13 | 武汉钢铁(集团)公司 | Large-sized overhang steel structure mounting method |
| CN103388405B (en) * | 2013-08-02 | 2015-07-22 | 武汉钢铁(集团)公司 | Large-sized overhang steel structure mounting method |
| CN105971292A (en) * | 2016-05-31 | 2016-09-28 | 上海宝冶集团有限公司 | Synchronous slippage construction technique for double-span net rack with middle column |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2818754B2 (en) | 1998-10-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US6021910A (en) | Construction crane base | |
| CN101103161A (en) | equipment used in building construction | |
| JPH04111829A (en) | Construction method for large span roofs | |
| CN114908960A (en) | Support system for refuge layer structure construction and construction method thereof | |
| JP7666916B2 (en) | Concrete pouring device and concrete pouring method | |
| JP2002047805A (en) | Construction method of vertical pipe and lifting device used in the method | |
| JPH11343729A (en) | Slide rising type suspended scaffold | |
| JP3049300B2 (en) | Construction method of beam truss in building with overhead traveling crane | |
| CN110847031A (en) | Mobile gondolas for bridge construction | |
| JP2001032524A (en) | Building construction method | |
| KR101904060B1 (en) | Prefabricated shoring system | |
| JP2818754B2 (en) | High-rise steel frame construction method | |
| JPH0460059A (en) | Steel structure building method | |
| KR101191918B1 (en) | Rotating-up building roof structure using keel truss and rotating-up building method using keel truss | |
| JP3532161B2 (en) | Tower construction machine and tower construction method | |
| JP2764366B2 (en) | Temporary tent with opening and closing mechanism | |
| CN114809579B (en) | Erection method of elevating construction platform used for erecting formwork system around lighting shaft | |
| JP2004270377A (en) | Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same | |
| JP2585174B2 (en) | How to fix scaffolding for temporary tents | |
| RU2122092C1 (en) | Building with superstructure of mansard type and method of superstructure of buildings with rooms of mansard type | |
| JP2858891B2 (en) | Construction method of large span dome roof | |
| JP2897663B2 (en) | How to build underground structures | |
| KR102733206B1 (en) | Pier column work platform provided with fail-safe function and method of constructing pier column using the same | |
| KR102914419B1 (en) | Modular structure for building tubular pole and modular structuring method for the pole | |
| JP3128178B2 (en) | How to build a tent frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |