JPH0610340A - Construction method of continuous underground wall using precast plate - Google Patents
Construction method of continuous underground wall using precast plateInfo
- Publication number
- JPH0610340A JPH0610340A JP16598192A JP16598192A JPH0610340A JP H0610340 A JPH0610340 A JP H0610340A JP 16598192 A JP16598192 A JP 16598192A JP 16598192 A JP16598192 A JP 16598192A JP H0610340 A JPH0610340 A JP H0610340A
- Authority
- JP
- Japan
- Prior art keywords
- precast plate
- earth auger
- earth
- opening
- underground wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
(57)【要約】
【目的】 地山の崩落の恐れがなく、地盤安定化のため
の安定液を使用せずに、プレキャスト版を確実に埋設し
て連続地中壁を築造する。
【構成】 土留め用のプレキャスト版10の貫通開口1
1,12,13にアースオーガー20を通し、アースオ
ーガー20により掘削すると共に貫通開口11,12,
13を通して掘削土砂を排出する。
(57) [Summary] [Purpose] There is no risk of ground collapse, and the precast plate is securely buried to build a continuous underground wall without using a stabilizing solution for ground stabilization. [Configuration] Through-opening 1 of precast plate 10 for retaining soil
The earth auger 20 is passed through 1, 12, 13 and excavated by the earth auger 20, and the through openings 11, 12,
The excavated soil is discharged through 13.
Description
【0001】[0001]
【産業上の利用分野】本発明はプレキャスト版を用いる
連続地中壁の築造方法に関する。FIELD OF THE INVENTION The present invention relates to a method of constructing a continuous underground wall using a precast plate.
【0002】[0002]
【従来の技術】従来、連続地中壁の築造に当っては、所
定場所をあらかじめ掘削し、掘削溝内に鉄筋篭を建込ん
だ後、コンクリートを打設する施工法が公知である。し
かしながら、この施工法では掘削時に溝壁の崩落を防ぐ
ため、掘削溝内を地盤安定化のための安定液で満たした
状態で掘削する必要があるため、多量の安定液を含むス
ラリーを産業廃棄物として処分しなければならず、また
安定液を現場で調製するためのプラントの設置並びに安
定液の品質管理が必要となるなどの欠点がある。2. Description of the Related Art Conventionally, in the construction of a continuous underground wall, a construction method is known in which a predetermined place is previously excavated, a rebar cage is installed in the excavation groove, and then concrete is poured. However, in this construction method, it is necessary to excavate the excavation groove with a stabilizing solution for ground stabilization in order to prevent the groove wall from collapsing during excavation. However, there are drawbacks such as that it must be disposed of as a product, and that a plant for preparing a stabilizing solution on site and quality control of the stabilizing solution are required.
【0003】他の連続地中壁の築造方法としては所定場
所をあらかじめ掘削し、掘削溝にプレキャスト版を建込
む施工法が知られている。しかしながら、この施工法で
は前述の溝壁の崩落並びに安定液に伴なう問題の他プレ
キャスト版の建込み時に地山との摩擦により建込みが困
難となるという欠点を有する。As another method for constructing a continuous underground wall, there is known a construction method in which a predetermined place is previously excavated and a precast plate is erected in the excavation groove. However, this construction method has a drawback in that it is difficult to install due to friction with the ground when the precast plate is installed, in addition to the problems associated with the collapse of the groove wall and the stabilizing solution described above.
【0004】[0004]
【発明が解決しようとする課題】本発明によれば、連続
地中壁を築造するための溝をあらかじめ掘削せずに、従
って溝壁の崩落の恐れがなく且つ地盤安定化のための安
定液を使用する必要なしにプレキャスト版を用いて連続
地中壁を築造する方法が提供される。SUMMARY OF THE INVENTION According to the present invention, a stabilizing liquid for stabilizing the ground is not required to previously excavate a groove for constructing a continuous underground wall, and thus there is no fear of the groove wall collapsing. There is provided a method of constructing a continuous underground wall with a precast plate without the need to use.
【0005】[0005]
【課題を解決するための手段】本発明のプレキャスト版
を用いる連続地中壁の築造方法では、(a)土留め用の
第1のプレキャスト版の貫通開口にアースオーガーを通
して該アースオーガーを前記第1のプレキャスト版の貫
通開口の下端より突出させる工程と、(b)前記アース
オーガーにより掘削すると共に掘削土砂を前記貫通開口
を通して搬出する工程とを行なう。また、本発明の連続
地中壁の築造方法では、前記工程(a)及び(b)を行
なった後、(c)前記アースオーガーを前記貫通開口よ
り引抜いて前記第1のプレキャスト版の上に第2のプレ
キャスト版を載置する工程と、(d)前記第1及び第2
のプレキャスト版の貫通開口にアースオーガーを通して
該アースオーガーを前記第1のプレキャスト版の貫通開
口の下端より突出させる工程と、(e)前記アースオー
ガーにより掘削すると共に掘削土砂を前記貫通開口を通
して搬出する工程と、必要に応じ前記工程(c),
(d)及び(e)を繰返す工程とを更に行なうことがで
きる。In the method of constructing a continuous underground wall using a precast plate according to the present invention, (a) an earth auger is passed through a through opening of a first precast plate for retaining soil, and The step of projecting from the lower end of the through opening of the precast plate 1 and the step of (b) excavating with the earth auger and carrying out excavated earth and sand through the through opening. In addition, in the method for constructing a continuous underground wall of the present invention, after performing the steps (a) and (b), (c) the earth auger is pulled out from the through opening and placed on the first precast plate. Placing a second precast plate, and (d) the first and second
Through an earth auger through the through opening of the precast plate to project the earth auger from the lower end of the through opening of the first precast plate, and (e) excavate by the earth auger and carry out excavated soil through the through opening. Step, and optionally the step (c),
The step of repeating (d) and (e) can be further performed.
【0006】前記アースオーガーにより掘削する際にそ
の先端部付近に泡状流動化剤を供給してもよく、泡状流
動化剤を前記アースオーガー内を通して供給することも
できる。When excavating with the earth auger, a foaming fluidizing agent may be supplied near the tip portion thereof, or the foaming fluidizing agent may be supplied through the earth auger.
【0007】[0007]
【作用】本発明の連続地中壁の築造方法では工程(a)
において土留め用の第1のプレキャスト版の貫通開口に
アースオーガーを通して貫通開口の下端よりアースオー
ガーを突出させ、次いで工程(b)においてアースオー
ガーにより掘削すると共に掘削土砂をプレキャスト版の
貫通開口を通して搬出するので、プレキャスト版が掘削
時の土留めの機能をはたすと共に掘削土砂を地表に搬出
する際の搬出口の役割をはたし、掘削が進むにつれてプ
レキャスト版は確実に土中に埋入される。In the method of constructing a continuous underground wall of the present invention, the step (a)
In the step (b), the earth auger is protruded from the lower end of the through opening, and the earth auger is excavated by the earth auger in the step (b) and the excavated soil is carried out through the through opening of the precast plate. As a result, the precast plate serves as an earth retaining function during excavation and also serves as a carry-out port when the excavated soil is carried to the surface of the ground, and the precast plate is reliably buried in the soil as the excavation proceeds. .
【0008】掘削が進行した際に、工程(c)において
アースオーガーを引抜いて第2のプレキャスト版を第1
のプレキャスト版上に載置し、工程(d)においてアー
スオーガーを貫通開口を通して突出させ、工程(e)に
て掘削搬出を行なうので、深く掘削する場合にも全く地
盤の崩落の恐れなく土砂を貫通開口を通して排出しなが
ら掘り進むことができる。As the excavation progressed, the earth auger was pulled out in the step (c) to remove the second precast plate into the first
It is placed on the precast plate of, the earth auger is projected through the through opening in the step (d), and the excavation is carried out in the step (e). It is possible to dig while discharging through the through opening.
【0009】また一方、泡状流動化剤をアースオーガー
の先端部付近に供給しながら掘削すれば、土砂の流動性
が改善され、円滑に土砂を掘削し、且つ貫通開口を通し
て地上に排出することができる。更に、アースオーガー
の先端付近で泡状流動化剤と混合された掘削土砂の一部
はプレキャスト版と地山との間の隙間を埋めてプレキャ
スト版の沈降の際の摩擦抵抗を減少し、地山の崩壊を防
止する。On the other hand, if the foaming fluidizing agent is excavated while being supplied to the vicinity of the tip of the earth auger, the fluidity of the earth and sand is improved, and the earth and sand can be excavated smoothly and discharged to the ground through the through opening. You can Furthermore, part of the excavated soil mixed with the foaming fluidizing agent near the tip of the earth auger fills the gap between the precast plate and the ground, reducing the frictional resistance when the precast plate sinks, Prevent mountain collapse.
【0010】[0010]
【実施例】以下、本発明の実施例につき添付図面を参照
して説明する。Embodiments of the present invention will be described below with reference to the accompanying drawings.
【0011】図1を参照すれば、土留め用のプレキャス
ト版10には3個の貫通開口11,12,13が設けら
れ、アースオーガー20が装着される。アースオーガー
20は図示の例では3個のユニットから構成される。す
なわち、第1のユニット21は貫通開口11に通された
回転軸21aと、回転軸21aに固定した掘削土砂搬送
のためのスクリュー21bと、回転軸21aの先端に取
付けたビット21cとを備える。第2のユニット22は
貫通開口12に通された回転軸22aと、回転軸22a
に固定したスクリュー22bとを具備する。第3のユニ
ット23は第1のユニット21と同一の構成で回転軸2
3aと、スクリュー23bと、ビット23cとを備え
る。Referring to FIG. 1, a precast plate 10 for retaining earth is provided with three through openings 11, 12, and 13 and an earth auger 20 is attached thereto. The earth auger 20 is composed of three units in the illustrated example. That is, the first unit 21 includes a rotary shaft 21a that is passed through the through opening 11, a screw 21b that is fixed to the rotary shaft 21a and that is used for carrying excavated earth and sand, and a bit 21c that is attached to the tip of the rotary shaft 21a. The second unit 22 includes a rotary shaft 22a passed through the through opening 12 and a rotary shaft 22a.
And a screw 22b fixed to. The third unit 23 has the same configuration as the first unit 21 and has the same structure as the rotary shaft 2
3a, a screw 23b, and a bit 23c.
【0012】図2にはプレキャスト版10の下部におい
てプレキャスト版10を貫通するアースオーガー20の
下方部分が拡大して示される。貫通開口11の下部は図
示のように下方に向って拡開するテーパー面11aを有
し、すりばち状に半径方向に拡大しており、軸21aの
下端部には上方のスクリュー21b−iよりも大きい直
径のスクリュー21b−iiが取り付けられる。貫通開
口12,13の下方部分も貫通開口11と同様に拡開さ
れ、直径の大きいスクリュー22b,23bが取り付け
られる(図1参照)。FIG. 2 is an enlarged view of a lower portion of the earth auger 20 which penetrates the precast plate 10 in the lower part of the precast plate 10. The lower part of the through opening 11 has a tapered surface 11a that expands downward as shown in the drawing, and expands in a radial shape like a brim, and at the lower end of the shaft 21a, there is more than the upper screw 21b-i. A large diameter screw 21b-ii is attached. The lower portions of the through openings 12 and 13 are also expanded similarly to the through opening 11, and the screws 22b and 23b having large diameters are attached (see FIG. 1).
【0013】次に、図1〜3を参照して連続地中壁の築
造方法を説明する。図1のように第1のプレキャスト版
10の貫通開口11,12,13にアースオーガー20
の各ユニット21,22,23を各々装着し、貫通開口
11,12,13の先端より突出させ、回転軸21a,
22a,23aを各々回転させるとビット21c,23
cが地山30を掘削する。図示のビット21c,23c
では掘削平面断面が矩形状に掘削されるので掘り残しが
ないよう掘削することが可能である。掘削と同時に掘削
土砂は大直径のスクリュー21b−ii(図2),22
b,23b(図1)により各貫通開口11,12,13
の下端部のすりばち状の拡開部に上昇する。拡開部がす
りばち状となっているため掘削土砂はスクリューに沿っ
て円滑に各貫通開口11,12,13内に押込まれ貫通
開口を通って上方に搬出される。Next, a method of constructing a continuous underground wall will be described with reference to FIGS. As shown in FIG. 1, the ground auger 20 is placed in the through openings 11, 12, 13 of the first precast plate 10.
Each of the units 21, 22, and 23 are mounted respectively, and protruded from the tips of the through openings 11, 12, and 13, and the rotary shaft 21a,
When bits 22a and 23a are respectively rotated, bits 21c and 23
c excavates the ground 30. Illustrated bits 21c, 23c
Since the excavation plane section is excavated in a rectangular shape, it is possible to excavate without leaving unexcavated areas. At the same time as the excavation, the excavated earth and sand will have large diameter screws 21b-ii (Fig. 2), 22
b, 23b (FIG. 1), each through opening 11, 12, 13
Ascends to the skirt-like widening at the lower end of the. Since the widening portion is in the shape of a burch, the excavated earth and sand are smoothly pushed into the through openings 11, 12, 13 along the screw and carried out upward through the through openings.
【0014】図3に示されるように、第1のプレキャス
ト版10が埋設された段階で、アースオーガー20を引
抜き、第2のプレキャスト版10−iを第1のプレキャ
スト版10上に上面継手部材10a(図1)を介して固
定接続し、第1及び第2のプレキャスト版の貫通開口に
アースオーガー20を装着して前述と同様に掘削し第2
のプレキャスト版10−iを埋設する。As shown in FIG. 3, at the stage where the first precast plate 10 is embedded, the earth auger 20 is pulled out, and the second precast plate 10-i is placed on the first precast plate 10. 10a (FIG. 1) is fixedly connected, the earth auger 20 is attached to the through openings of the first and second precast plates, and the same excavation is performed as described above.
The precast plate 10-i is embedded.
【0015】図3には埋設された第1及び第2のプレキ
ャスト版10,10−iの側方に連続地中壁を築造して
いるところが概略的に示される。第3及び第4のプレキ
ャスト版10−ii,10−iiiは側面継手部材10
b(図1)を介して第1及び第2のプレキャスト版1
0,10−iに固定接続し、前述と同様にして掘削す
る。この操作を連続して行ない、連続地中壁を築造す
る。FIG. 3 schematically shows the construction of a continuous underground wall on the side of the buried first and second precast plates 10, 10-i. The third and fourth precast plates 10-ii and 10-iii are side joint members 10.
b (Fig. 1) via first and second precast plates 1
Fixedly connected to 0, 10-i and excavated in the same manner as described above. This operation is performed continuously to build a continuous underground wall.
【0016】アースオーガー20の各ユニットの回転軸
21a,22a,23aを中空とし、泡状流動化剤、た
とえば商品名「OK−1」第一化成産業(株)(アニオ
ン系界面活性剤主成分)を各回転軸を通して先端部より
噴出させれば、土砂の流動性が改善され、掘削が円滑に
行なわれ、且つ貫通開口11,12,13を通る掘削土
砂の搬出が容易となる。また泡状流動化剤と混合された
掘削土砂の一部は図3に示すように地山30とプレキャ
スト版10−ii,10−iiiとの間31に入り、プ
レキャスト版の沈降の際の摩擦抵抗を減小する。排出さ
れた泡状流動化剤と土砂との混合物には消泡剤を散布
し、無公害にて処分することができる。The rotary shafts 21a, 22a, 23a of the respective units of the earth auger 20 are hollow, and a foaming fluidizing agent, for example, "OK-1" manufactured by Daiichi Kasei Sangyo Co., Ltd. (anionic surfactant main component). ) Is jetted from the tip through each rotary shaft, the fluidity of the earth and sand is improved, the excavation is smoothly performed, and the excavated earth and sand is easily carried out through the through openings 11, 12, 13. Further, a part of the excavated soil mixed with the foamy fluidizing agent enters between the ground 30 and the precast plates 10-ii and 10-iii 31, as shown in FIG. 3, and causes friction during settling of the precast plate. Reduce resistance. The discharged mixture of the foaming fluidizing agent and the earth and sand can be sprayed with an antifoaming agent and disposed of without pollution.
【0017】[0017]
【発明の効果】本発明によれば、連続地中壁を築造する
ための溝をあらかじめ掘削する必要がなく、故に溝壁の
崩落の恐れがなく且つ地盤を安定化するための安定液を
使用せずにプレキャスト版を確実に掘削に伴って埋設す
ることができる。According to the present invention, it is not necessary to excavate a groove for constructing a continuous underground wall in advance, and therefore, there is no risk of the groove wall collapsing and a stabilizing solution for stabilizing the ground is used. Without it, the precast plate can be surely buried along with the excavation.
【図1】本発明の方法によりプレキャスト版を用いて連
続地中壁を築造しているところを概略的に示す部分破断
斜視図である。FIG. 1 is a partially cutaway perspective view schematically showing the construction of a continuous underground wall using a precast plate according to the method of the present invention.
【図2】図1の線2−2に沿う部分断面図である。2 is a partial cross-sectional view taken along line 2-2 of FIG.
【図3】本発明の方法により連続的にプレキャスト版を
築造しているところを示す略示図である。FIG. 3 is a schematic view showing a precast plate being continuously built by the method of the present invention.
10,10−i,10−ii,10−iii プレキャ
スト版 11,12,13 貫通開口 20 アースオーガー 21a,22a,23a 回転軸 21b,22b,23b スクリュー 21c,23c ビット10, 10-i, 10-ii, 10-iii Precast plate 11, 12, 13 Through opening 20 Earth auger 21a, 22a, 23a Rotating shaft 21b, 22b, 23b Screw 21c, 23c Bit
Claims (4)
の貫通開口にアースオーガーを通して該アースオーガー
を前記第1のプレキャスト版の貫通開口の下端より突出
させる工程と、(b)前記アースオーガーにより掘削す
ると共に掘削土砂を前記貫通開口を通して搬出する工程
とを含むプレキャスト版を用いる連続地中壁の築造方
法。1. A step of: (a) passing an earth auger through a through opening of a first precast plate for earth retaining so that the earth auger protrudes from a lower end of the through opening of the first precast plate; and (b) the earth. A method of constructing a continuous underground wall using a precast plate, which comprises a step of excavating with an auger and carrying out excavated soil through the through opening.
後、(c)前記アースオーガーを前記貫通開口より引抜
いて前記第1のプレキャスト版の上に第2のプレキャス
ト版を載置する工程と、(d)前記第1及び第2のプレ
キャスト版の貫通開口にアースオーガーを通して該アー
スオーガーを前記第1のプレキャスト版の貫通開口の下
端より突出させる工程と、(e)前記アースオーガーに
より掘削すると共に掘削土砂を前記貫通開口を通して搬
出する工程と、必要に応じ前記工程(c),(d)及び
(e)を繰返す工程とを更に含む請求項1記載の方法。2. After performing the steps (a) and (b), (c) the earth auger is pulled out from the through opening, and the second precast plate is placed on the first precast plate. And (d) a step of passing an earth auger through the through openings of the first and second precast plates to project the earth auger from the lower end of the through openings of the first precast plate, and (e) by the earth auger. The method according to claim 1, further comprising the steps of excavating and discharging excavated soil through the through opening, and repeating the steps (c), (d) and (e) if necessary.
その先端部付近に泡状流動化剤を供給する請求項1又は
2記載の方法。3. The method according to claim 1, wherein a foaming fluidizing agent is supplied near the tip of the earth auger when excavating.
内を通してその先端部付近に供給する請求項3記載の方
法。4. The method according to claim 3, wherein the foaming fluidizing agent is fed through the earth auger and near its tip.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16598192A JPH0610340A (en) | 1992-06-24 | 1992-06-24 | Construction method of continuous underground wall using precast plate |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16598192A JPH0610340A (en) | 1992-06-24 | 1992-06-24 | Construction method of continuous underground wall using precast plate |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH0610340A true JPH0610340A (en) | 1994-01-18 |
Family
ID=15822664
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16598192A Pending JPH0610340A (en) | 1992-06-24 | 1992-06-24 | Construction method of continuous underground wall using precast plate |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0610340A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100635928B1 (en) * | 2006-03-07 | 2006-10-18 | (주)공간에이엔앰건축사사무소 | Multi-unit housing base structure |
| KR101428698B1 (en) * | 2013-11-07 | 2014-08-12 | 석정건설(주) | Sheet pile and it's construction method |
| JP2022547612A (en) * | 2019-09-12 | 2022-11-14 | オ’スリヴァン,ケネス | Modular panel foundation support device |
| CN116988488A (en) * | 2023-09-27 | 2023-11-03 | 四川省建筑科学研究院有限公司 | Excavation protection device and excavation protection method for foundation square pit |
-
1992
- 1992-06-24 JP JP16598192A patent/JPH0610340A/en active Pending
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100635928B1 (en) * | 2006-03-07 | 2006-10-18 | (주)공간에이엔앰건축사사무소 | Multi-unit housing base structure |
| KR101428698B1 (en) * | 2013-11-07 | 2014-08-12 | 석정건설(주) | Sheet pile and it's construction method |
| JP2022547612A (en) * | 2019-09-12 | 2022-11-14 | オ’スリヴァン,ケネス | Modular panel foundation support device |
| CN116988488A (en) * | 2023-09-27 | 2023-11-03 | 四川省建筑科学研究院有限公司 | Excavation protection device and excavation protection method for foundation square pit |
| CN116988488B (en) * | 2023-09-27 | 2023-12-01 | 四川省建筑科学研究院有限公司 | Excavation protection device and excavation protection method for foundation square pit |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0610340A (en) | Construction method of continuous underground wall using precast plate | |
| JP2505976B2 (en) | How to create an underground structure | |
| JP3948655B2 (en) | Construction method of retaining wall and underground structure | |
| JP2001200539A (en) | Center deviation preventing device for hollow pipe pile, and center deviation preventing work method for hollow pipe pile | |
| JP2004218378A (en) | Removing method for existing pile | |
| JPS6351515A (en) | Excavator for ground improvement | |
| JPS5924026A (en) | Pile formation work | |
| JPS6254929B2 (en) | ||
| JP2886365B2 (en) | Construction method of pile | |
| JP3200240B2 (en) | Filling method of self-hardening material in ground reinforcement method | |
| JPH07197469A (en) | Structure of earth retaining wall and earth retaining method | |
| JPH02140323A (en) | Formation of soil cement synthetic pile | |
| JP2743986B2 (en) | Excavation method of large section tunnel by preceding rock bolt construction | |
| JPS6321796B2 (en) | ||
| JP2726617B2 (en) | Construction method of underground continuous wall | |
| JP3182674B2 (en) | Construction method of agitated mixing reinforcement | |
| JP2000337077A (en) | Method for constructing tunnel | |
| JPS6040414A (en) | Improvement of horizontal ground | |
| JPS59145821A (en) | Method and apparatus for construction of pillar-row pile | |
| JPH07158389A (en) | Independent construction method of face of collapsible ground tunnel | |
| JP3086183B2 (en) | Multi-axis excavator with detachable guide and underground wall construction method using it | |
| JPS60164511A (en) | Pile pit formation work | |
| JPS6098009A (en) | Method and apparatus for ground improvement | |
| JP2000064275A (en) | Soil-cement synthetic steel pipe pile, method of forming the same, and structure having soil-cement synthetic steel pipe pile | |
| JPS6353329B2 (en) |