JPH0474488B2 - - Google Patents

Info

Publication number
JPH0474488B2
JPH0474488B2 JP59038739A JP3873984A JPH0474488B2 JP H0474488 B2 JPH0474488 B2 JP H0474488B2 JP 59038739 A JP59038739 A JP 59038739A JP 3873984 A JP3873984 A JP 3873984A JP H0474488 B2 JPH0474488 B2 JP H0474488B2
Authority
JP
Japan
Prior art keywords
block
concrete
cutting edge
press
concrete block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59038739A
Other languages
Japanese (ja)
Other versions
JPS60184126A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP3873984A priority Critical patent/JPS60184126A/en
Publication of JPS60184126A publication Critical patent/JPS60184126A/en
Publication of JPH0474488B2 publication Critical patent/JPH0474488B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)

Description

【発明の詳細な説明】 この発明は下水道を中心とする管渠施設の推進
工事用の基地としてのプレキヤストコンクリート
多層ケーソンの圧入沈設工法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for press-fitting and sinking a precast concrete multilayer caisson as a base for propulsion work of pipe facilities, mainly sewerage.

その目的とするところは、ケーソン(立坑)の
地中設置工事を合理、簡素化して工期を短縮し且
つ工費を節減することにある。
The purpose is to rationalize and simplify the underground installation work of caissons (shafts), shorten the construction period, and reduce construction costs.

従来この種の立坑は、一定の範囲の土中に鋼矢
板を並列打込みして、内部土砂を掘削排出して
後、底部にコンクリートを打設し、次いで鋼矢板
の一部を切除して発進兼到達坑口を作り、立坑内
に吊入れる管渠を発進坑口より順次推進布設し、
または推進管渠の前端部を受入れ、管渠の推進布
設の完了後に立坑内に現場打ちコンクリートで角
形または丸形のマンホールを形成して土砂を埋戻
し、鋼矢板を撤去する順序により形成してきたの
で、工期が長く、且つ所要工費が多大であるとい
う問題があつた。
Conventionally, this type of shaft was built by driving steel sheet piles in parallel into the soil in a certain area, excavating and discharging the internal soil, then pouring concrete at the bottom, and then cutting out a portion of the steel sheet piles before starting. A dual-reaching tunnel entrance was created, and the pipes to be suspended into the shaft were installed sequentially from the starting tunnel entrance.
Alternatively, the front end of the propulsion culvert is received, and after completion of the propulsion installation of the culvert, a rectangular or round manhole is formed in the shaft with cast-in-place concrete, backfilled with earth and sand, and the steel sheet piles are removed. Therefore, there were problems in that the construction period was long and the required construction costs were large.

本発明はこれを改良したもので、その構成は四
隅地点より4本のアースアンカーを地中深く挿立
て、該各アースアンカーの内側に平面視四角枠形
状に形成した刃口ブロツクを吊入れ、該刃口ブロ
ツクを前記各アースアンカーに止着する上部耐圧
板下に設ける複数個の油圧ジヤツキによる多点押
しと該刃口ブロツク内の土砂の掘削排土の協動と
により地中に圧入し、該刃口ブロツクが一定深度
に圧入した点で前記の該油圧ジヤツキを外して、
該刃口ブロツク上に下部コンクリートブロツクを
載置連結して、該各油圧ジヤツキを再取付けして
多点押しと掘削排土の反複とにより、該刃口ブロ
ツク上に縦割り分割した接合面が隣接する各ブロ
ツク間において千鳥状に互いにずれるように形成
した下部コンクリートブロツク、中間コンクリー
トブロツクおよび上部コンクリートブロツクを順
次載着して所定深度に圧入沈設するようにしたこ
とにある。
The present invention is an improvement on this, and its configuration is such that four earth anchors are inserted deep into the ground from the four corner points, and a cutting edge block formed in a square frame shape in plan view is suspended inside each of the earth anchors. The cutting edge block is pressed into the ground by multi-point pushing using a plurality of hydraulic jacks provided under the upper pressure plate that is fixed to each of the earth anchors, and the cooperation of excavating and discharging the earth and sand in the cutting edge block. , at the point where the cutting edge block is press-fitted to a certain depth, remove the hydraulic jack,
The lower concrete block is placed and connected on the cutting edge block, the hydraulic jacks are reattached, and the vertically divided joint surfaces are formed on the cutting edge block by repeating multi-point pushing and excavation and removal. A lower concrete block, an intermediate concrete block, and an upper concrete block, which are formed so as to be shifted from each other in a staggered manner between adjacent blocks, are sequentially mounted and press-fitted to a predetermined depth.

以上の構成によつて、地中に順次圧入し沈設さ
れる推進管渠布設用の基地としてのプレキヤスト
コンクリート多層ケーソンの刃口ブロツク乃至上
部コンクリートブロツクは四隅地点より土中深く
挿立てた4本のアースアンカーを止点にして複数
個の油圧ジヤツキによる多点押しにて4辺が均等
に押圧されて圧入するため、水平を保ちつつ能率
よく圧入し沈設することとなる。
With the above configuration, there are four precast concrete multilayer caisson cutting blocks or upper concrete blocks that are inserted deep into the soil from the four corner points and serve as bases for laying propulsion pipes that are successively press-fitted and sunk into the ground. Using the earth anchor as the stopping point, the four sides are pressed evenly by multi-point pushing using a plurality of hydraulic jacks, so it can be press-fitted and sunk efficiently while maintaining the horizontal position.

また下部乃至上部コンクリートブロツクはプレ
キヤスト製品によつて、任意の立坑深さおよび
形状にて製造して対応させることができる。コ
ンクリートの品質を良好にして強度にばらつきを
生じないものとすることができる。現場に合わ
せたブロツクを積木方式にて組立てるため、迅速
に施工をすすめることができる。工期短縮によ
り交通路の開放が早くできて交通障害を少なくす
ることができる。
Furthermore, the lower and upper concrete blocks can be manufactured using precast products to correspond to any shaft depth and shape. It is possible to improve the quality of concrete and prevent variations in strength. Since blocks are assembled using the building block method to suit the site, construction can be carried out quickly. By shortening the construction period, traffic routes can be opened quickly and traffic disturbances can be reduced.

以下本発明を実施例図面に基づいて詳細説明す
る。
Hereinafter, the present invention will be explained in detail based on the drawings.

プレキヤストコンクリート多層ケーソンを圧入
沈設する地盤11上の四隅個所よりアースアンカ
ー12を土中深く打込み、該アースアンカー12
の下端部をグラウト13の注入にて堅め、先ず平
面視四角形枠形状に形成した刃口ブロツク14を
アースアンカー12間の地盤11上に吊入れ、平
行するアースアンカー12間に加圧用H型鋼15
を2本平行して載せ渡す。16は刃口ブロツク1
4とH型鋼15間の敷板である。H型鋼15の両
端上にはアースアンカー12に通して下部耐圧盤
17を載上し、該耐圧盤17上に2個1組の油圧
ジヤツキ18を載せ、該油圧ジヤツキ18上に上
部耐圧盤19を載置し、アースアンカー12に嵌
挿着するコーン油圧チヤツク20により締付ける
のである。
The earth anchors 12 are driven deep into the soil from the four corners of the ground 11 where the precast concrete multilayer caisson is to be press-fitted.
The lower end is hardened by injecting grout 13, and first, the cutting edge block 14 formed into a rectangular frame shape in plan view is suspended on the ground 11 between the earth anchors 12, and the pressurizing H-shaped steel 15 is placed between the parallel earth anchors 12.
Place two pieces in parallel. 16 is the blade mouth block 1
4 and the H-shaped steel 15. A lower pressure plate 17 is mounted on both ends of the H-shaped steel 15 through the earth anchors 12, a set of two hydraulic jacks 18 are placed on the pressure plate 17, and an upper pressure plate 19 is mounted on the hydraulic jacks 18. is placed and tightened by a cone hydraulic chuck 20 that is inserted into the earth anchor 12.

刃口ブロツク14は内側に先部を細くする傾斜
を附し、先部に金属板14aを被着しており、1
4bは上部アンカー筋、14cは下部アンカー筋
であり、上部アンカー筋14bは内側に面する部
分にネジ部14dにカツプラー26を螺着して開
口されており、又凹み14eを設けている。また
刃口ブロツク14の中間部の外面に凹溝14fを
設けて、止水用のゴム環体14gを一部突出する
ようにして嵌着している。なお14iはフラツト
バーであり、14jは各内側コーナーの上部に設
けた縦方向PC鋼棒23の止溝である。
The blade block 14 has a tapered tip on the inside, and a metal plate 14a is attached to the tip.
Reference numeral 4b indicates an upper anchor line, and 14c indicates a lower anchor line. The upper anchor line 14b has an opening formed by screwing a coupler 26 onto a threaded portion 14d, and is provided with a recess 14e. Further, a groove 14f is provided on the outer surface of the intermediate portion of the blade block 14, into which a water-stopping rubber ring 14g is fitted so as to partially protrude. Note that 14i is a flat bar, and 14j is a stop groove for the vertical PC steel bar 23 provided at the top of each inner corner.

刃口ブロツク14の内側土砂を掘削排出しつ
つ、各油圧ジヤツキ18を作動すると、加圧用H
型鋼15を押して刃口ブロツク14は多点押しさ
れて土中に圧入する。この際刃口ブロツク14が
片側に傾くときは各油圧ジヤツキ18間の作動圧
を調整して刃口ブロツク14を水平に戻し、以後
水平を保つようにして圧入させる。刃口ブロツク
14が一定深度に圧入した点で一旦加圧用H型鋼
15より上の圧入機構および敷板16を外して、
下部コンクリートブロツク21aを刃口ブロツク
14上に載置し四隅部に縦設する縦方向シース2
2に縦方向PC鋼体23を挿嵌して下端を刃口ブ
ロツク14の該内側コーナーの上部に設ける止溝
14jにてナツト23b止め緊張させるようにす
る。この下部コンクリートブロツク21aは刃口
ブロツク14より平面形において小さく形成され
ており、従つて下部コンクリートブロツク21a
と土壁11a間には刃口ブロツク14が圧入する
ことによつて間隙24が存置される。
When each hydraulic jack 18 is operated while excavating and discharging the soil inside the cutting edge block 14, the pressurizing H
By pressing the mold steel 15, the cutting edge block 14 is pressed at multiple points and press-fitted into the soil. At this time, when the cutting edge block 14 is tilted to one side, the operating pressure between the hydraulic jacks 18 is adjusted to return the cutting edge block 14 to the horizontal position, and thereafter the cutting edge block 14 is press-fitted while maintaining the horizontal position. At the point where the cutting edge block 14 is press-fitted to a certain depth, the press-fitting mechanism and the bottom plate 16 above the pressurizing H-shaped steel 15 are removed,
The lower concrete block 21a is placed on the cutting edge block 14 and the vertical sheath 2 is installed vertically at the four corners.
2, the vertical PC steel body 23 is inserted and the lower end is tightened by tightening the nut 23b at the stop groove 14j provided at the upper part of the inner corner of the cutting edge block 14. This lower concrete block 21a is formed smaller in plan view than the cutting edge block 14, and therefore the lower concrete block 21a
A gap 24 is left between the earth wall 11a and the earth wall 11a by press-fitting the blade block 14.

下部コンクリートブロツク21aを第5図に示
すように4個の縦割り分割体21−1,21−
2,21−3,21−4にて形成するときは、刃
口ブロツク14上に載置する前に地上において組
付けするのである。各分割体間には連通する横方
向シース25が設けられていて、横方向PC鋼棒
23aを用いて緊張止めし、さらに各分割体の凹
凸した連結面間にはシール材(図示していない)
を挟入し、且つボルト27、ナツト27a止めす
る。刃口ブロツク14上に載置連結した下部コン
クリートブロツク21aに一旦外した圧入機構お
よび敷板16を載置し、各油圧ジヤツキ18の押
し作動と内部土砂の掘削排出を再開して圧入する
のである。この繰返しにて複数個の中間コンクリ
ートブロツク21b、上部コンクリートブロツク
21cを順次圧入し沈設するのである。なお各コ
ンクリートブロツク21の圧入に当たつては地上
より外側底部に下げ入れるホース28または下部
コンクリートブロツク21aの内側下部より横断
孔29を経て外側に通すホース28により間隙2
4内にベントナイト泥水30を圧入し続けて土壁
11aの崩壊を防ぎ、また摩擦抵抗を小さくす
る。
The lower concrete block 21a is divided into four vertically divided bodies 21-1, 21- as shown in FIG.
2, 21-3, and 21-4, they are assembled on the ground before being placed on the cutting edge block 14. A lateral sheath 25 communicating with each other is provided between each divided body, which is tension-stopped using a lateral PC steel rod 23a, and a sealing material (not shown) is provided between the uneven connecting surfaces of each divided body. )
Insert and secure with bolt 27 and nut 27a. The press-fitting mechanism and the bottom plate 16 that have been removed are placed on the lower concrete block 21a placed and connected on the cutting edge block 14, and the pushing operation of each hydraulic jack 18 and the excavation and discharge of internal earth and sand are restarted to perform press-fitting. By repeating this process, a plurality of intermediate concrete blocks 21b and upper concrete blocks 21c are successively press-fitted and submerged. When press-fitting each concrete block 21, the gap 2 is filled with a hose 28 that is lowered from the ground to the outside bottom, or a hose 28 that is passed from the inside lower part of the lower concrete block 21a to the outside through the cross hole 29.
Bentonite mud water 30 is continuously forced into the interior of the wall 11a to prevent the earth wall 11a from collapsing and to reduce frictional resistance.

また中間および上部コンクリートブロツクを下
部コンクリートブロツク21aと同様に縦割り四
分割体にて形成するときは、接合面31が側面視
千鳥状となるように分割位置を相互にずらして接
合面31を交差させて、接合面が揃うことによつ
てケーソンの弱化することを防止する。
In addition, when the middle and upper concrete blocks are formed into vertically divided quarters like the lower concrete block 21a, the dividing positions are mutually shifted so that the joint surfaces 31 are staggered when viewed from the side, and the joint surfaces 31 cross each other. This prevents the caisson from weakening due to alignment of the joint surfaces.

下部コンクリートブロツク21aは単独で、ま
たは2個の下部コンクリートブロツク21aに跨
がつて相対する長手方向の側面に仮閉塞された発
進兼到達坑口32を有している。なお発進兼到達
坑口は推進管渠布設の出発点となるときは発進坑
口であり、別所からの推進管渠を受入れるときは
到達坑口となる。
The lower concrete block 21a has a starting/reaching tunnel entrance 32 which is temporarily closed on the longitudinal side facing each other either alone or across two lower concrete blocks 21a. The departure and arrival wellhead is the starting wellhead when it is the starting point for installing a propulsion pipe, and it is the arrival wellhead when receiving the propulsion pipe from another location.

発進兼到達坑口32は内側に環部32aと、該
環部32aの内側にボルト32b止めされたゴム
パツキング32cと、外面側に両端部を埋込み並
列した鋼材部32dと、鋼材部32dの外面に溶
接した閉塞板32eからなつている。なお環部3
2af第7図Bに示すように補強のため増厚32
a′したものもある。下部コンクリートブロツク2
1aから上部コンクリートブロツク21cまでが
所定深度に圧入されると、油圧ジヤツキ18等圧
入機構は外され、刃口ブロツク14内を整地して
後、砕石等を投入して中詰層33を形成し、次い
で凹み14eに接続して底版コンクリート34を
打説する。35は鉄筋であり、カツプラー26に
より上部アンカー筋に接続される。
The starting/reaching pit 32 has a ring part 32a on the inside, a rubber packing 32c fixed with bolts 32b on the inside of the ring part 32a, a steel part 32d with both ends buried in parallel on the outside surface, and welded to the outside surface of the steel part 32d. It consists of a closed-off plate 32e. Note that the ring part 3
2af As shown in Figure 7B, the thickness is increased by 32 for reinforcement.
Some have a'. Lower concrete block 2
When the parts from 1a to the upper concrete block 21c are press-fitted to a predetermined depth, the press-fitting mechanism such as the hydraulic jack 18 is removed, and after the inside of the cutting edge block 14 is leveled, crushed stone or the like is thrown in to form the filling layer 33. , and then connect the bottom slab concrete 34 to the recess 14e. 35 is a reinforcing bar, which is connected to the upper anchor bar by a coupler 26.

仮閉塞されている発進兼到達坑口32は鋼材3
2dと閉塞板32eを円形に切除して開口する。
The temporarily blocked starting/reaching tunnel entrance 32 is made of steel material 3.
2d and the closing plate 32e are cut out in a circular shape to open them.

上部コンクリートブロツク21cは上面に親柱
36を取外し可能に取付けており、土留め板37
を支持している。
The upper concrete block 21c has a main pillar 36 removably attached to the upper surface, and an earth retaining plate 37.
is supported.

以上により管渠38の推進布設を可能とするケ
ーソンが形成されるので、推進刃口38aのほ
か、管渠38を順次搬入して、発進坑口より推進
布設するのである。
As described above, a caisson that enables the propulsion installation of the pipe culvert 38 is formed, so that in addition to the propulsion cutting port 38a, the pipe culvert 38 is sequentially carried in and propulsion installation is carried out from the starting shaft opening.

管渠38の推進布設完了後に必要に応じて中間
ブロツク21bの内面間にカツプラー26にて鉄
筋35を接続して増幅部43付の中床版コンクリ
ートを打設し、上部ブロツク21cの上部増幅部
44上に頂部コンクリート版40を載着し、地表
までマンホール筒体41を据付けし、ステツプ4
2を取付けて後、土砂を埋戻しつつ親柱36およ
び土留め板37を抜取り撤去する。なお、第10
図に示すように親柱36を横ボルト45とナツト
45aにて止めるときはさらに撤去が容易にな
る。
After the propulsion of the pipe 38 is completed, if necessary, reinforcing bars 35 are connected between the inner surfaces of the intermediate block 21b with the coupler 26, and the intermediate deck concrete with the amplifying section 43 is poured, and the upper amplifying section of the upper block 21c is placed. The top concrete slab 40 is placed on top of the concrete slab 44, and the manhole cylinder 41 is installed up to the ground surface.
2, the main pillar 36 and earth retaining plate 37 are extracted and removed while backfilling with earth and sand. In addition, the 10th
As shown in the figure, when the main pillar 36 is fastened with a horizontal bolt 45 and a nut 45a, removal becomes easier.

かようにして本発明は四隅地点より4本のアー
スアンカーを土中深く挿立て、該アースアンカー
に止着する上部耐圧板下に複数個の油圧ジヤツキ
を取付けて、刃口ブロツク以下を多点押しするよ
うにしたので、各油圧ジヤツキによる多点押しと
内部土砂の掘削排土との協動により、刃口ブロツ
ク以下の各コンクリートブロツクを水平に保つて
能率よく土中の所定位置に圧入し沈設することが
できるという効果を生ずる。
In this way, the present invention inserts four earth anchors deep into the soil from the four corner points, attaches a plurality of hydraulic jacks under the upper pressure plate that is fixed to the earth anchors, and connects the ground anchors at multiple points below the cutting edge block. Since the concrete blocks below the cutting edge block are held horizontally by multi-point pushing by each hydraulic jack and the excavation and removal of internal earth and sand, each concrete block below the cutting edge block is kept horizontal and efficiently press-fitted into the specified position in the soil. This produces the effect that it can be submerged.

下水道を中心とする推進管渠布設用の基地とし
てのプレキヤストコンクリート多層ケーソンを圧
入沈設するにあたつて該プレキヤストコンクリー
ト多層ケーソンの圧入、沈設工事を工期を短縮
し、工費を節減して達成することができるという
効果を生ずる。
When press-fitting and sinking a precast concrete multi-layer caisson as a base for laying propulsion pipes mainly for sewerage, the press-fitting and sinking work of the precast concrete multi-layer caisson was achieved by shortening the construction period and reducing construction costs. This produces the effect that it is possible to

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は中間コンクリートブロツクを圧入しつ
つある時の縦断正面図、第2図は上部コンクリー
トブロツクの圧入時の状態を示す平面図、第3図
は同、部分縦断正面図、第4図は同、部分縦断側
面図、第5図は中間コンクリートブロツクを分割
体にて形成したときの下半を横断面した平面図、
第6図は発進兼到達坑口部分の一部閉塞板を切除
して示す拡大正面図、第7図Aは同、縦断面図、
第7図Bは同、環部を増厚した縦断面図、第8図
は刃口ブロツクと下部コンクリートブロツクおよ
び底版コンクリートの連結状態を示す部分図、第
9図は中間コンクリートブロツクと中床版コンク
リートの連結状態を示す部分図、第10図は上部
コンクリートブロツクと頂部コンクリート版およ
び親柱の連結状態を示す部分図、第11図は多層
ケーソンを所定深度に圧入沈設した状態を示す縦
断正面図、第12図は同、底版コンクリートを打
設して、発進坑口より管渠を推進布設した状態を
示す縦断正面図、第13図は中床版コンクリート
を打設し、頂部コンクリート版を載着し、マンホ
ール筒体を据付け、土砂を埋戻した状態の縦断正
面図、第14図は同、縦断側面図、11は地盤、
12はアースアンカー、13はグラウト、14は
刃口ブロツク、15は加圧用H型鋼、16は敷
板、17は下部耐圧盤、18は油圧ジヤツキ、1
9は上部耐圧盤、20はコーン油圧チヤツク、2
1はコンクリートブロツク、22は縦方向シー
ス、23は縦方向PC鋼棒、23aは横方向PC鋼
棒、24は間隙、25は横方向シース、26はカ
ツプラー、27はボルト、28はホース、29は
横断孔、30はベントナイト泥水、31は接合
面、32は発進兼到達坑口、33は中詰層、34
は底版コンクリート、35は鉄筋、36は親柱、
37は土留め板、38は管渠、39は中床版コン
クリート、40は頂部コンクリート版、41はマ
ンホール筒体、42はステツプ、43は中床版コ
ンクリートの増厚部、44は上部コンクリートブ
ロツクの増厚部、45は横ボルトである。
Figure 1 is a longitudinal front view of the middle concrete block being press-fitted, Figure 2 is a plan view of the upper concrete block being press-fitted, Figure 3 is a partial front view of the same, and Figure 4 is a partial front view of the same. Figure 5 is a cross-sectional plan view of the lower half of the intermediate concrete block formed as a divided body;
Fig. 6 is an enlarged front view showing the starting/arrival tunnel entrance with a part of the blocking plate removed, Fig. 7A is a vertical sectional view of the same,
Figure 7B is a longitudinal sectional view of the same with the ring part thickened, Figure 8 is a partial view showing the connection state of the cutting edge block, lower concrete block and bottom slab concrete, Figure 9 is the intermediate concrete block and middle slab. Figure 10 is a partial view showing the connection of the upper concrete block, top concrete slab, and main column; Figure 11 is a longitudinal sectional view showing the state of the multilayer caisson press-fitted to a predetermined depth. , Figure 12 is a longitudinal front view showing the state in which the bottom slab concrete has been poured and the pipe is propelled and laid from the starting tunnel entrance, and Figure 13 is the middle slab concrete poured and the top concrete slab placed. Figure 14 is a longitudinal front view of the manhole cylinder installed and backfilled with earth and sand; Figure 14 is a longitudinal side view; 11 is the ground;
12 is an earth anchor, 13 is grout, 14 is a cutting edge block, 15 is an H-type steel for pressurization, 16 is a bottom plate, 17 is a lower pressure plate, 18 is a hydraulic jack, 1
9 is the upper pressure plate, 20 is the cone hydraulic chuck, 2
1 is a concrete block, 22 is a longitudinal sheath, 23 is a longitudinal PC steel bar, 23a is a lateral PC steel bar, 24 is a gap, 25 is a lateral sheath, 26 is a coupler, 27 is a bolt, 28 is a hose, 29 is a cross-hole, 30 is bentonite mud water, 31 is a joint surface, 32 is a starting/arrival wellhead, 33 is a filling layer, 34
is concrete bottom slab, 35 is reinforcing steel, 36 is main pillar,
37 is the earth retaining board, 38 is the pipe, 39 is the middle deck concrete, 40 is the top concrete block, 41 is the manhole cylinder, 42 is the step, 43 is the thickened part of the middle deck concrete, and 44 is the upper concrete block. The thickened portion 45 is a horizontal bolt.

Claims (1)

【特許請求の範囲】[Claims] 1 潜函用の刃口ブロツク上に複数個に縦割り分
割した下部コンクリートブロツクと複数個の中間
コンクリートブロツクおよび上部コンクリートブ
ロツクを順次載置し連結して、内側の掘削排土と
外側に掘削安定液の注入および複数個の油圧ジヤ
ツキによる水平を保ちながらの押圧とにより地中
に埋設するようにした多層ケーソンの圧入沈設工
法において、前記上中下のコンクリートブロツク
を縦方向の接合面が千鳥状に互いにずれるように
分割し、前記刃口ブロツクの外面中間に止水用の
ゴム環体を一部突出させて嵌着して前記掘削安定
液の注入を該ゴム環体の上面にて受止め、前記下
部コンクリートブロツクの側壁に設けた仮閉塞部
分を解放することにより管渠の発進兼到達坑口を
形成し、前記上部コンクリートブロツクの周壁上
に土留め板支持用の親柱を取外し可能に縦設する
ことを特徴とする下水道を中心とする推進管渠の
発進、到達基地としてのプレキヤストコンクリー
ト多層ケーソンの圧入沈設工法。
1. A lower concrete block divided vertically into multiple pieces, a plurality of intermediate concrete blocks, and an upper concrete block are sequentially placed and connected on the cutting edge block for the subcase, and the excavated soil on the inside and the excavation stabilizing liquid on the outside are placed. In the press-in method of burying a multi-layer caisson underground by injecting water and pressing while maintaining the horizontal position using multiple hydraulic jacks, the vertical joint surfaces of the upper, middle and lower concrete blocks are staggered. The cutter block is divided so as to be offset from each other, and a water-stopping rubber ring is fitted in the middle of the outer surface of the cutting edge block with a part thereof protruding, so that the injection of the drilling stabilizing liquid is received on the upper surface of the rubber ring; By releasing the temporarily closed part provided on the side wall of the lower concrete block, a starting and reaching entrance for the pipe is formed, and a removable main column for supporting the retaining plate is installed vertically on the peripheral wall of the upper concrete block. This method is characterized by the press-in and sinking of precast concrete multi-layer caissons as starting and reaching bases for propulsion pipes mainly for sewerage.
JP3873984A 1984-03-02 1984-03-02 Pressing-in sinking method for precast concrete multilayered caisson Granted JPS60184126A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3873984A JPS60184126A (en) 1984-03-02 1984-03-02 Pressing-in sinking method for precast concrete multilayered caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3873984A JPS60184126A (en) 1984-03-02 1984-03-02 Pressing-in sinking method for precast concrete multilayered caisson

Publications (2)

Publication Number Publication Date
JPS60184126A JPS60184126A (en) 1985-09-19
JPH0474488B2 true JPH0474488B2 (en) 1992-11-26

Family

ID=12533687

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3873984A Granted JPS60184126A (en) 1984-03-02 1984-03-02 Pressing-in sinking method for precast concrete multilayered caisson

Country Status (1)

Country Link
JP (1) JPS60184126A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03257280A (en) * 1990-03-06 1991-11-15 Daiki Kensetsu Kk Construction method of vertical shaft
CN110485470B (en) * 2019-08-08 2021-05-04 郑州安源工程技术有限公司 Rectangular working well with pre-arranged jacking pipe door opening and sliding type rear wall in water-rich stratum and construction method of rectangular working well

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5240777A (en) * 1975-09-25 1977-03-29 Shin Ei Kogyo Method of producing printed circuit board
JPS5240516A (en) * 1975-09-26 1977-03-29 Kubota Ltd Method of coloring and patterning building materials
JPS53105015A (en) * 1977-02-24 1978-09-12 Shinkouzou Gijiyutsu Kk Method of building direct foundation for bridge and other structures

Also Published As

Publication number Publication date
JPS60184126A (en) 1985-09-19

Similar Documents

Publication Publication Date Title
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
CN101736749A (en) Method for constructing soft soil foundation continuous caisson
EA027027B1 (en) Method for forming a retaining wall
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
CN114992382B (en) Open caisson method construction muddy water balance pipe jacking working well opening construction method
CA1185441A (en) Process of forming a continuous wall in the ground
KR20000006650A (en) a pole for mud wall and constrution method of fence for mud
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
JPH0474489B2 (en)
CN114703866A (en) Compound integral bank protection of assembly
JPH0474488B2 (en)
JP3931123B2 (en) Non-open-cutting construction method for underground structures
CN113174995B (en) Construction method of TRD composite type enclosure comprehensive pipe gallery close to river channel
CN212896374U (en) Foundation pit support structure located in underground space of existing building
CN114809053A (en) Novel construction method for quickly treating underground obstacles by prefabricated open caisson
KR102942877B1 (en) Construction Method of Non-Open Tunnel Using Two Steel Pipes
JP3806069B2 (en) Seismic isolation method from the ground of existing buildings
US1877351A (en) Trench bracing
CN212896381U (en) Subway tunnel foundation pit bottom pressing bottom plate structure
JPS6124624Y2 (en)
KR20200088659A (en) Top-down type underground structure construction method using earth support plate
JP3020882B2 (en) Construction method of building structure with underground space
US1835665A (en) Method of installing sheet piling
JP3424117B2 (en) Construction method of continuous underground wall
KR910003748B1 (en) Construction method for construction of excavation underground structure by installing reverse casting concrete continuous wall

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term