JPH0489915A - Water cutoff member and sheet pile using this cutoff structure and executing method for sheet pile - Google Patents

Water cutoff member and sheet pile using this cutoff structure and executing method for sheet pile

Info

Publication number
JPH0489915A
JPH0489915A JP20570190A JP20570190A JPH0489915A JP H0489915 A JPH0489915 A JP H0489915A JP 20570190 A JP20570190 A JP 20570190A JP 20570190 A JP20570190 A JP 20570190A JP H0489915 A JPH0489915 A JP H0489915A
Authority
JP
Japan
Prior art keywords
pile
water
joint
leading chip
stopping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20570190A
Other languages
Japanese (ja)
Other versions
JPH0663226B2 (en
Inventor
Morio Kitamura
精男 北村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Giken Seisakusho Co Ltd
Original Assignee
Giken Seisakusho Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giken Seisakusho Co Ltd filed Critical Giken Seisakusho Co Ltd
Priority to JP2205701A priority Critical patent/JPH0663226B2/en
Publication of JPH0489915A publication Critical patent/JPH0489915A/en
Publication of JPH0663226B2 publication Critical patent/JPH0663226B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

PURPOSE:To construct a pile wall having sure water stopping effect by coupling a water stop member with a leading chip fitted in a joint, and arranging this water stop member along the longitudinal of the joint in the position outside of the joint of pile row in the ground on the side opposite the excavation side. CONSTITUTION:A leading chip 2 formed in a shape capable of fitting on joints 10g, 11g is fitted on the joint 10g of an existing pile 10 along the longitudinal of the joints 10g, 11g in the position outside of joint of pile row in the ground on the side opposite the excavation side. Then the joint 11g of a next pile 11 to be driven is fitted on the joint 10g of the existing pile 10, and the leading chip 2 is intruded in the joint 10g of the existing pile 10 and moved by driving of the next pile 11. On the outside of the joints 10g, 11g is furnished a water stop member 3 coupled with this leading chip 2 associate with this intrusive movement.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は止水構造を有する杭壁と、この杭壁に使用され
る止水用部材と、杭壁を上水構造とする施工方法に関す
る。
Detailed Description of the Invention (Field of Industrial Application) The present invention relates to a pile wall having a water-stopping structure, a water-stopping member used for the pile wall, and a construction method for making the pile wall a water-tight structure. .

(従来の技術) 鋼矢板により構築される杭壁は護岸、土留めなどに用い
られているが、止水を確実にすることが要求されている
。この止水を行なうためには、漏水が生じる杭の継手部
に対して何らかの処理を行なうことが有効であり、この
点に着目した考案や発明が従来よりなされている。
(Prior Art) Pile walls constructed from steel sheet piles are used for bank protection, earth retaining, etc., but are required to ensure water stoppage. In order to stop this water, it is effective to perform some kind of treatment on the joints of piles where water leaks, and ideas and inventions that have focused on this point have been made in the past.

このうち、実公昭64−432号公報には杭の継手部に
沿って水膨潤性シール材をサポート板により固定した考
案が提案されていて、杭列の掘削側の継手部に、この水
膨潤性シール材を施して掘削側に漏出する水を止めてい
る。
Among these, Japanese Utility Model Publication No. 64-432 proposes a device in which a water-swellable sealing material is fixed by a support plate along the joints of piles, and this water-swellable sealing material is attached to the joints on the excavation side of the pile row. Water leaking to the excavation side is stopped by applying a rubber sealant.

特開昭56−12424号公報、特開平1−28012
1号公報および同1−280122号公報に記載された
発明は杭の継手部分を止水材で封鎖するものであり、杭
の継手部を覆う鋼材などを杭に取り付けて鋼材内に止水
材を注入したり、あるいは空間を有する特殊形状となる
ように杭の継手部を成形し、空間部分に止水材を注入す
ることを特徴としている。
JP-A-56-12424, JP-A-1-28012
The invention described in Publication No. 1 and Publication No. 1-280122 is to seal the joint part of a pile with a water-stopping material, and by attaching a steel material etc. to the pile to cover the joint part of the pile, the water-stopping material is placed inside the steel material. It is characterized by injecting water into the space, or by forming the joint part of the pile into a special shape with a space, and injecting a water-stopping material into the space.

(発明が解決しようとする課題) しかしながら前者の従来技術は、水膨潤性シール材が杭
列の掘削側に設けるため掘削側と反対側の土庄や水圧が
継手部の隙間から作用すると、継手部に対するシール材
の密着度が低下したり、シール材が継手部から離脱する
。このため、止水効果がなくなるという致命点な問題が
ある。
(Problem to be Solved by the Invention) However, in the former prior art, the water-swellable sealing material is provided on the excavation side of the pile row, so if the soil or water pressure on the opposite side to the excavation side acts from the gap in the joint, the joint The degree of adhesion of the sealing material to the joint decreases, or the sealing material separates from the joint. For this reason, there is a fatal problem that the water-stopping effect is lost.

一方、後者の従来技術は、止水材を充填するように杭に
鋼材を取り付けたり、杭の継手部を特殊形状に成形しな
くてはならないため、このための作業が必要であると共
に止水以外の他の目的に杭を使用することができず転用
性がない。
On the other hand, the latter conventional technology requires work such as attaching steel to the pile so as to fill it with water-stopping material, and molding the joints of the pile into a special shape. The piles cannot be used for any other purpose and have no versatility.

また、止水材の充填に際しては、鋼材や継手部内を高圧
水で排土する必要があり作業性が悪いばかりでなく確実
に排土できないこともあり、この場合には止水材の止水
効果が部分的に低下している。さらに鋼材を取り付けた
場合には、杭打設時の抵抗が大きくなるため、杭が前倒
れ現象を起こすこともある。
In addition, when filling with water-stopping material, it is necessary to drain the inside of the steel materials and joints with high-pressure water, which not only has poor work efficiency but also may not be able to drain the soil reliably. The effectiveness is partially reduced. Furthermore, if steel is attached, the resistance during pile driving increases, which may cause the pile to fall forward.

本発明はこれらの従来技術の問題点に鑑みてなされたも
のであり、十分な止水力を有した構造とすると共に、杭
本来の形状に変更を与えることなく、簡単に施工するこ
とができる杭壁を提供することを目的とする。また、本
発明はこの杭壁の施工に使用される止水用部材およびこ
の止水用部材を使用した杭壁の施工方法を提供すること
を目的とする。
The present invention has been made in view of these problems in the prior art, and provides a pile that has a structure that has sufficient water-stopping power and that can be easily constructed without changing the original shape of the pile. The purpose is to provide a wall. Another object of the present invention is to provide a water-stopping member used for constructing this pile wall and a method for constructing a pile wall using this water-stopping member.

(課題を解決するための手段) 本発明に係る杭壁は、掘削側と反対側地盤の杭列の継手
外側に、継手部の長平方向に沿う止水材を設けた止水構
造を有することを特徴とし、また、この杭壁の施工に使
用される本発明の止水用具は、杭の継手部内に嵌合可能
な形状に成形された先導チップと、該先導チップに連結
される止水材とを備え、止水材の連結状態で先導チップ
を既設杭の継手内部に押し込むことを特徴とし、さらに
本発明による杭壁の施工方法は、杭の継手部内に嵌合可
能な形状に成形された先導チップを既設杭の継手部に嵌
め、その後次設杭の継手部を既設杭の継手部に嵌め合わ
せ、この次設杭の打設により先導チップを既設杭の継手
部内に押し込み移動させ、この押し込み移動に追随して
継手部に沿う止水材を継手部の外側に施すことを特徴と
する。
(Means for Solving the Problems) The pile wall according to the present invention has a water-stopping structure in which a water-stopping material is provided along the longitudinal direction of the joint on the outside of the joint of the pile row on the ground opposite to the excavation side. The water stop tool of the present invention used for the construction of pile walls includes a leading tip formed into a shape that can be fitted into a joint of a pile, and a water stopping tool connected to the leading tip. The method for constructing a pile wall according to the present invention is characterized in that the leading chip is pushed into the joint of an existing pile while the water-stopping material is connected, and furthermore, the method for constructing a pile wall according to the present invention includes: The leading chip that has been installed is fitted into the joint part of the existing pile, and then the joint part of the next pile is fitted into the joint part of the existing pile, and by driving this next pile, the leading chip is pushed into the joint part of the existing pile and moved. A feature is that a water stop material is applied to the outside of the joint part along the joint part following this pushing movement.

(作用) 上記構成の杭壁は、止水材が掘削側と反対の地盤側に設
けられるため、地盤の土圧や水圧が作用すると、止水材
が杭の継手部に密着して止水力が大きくなる。
(Function) In the pile wall with the above configuration, the water stop material is installed on the ground side opposite to the excavation side, so when the soil pressure or water pressure of the ground acts, the water stop material adheres to the joint of the pile and has a water stop effect. becomes larger.

また、上記構成の止水用部材は、先導チップが既設杭の
継手部内に押し込まれると、継手部内の排土を行ないな
がら、止水材を継手部に沿って配設するように作用する
In addition, when the leading chip is pushed into the joint of an existing pile, the water-stopping member configured as described above functions to dispose the water-stopping material along the joint while discharging soil from within the joint.

さらに上記構成の杭壁の施工方法は、次設杭の圧入また
は打設に伴って先導チップを既設杭の継手部に押し込み
移動させると共に、この押し込み移動に追随して止水材
を継手部に沿って施すため、杭の設計変更を要すること
なく、杭に止水力を付与させた杭壁を施工することがで
きる。
Furthermore, the method for constructing a pile wall with the above structure involves pushing and moving the leading chip into the joint of the existing pile as the next pile is press-fitted or driven, and following this pushing movement, the waterproofing material is applied to the joint. Because it is installed along the pile, it is possible to construct a pile wall that provides water-stopping power to the piles without having to change the design of the piles.

(実施例) 第1図は止水用部材1の第1実施例を示し、先導チップ
2と止水材3とを有している。先導チップ2の上部2a
は杭の継手部の内面と同形状および同寸法に成形され、
杭の継手部内に嵌合されて押し込まれる。また先導チッ
プ2の下部2bは一方向に傾斜するテーパ面を形成する
ことにより先尖形状となっている。このように下部2b
を先尖形状に成形したため杭の継手部内の土砂が排土さ
れ、継手部の抵抗が少なくなり継手部内での押し込み移
動が容易となる。
(Example) FIG. 1 shows a first example of a water-stopping member 1, which includes a leading tip 2 and a water-stopping material 3. As shown in FIG. Upper part 2a of leading chip 2
is molded to the same shape and dimensions as the inner surface of the joint part of the pile,
Fitted and pushed into the joint of the pile. Further, the lower part 2b of the leading tip 2 has a pointed shape by forming a tapered surface that slopes in one direction. Like this lower part 2b
Since the pile is formed into a pointed shape, the earth and sand inside the joint of the pile is removed, the resistance at the joint is reduced, and it is easier to push and move within the joint.

止水材3は上記先導チップ2の片面側に連結されている
。第2図はこの止水材3の一例を示すものであり、水膨
潤性シール材5内にワイヤやロープなどの芯材を挿入し
て構成している。水膨潤性シール材5は水を吸収して膨
潤する性質を有していて、この膨潤により止水効果を発
揮する。この止水材3は先導チップ2に連結され、先導
チップ2の杭の継手部内の押し込み移動に追随して継手
部に沿って移動する。
The water stop material 3 is connected to one side of the leading chip 2. FIG. 2 shows an example of this water-stopping material 3, which is constructed by inserting a core material such as a wire or rope into a water-swellable sealing material 5. The water-swellable sealing material 5 has the property of absorbing water and swelling, and this swelling exhibits a water-stopping effect. This water stop material 3 is connected to the leading chip 2 and moves along the joint part following the pushing movement of the leading chip 2 into the joint part of the pile.

本実施例における止水材3の連結は、第1図に示すよう
に、先導チップ2の上部片面側に上方に延びる連結バイ
ブロを設け、この連結バイブロ内に止水材3を挿入し、
かしぬることにより行なわれる。なお、止水材3として
は、地盤からの土庄や水圧が作用することにより変形す
るものであれば、水膨潤性シール材でなくても良く、例
えばゴムなどの弾性体でも良い。
To connect the water stop material 3 in this embodiment, as shown in FIG.
It is done by carving. Note that the water stop material 3 does not need to be a water-swellable sealing material as long as it is deformed by the action of soil or water pressure from the ground, and may be an elastic material such as rubber, for example.

また、本発明における止水材はこのように、それ自体で
止水能力を有するものに限られず、第9図および第10
図に示すように、グラウト剤を継手部に沿って地盤に注
入するための注入パイプ8を含むものであり、注入パイ
プ8の場合には先導チップ2との溶接によって連結でき
る。
Furthermore, the water-stopping material in the present invention is not limited to having water-stopping ability by itself, as shown in FIGS. 9 and 10.
As shown in the figure, it includes an injection pipe 8 for injecting grout into the ground along the joint, and in the case of the injection pipe 8, it can be connected to the leading tip 2 by welding.

このような止水材3は杭の継手部の外側に位置するよう
に先導チップ2に連結される。第3図は先導チップ2に
対する止水材3の連結位置を示し、既設杭10の継手部
(グリップ)Logと次設杭11の継手部(グリップ)
11gとの嵌合位置の外側となるように連結される。
The water stop material 3 is connected to the leading tip 2 so as to be located outside the joint portion of the pile. FIG. 3 shows the connection position of the water stop material 3 to the leading chip 2, and shows the joint part (grip) Log of the existing pile 10 and the joint part (grip) of the next pile 11.
It is connected so that it is outside the fitting position with 11g.

次に本実施例による杭壁の施工方法を説明する。Next, a method for constructing a pile wall according to this embodiment will be explained.

まず、鋼矢板などの杭を地盤に打設して既設杭10とす
る。この既設杭1oの継手部10g内に第3図に示すよ
うに、先導チップ2を嵌め込む。
First, piles such as steel sheet piles are driven into the ground to form the existing piles 10. As shown in FIG. 3, the leading chip 2 is fitted into the joint portion 10g of the existing pile 1o.

この場合、先導チップ2は既設杭10の継手部10gに
嵌合する形状となっているため、簡単に嵌め込むことが
できる。
In this case, since the leading chip 2 has a shape that fits into the joint portion 10g of the existing pile 10, it can be easily fitted.

次に既設杭10の継手部Logに次設杭11の継手部1
1gを嵌合し次設杭11を打設する。これにより次設杭
11は継手部Log、l1gの連結状態で地盤内に進入
するが、既設杭10の継手部10g内には先導チップ2
が嵌合されているため、第4図に示すように、先導チッ
プ2は継手部10g内を徐々に押し込み移動する。この
押し込み移動により先導チップ2は継手部10g内の土
砂を排土するため次設杭11の継手部11gに作用する
抵抗が減じ1次設杭11は円滑に地盤内に進入する。
Next, the joint part 1 of the next pile 11 is set to the joint part Log of the existing pile 10.
1g and drive the subsequent pile 11. As a result, the next pile 11 enters the ground with the joint parts Log and l1g connected, but the leading chip 2 is inside the joint part 10g of the existing pile 10.
As shown in FIG. 4, the leading tip 2 is gradually pushed into the joint portion 10g. By this pushing movement, the leading tip 2 discharges the earth and sand in the joint part 10g, so the resistance acting on the joint part 11g of the subsequent pile 11 is reduced, and the primary pile 11 smoothly enters into the ground.

そして、次設杭11の打設が終了すると、先導チップ2
は既設杭1oの継手部logの下端部分に達する。先導
チップ2には止水材3が連結されているため、先導チッ
プ2の押し込み移動と共に止水材3が継手部Log、l
1gの外側に同時に施される。
When the driving of the next pile 11 is completed, the leading chip 2
reaches the lower end of the joint log of the existing pile 1o. Since the water stop material 3 is connected to the leading tip 2, as the leading chip 2 is pushed and moved, the water stop material 3 moves to the joint part Log, l.
It is applied simultaneously to the outside of 1g.

このような杭壁の施工方法では、次設杭11の打設と同
時に、止水材3を杭の継手部に施すことができるため継
手部の排土のための高圧水噴射が不要となり、工期を短
縮することができると共に、確実に止水材を施すことが
できる。また、杭の継手部に鋼材を取り付けたり、杭の
継手部を特殊形状とすることなく、在来の杭をそのまま
使用することができるため杭の再使用も可能となる。
In this method of constructing a pile wall, the water stop material 3 can be applied to the joints of the piles at the same time as the subsequent piles 11 are driven, so there is no need for high-pressure water injection to remove earth from the joints. Not only can the construction period be shortened, but also the water stop material can be applied reliably. In addition, existing piles can be used as they are without attaching steel to the joints of the piles or making the joints of the piles have a special shape, making it possible to reuse the piles.

第5図および第6図はこの施工が行なわれた杭壁の第1
実施例を示し、止水材3は杭列10.11の継手部Lo
g、l1gの外側に沿って、その長手方向に施されてい
る。これらの図において、Aは杭壁施工後に掘削される
掘削側、Bは掘削側と反対側の地盤側であり、止水材3
はこの地盤側已における継手部分に位置している。その
ため、土庄や水圧などの圧力Pが作用すると止水材3は
継手部に外側から密着し、大きな止水力を発揮し確実な
止水構造となる。
Figures 5 and 6 show the first pile wall where this construction was carried out.
An example is shown, and the water stop material 3 is attached to the joint part Lo of the pile row 10.11.
g, l1g along the outside in its longitudinal direction. In these figures, A is the excavation side that will be excavated after the pile wall construction, B is the ground side opposite to the excavation side, and water stop material 3
is located at the joint part of this ground side. Therefore, when pressure P such as pressure or water pressure is applied, the water stop material 3 comes into close contact with the joint from the outside, exerts a large water stop force, and provides a reliable water stop structure.

また、圧力Pは止水材3が継手部に密着する方向にかか
るため、止水材3が継手部から離脱することなく、経時
的にも確実な止水を行なうことができる。この場合、止
水材3は地盤側Bからの掘削側Aへの漏水の防止が目的
であるため止水材3を杭の全長にわたって施す必要はな
い。
Moreover, since the pressure P is applied in the direction in which the water stop material 3 comes into close contact with the joint part, the water stop material 3 does not separate from the joint part, and reliable water stop can be performed over time. In this case, since the purpose of the water stop material 3 is to prevent water from leaking from the ground side B to the excavation side A, it is not necessary to apply the water stop material 3 over the entire length of the pile.

第7図は止水用部材1の第2実施例を示し、止水材3の
外側に硬質プラスチックや鋼材などからなるカバープレ
ート7が設けられている。カバープレート7は止水材3
の外面を覆うように、先導チップ2に取り付けられてお
り、先導チップ2の継手部10g内の押し込み移動に追
随して止水材3と一体となって地盤内に進入する。
FIG. 7 shows a second embodiment of the water-stopping member 1, in which a cover plate 7 made of hard plastic, steel, or the like is provided on the outside of the water-stopping member 3. Cover plate 7 is waterproof material 3
It is attached to the leading chip 2 so as to cover the outer surface of the leading chip 2, and follows the pushing movement of the leading chip 2 into the joint part 10g and enters into the ground together with the water stop material 3.

このカバープレート7は止水材3の外面を覆うため、漏
水を阻止すると共に、土圧や水圧などの圧力Pが作用す
ると、止水材3を継手部方向に押圧して止水材3の継手
部への密着を促進するため、止水をより確実に行なうこ
とができる。特に、止水材3として水膨潤性シール材を
用いた場合には、その膨潤方向を規制してシール材が継
手部方向に膨潤するように作用するため、シール材によ
る止水力の増大を図ることができる。
Since this cover plate 7 covers the outer surface of the water stop material 3, it prevents water from leaking, and when pressure P such as earth pressure or water pressure is applied, it presses the water stop material 3 toward the joint part and closes the water stop material 3. Since it promotes close contact with the joint, water can be stopped more reliably. In particular, when a water-swellable sealing material is used as the waterstopping material 3, the swelling direction is regulated so that the sealant swells toward the joint, thereby increasing the waterstopping power of the sealant. be able to.

第8図に示す止水部材の第3実施例では、次設杭11の
下方に予め止水材接続金具21を直接取付けである。施
工に際しては、止水材3を止水材接続金具21に取付け
て、次設杭11をそのまま打ち込めばよい。
In the third embodiment of the water stop member shown in FIG. 8, a water stop material connection fitting 21 is directly attached below the subsequent pile 11 in advance. During construction, the water stop material 3 may be attached to the water stop material connection fitting 21, and the subsequent pile 11 may be driven in as is.

第9図は杭壁の施工方法の第2実施例を示し、止水材と
して注入パイプ8を使用している。注入。
FIG. 9 shows a second embodiment of the pile wall construction method, in which an injection pipe 8 is used as the water-stopping material. injection.

パイプ8は小孔が多数形成されており、先導チップ2に
溶接などの方法で連結されている。この注入パイプ8は
既設杭10の継手部10a内の先導チップ2の押し込み
移動とに追随して、杭列10.11の継手部に沿って地
盤内に進行する。
The pipe 8 has many small holes formed therein, and is connected to the leading tip 2 by a method such as welding. This injection pipe 8 follows the pushing movement of the leading chip 2 in the joint part 10a of the existing pile 10, and advances into the ground along the joint part of the pile row 10.11.

そして、この進行と共にグラウト剤9が高圧注入され、
注入パイプ8の小孔からグラウト剤9の噴射が行なわれ
る。この施工では先導チップ2の押し込み移動と同時に
杭列の継手部に沿ってグラウト剤9が地盤に注入される
ため、止水構造を有する杭壁を迅速、簡単に施工するこ
とができる。
As this progresses, grouting agent 9 is injected under high pressure.
The grouting agent 9 is injected from a small hole in the injection pipe 8. In this construction, the grouting agent 9 is injected into the ground along the joints of the rows of piles simultaneously with the pushing movement of the leading chip 2, so that a pile wall having a water-stopping structure can be constructed quickly and easily.

第10図は杭壁の施工方法の第3実施例を示す。FIG. 10 shows a third embodiment of the pile wall construction method.

この実施例においても止水材としても注入パイプ8を使
用するが、既設杭10の継手部下端部近辺に当板13が
取り付けられている。当板13は注入パイプ8が当接す
ると注入パイプ8の進入を停止するように使用する。従
って、注入パイプ8は先導チップ2の押し込み移動に追
随して地盤内を進入するが、当板13に達すると進入が
停止する。
In this embodiment as well, the injection pipe 8 is used as a water stop material, but a contact plate 13 is attached to the existing pile 10 near the lower end of the joint. The contact plate 13 is used to stop the injection pipe 8 from entering when the injection pipe 8 comes into contact with it. Therefore, the injection pipe 8 follows the pushing movement of the leading chip 2 and enters into the ground, but when it reaches the contact plate 13, the entry stops.

そしてこの状態でさらに次設杭11を打設すると注入パ
イプ8と先導チップ2とが切り離される。
When a subsequent pile 11 is further driven in this state, the injection pipe 8 and the leading chip 2 are separated.

この切り離し後に、注入パイプ8を引き上げながらグラ
ウト剤を高圧注入すると地盤中にはグラウト剤だけが残
って、止水を行なうようになる。
After this separation, when grouting agent is injected under high pressure while pulling up the injection pipe 8, only the grouting agent remains in the ground, and water is stopped.

この施工では、当板13を任意の高さ位置に取り付ける
ことにより、グラウト剤の深さ調製を行なうことができ
る。
In this construction, the depth of the grouting agent can be adjusted by attaching the backing plate 13 at an arbitrary height position.

(発明の効果) 本発明の杭壁は、止水材を掘削側と反対の地盤側の杭継
手部に沿って設けるため、土庄や水圧により止水材が杭
継手部に密着して確実な止水を行なうことができる。ま
た、本発明の止水用部材によると、杭の継手部に沿う止
水材の施工を簡単に行なうことができる。さらに本発明
の施工法によれば、杭の設計変更を要することなく止水
効果のある杭壁を短期間に施工することができる。
(Effect of the invention) In the pile wall of the present invention, the water-stopping material is provided along the pile joint on the ground side opposite to the excavation side, so the water-stopping material adheres to the pile joint due to soil pressure and water pressure, making it reliable. Water can be stopped. Moreover, according to the water stop member of the present invention, the water stop material can be easily installed along the joint portion of the pile. Further, according to the construction method of the present invention, a pile wall having a water-stopping effect can be constructed in a short period of time without requiring a change in the design of the pile.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の実施例を示すもので、第1図は止水用部
材の第1実施例を示す拡大斜視図、第2図は止水材の一
例を示す拡大断面図、第3図は施工方法の第1実施例を
示す拡大平面図、第4図はその斜視図、第5図および第
6図は杭壁の第1実施例を示す平面図および側面図、第
7図は止水用部材の第2実施例を示す拡大平面図、第8
図は止水用部材の第3実施例を示す側面図、第9図は施
工方法の第2実施例を示す斜視図および第10図は施工
方法の第3実施例を示す斜視図である。 1・・止水用部材    2・・先導チップ3・・止水
材      4・・芯材 5・・・水膨潤性シール材 6・・連結パイプ7・カバ
ープレート  8・・注入パイプ10・・・既設杭  
Log、l1g・・継手部11・・次設杭 A・・掘削側   B・・・地盤側
The drawings show embodiments of the present invention, and FIG. 1 is an enlarged perspective view showing a first embodiment of a water-stopping member, FIG. 2 is an enlarged sectional view showing an example of a water-stopping material, and FIG. An enlarged plan view showing the first embodiment of the construction method, FIG. 4 is a perspective view thereof, FIGS. 5 and 6 are a plan view and side view showing the first embodiment of the pile wall, and FIG. 7 is a water-stopping diagram. Enlarged plan view showing the second embodiment of the member for use, No. 8
9 is a side view showing a third embodiment of the water-stopping member, FIG. 9 is a perspective view showing a second embodiment of the construction method, and FIG. 10 is a perspective view showing a third embodiment of the construction method. 1. Water-stopping member 2. Leading chip 3. Water-stopping material 4. Core material 5. Water-swellable sealing material 6. Connecting pipe 7. Cover plate 8. Injection pipe 10. Existing pile
Log, l1g...Joint part 11...Next pile A...Excavation side B...Ground side

Claims (3)

【特許請求の範囲】[Claims] (1)杭の継手部内に嵌合可能な形状に成形された先導
チップと、該先導チップに連結される止水材とを備え、
止水材の連結状態で先導チップを既設杭の継手内部に押
し込む止水用部材。
(1) A leading chip formed into a shape that can be fitted into a joint of a pile, and a water stop material connected to the leading chip,
A water-stopping member that pushes the leading chip into the joint of an existing pile while the water-stopping material is connected.
(2)掘削側と反対側地盤の杭列の継手外側に、継手部
の長手方向に沿う止水材を設けた止水構造を有する杭壁
(2) A pile wall with a water-stop structure in which a water-stop material is provided along the longitudinal direction of the joint on the outside of the joint of the pile row on the ground opposite to the excavation side.
(3)杭の継手部内に嵌合可能な形状に成形された先導
チップを既設杭の継手部に嵌め、その後次設杭の継手部
を既設杭の継手部に嵌め合わせ、この次設杭の打設によ
り先導チップを既設杭の継手部内に押し込み移動させ、
この押し込み移動に追随して継手部に沿う止水材を継手
部の外側に施す止水構造杭壁の施工方法。
(3) Fit the leading chip shaped to fit into the joint of the existing pile into the joint of the existing pile, and then fit the joint of the next pile into the joint of the existing pile. By driving, the leading chip is pushed into the joint of the existing pile and moved.
A construction method for a pile wall with a water-stop structure in which a water-stop material is applied to the outside of the joint to follow this pushing movement.
JP2205701A 1990-08-02 1990-08-02 Pile wall having waterproofing member and waterproof structure, and method for implementing the pile wall Expired - Lifetime JPH0663226B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2205701A JPH0663226B2 (en) 1990-08-02 1990-08-02 Pile wall having waterproofing member and waterproof structure, and method for implementing the pile wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2205701A JPH0663226B2 (en) 1990-08-02 1990-08-02 Pile wall having waterproofing member and waterproof structure, and method for implementing the pile wall

Publications (2)

Publication Number Publication Date
JPH0489915A true JPH0489915A (en) 1992-03-24
JPH0663226B2 JPH0663226B2 (en) 1994-08-22

Family

ID=16511277

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2205701A Expired - Lifetime JPH0663226B2 (en) 1990-08-02 1990-08-02 Pile wall having waterproofing member and waterproof structure, and method for implementing the pile wall

Country Status (1)

Country Link
JP (1) JPH0663226B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1010408C2 (en) * 1998-10-27 2000-04-28 Rich Consultancy Forming watertight joint between sheet piles in retaining wall, using sheet piles with male and female joint members that hook together
JP2009215830A (en) * 2008-03-12 2009-09-24 Taisei Corp Joining structure of concrete sheet pile
JP2012122284A (en) * 2010-12-10 2012-06-28 Giken Seisakusho Co Ltd Positioning jig for existing pile
CN104153397A (en) * 2014-08-06 2014-11-19 中国三冶集团有限公司 Concrete wall construction joint waterproof treatment method
EP3947824A4 (en) * 2019-03-29 2023-01-11 The Trout Group, Inc. STRUCTURAL SHEET SPUR

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61173545U (en) * 1985-04-17 1986-10-28

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61173545U (en) * 1985-04-17 1986-10-28

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1010408C2 (en) * 1998-10-27 2000-04-28 Rich Consultancy Forming watertight joint between sheet piles in retaining wall, using sheet piles with male and female joint members that hook together
JP2009215830A (en) * 2008-03-12 2009-09-24 Taisei Corp Joining structure of concrete sheet pile
JP2012122284A (en) * 2010-12-10 2012-06-28 Giken Seisakusho Co Ltd Positioning jig for existing pile
CN104153397A (en) * 2014-08-06 2014-11-19 中国三冶集团有限公司 Concrete wall construction joint waterproof treatment method
CN104153397B (en) * 2014-08-06 2016-05-18 中国三冶集团有限公司 A kind of concrete wall Case Study on Construction Joint Water-proofing
EP3947824A4 (en) * 2019-03-29 2023-01-11 The Trout Group, Inc. STRUCTURAL SHEET SPUR

Also Published As

Publication number Publication date
JPH0663226B2 (en) 1994-08-22

Similar Documents

Publication Publication Date Title
JP2004183338A (en) Tunnel waterproof structure and its construction method
JPH0489915A (en) Water cutoff member and sheet pile using this cutoff structure and executing method for sheet pile
JP2009114643A (en) Connecting structure of underground structure
JP2000192446A (en) Steel sheet pile and steel sheet pile wall construction method
JP2003278149A (en) How to shut off steel sheet pile joints
JP4839145B2 (en) Construction method and joint structure of joint part of water shielding material
JP3838484B2 (en) Steel pipe sheet pile joint and its construction method
JP7243305B2 (en) Water stop structure of steel pipe sheet pile joint
JP2005273170A (en) Starting pit wall
JP2908735B2 (en) Construction method of earth anchor on steel pipe column retaining wall
JP2807587B2 (en) Water sheet for steel sheet pile and ground excavation method
JP3530047B2 (en) Headwater stopping device for non-cutting propulsion and headwater stopping method using the headwater stopping device
JP3768146B2 (en) Water shielding structure of steel pipe sheet pile joints
JP2020066839A (en) Steel sheet pile joint and cut-off method for steel sheet pile joint fitting part
JP2954272B2 (en) Guided backfill injection water stoppage method
JP2003138557A (en) Construction method of steel sheet pile and steel sheet pile wall
JP4340018B2 (en) Joint water stop structure of straight steel sheet pile and steel sheet pile continuous wall
JPH0223633Y2 (en)
JP2887170B2 (en) Combined backfill injection water stop method
JP3332507B2 (en) How to build underground structures
JPH01280122A (en) Cut-off sheet pile and cut-off method to be carried out by using it
JP3923482B2 (en) Underground conduit construction method
JPH0584772B2 (en)
JP3628082B2 (en) Water stop structure
JP3903371B2 (en) Opening structure of shaft and start and arrival method from shaft

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term