JPH0579778B2 - - Google Patents

Info

Publication number
JPH0579778B2
JPH0579778B2 JP26149485A JP26149485A JPH0579778B2 JP H0579778 B2 JPH0579778 B2 JP H0579778B2 JP 26149485 A JP26149485 A JP 26149485A JP 26149485 A JP26149485 A JP 26149485A JP H0579778 B2 JPH0579778 B2 JP H0579778B2
Authority
JP
Japan
Prior art keywords
water
floor
piping
floor slab
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP26149485A
Other languages
Japanese (ja)
Other versions
JPS62125136A (en
Inventor
Sadaki Yagi
Shigeki Tagawa
Hiroaki Matsui
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP26149485A priority Critical patent/JPS62125136A/en
Publication of JPS62125136A publication Critical patent/JPS62125136A/en
Publication of JPH0579778B2 publication Critical patent/JPH0579778B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Panels For Use In Building Construction (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 この発明は、マンシヨンなどの多層集合住宅に
おいて、ウオーターセクシヨン部の漏水による下
の階への被害を防止するための防水施工方法に関
する。
DETAILED DESCRIPTION OF THE INVENTION <<Industrial Application Field>> The present invention relates to a waterproofing method for preventing damage to lower floors due to water leakage in a water section in a multi-story housing complex such as a condominium.

《従来の技術》 通常集合住宅のキツチン、洗面所、バスルーム
およびトイレツト等の水を多く使用する部分では
ウオーターセクシヨンとして一つにまとめられて
いる。
《Prior Art》 Normally, parts of apartment buildings that use a lot of water, such as kitchens, washrooms, bathrooms, and toilets, are integrated into a water section.

このウオーターセクシヨンでは、鉄筋コンクリ
ート床面上に共有のパイプスペースより分離され
た給水管および排水管、ガス管等を配管し、その
上部にフローリング材を設けてある。
In this water section, water supply pipes, drainage pipes, gas pipes, etc. are laid out on a reinforced concrete floor surface separated from a common pipe space, and flooring material is provided above.

《発明が解決しようとする問題点》 これらのウオーターセクシヨン部ではおうおう
にして取り扱い上の不注意により水漏れを生ずる
ことがある。
<<Problems to be Solved by the Invention>> Water leaks can often occur in these water sections due to careless handling.

例えば洗濯機の排水ホースを外したままで給水
を行ない、排水ホースから水が床面にこぼれた
り、排水口が目詰りをおこし、オーバーフローす
るなどといつたことがある。
For example, there have been cases where water was supplied to a washing machine with the drain hose disconnected, resulting in water spilling from the drain hose onto the floor, or the drain becoming clogged and overflowing.

こうした水漏れが生じた場合、従来の現場打ち
コンクリート床では、防水が充分なされていない
ために、亀裂などから下の階へ漏水し、階下の住
戸の天井面や壁面を汚したり、ここから漏水する
といつたトラブルが発生している。
When such water leaks occur, because conventional cast-in-place concrete floors are not sufficiently waterproof, water leaks to the floor below through cracks, stains the ceilings and walls of the units below, and water leaks from there. Then a problem occurred.

また、プレキヤスト構造の建物では、プレキヤ
スト版相互には防水性があるものの、その周縁部
の継目から漏水する惧れが充分にある。
Furthermore, in buildings with a precast structure, although the precast plates are waterproof, there is a good chance that water will leak from the joints at their peripheral edges.

これに対し、ウオーターセクシヨン部の床面全
体をアスフアルト防水することも一部行なわれて
いるが、この種の防水施工はコスト面や工事の煩
雑さのために一般には行なわれていないのが現状
であつた。
In response to this, some methods have been used to waterproof the entire floor surface of the water section with asphalt, but this type of waterproofing is generally not carried out due to the cost and complexity of construction. It was the current situation.

この発明は以上の如き背景に基づきなされたも
のであつて、簡単な施工方法によりウオーターセ
クシヨン部を完全な防水床面とすることおよび給
排水管などの配管および設備機器の設置、施工の
合理化を図ることを目的としている。
This invention was made based on the above background, and it is possible to make a water section a completely waterproof floor surface using a simple construction method, and to streamline the installation and construction of piping and equipment such as water supply and drainage pipes. The purpose is to

《問題点を解決するための手段》 前記目的を達成するため、この発明では、多層
集合住宅のウオーターセクシヨン部に対応する床
面形状であつて、周縁に立ち上がりを設けてパン
形に成形されたプレキヤスト床版上に、予め設備
機器ユニツトの配置に応じた先行配管を行ない、
該配管済みのプレキヤスト床版を吊り上げて前記
ウオーターセクシヨン部周縁の梁、スラブに嵌合
固定するようにしたことを特徴とする。
<<Means for Solving the Problems>> In order to achieve the above object, the present invention provides a floor surface shape corresponding to the water section of a multi-story apartment complex, which is formed into a bread shape with a rise on the periphery. On the precast floor slab, we perform preliminary piping according to the layout of the equipment units,
It is characterized in that the piped precast floor slab is lifted up and fitted and fixed to the beams and slabs around the water section.

《実施例》 以下、この発明方法の一実施例を図面を用いて
詳細に説明する。
<<Example>> Hereinafter, an example of the method of this invention will be described in detail using the drawings.

第1図はこの発明を適用したプレキヤスト床版
1を示すものである。
FIG. 1 shows a precast floor slab 1 to which the present invention is applied.

該床版1は、ウオーターセクシヨン部の床面形
状に対応して長方形に形成されたもので、その床
面の四周に立ち上げ部3を設け、全体としてパン
形に形成してある。また、立ち上げ部3の一部に
は排水用の切欠4が形成されており、床版1の床
面2はこの切欠4に向けて下り勾配となる傾斜面
に形成されている。
The floor slab 1 is formed into a rectangle corresponding to the shape of the floor surface of the water section, and has raised portions 3 provided around the four peripheries of the floor surface, and is formed into a bread shape as a whole. Further, a notch 4 for drainage is formed in a part of the upright portion 3, and the floor surface 2 of the floor slab 1 is formed into an inclined surface that slopes downward toward this notch 4.

さらに、立ち上げ部3の適宜位置には所定の間
隔でコツタ取付け用の切欠5が形成されている。
Furthermore, cutouts 5 for attaching a cotter are formed at predetermined intervals at appropriate positions on the upright portion 3.

以上の如く形成されたプレキヤスト床版1には
第2図に示すように給、排水およびガスパイプ7
がその床面上に設備機器ユニツトの配置に応じて
配管され、その端部を共通配管の引き込み部分に
集中させている。
The precast floor slab 1 formed as described above has supply, drainage and gas pipes 7 as shown in FIG.
Piping is arranged on the floor according to the arrangement of the equipment units, and the ends are concentrated at the lead-in part of the common piping.

なお、図示はしないが、各パイプ7は取付金具
などにより固定され、特に排水パイプは所定の勾
配で出口側に向けて下がり勾配となるようにして
いる。
Although not shown, each pipe 7 is fixed with a fitting or the like, and the drain pipe in particular has a predetermined slope that slopes downward toward the outlet side.

以上の先行配管終了後床面の適宜位置に根太等
を介してフローリングFを取付け、さらに第3図
に示すように浴室ユニツトやキツチンセツト洗面
ユニツト、および便器等の設備ユニツト8の梱包
体を設置した状態で、施工現場に移送し、これを
吊り上げ治具9を介してクレーン等で吊り上げ、
下階から順次床版1を嵌合固定することによりそ
の設置作業を終了する。
After completing the above preliminary piping, the flooring F was installed at appropriate positions on the floor via joists, etc., and the package of equipment unit 8 such as the bathroom unit, kitchen set, washbasin unit, and toilet bowl was installed as shown in Figure 3. In this state, it is transported to the construction site, and lifted by a crane or the like via a lifting jig 9.
The installation work is completed by sequentially fitting and fixing the floor slabs 1 from the lower floor.

第4図はその取付け状態を示すもので、プレキ
ヤスト床版1の周縁部は各階層毎に設けた梁10
の縁部に形成した段部10aに係合した状態とな
つている。また、フローリングFは点検用として
取外し可能となつている。
Figure 4 shows the installation state.
It is in a state where it is engaged with a stepped portion 10a formed on the edge of. Additionally, the flooring F can be removed for inspection.

第5図はプレキヤスト床版1の取付け部分の詳
細を示すもので、梁10には前記コツター挿通用
の切欠部5に対応する位置に同じくコツター挿通
用の穴10bが形成されており、両者間にまたが
るようにして所定厚みのコツタープレート11を
嵌合し、その上部をコンクリートまたはモルタル
で覆つてしまうことによりコツタープレート11
の楔効果によりプレキヤスト床版1と梁10との
接合部は補強状態で一体に接合することになる。
FIG. 5 shows the details of the installation part of the precast deck slab 1. The beam 10 is also formed with a hole 10b for inserting the caster at a position corresponding to the notch 5 for inserting the caster, and a hole 10b for inserting the caster is formed between the two. By fitting the cotter plate 11 of a predetermined thickness so as to straddle the turrets, and covering the upper part with concrete or mortar, the cotter plate 11
Due to the wedge effect, the joint between the precast floor slab 1 and the beam 10 is joined together in a reinforced state.

なお、他の接合部にもコンクリートまたはモル
タルあるいはアスフアルト施工等により接合す
る。そして、パイプ7の端部を対向する共通配管
からの引き込み配管部(図示略)と継手を介して
接合すれば、完全に各パイプ7は共通の配管部と
接続されることになる。
Other joints will also be joined using concrete, mortar, asphalt, etc. Then, by joining the ends of the pipes 7 to a lead-in piping section (not shown) from the opposing common piping via a joint, each pipe 7 is completely connected to the common piping section.

その後、設備ユニツト8の梱包を解き、各パイ
プ7にその給排水部を接続し、所定の場所に設置
すれば各階毎のウオーターセクシヨン部の施工を
終了することになるのである。
Thereafter, the equipment unit 8 is unpacked, its water supply and drainage section is connected to each pipe 7, and installed at a predetermined location, thereby completing the construction of the water section section for each floor.

なお、排水用の切欠部4の部分は共通の排水溝
等に連絡するものであり、この接合部分を十分に
防水施工すれば万が一床面2上に漏水があつたと
しても階下にその水がしみ出たり、滴下する惧れ
はない。しかしながら、さらに安全性を増すため
に、この部分に漏水センサー等を配置しておき、
漏水時に警報出力を発生させるようにすれば、漏
水状態を早期に発見でき、さらに安全性を増すこ
とができる。
Note that the drainage notch 4 connects to a common drainage ditch, etc., and if this joint is sufficiently waterproofed, even if water leaks onto the floor 2, the water will not leak downstairs. There is no risk of it seeping or dripping. However, in order to further increase safety, a water leak sensor etc. is placed in this area.
By generating an alarm output in the event of a water leak, the water leak condition can be detected early and safety can be further increased.

また、前記実施例では設備ユニツト8を単にプ
レキヤスト床版1上にフローリングFを介して設
置しておくのみであつたが、予め前記各パイプ類
7と接合した状態で床版1上に予め組付けておい
た後に各階毎に配置することもできる。
Further, in the above embodiment, the equipment unit 8 was simply installed on the precast floor slab 1 via the flooring F, but it is pre-assembled on the floor slab 1 in a state where it is connected to each of the pipes 7 in advance. You can also place them on each floor after attaching them.

《発明の効果》 以上実施例により詳細に説明したように、この
発明の多層集合住宅における防水施工方法によれ
ば、従来に比べて漏水による階下への影響がな
く、しかも工期が長く、高価なアスフアルト防水
施工によらず簡易に防水を行なえるので、施工が
簡単で工期も極めて短くできる。
《Effects of the Invention》 As explained in detail in the examples above, according to the waterproofing construction method for multi-story housing complexes of the present invention, compared to the conventional method, water leakage does not affect the downstairs, and moreover, the construction period is long and expensive. Since waterproofing can be easily performed without asphalt waterproofing construction, construction is easy and the construction period can be extremely short.

また、この発明では地上で先行配管を行なえる
ようになつているため、配管の継手部分などで生
ずる漏水に対しても、検査が容易であり、施工の
バラツキおよびこれに伴う漏水等を未然に防止で
きる。さらに、床版上に予め設備ユニツトを前記
配管とともに設置固定しておけばさらに工期が短
縮するものとなる。
In addition, since this invention allows preliminary piping to be carried out above ground, it is easy to inspect for water leaks that occur at pipe joints, etc., and prevents variations in construction work and water leaks that occur due to this. It can be prevented. Furthermore, if the equipment unit is installed and fixed in advance on the floor slab together with the piping, the construction period will be further shortened.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明を適用したプレキヤスト床版
1の全体構成を示す斜視図、第2図は同プレキヤ
スト床版1上に先行配管をした状態を示す斜視
図、第3図は同プレキヤスト床版1を吊り上げる
ときの状態を示す側面図、第4図は同プレキヤス
ト床版1を各階毎に固定した状態を示す断面図、
第5図はプレキヤスト床版1と梁との接合状態を
示す断面図である。 1……プレキヤスト床版、2……床面、3……
立上げ部、7……パイプ、9……吊り上げ治具、
10……梁。
FIG. 1 is a perspective view showing the overall configuration of a precast deck 1 to which the present invention is applied, FIG. 2 is a perspective view showing a state in which preliminary piping is installed on the precast deck 1, and FIG. 3 is a perspective view of the same precast deck 1. Fig. 4 is a side view showing the state when the precast floor slab 1 is lifted; Fig. 4 is a sectional view showing the state in which the precast floor slab 1 is fixed for each floor;
FIG. 5 is a sectional view showing the state of connection between the precast deck slab 1 and the beam. 1... Precast floor slab, 2... Floor surface, 3...
Standing part, 7...pipe, 9...lifting jig,
10...beam.

Claims (1)

【特許請求の範囲】[Claims] 1 多層集合住宅のウオーターセクシヨン部に対
応する床面形状であつて、周縁に立ち上がりを設
けてパン形に成形されたプレキヤスト床版上に、
予め設備機器ユニツトの配置に応じた先行配管を
行ない、該配管済みのプレキヤスト床版を吊り上
げて前記ウオーターセクシヨン部周縁の梁、スラ
ブに嵌合固定するようにしたことを特徴とする多
層集合住宅における防水施工方法。
1. On a precast floor slab formed into a bread shape with a rising edge on the periphery, the floor surface shape corresponds to the water section of a multi-story apartment building.
A multi-story housing complex, characterized in that preliminary piping is performed in advance according to the arrangement of equipment units, and the precast floor slab with the piping completed is lifted and fitted and fixed to beams and slabs around the water section. Waterproofing construction method.
JP26149485A 1985-11-22 1985-11-22 Waterproof construction in multistaired multiple dwelling house Granted JPS62125136A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26149485A JPS62125136A (en) 1985-11-22 1985-11-22 Waterproof construction in multistaired multiple dwelling house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26149485A JPS62125136A (en) 1985-11-22 1985-11-22 Waterproof construction in multistaired multiple dwelling house

Publications (2)

Publication Number Publication Date
JPS62125136A JPS62125136A (en) 1987-06-06
JPH0579778B2 true JPH0579778B2 (en) 1993-11-04

Family

ID=17362687

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26149485A Granted JPS62125136A (en) 1985-11-22 1985-11-22 Waterproof construction in multistaired multiple dwelling house

Country Status (1)

Country Link
JP (1) JPS62125136A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62197547A (en) * 1986-02-25 1987-09-01 大成建設株式会社 Floor structure
JP2675319B2 (en) * 1987-12-23 1997-11-12 東陶機器株式会社 Wall panel with piping
JP4757772B2 (en) * 2006-10-30 2011-08-24 新日本製鐵株式会社 Hat-shaped steel sheet pile with interval holding part and stacking method thereof

Also Published As

Publication number Publication date
JPS62125136A (en) 1987-06-06

Similar Documents

Publication Publication Date Title
US8919049B2 (en) Prefabricated temporary house addition
CA1282570C (en) Building system for multi-storey buildings
US5113625A (en) Non-cumbustible modular building
JP2018528127A (en) Fluid holding structure
US20180238046A1 (en) Prefab Utility Wall
JPS62125136A (en) Waterproof construction in multistaired multiple dwelling house
RU2418926C2 (en) Method to repair bathroom units of apartment building
JP2990434B1 (en) How to assemble the plumbing unit of the building to the frame by the frame wall method
JP3140229B2 (en) Dwelling unit variable housing system
CN209211733U (en) A prefabricated floor welded connection node
JP3245457U (en) modular drainage structure
EP0229460B1 (en) Improved building system for multi-storey buildings
JPH06272343A (en) Floor construction of precast reinforced concrete structure
KR200352175Y1 (en) Low noise drainage plumbing in bathroom
JP2777591B2 (en) Bus system and unit bus for assembling it
AU593037B2 (en) Improved building system for multi-storey buildings
JPH0439966Y2 (en)
JP2570176Y2 (en) Floor panel
JPH0745658Y2 (en) Piping set jig
JPH02304150A (en) Floor construction method
JPS583884Y2 (en) Side block for manhole
JPS627741Y2 (en)
JP2007146376A (en) Drainage
JPH0128194B2 (en)
JP3671979B2 (en) Sanitary equipment construction structure and construction method