JPH05295709A - Bridge pier and its construction method - Google Patents

Bridge pier and its construction method

Info

Publication number
JPH05295709A
JPH05295709A JP12421192A JP12421192A JPH05295709A JP H05295709 A JPH05295709 A JP H05295709A JP 12421192 A JP12421192 A JP 12421192A JP 12421192 A JP12421192 A JP 12421192A JP H05295709 A JPH05295709 A JP H05295709A
Authority
JP
Japan
Prior art keywords
steel
steel pipe
pier
formwork
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12421192A
Other languages
Japanese (ja)
Other versions
JP2878525B2 (en
Inventor
Masayuki Yamamoto
正幸 山本
Mitsuo Mori
満夫 森
Sugao Tanaka
壽賀夫 田中
Yoshio Sugiyama
良夫 杉山
Shoichi Ueda
正一 上田
Kiyotomo Okamoto
聖智 岡本
Hideji Yajima
秀治 矢島
Nobuo Manabe
伸穂 真部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
J R NISHI NIPPON CONSULTANTS KK
West Japan Railway Co
Araigumi Co Ltd
Original Assignee
J R NISHI NIPPON CONSULTANTS KK
West Japan Railway Co
Araigumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by J R NISHI NIPPON CONSULTANTS KK, West Japan Railway Co, Araigumi Co Ltd filed Critical J R NISHI NIPPON CONSULTANTS KK
Priority to JP12421192A priority Critical patent/JP2878525B2/en
Publication of JPH05295709A publication Critical patent/JPH05295709A/en
Application granted granted Critical
Publication of JP2878525B2 publication Critical patent/JP2878525B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】 【目的】 二重締切工や深い掘削を施工する必要がな
く、施工に必要な工程数が簡略化され、工期が短縮され
て施工費用を削減でき、とくに既設橋脚に近接して施工
する場合にも既設橋脚に悪影響を及ぼすおそれがない、
橋脚(の構造)とその施工方法を提供する。 【構成】 水底下の地盤中の支持層に下端が達し、水面
上に上端が突出する複数本の鋼管杭2と、それらの鋼管
杭2の周囲を取り囲み、水底下の地盤中に一部を埋設し
た鋼製型枠5と、該鋼製型枠5の内周面に沿って鋼管杭
2の周囲に配装され、鋼製型枠5の下端から鋼管杭2の
上端をやや越える高さを有する鉄筋籠と、鋼製型枠5内
の空間部に打設されたコンクリート部および鋼製型枠5
の外周面に沿って上方に延設され、鋼管杭2の上端部を
鉄筋籠とともに一体化したコンクリート部7とを備えて
いる。
(57) [Summary] [Purpose] There is no need to construct a double cut-off work or deep excavation, the number of steps required for construction is simplified, the construction period is shortened, and construction costs can be reduced, especially close to the existing piers. There is no risk of adversely affecting the existing piers even if
Provide (the structure of) the pier and its construction method. [Structure] A plurality of steel pipe piles 2 whose lower end reaches the support layer in the ground below the water bottom and whose upper end projects above the water surface, and those steel pipe piles 2 are surrounded, and a part of the steel pipe pile 2 is placed in the ground below the water bottom. A buried steel form 5 and a height that is arranged around the steel pipe pile 2 along the inner peripheral surface of the steel form 5 and that slightly exceeds the upper end of the steel pipe pile 2 from the lower end of the steel form 5 Reinforcement basket having a concrete part, a concrete part and a steel form frame 5 placed in a space in the steel form frame 5.
And a concrete portion 7 that extends upward along the outer peripheral surface of the steel pipe, and that integrates the upper end portion of the steel pipe pile 2 with the reinforcing bar cage.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、鉄道橋や道路橋の橋
脚とその施工方法に関し、詳しくはとくに既設橋脚(橋
梁)に近接して施工するのに好適な橋脚とその施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pier of a railway bridge or a road bridge and a construction method therefor, and more particularly to a pier and a construction method suitable for construction close to an existing pier (bridge). is there.

【0002】[0002]

【従来の技術】例えば河川に橋脚を施工する場合に、従
来、河川上に桟橋を設け、この桟橋上から、まず場所打
ち杭を施工し、次に橋脚躯体構築のために二重締切工を
施工する。続いて、締切内の土砂を掘削して橋脚躯体を
構築し、締切工を撤去するという施工手順が一般的であ
る。
2. Description of the Related Art For example, in the case of constructing a pier on a river, a pier has been conventionally installed on the river, and then cast-in-place piles are first constructed from this pier, and then a double cut-off work is performed to construct the pier frame. Install. Next, a general construction procedure is to excavate the earth and sand in the deadline to construct a pier frame and remove the deadline.

【0003】すなわち、従来の施工方法は、図6の(a)
および(b)に示すように、複数本の場所打ち杭31を、
一定の間隔をあけて方形のフーチング構築予定位置内に
河床下の地盤中深くまで施工する。次に、鋼矢板32を
フーチング構築予定外形から一定の間隔を設けて方形に
打ち込み、その外側に鋼矢板33を二重に打ち込み、内
外の鋼矢板32・33間に土砂36を充填して内側の鋼
矢板32内に水が入らないようにする(いわゆる、二重
締切工の施工)。鋼矢板(二重締切)32内の水を抜き
出したのち、土砂を掘削し、前記各場所打ち杭31の上
部を一体化して連結するフーチング34を、鉄筋コンク
リートで型枠を用いて構築し、さらにその上方に連続し
て橋脚躯体35を、鉄筋コンクリートで型枠(図示せ
ず)を用いて構築する。そして、型枠を取り外したの
ち、内外の鋼矢板32・33を引き抜いて撤去するとい
うものである。なお、図中の符号Sは、既設の橋脚(橋
梁)である。
That is, the conventional construction method is shown in FIG.
And as shown in (b), a plurality of cast-in-place piles 31,
Construction will be carried out at a certain interval deep within the ground beneath the riverbed within the planned square footing construction position. Next, the steel sheet pile 32 is punched in a square shape with a certain interval from the planned outer shape of the footing construction, the steel sheet pile 33 is double-dried on the outer side thereof, and sand 36 is filled between the inner and outer steel sheet piles 32 and 33 to fill the inside. Prevent water from entering the steel sheet pile 32 (so-called double deadline construction). After extracting the water from the steel sheet pile (double deadline) 32, excavating the earth and sand, and constructing a footing 34 that integrally connects the upper portions of the cast-in-place piles 31 together with a reinforced concrete using a formwork, and further The pier frame 35 is continuously constructed above the pier frame 35 using reinforced concrete using a form (not shown). Then, after removing the formwork, the inner and outer steel sheet piles 32 and 33 are pulled out and removed. In addition, the code | symbol S in a figure is an existing bridge pier (bridge).

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上記し
た従来の橋脚の施工方法には、下記のような点で改良の
余地がある。
However, the above-mentioned conventional method of constructing a bridge pier has room for improvement in the following points.

【0005】二重締切工などの工法を必要とするた
め、施工工程数が多く、各工程作業が複雑で、工期が長
くかかる(橋脚1基あたり4カ月程度)ため、渇水期内
に工事を完了しなければならない河川の場合、相当の昼
夜作業が必要になるなど、作業者の負担が大きい。
Since a construction method such as double cut-off work is required, the number of construction steps is large, each step work is complicated, and the construction period is long (about 4 months per pier). In the case of a river that has to be completed, it requires a lot of day and night work, which puts a heavy burden on the worker.

【0006】既設橋脚S(図6)に近接した場所に橋
脚を構築する場合には、二重締切工の施工時(とくに撤
去時)に地盤をゆるめ、既設橋脚に悪影響を及ぼすおそ
れがある。
When the pier is constructed near the existing pier S (FIG. 6), the ground may be loosened during the construction of the double cofferdam (particularly at the time of removal), which may adversely affect the existing pier.

【0007】掘削内や掘削底面付近の地盤が軟弱な場
合には、二重締切工の変位を抑制するために地盤を改良
したり、掘削底面の安定化を図るために底面下に薬液を
注入したりする必要があり、施工費がかなり高額にな
る。
When the ground in the excavation or near the bottom of the excavation is soft, the ground is improved to suppress the displacement of the double cut-off work, or a chemical solution is injected below the bottom to stabilize the bottom of the excavation. Need to be done and the construction cost will be quite high.

【0008】この発明は上述の点に鑑みなされたもの
で、二重締切工や深い掘削を施工する必要がなく、施工
工程が簡略化され、工期が短縮されて施工費用を削減で
き、とくに既設橋脚に近接して施工する場合にも既設橋
脚に悪影響を及ぼすおそれがない、橋脚(の構造)とそ
の施工方法を提供することを目的としている。
The present invention has been made in view of the above-mentioned points, and it is not necessary to perform a double cut-off work or deep excavation, the construction process is simplified, the construction period is shortened, and the construction cost can be reduced. It is an object of the present invention to provide a pier (structure of pier) and a construction method therefor, which does not have an adverse effect on an existing pier even when it is constructed near the pier.

【0009】[0009]

【課題を解決するための手段】上記した目的を達成する
ためにこの発明の橋脚は、a)水底下の地盤中の支持層
に下端が達し、水面上に上端が突出する複数本の鋼管杭
と、b)それらの鋼管杭の周囲を取り囲み、水底下の地
盤中に一部を埋設した鋼製型枠と、c)該鋼製型枠の内
周面に沿って前記鋼管杭の周囲に配装された鉄筋籠と、
d)前記鋼製型枠内の空間部に打設されたコンクリート
部および鋼製型枠の外周面に沿って上方に延設され、前
記鋼管杭の上端部を前記鉄筋籠とともに一体化したコン
クリート部とを備えている。
In order to achieve the above-mentioned object, the pier of the present invention comprises: a) a plurality of steel pipe piles whose lower end reaches a supporting layer in the ground below the water bottom and whose upper end projects above the water surface. And b) a steel form frame that surrounds the steel pipe piles and is partially buried in the ground under the water bottom, and c) around the steel pipe piles along the inner peripheral surface of the steel form frame. With the rebar baskets distributed,
d) Concrete that extends upward along the outer peripheral surface of the steel form and the concrete part cast in the space inside the steel form, and integrates the upper end of the steel pipe pile with the rebar cage. And a section.

【0010】またこの発明にかかる橋脚の施工方法は、
1)複数本の鋼管杭を、水底下の地盤中の支持層に下端
が達しかつ水面上に上端が突出するように構築し、2)
構築された複数本の鋼管杭の周囲を取り囲む鋼製型枠
を、水面上方からクレーン等により吊り下げて各鋼管と
一定の間隔をあけて水底下方の地盤中の比較的浅い位置
まで沈設し、前記鋼製型枠の上端を水面上に突出させ、
3)前記鋼製型枠内の土砂を掘削したのち、あらかじめ
組み立てた鉄筋籠を、水面上方からクレーン等により吊
り下げて前記鋼製型枠の内周面に沿って前記鋼管の周囲
に落とし込み、鉄筋籠の上端部は鋼管杭の上端よりやや
上方に突出させ、4)前記鋼製型枠に沿ってその上方に
前記鉄筋籠を取り囲むように型枠を仮設し、該仮設型枠
内および鋼製型枠内にコンクリートを打設したのち、前
記仮設型枠を取り除くものである。
The construction method of the bridge pier according to the present invention is
1) Multiple steel pipe piles are constructed so that the lower end reaches the supporting layer in the ground below the water bottom and the upper end projects above the water surface.
A steel formwork that surrounds the constructed multiple steel pipe piles is hung from above the water surface with a crane or the like, and is sunk to a relatively shallow position in the ground below the bottom of the water with a certain distance from each steel pipe, Projecting the upper end of the steel formwork above the water surface,
3) After excavating the earth and sand in the steel formwork, pre-assembled rebar cages are suspended from above the water surface by a crane or the like and dropped around the steel pipe along the inner peripheral surface of the steel formwork, The upper end of the rebar cage is made to project slightly above the upper end of the steel pipe pile, and 4) a formwork is temporarily installed above the steel formwork so as to surround the rebar cage, and inside the temporary formwork and steel. After the concrete is cast in the formwork, the temporary formwork is removed.

【0011】また上記本発明の施工方法において、前記
鋼製型枠の内面の適所に、その上下方向にガイド鋼を突
設し、鋼製型枠を複数本の鋼管杭の周囲に建て込む際
に、前記ガイド鋼にH鋼の一方を差し込んで各鋼管杭と
の間に一定の間隙を保たせるとともに、鉄筋籠を鋼製型
枠内に落とし込む際に、前記ガイド鋼に、鉄筋籠に取り
付けたCT鋼の先端部を挿入して案内させることが、好
ましい。
In the construction method of the present invention, when a guide steel is projected in a vertical direction at an appropriate position on the inner surface of the steel form, and the steel form is built around a plurality of steel pipe piles. In addition, one of the H steels is inserted into the guide steel to maintain a constant gap between the steel pipe piles, and when the rebar cage is dropped into the steel form, the guide steel is attached to the rebar cage. It is preferable to insert and guide the tip of the CT steel.

【0012】[0012]

【作用】上記の構成を有する本発明の橋脚(請求項1)
およびその施工方法(請求項2)によれば、鋼管杭の一
部を水面上方に突出させ、それらの周囲を鋼製型枠によ
り取り囲み、その鋼製型枠は一部を水面上に突出させ、
下端部を水底下の地盤中に沈設するので、鋼製型枠内で
土砂を掘削するなどの作業が可能になり、また鋼製型枠
内に鉄筋籠を落とし込んでコンクリートを打設すること
で、鋼管杭の上部を一体化することができる。したがっ
て、橋脚躯体を構築するための二重締切工が不要にな
り、掘削からコンクリート打設までの作業が水中内で施
工でき、また地盤をゆるめるおそれがないため、既設橋
脚に近接したところで施工しても既設橋脚に悪影響を及
ぼさない。さらに、既設橋脚の防護のための補助工法を
必要とせず、工期の短縮および工費の削減が図られる。
The pier of the present invention having the above construction (claim 1)
According to the construction method (Claim 2), a part of the steel pipe pile is projected above the water surface, and the periphery thereof is surrounded by a steel mold, and the steel mold part is projected above the water surface. ,
Since the lower end is sunk in the ground below the water bottom, it is possible to perform work such as excavating earth and sand in the steel form, and by dropping the rebar cage in the steel form and placing concrete. , The upper part of the steel pipe pile can be integrated. Therefore, there is no need for a double cut-off work to construct the pier frame, the work from excavation to concrete placement can be performed underwater, and there is no risk of loosening the ground.Construction should be performed near the existing pier. However, it does not adversely affect the existing piers. Furthermore, the auxiliary construction method for protecting the existing piers is not required, and the construction period and cost can be reduced.

【0013】また請求項3記載の施工方法によれば、複
数本の鋼管杭の周囲に鋼製型枠を建て込む際に、H鋼に
よって複数本の鋼管杭との間隔が一定に保たれ、鉄筋籠
を鋼製型枠と鋼管杭とに落とし込む際の間隔が確保され
るとともに、鉄筋籠の落とし込み時に、鉄筋籠を鋼製型
枠の内周面に沿ってガイド鋼とCT鋼とによって案内す
ることができ、鉄筋籠を円滑に落とし込むことができ
る。
Further, according to the construction method of claim 3, when the steel form is built around the plurality of steel pipe piles, the interval between the steel pipe piles is kept constant by the H steel. A space is secured when the rebar cage is dropped into the steel form and the steel pipe pile, and when the rebar basket is dropped, the rebar cage is guided by the guide steel and the CT steel along the inner peripheral surface of the steel form. It is possible to smoothly drop the rebar cage.

【0014】[0014]

【実施例】以下、この発明の橋脚の実施例を図面に基づ
いて説明し、併せてその施工方法についても説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of a bridge pier according to the present invention will be described below with reference to the drawings and a construction method thereof will be described.

【0015】図1は既設橋脚に近接して構築された本発
明の実施例にかかる橋脚を示す正面視断面図である。図
2は図1の橋脚のII−II線拡大断面図と、同拡大断面図
におけるA部およびB部の拡大断面図である。図3は鋼
管杭に用いられる鋼管の下部を示す正面図と、同正面図
のC部の拡大図、同拡大図のD−D線断面図である。図
1に示すように、橋脚1は、一定の間隔をあけて沈設さ
れた2本の鋼管杭2と、各鋼管杭2に連続して下方に延
設された鉄筋コンクリート杭3と、2本の鋼管杭2の上
部を取り囲む鋼製型枠5と、鋼製型枠5の外周面に沿っ
て上方に延設されたコンクリート部7とを具備する。な
お、本実施例の橋脚1は、既設橋脚Sに近接して構築さ
れている。
FIG. 1 is a front sectional view showing a pier according to an embodiment of the present invention constructed near an existing pier. FIG. 2 is an enlarged cross-sectional view of the bridge pier of FIG. 1 taken along the line II-II and enlarged cross-sectional views of a portion A and a portion B in the enlarged cross-sectional view. FIG. 3 is a front view showing a lower portion of a steel pipe used for a steel pipe pile, an enlarged view of a portion C of the front view, and a sectional view taken along line D-D of the enlarged view. As shown in FIG. 1, the bridge pier 1 includes two steel pipe piles 2 that are sunk at regular intervals, a reinforced concrete pile 3 that extends downward from each of the steel pipe piles 2, and two steel pipe piles. The steel form 5 includes a steel form 5 surrounding the upper part of the steel pipe pile 2, and a concrete part 7 extending upward along the outer peripheral surface of the steel form 5. The pier 1 of the present embodiment is constructed close to the existing pier S.

【0016】前記各鋼管杭2は、その下端が川底(河
床)下の地盤中の支持層に達し、上端は水面上に突出す
る長尺の鋼管2aと、この鋼管2aの内周面に沿って配
筋された多数の鉄筋2bとを備え、鋼管2a内にコンク
リート2cを打設した構造からなる。なお、鋼管2aの
下端周囲には、図3のように凹凸状の多数の刃先2a−
1を円周方向に等間隔に形設し、刃先2a−1の硬度を
上げるためにハードフェイシング加工を施している。こ
のため、鋼管2aの地盤中へ沈降(貫入)作業が容易に
行われる。
Each of the steel pipe piles 2 has a lower end reaching a support layer in the ground below the river bottom (river bed) and an upper end protruding along the water surface along a long steel pipe 2a and an inner peripheral surface of the steel pipe 2a. It has a structure in which concrete 2c is cast in a steel pipe 2a. Around the lower end of the steel pipe 2a, as shown in FIG.
1 are formed at equal intervals in the circumferential direction, and hard facing processing is performed to increase the hardness of the cutting edge 2a-1. Therefore, the work of sinking (penetrating) the steel pipe 2a into the ground is easily performed.

【0017】鉄筋コンクリート杭3は、下端が地盤中の
支持層に達し、前記鉄筋2bに連続する鉄筋3bにより
筒状に組みつけられた鉄筋筒を、コンクリート3aで一
体化した構造からなる。本実施例では、鋼管杭2と鉄筋
コンクリート杭3の2段構造にして施工費用を削減した
が、鉄筋コンクリート杭3の部分まで鋼管杭2を延長し
てもよい。
The reinforced concrete pile 3 has a structure in which a lower end reaches a support layer in the ground and a reinforced cylinder which is assembled in a tubular shape by a reinforcing bar 3b continuous with the reinforcing bar 2b is integrated with concrete 3a. In the present embodiment, the construction cost is reduced by making the steel pipe pile 2 and the reinforced concrete pile 3 into a two-stage structure, but the steel pipe pile 2 may be extended to the portion of the reinforced concrete pile 3.

【0018】鋼製型枠5は、図2に示すように、上方よ
り見て略楕円形状をなし、表面には塗装を施してある。
鋼製型枠5の下端は、川底下の地盤中に埋設され、上端
は水面の上方に突出するが、前記鋼管杭2の上端より低
くして、鋼管杭2の上端部を鋼製型枠5の上方に突出さ
せている。
As shown in FIG. 2, the steel frame 5 has a substantially elliptical shape when viewed from above, and its surface is coated.
The lower end of the steel form 5 is buried in the ground below the riverbed, and the upper end projects above the water surface, but it is lower than the upper end of the steel pipe pile 2 so that the upper end of the steel pipe pile 2 is made of steel. 5 is projected above.

【0019】鋼製型枠5の内周面側において、左右の鋼
管杭2と対応する円弧状部の4箇所および中間の対向す
る平面部の4箇所の合計8箇所には、一対のL形鋼を間
隔をあけて溶接することにより形成されるガイド鋼5a
を高さ方向に突設している。鋼製型枠5内には鉄筋籠6
を挿入しているが、この鉄筋籠6は多数の鉄筋を用いて
鋼製型枠5よりわずかに小さい略楕円形状に組みつけた
もので、その高さは鋼製型枠5よりも高く、すなわち鋼
製型枠5の上方に突出する鋼管杭2の上端を越える高さ
にしてある。鉄筋籠6の中間部の左右に、対向する籠部
材間に跨がってL形鋼のフレーム部材6aをL形鋼6b
を介して溶接し、前記鋼製型枠5の中間のガイド鋼5a
と対向する位置には、断面T形のCT鋼6cを溶接によ
り鉄筋籠6に対し外向けに突設している。
On the inner peripheral surface side of the steel form 5, a pair of L-shapes are provided at a total of 8 locations, that is, 4 locations on the arcuate portions corresponding to the left and right steel pipe piles 2 and 4 locations on the intermediate facing flat portions. Guide steel 5a formed by welding steel at intervals
Are projected in the height direction. Reinforcing cage 6 in steel form 5
The rebar cage 6 is assembled into a substantially elliptical shape slightly smaller than the steel form 5 using a large number of rebars, and its height is higher than that of the steel form 5. That is, the height is higher than the upper end of the steel pipe pile 2 protruding above the steel form frame 5. On the left and right of the middle portion of the rebar cage 6, the L-shaped steel frame member 6a is provided across the opposing cage members.
Guide steel 5a intermediate between the steel form 5 by welding through
A CT steel 6c having a T-shaped cross section is projected outward from the rebar cage 6 by welding at a position opposed to.

【0020】鋼製型枠5内の川底下方の土砂が掘削さ
れ、鋼製型枠5内に鉄筋籠6が挿入されたのち、鋼製型
枠5内の空間部にコンクリートが打設されるとともに、
このコンクリート部(図示せず)に連続して、鋼管杭2
の上端部を鉄筋籠6とともに一体化するコンクリート部
7が、鋼製型枠5の外周面に沿って上方に延設されてい
る。なお、コンクリート部7の頂部7aは、橋げた(図
示せず)のシューを設置する関係上、全周にわたり外方
へ膨出させてその下方部分に比べてやや大きく形成して
いる。
The earth and sand below the bottom of the river in the steel form 5 is excavated, the reinforcing bar cage 6 is inserted into the steel form 5, and then concrete is poured into the space inside the steel form 5. With
Steel pipe pile 2 in succession to this concrete part (not shown)
A concrete portion 7 that integrates the upper end portion of the steel sheet with the rebar cage 6 is extended upward along the outer peripheral surface of the steel form frame 5. The top portion 7a of the concrete portion 7 is formed to be slightly larger than the lower portion thereof by bulging outward over the entire circumference because a bridged shoe (not shown) is installed.

【0021】図4は橋脚1の配筋を示す略図で、同図の
ように、橋脚1内に装入されている鉄筋は、鋼管2aの
内周面に添わせて円筒状に配装され、下方の鉄筋コンク
リート杭3内の鉄筋に連続する鉄筋2bと、鉄筋籠6を
構成する鉄筋とからなる。鉄筋2bの上端部は鋼管2a
より突出してJの字状に屈曲し、鉄筋籠6の上端は前記
コンクリート部7の頂部7aに至っている。
FIG. 4 is a schematic view showing the bar arrangement of the pier 1. As shown in the figure, the reinforcing bars inserted in the pier 1 are arranged in a cylindrical shape along the inner peripheral surface of the steel pipe 2a. , A reinforcing bar 2b continuous with the reinforcing bar in the lower reinforced concrete pile 3 and a reinforcing bar constituting the reinforcing bar cage 6. The upper end of the reinforcing bar 2b is the steel pipe 2a
It projects further and bends in a J shape, and the upper end of the reinforcing bar cage 6 reaches the top portion 7a of the concrete portion 7.

【0022】次に、上記した構成からなる実施例の橋脚
1について、その施工方法を順番に説明する。
Next, the construction method of the pier 1 of the embodiment having the above-mentioned structure will be described in order.

【0023】まず、河川の橋脚1の構築位置まで、図
5に示すように河岸から仮設桟橋20を設ける。図5中
の符号21は、桟橋20を支持するための杭で、複数本
の杭21を一定の間隔をおいて打ち立てている。
First, as shown in FIG. 5, a temporary jetty 20 is installed from the bank to the construction position of the bridge pier 1 of the river. Reference numeral 21 in FIG. 5 is a pile for supporting the jetty 20, and a plurality of piles 21 are erected at regular intervals.

【0024】所定長さ(本実施例では、21.20
m)の鋼管2aを、桟橋20(図5)上のクレーン22
で吊り下げ、川底下方の地盤中に打設して支持層まで貫
入させる。鋼管2aは、一定の間隔(中心点間隔で4.
5m)をあけて河の流れに沿って2本打設し、図1のよ
うに各鋼管2aの上部を水面の上方に突出させる。
A predetermined length (21.20 in this embodiment)
m) steel pipe 2a to the crane 22 on the pier 20 (Fig. 5)
Suspend with, and drive into the ground below the river bottom to penetrate the support layer. The steel pipes 2a are arranged at regular intervals (4.
5 m) is opened and two pipes are placed along the river, and the upper portions of the steel pipes 2a are projected above the water surface as shown in FIG.

【0025】各鋼管2a内の土砂(川底より下方)を
掘削したのち、さらに各鋼管2a下方の土砂を次の支持
層に達するまで掘削し、各鋼管2a内からその下方の掘
削部まで鉄筋2bを連続して円筒状に間隔をあけて配筋
し、鉄筋2bの上端部は鋼管2aの上方に突出させる。
After excavating the earth and sand in each steel pipe 2a (below the riverbed), the earth and sand below each steel pipe 2a is excavated until it reaches the next support layer, and the reinforcing bars 2b are formed from inside each steel pipe 2a to the excavated portion below it. Are continuously arranged in a cylindrical shape at intervals, and the upper end of the reinforcing bar 2b is projected above the steel pipe 2a.

【0026】各鋼管2a内およびその下方の掘削部内
にコンクリートを打設し、鋼管杭2とその下方に連続す
る鉄筋コンクリート杭3からなる基礎杭を構築する。
Concrete is placed in each steel pipe 2a and in the excavated portion below the steel pipe 2a to construct a foundation pile consisting of the steel pipe pile 2 and the reinforced concrete pile 3 continuous therebelow.

【0027】鋼製型枠5を、桟橋20上のクレーン2
2で吊り下げて2本の鋼管杭2を取り囲み、かつ各鋼管
杭2と一定の間隔をあけて川底下方の地盤中の比較的浅
い位置まで沈設し、鋼製型枠5の上端は水面上方に突出
させる。このように、鋼管杭2の周囲に鋼製型枠5を建
て込む際には、図2のように、H鋼11の一方をガイド
鋼5a内に挿入して鋼管杭2との間隔を一定に保ちなが
ら、ゆっくりと下降させていく。鋼製型枠5の沈設作業
は、限定するものではないが、ウォータジェットを鋼製
型枠5内に装着するとともに上部にバイブロを設置し、
ウォータジェットで下方の地盤を切削しながらバイブロ
の振動によって行うとよい。
The steel formwork 5 is attached to the crane 2 on the pier 20.
It is suspended by 2 and surrounds two steel pipe piles 2, and it is sunk to a relatively shallow position in the ground below the river bottom at regular intervals with each steel pipe pile 2, and the upper end of the steel form 5 is above the water surface. To project. In this way, when building the steel form 5 around the steel pipe pile 2, one of the H steels 11 is inserted into the guide steel 5a as shown in FIG. While keeping at, slowly descend. The work of immersing the steel form 5 is not limited, but a water jet is installed in the steel form 5 and a vibro is installed on the upper part,
It is recommended to use the vibration of the vibro while cutting the ground below with a water jet.

【0028】鋼製型枠5内の土砂(川底下方)を掘削
したのち、鉄筋籠6を桟橋20上のクレーン22で吊り
下げ鋼製型枠5の内周面に沿って2本の鋼管杭2を取り
囲むように落とし込み、鉄筋籠6の上端部は鋼管杭2の
上端よりやや上方に突出させる。そして、鉄筋籠6を鋼
製型枠5と鋼管杭2の間に落とし込む際には、CT鋼6
cの先端部をガイド鋼5a内に挿入した状態で、ガイド
鋼5aとCT鋼6cによって案内して落とし込むことに
より、鋼製型枠5および鋼管杭2と、鉄筋籠6との間に
それぞれ一定の間隔を確保することができる。
After excavating the earth and sand in the steel form 5 (below the river bottom), the rebar cage 6 is suspended by the crane 22 on the pier 20 and two steel pipe piles are provided along the inner peripheral surface of the steel form 5. It is dropped so as to surround 2, and the upper end portion of the reinforcing rod cage 6 projects slightly above the upper end of the steel pipe pile 2. When the rebar cage 6 is dropped between the steel form 5 and the steel pipe pile 2, the CT steel 6
With the tip end of c inserted into the guide steel 5a, the guide steel 5a and the CT steel 6c guide and drop it so that the steel form 5 and the steel pipe pile 2 and the rebar cage 6 are kept constant. It is possible to secure the interval.

【0029】鋼製型枠5に沿ってその上方に突出する
鉄筋籠6を取り囲むように、ベニヤ板などによる型枠
(図示せず)を仮設して、その仮設型枠内および鋼製型
枠5内にコンクリートを打設し、コンクリートが固化し
たのちに仮設型枠を取り除く。そして、最後に、仮設桟
橋20を撤去すれば、全ての作業が終了する。
A form (not shown) such as a veneer plate is temporarily installed so as to surround the reinforcing bar cage 6 projecting upward along the steel form 5, and inside the temporary form and the steel form 5 Place concrete inside and remove the temporary formwork after the concrete has solidified. Finally, if the temporary pier 20 is removed, all the work is completed.

【0030】上記した〜の工程からなる施工方法に
より、本発明の実施例にかかる橋脚1が構築された。本
施工方法によると、主として2本の鋼管杭2によって橋
脚1を支持し、従来の橋脚に必須のフーチングが不要に
なったので、掘削深さが浅くてすみ、またその掘削作業
は鋼製型枠5内で行うので、二重締切工の施工が省略で
きるとともに、既設橋脚の防護のための補助工法が不要
になった。このため、施工作業が簡略化され、仮設桟橋
20等の設置作業を含めても、渇水期(11月〜5月)
内に4基の橋脚が完成し、工期の大幅な短縮(従来の工
期の約1/2)とともに、工費の削減(従来の工費の約
1/2)が達成された。また、二重締切工の撤去が不要
なうえに、地盤深くまで掘削する必要がなく、しかも水
中掘削が可能なため、既設橋脚S(図1)に近接した施
工にも拘わらず、既設橋脚に与える影響もなかった。
The pier 1 according to the embodiment of the present invention was constructed by the construction method comprising the above steps (1) to (3). According to this construction method, since the bridge pier 1 is mainly supported by the two steel pipe piles 2 and the footing that is indispensable for the conventional bridge piers is not required, the excavation depth is shallow, and the excavation work is made by the steel mold. Since it is carried out in the frame 5, the construction of double deadening work can be omitted and the auxiliary construction method for protecting the existing piers is no longer necessary. Therefore, the construction work is simplified, and even if the installation work of the temporary pier 20 etc. is included, the dry season (November to May)
The four piers were completed within the building, and the construction period was drastically shortened (about 1/2 of the conventional construction period) and the construction cost was reduced (about 1/2 of the conventional construction cost). In addition, it is not necessary to remove the double cofferdam, and it is not necessary to excavate deep into the ground, and since it is possible to perform underwater excavation, despite the construction close to the existing pier S (Fig. 1), It had no effect.

【0031】[0031]

【発明の効果】以上説明したことから明らかなように、
この発明の橋脚とその施工方法には、次のような優れた
効果がある。
As is clear from the above description,
The bridge pier and its construction method of the present invention have the following excellent effects.

【0032】(1) 二重締切工や深い掘削を施工する必要
がなく、施工に必要な工程数が軽減され、工期の短縮を
図ることができる。
(1) It is not necessary to construct a double cut-off work or deep excavation, the number of steps required for construction can be reduced, and the construction period can be shortened.

【0033】(2) 既設橋脚に近接した場所に橋脚を構築
する場合にも、二重締切工の施工が不要で、とくにその
撤去時に地盤をゆるめることがないので、既設橋脚に悪
影響を及ぼすおそれがなく、また既設橋脚の防護のため
の補助工法を要しないので、施工費用の削減ができる。
(2) Even when constructing a pier close to the existing pier, there is no need to construct a double deadline, and the ground will not be loosened when the pier is removed, which may adversely affect the existing pier. Since there is no need and no auxiliary construction method is required to protect the existing piers, construction costs can be reduced.

【0034】(3) 請求項3記載の施工方法は、上記の
(1)〜(2)の効果に加えて、複数本の鋼管杭の周囲に鋼製
型枠を建て込む際に、並びに鉄筋籠を鋼製型枠と鋼管杭
との間に落とし込む際に、鋼製型枠および鉄筋籠を円滑
に挿入できるとともに、各部材間に一定の間隔を確保す
ることができる。
(3) The construction method according to claim 3 is the same as above.
In addition to the effects of (1) to (2), when building a steel form around a plurality of steel pipe piles, and when dropping the rebar cage between the steel form and the steel pipe pile, The steel form and the rebar cage can be smoothly inserted, and a constant space can be secured between the respective members.

【図面の簡単な説明】[Brief description of drawings]

【図1】既設橋脚に近接して構築された本発明の実施例
にかかる橋脚を示す正面視断面図である。
FIG. 1 is a front view cross-sectional view showing a pier according to an embodiment of the present invention constructed near an existing pier.

【図2】図1の橋脚のII−II線拡大断面図と、同拡大断
面図におけるA部およびB部の拡大断面図である。
FIG. 2 is an enlarged cross-sectional view taken along line II-II of the bridge pier of FIG. 1 and enlarged cross-sectional views of a portion A and a portion B in the enlarged cross-sectional view.

【図3】鋼管杭に用いられる鋼管の下部を示す正面図
と、同正面図のC部の拡大図と、同拡大図のD−D線断
面図である。
FIG. 3 is a front view showing a lower portion of a steel pipe used for a steel pipe pile, an enlarged view of a C portion of the front view, and a sectional view taken along line D-D of the enlarged view.

【図4】図4(a)は橋脚の配筋略図で、左半分は鋼管内
の配筋を表し、右半分は鋼製型枠内およびその上方のコ
ンクリート部内の配筋を表す。図4(b)は図4(a)のE
−E線断面図、図4(c)は図4(a)のF−F線断面図で
ある。
FIG. 4 (a) is a schematic view of the reinforcement of the pier, where the left half shows the reinforcement in the steel pipe and the right half shows the reinforcement in the steel form and in the concrete part above it. FIG. 4B shows E of FIG. 4A.
4E is a sectional view taken along the line E, and FIG. 4C is a sectional view taken along the line FF in FIG.

【図5】鋼管を沈設する作業状態を示す正面視断面図で
ある。
FIG. 5 is a front cross-sectional view showing a working state in which a steel pipe is sunk.

【図6】図6(a)は従来の一般的な施工方法による橋脚
を示す正面視断面図、図6(b)は図6(a)の橋脚のVI−
VI線断面図である。
FIG. 6 (a) is a front sectional view showing a pier by a conventional general construction method, and FIG. 6 (b) is a VI-of the pier of FIG. 6 (a).
FIG. 6 is a sectional view taken along line VI.

【符号の説明】[Explanation of symbols]

1 橋脚 2 鋼管杭 3 鉄筋コンクリート杭 5 鋼製型枠 5a ガイド鋼 6 鉄筋籠 7 コンクリート部 1 Pier 2 Steel pipe pile 3 Reinforced concrete pile 5 Steel formwork 5a Guide steel 6 Reinforcing cage 7 Concrete part

フロントページの続き (72)発明者 山本 正幸 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 森 満夫 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 田中 壽賀夫 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 杉山 良夫 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 上田 正一 大阪府大阪市北区芝田二丁目4番24号 西 日本旅客鉄道株式会社内 (72)発明者 岡本 聖智 大阪府大阪市淀川区西中島5丁目4番20号 ジェイアール西日本コンサルタンツ株式 会社内 (72)発明者 矢島 秀治 大阪府大阪市淀川区西中島5丁目4番20号 ジェイアール西日本コンサルタンツ株式 会社内 (72)発明者 真部 伸穂 兵庫県西宮市池田町9番18号 株式会社新 井組内Front Page Continuation (72) Inventor Masayuki Yamamoto 2-4-24 Shibata Kita-ku, Osaka City, Osaka Prefecture West Japan Railway Company (72) Inventor Mitsuo Mori 2-4-2-4 Shibata, Kita-ku, Osaka City, Osaka Prefecture No. West Japan Railway Company (72) Inventor Tokio Tanaka 2-4-24 Shibata Kita-ku, Osaka City, Osaka Prefecture West Japan Railway Company (72) Inventor Yoshio Sugiyama Kita-ku, Osaka City, Osaka Prefecture 2-4-24 Shibata West Japan Railway Company (72) Inventor Shoichi Ueda 2-4-24 Shibata Shibata Kita-ku, Osaka City, Osaka Prefecture (72) Inventor Seichi Okamoto Within 5-21-20 Nishinakajima, Yonagawa-ku, Osaka-shi, Osaka Prefecture JR West Japan Consultants Co., Ltd. (72) Inventor Shuji Yajima 5-4-20 Nishinakajima, Yonagawa-ku, Osaka-shi, Osaka City JR West Japan Consultants Co., Ltd. ( 72) Inventor Shinho Mabe 9-18 Ikeda-cho, Nishinomiya-shi, Hyogo New Co., Ltd. In the group

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 水底下の地盤中の支持層に下端が達し、
水面上に上端が突出する複数本の鋼管杭と、 それらの鋼管杭の周囲を取り囲み、水底下の地盤中に一
部を埋設した鋼製型枠と、 該鋼製型枠の内周面に沿って前記鋼管杭の周囲に配装さ
れた鉄筋籠と、 前記鋼製型枠内の空間部に打設されたコンクリート部お
よび鋼製型枠の外周面に沿って上方に延設され、前記鋼
管杭の上端部を前記鉄筋籠とともに一体化したコンクリ
ート部とを備えたことを特徴とする橋脚。
1. The lower end reaches a supporting layer in the ground below the bottom of the water,
A plurality of steel pipe piles with an upper end protruding above the water surface, a steel form frame that surrounds the circumference of these steel pipe piles and is partially embedded in the ground under the water bottom, and an inner peripheral surface of the steel form frame. Reinforcing bar baskets arranged around the steel pipe pile along, and extending upward along the outer peripheral surface of the concrete part and the steel form frame placed in the space part of the steel form frame, A pier comprising a concrete portion in which an upper end portion of a steel pipe pile is integrated with the rebar cage.
【請求項2】 複数本の鋼管杭を、水底下の地盤中の支
持層に下端が達し、かつ水面上に上端が突出するように
構築し、 構築された複数本の鋼管杭の周囲を取り囲む鋼製型枠
を、水面上方からクレーン等により吊り下げて各鋼管と
一定の間隔をあけて水底下方の地盤中の比較的浅い位置
まで沈設し、前記鋼製型枠の上端を水面上に突出させ、 前記鋼製型枠内の土砂を掘削したのち、あらかじめ組み
立てた鉄筋籠を、水面上方からクレーン等により吊り下
げて前記鋼製型枠の内周面に沿って前記鋼管の周囲に落
とし込み、鉄筋籠の上端部は鋼管杭の上端よりやや上方
に突出させ、前記鋼製型枠に沿ってその上方に前記鉄筋
籠を取り囲むように型枠を仮設し、該仮設型枠内および
鋼製型枠内にコンクリートを打設したのち、前記仮設型
枠を取り除くことを特徴とする橋脚の施工方法。
2. A plurality of steel pipe piles are constructed so that the lower end reaches a supporting layer in the ground below the water bottom and the upper end projects above the water surface, and surrounds the periphery of the constructed multiple steel pipe piles. The steel formwork is hung from above the water surface by a crane or the like, and is sunk to a relatively shallow position in the ground below the bottom of the water with a certain distance from each steel pipe, and the upper end of the steel formwork is projected above the water surface. Then, after excavating the earth and sand in the steel mold, pre-assembled rebar baskets are suspended from above the water surface by a crane or the like and dropped around the steel pipe along the inner peripheral surface of the steel mold, The upper end of the rebar cage is made to project slightly above the upper end of the steel pipe pile, and a formwork is temporarily installed along the steel formwork so as to surround the rebar cage, and inside the temporary formwork and the steel formwork. After placing concrete in the frame, remove the temporary formwork Method of constructing piers, characterized in that.
【請求項3】 前記鋼製型枠の内面の適所に、その上下
方向にガイド鋼を突設し、 鋼製型枠を複数本の鋼管杭の周囲に建て込む際に、前記
ガイド鋼にH鋼の一方を差し込んで各鋼管杭との間に一
定の間隙を保たせるとともに、 鉄筋籠を鋼製型枠内に落とし込む際に、前記ガイド鋼
に、鉄筋籠に取り付けたCT鋼の先端部を挿入して案内
させる請求項2記載の橋脚の施工方法。
3. A guide steel projecting in a vertical direction at a proper position on the inner surface of the steel formwork, and when the steel formwork is built around a plurality of steel pipe piles, H is added to the guide steel. Insert one side of the steel to maintain a constant gap between each steel pipe pile, and when dropping the rebar cage into the steel form, insert the tip end of the CT steel attached to the rebar cage into the guide steel. The pier construction method according to claim 2, wherein the pier is inserted and guided.
JP12421192A 1992-04-16 1992-04-16 Bridge pier and its construction method Expired - Lifetime JP2878525B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12421192A JP2878525B2 (en) 1992-04-16 1992-04-16 Bridge pier and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12421192A JP2878525B2 (en) 1992-04-16 1992-04-16 Bridge pier and its construction method

Publications (2)

Publication Number Publication Date
JPH05295709A true JPH05295709A (en) 1993-11-09
JP2878525B2 JP2878525B2 (en) 1999-04-05

Family

ID=14879749

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12421192A Expired - Lifetime JP2878525B2 (en) 1992-04-16 1992-04-16 Bridge pier and its construction method

Country Status (1)

Country Link
JP (1) JP2878525B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021076004A (en) * 2019-10-31 2021-05-20 株式会社熊谷組 Pier, pier construction method, bridge reconstruction method and bridge construction method
CN116815635A (en) * 2023-05-18 2023-09-29 中建八局第一建设有限公司 Wading bridge cofferdam integrated construction process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2021076004A (en) * 2019-10-31 2021-05-20 株式会社熊谷組 Pier, pier construction method, bridge reconstruction method and bridge construction method
JP2025061516A (en) * 2019-10-31 2025-04-10 株式会社熊谷組 Pier construction method and bridge construction method
CN116815635A (en) * 2023-05-18 2023-09-29 中建八局第一建设有限公司 Wading bridge cofferdam integrated construction process

Also Published As

Publication number Publication date
JP2878525B2 (en) 1999-04-05

Similar Documents

Publication Publication Date Title
JP6806465B2 (en) Construction method of foundation structure
JP4226954B2 (en) Underpinning method and viaduct
JP4508400B2 (en) Construction method for underwater structure foundation
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP3516391B2 (en) Ground excavation method
JP3453664B2 (en) Shaft construction method
CN112681333B (en) Foundation pit supporting structure of waterside bridge abutment foundation and construction method thereof
JPH10168915A (en) Ground excavation method in deadline sheet pile
JP2878525B2 (en) Bridge pier and its construction method
JP2000129696A (en) Pile foundation method and pile foundation constructed by the method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP2980311B2 (en) Construction method of coping submerged revetment and vibro hammer used in the construction method.
JP2518596B2 (en) Lifting pressure resistant construction method of bottom concrete in steel well
JP4132320B2 (en) Foundation construction method
JPH073781A (en) Construction method of foundation footing on cast-in-place concrete pile head.
JPH01226921A (en) Earthquake-proof reinforced revetment construction
CN217517600U (en) Deep foundation pit supporting structure for supporting inclined struts in pit
JP7480069B2 (en) How to reinforce existing revetments
JP3776280B2 (en) Mountain fastening method
JP3938393B2 (en) Single column foundation reinforcement method
JPH06194485A (en) Nuclear power plant building construction method
JP3147437B2 (en) Construction method of underground diaphragm wall
JPH09256356A (en) Underground wall and its construction method
JP2000220374A (en) How to build a shaft

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090122

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20100122

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110122

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110122

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20120122

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120122

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130122

Year of fee payment: 14

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20130122