JPH06108459A - Construction of underground continuous wall - Google Patents
Construction of underground continuous wallInfo
- Publication number
- JPH06108459A JPH06108459A JP28384692A JP28384692A JPH06108459A JP H06108459 A JPH06108459 A JP H06108459A JP 28384692 A JP28384692 A JP 28384692A JP 28384692 A JP28384692 A JP 28384692A JP H06108459 A JPH06108459 A JP H06108459A
- Authority
- JP
- Japan
- Prior art keywords
- steel casing
- casing
- steel
- underground continuous
- continuous wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 56
- 239000010959 steel Substances 0.000 claims abstract description 56
- 239000004567 concrete Substances 0.000 claims abstract description 17
- 239000012779 reinforcing material Substances 0.000 claims abstract description 3
- 238000000034 method Methods 0.000 abstract description 8
- 230000003014 reinforcing effect Effects 0.000 abstract description 4
- 238000012545 processing Methods 0.000 abstract 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 6
- 230000002787 reinforcement Effects 0.000 description 5
- 238000009434 installation Methods 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 230000000452 restraining effect Effects 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 210000001015 abdomen Anatomy 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000013049 sediment Substances 0.000 description 1
- 239000010802 sludge Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】この発明は、地下連続壁の構築工
法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground continuous wall.
【0002】[0002]
【従来の技術】従来の地下連続壁は、通常の水中コンク
リートによる鉄筋コンクリートにより作られる仮設土止
壁用の地下連続壁、あるいは鉄筋篭に床・柱・壁に繋げ
るため埋込まれた繋ぎ鉄筋が配置されている地下連続壁
で、そのまま本体構造物又は本体構造物の部分として用
いるものがあり、いずれもバケット式又はスクリューオ
ーガーを用いた泥水掘削工法によりエレメントを掘削
し、その内部に鉄筋篭又は鉄骨鉄筋篭を沈設した後、コ
ンクリートを充填する工法を用いるものであった。2. Description of the Related Art A conventional underground continuous wall is an underground continuous wall for a temporary earth retaining wall made of reinforced concrete made of normal underwater concrete, or a connecting rebar embedded in a rebar cage to connect floors, columns and walls. There are underground continuous walls that are placed and used as the main structure or part of the main structure as it is, both of which excavate the element by a mud excavation method using a bucket type or a screw auger, and inside it, a rebar cage or After the steel frame rebar cage was sunk, the method of filling concrete was used.
【0003】[0003]
【発明が解決しようとする課題】上記従来の工法では、
予め鉄筋篭に埋め込まれた床・柱・壁に繋げるための繋
ぎ鉄筋の位置を確保すること、連続する鉄筋篭の高さを
所定の位置にセットすること、並びにコンクリート打設
に際して、鉄筋篭の浮上がりを防止することが不可能に
近いくらいに困難であると共に、掘削中のエレメント壁
面の崩壊防止は土質によっては細心の注意を払っても困
難な作業であった。SUMMARY OF THE INVENTION In the above conventional method,
Securing the position of the connecting rebars to be connected to the floor, pillars, and walls that are embedded in the rebar cage in advance, setting the height of continuous rebar cages to a predetermined position, and when placing concrete, Preventing uplift is almost impossible, and preventing collapse of the element wall surface during excavation was a difficult task even with the utmost care depending on the soil quality.
【0004】[0004]
【課題を解決するための手段】この発明は、内面に拘束
補強材4を突設し、かつ両側面に互いに掛合する継手片
6,6’を上下方向に設けた筒状板体からなる鋼製ケー
シング2を地盤上に設置し、その内部に入れた掘削機7
により底部地盤を多少掘削しては打設機12により地中
に打ち込む工程を繰り返して所定深さに沈設した後、そ
の内部にコンクリート3を充填し、その後前記鋼製ケー
シング2の左右に隣接する位置に新たに鋼製ケーシング
2,2を設置し、互いに隣合う鋼製ケーシング2,2相
互の継手片6,6’を噛み合わせて連結しながら前記同
様に新たな鋼製ケーシング2を沈設し、その内部にコン
クリート3を打設する工程を繰り返すようにした地下連
続壁の構築工法を提案するものである。SUMMARY OF THE INVENTION The present invention is a steel plate made of a cylindrical plate having a restraining reinforcing member 4 projecting from the inner surface thereof and joint pieces 6 and 6'interlocking with each other on both side surfaces provided vertically. Excavator 7 with casing 2 installed on the ground and placed inside
After excavating the bottom ground to some extent by repeating the steps of driving into the ground by the driving machine 12, the concrete is filled into the inside after being sunk to a predetermined depth, and then the steel casing 2 is adjacent to the left and right. The steel casings 2 and 2 are newly installed at the positions, and the new steel casing 2 is laid down in the same manner as described above while the joint pieces 6 and 6 ′ of the steel casings 2 and 2 adjacent to each other are engaged and connected. It proposes a construction method for a continuous underground wall in which the step of placing concrete 3 inside is repeated.
【0005】[0005]
【作用】鋼製ケーシング2とその内部のコンクリート3
が拘束補強材4と共に一体化して剛性の大きい地下連続
壁1が得られ、鉄筋篭を必要とせずに工事が早くでき、
鋼製ケーシング2による掘削面の保持が容易になる。[Operation] Steel casing 2 and concrete 3 inside
Can be integrated with the restraint reinforcement material 4 to obtain the underground continuous wall 1 with high rigidity, and the construction can be done quickly without the need for a rebar cage.
The excavated surface can be easily held by the steel casing 2.
【0006】[0006]
【実施例】この発明の地下連続壁1は、筒状板体からな
る鋼製ケーシング2を地中に沈設し、その内部にコンク
リート3を充填することにより構築する。EXAMPLE A continuous underground wall 1 of the present invention is constructed by immersing a steel casing 2 made of a tubular plate body in the ground and filling concrete 3 therein.
【0007】鋼製ケーシング2は図1〜図4に示すよう
に、地下連続壁1の直線状壁部分用としては中空箱型
に、また壁の隅角部用としては中空鉤型に、さらに変曲
部用としては中空S字型や中空稲妻型等、鋼板を用いて
設置部分に適応した横断面形態に形成し、その内面には
内部に充填したコンクリート3と一体化して所要の強度
を保持させるためのジベル等の拘束補強材4が縦横に所
定間隔を置いて多数取付けられ、また下端部の内外いず
れか一方又は両方の面には堅い沈設地盤などに対して打
ち込み先端を補強するための補強板5が取付けられてい
る。As shown in FIGS. 1 to 4, the steel casing 2 is a hollow box type for the straight wall portion of the underground continuous wall 1 and a hollow hook type for the corner portions of the wall. For the inflection part, a steel plate such as a hollow S-shape or a hollow lightning bolt is used to form a transverse cross section suitable for the installation part, and the inner surface of the concrete 3 is integrated with the concrete 3 filled to the required strength. A large number of restraint reinforcements 4 such as jibbels for holding are attached at predetermined intervals in the vertical and horizontal directions, and for reinforcing the tip of the driven bottom against the hard ground or the like on one or both of the inner and outer surfaces of the lower end. The reinforcing plate 5 is attached.
【0008】なお、拘束補強材4は、後述する掘削機の
ガイドとしても利用するようにその取付位置が設定され
ている。The restraint reinforcement member 4 has its mounting position set so as to be used also as a guide for an excavator described later.
【0009】鋼製ケーシング2の両側面には、横方向に
隣接する鋼製ケーシング2,2同士を堅固に嵌め合い連
結するための断面鉤型状等の継手片6,6’が上下方向
に一連に1又は複数本取付けられている。On both sides of the steel casing 2, joint pieces 6, 6'having a hook-shaped cross section for firmly fitting and connecting the horizontally adjacent steel casings 2, 2 are connected in the vertical direction. One or more are attached in series.
【0010】図5は両側面に2個の継手片6,6’を取
付けた鋼製ケーシング2の連結状態を示したもので、こ
の場合には隣接する鋼製ケーシング2,2間は2組の継
手片6,6’で仕切られるため、1組の継手片6,6’
の場合に比較して止水性が向上する。FIG. 5 shows the connected state of the steel casing 2 having two joint pieces 6 and 6'mounted on both side surfaces. In this case, two sets are provided between the adjacent steel casings 2 and 2. Since it is partitioned by the joint pieces 6, 6'of
The water stopping property is improved as compared with the case of.
【0011】上記構成の鋼製ケーシング2を用いて地下
連続壁1を施工する際には、先ず図7に示すように鋼製
ケーシング2を所定の位置に設置し、図1に示すように
内部に掘削機7を入れて底部の土砂を掘削する。When constructing the underground continuous wall 1 using the steel casing 2 having the above structure, first, the steel casing 2 is installed at a predetermined position as shown in FIG. The excavator 7 is put in to excavate the bottom sediment.
【0012】この掘削機7として、図1、図3の実施例
においては送水管8から圧送された水をジェット水とし
て噴射することにより掘削する水圧掘削機を示したが、
先端にオーガーを備えたジェット併用の掘削機、あるい
はブームの先端にグラブバケットを設けた掘削機等、各
種の掘削機を用いることができる。As the excavator 7, in the embodiment shown in FIGS. 1 and 3, a hydraulic excavator for excavating by injecting water pressure-fed from the water pipe 8 as jet water is shown.
It is possible to use various excavators such as a jet-excavator equipped with an auger at its tip, or an excavator provided with a grab bucket at the tip of a boom.
【0013】掘削機7の送水管8は排泥管9と共に周囲
にローラー10を設けた昇降台11に取付けられ、この
昇降台11を縦に並んだ拘束補強材4により案内しなが
ら鋼製ケーシング2内を下降させ、掘削機7により掘削
した掘削土砂を排泥管9により排出しながら底部地盤を
所要深さ掘削した後、油圧又は振動による打設機12に
より鋼製ケーシング2を打ち込み、順次同様の工程を繰
り返して鋼製ケーシング2を地中に沈設する。The water pipe 8 of the excavator 7 is attached together with the sludge discharge pipe 9 to a lift table 11 provided with rollers 10 on the periphery thereof, and a steel casing is provided while guiding the lift table 11 by the restraining reinforcement members 4 arranged vertically. After lowering the inside of 2, and excavating the excavated earth and sand excavated by the excavator 7 by the mud pipe 9, the bottom ground is excavated to the required depth, and then the steel casing 2 is driven by the driving machine 12 by hydraulic pressure or vibration, and sequentially. The same process is repeated to submerge the steel casing 2 in the ground.
【0014】鋼製ケーシング2は、その縦の長さが構築
すべき地下連続壁1の深さよりも小さい場合には、図8
に示すように複数個を順次上下に重ねて相互の接合端を
溶接して連結一体化する。If the vertical length of the steel casing 2 is smaller than the depth of the underground continuous wall 1 to be constructed, the steel casing 2 shown in FIG.
As shown in (1), a plurality of layers are sequentially stacked on top of each other, and their joint ends are welded to be connected and integrated.
【0015】このようにして鋼製ケーシング2を沈設し
た後、図9に示すようにその底部のスライムを除去した
上で内部にコンクリート3を打設充填し、1ユニットの
地下連続壁1の施工を終了する。After the steel casing 2 is sunk in this way, the bottom slime is removed as shown in FIG. To finish.
【0016】次に上記のように施工した地下連続壁1の
鋼製ケーシング2の左右に隣接する位置に新たに鋼製ケ
ーシング2を設置し、隣接する相互の継手片6,6’を
噛み合わせて連結しながら上記同様に新たな鋼製ケーシ
ング2を沈設し、その内部にコンクリート3を打設す
る。Next, the steel casing 2 is newly installed at a position adjacent to the left and right of the steel casing 2 of the underground continuous wall 1 constructed as described above, and the adjacent joint pieces 6 and 6'are engaged with each other. A new steel casing 2 is sunk in the same manner as described above while being connected, and concrete 3 is placed therein.
【0017】上記施工の手順として例えば、図6に数字
で設置順を示すように、1番目の鋼製ケーシング2を1
個掘削設置後、両側の隣接する2番目の鋼製ケーシング
2を掘削設置し、続いて1番目の鋼製ケーシング2に重
ねて2段目(数字順3番目)の鋼製ケーシング2を施工
し、続いて2番目の鋼製ケーシング2に隣接する4番目
の鋼製ケーシング2を施工し、以下順次図6の設置順に
従って垂直及び水平方向に連設して行く方法などを採用
する。As a procedure of the above construction, for example, as shown in FIG.
After the individual excavation and installation, the adjacent second steel casings 2 on both sides are excavated and installed, and then the second steel casing 2 (third numerical order) is overlaid on the first steel casing 2. Next, a method of constructing a fourth steel casing 2 adjacent to the second steel casing 2 and successively arranging them vertically and horizontally in accordance with the installation order of FIG. 6 is adopted.
【0018】構築した地下連続壁1は、従来の地下連続
壁と同様にそのまま土止壁として使用したり、あるいは
図10、図11又は図12に示すように腹起こし13と
切梁14で支持しながら地下連続壁1の内部を掘削した
後、床部材15及び梁部材16を鋼製ケーシング2に直
接溶接し、地下連続壁1を地下永久構造物の周辺壁部材
として利用することができる。The constructed underground continuous wall 1 can be used as an earth retaining wall as it is, like the conventional underground continuous wall, or can be supported by the belly up 13 and the girder 14 as shown in FIG. 10, FIG. 11 or FIG. However, after excavating the inside of the underground continuous wall 1, the floor member 15 and the beam member 16 can be directly welded to the steel casing 2 to use the underground continuous wall 1 as a peripheral wall member of an underground permanent structure.
【0019】[0019]
【発明の効果】以上の通りこの発明によれば、鋼製ケー
シングと内部のコンクリートが一体化した剛性の大き
く、しかも水密性がよい地下連続壁が得られると共に、
従来のような鉄筋篭を必要としないため、施工管理が単
純で円滑かつ迅速に施工できる。また、鋼製ケーシング
をその底部地盤を掘削しながら沈設するため、土砂の崩
落に対する掘削面の保持が容易になる。As described above, according to the present invention, it is possible to obtain an underground continuous wall having a high rigidity and a high water-tightness, in which the steel casing and the concrete inside are integrated.
Since there is no need for a rebar cage as in the past, construction management is simple and construction can be done smoothly and quickly. Further, since the steel casing is sunk while excavating the bottom ground, it becomes easy to hold the excavated surface against the collapse of the earth and sand.
【0020】地下連続壁を構造物本体に使用する時、中
間梁・床の継手鉄筋や鉄骨の取付けが後施工となるの
で、従来の鉄筋篭を設置するような困難さがなく、所定
の位置に正確に取付けることができる。When the underground continuous wall is used for the main body of the structure, the installation of the intermediate beam / floor joint rebar and steel frame will be done afterwards, so there is no difficulty like installing a conventional rebar cage, Can be installed accurately.
【図1】この発明に係る鋼製ケーシングの沈設状況を示
す縦断正面図。FIG. 1 is a vertical sectional front view showing a sinking state of a steel casing according to the present invention.
【図2】この発明に係る鋼製ケーシングの縦断側面図。FIG. 2 is a vertical sectional side view of a steel casing according to the present invention.
【図3】この発明に係る鋼製ケーシングの設置状態を示
す平面図。FIG. 3 is a plan view showing an installed state of a steel casing according to the present invention.
【図4】この発明に係る鋼製ケーシングの正面図。FIG. 4 is a front view of a steel casing according to the present invention.
【図5】この発明に係る他の態様の鋼製ケーシングの設
置状態を示す平面図。FIG. 5 is a plan view showing an installed state of a steel casing according to another aspect of the present invention.
【図6】この発明の地下連続壁の施工順序の一例を示す
工程概要図。FIG. 6 is a process outline view showing an example of a construction sequence of an underground continuous wall of the present invention.
【図7】この発明に係る鋼製ケーシングの沈設工程を示
す縦断側面図。FIG. 7 is a vertical cross-sectional side view showing the step of sinking the steel casing according to the present invention.
【図8】この発明に係る鋼製ケーシングを上下に重ねた
状態を示す縦断側面図。FIG. 8 is a vertical cross-sectional side view showing a state in which steel casings according to the present invention are vertically stacked.
【図9】この発明に係る鋼製ケーシング内にコンクリー
トを打設する状態を示す縦断側面図。FIG. 9 is a vertical cross-sectional side view showing a state in which concrete is placed in a steel casing according to the present invention.
【図10】この発明により構築した地下連続壁を本体構
造物に使用する場合の施工状態を示す縦断側面図。FIG. 10 is a vertical sectional side view showing a construction state when the underground continuous wall constructed according to the present invention is used for a main body structure.
【図11】この発明により構築した地下連続壁を本体構
造物に使用する場合の一態様を示す縦断側面図。FIG. 11 is a vertical cross-sectional side view showing one embodiment in the case where the underground continuous wall constructed according to the present invention is used for a main body structure.
【図12】この発明により構築した地下連続壁を本体構
造物に使用する場合の他の態様を示す縦断側面図。FIG. 12 is a vertical cross-sectional side view showing another embodiment of the case where the underground continuous wall constructed according to the present invention is used for the main body structure.
1 地下連続壁 2 鋼製ケーシング 3 コンクリート 4 拘束補強材 5 補強板 6 継手片 6’ 継手片 7 掘削機 8 送水管 9 排泥管 10 ローラー 11 昇降台 12 打設機 13 腹起こし 14 切梁 15 床部材 16 梁部材 1 Underground continuous wall 2 Steel casing 3 Concrete 4 Restraint reinforcing material 5 Reinforcement plate 6 Joint piece 6'Joint piece 7 Excavator 8 Water pipe 9 Mud pipe 10 Roller 11 Lifting table 12 Laying machine 13 Raising 14 Cut beam 15 Floor member 16 Beam member
Claims (1)
に互いに掛合する継手片を上下方向に設けた筒状板体か
らなる鋼製ケーシングを地盤上に設置し、その内部に入
れた掘削機により底部地盤を多少掘削しては打設機によ
り地中に打ち込む工程を繰り返して所定深さに沈設した
後、その内部にコンクリートを充填し、その後前記鋼製
ケーシングの左右に隣接する位置に新たに鋼製ケーシン
グを設置し、互いに隣合う鋼製ケーシング相互の継手片
を噛み合わせて連結しながら前記同様に新たな鋼製ケー
シングを沈設し、その内部にコンクリートを打設する工
程を繰り返すことを特徴とする地下連続壁の構築工法。1. A steel casing made of a tubular plate body having a constraining reinforcing material protruding from the inner surface thereof and having joint pieces engaging with each other on the both sides provided in the up-and-down direction is installed on the ground, and the steel casing is put in the interior of the steel casing. After excavating the bottom ground a little with an excavator and driving it into the ground with a placing machine, it is sunk to a predetermined depth and then filled with concrete, then adjacent to the left and right of the steel casing A new steel casing is installed at the position, the new steel casing is sunk in the same manner as described above while the joint pieces of adjacent steel casings are engaged and connected, and concrete is placed inside the casing. Construction method of underground continuous wall characterized by repeating.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28384692A JPH06108459A (en) | 1992-09-28 | 1992-09-28 | Construction of underground continuous wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28384692A JPH06108459A (en) | 1992-09-28 | 1992-09-28 | Construction of underground continuous wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH06108459A true JPH06108459A (en) | 1994-04-19 |
Family
ID=17670927
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP28384692A Pending JPH06108459A (en) | 1992-09-28 | 1992-09-28 | Construction of underground continuous wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH06108459A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101428698B1 (en) * | 2013-11-07 | 2014-08-12 | 석정건설(주) | Sheet pile and it's construction method |
-
1992
- 1992-09-28 JP JP28384692A patent/JPH06108459A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101428698B1 (en) * | 2013-11-07 | 2014-08-12 | 석정건설(주) | Sheet pile and it's construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100722665B1 (en) | Steel guide wall for underground continuous wall construction and underground continuous wall construction method | |
| CN108316339B (en) | Construction method of water-permeable geological large arch bridge foundation | |
| US3431736A (en) | Method of constructing underground concrete walls | |
| JP2837128B2 (en) | Construction method of cast-in-place concrete pile | |
| KR20140055639A (en) | A execution method of architecture beam | |
| WO2004033843A2 (en) | Subterranean structures and methods for constructing subterranean structures | |
| KR101324231B1 (en) | Soil cement wall structure and method for constructing thereof | |
| KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
| CN111287194A (en) | Recyclable foundation pit support structure using inclined steel sheet piles and its support method | |
| KR101181619B1 (en) | Building method of high wall block for large scale underground structure using earth anchor represtressing | |
| KR102021496B1 (en) | Retaining wall construction method and retaining wall structure by the method | |
| KR100967496B1 (en) | Device for constructing an underground structure | |
| KR102078794B1 (en) | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same | |
| JP3614587B2 (en) | How to install a shaft in the groundwater under pressure | |
| KR101219451B1 (en) | Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same | |
| JP4146250B2 (en) | Open caisson bottom plate construction method | |
| JP2004132124A (en) | Pneumatic caisson and pneumatic caisson method | |
| JP7096469B1 (en) | Small cross-section underground continuous wall | |
| JPH04185816A (en) | Construction of beam in underground wall | |
| KR100543284B1 (en) | Construction method of bracing walls used as columns and slabs | |
| JPH0376922A (en) | Construction of continuous underground wall and steel panel therefor | |
| JPS5921831A (en) | Reverse placement work | |
| JP2024134234A (en) | Methods for reinforcing existing concrete structures | |
| JPS63277342A (en) | Reverse execution of underground story | |
| KR20250132173A (en) | Method For Excavation Using H-beam And Concrete Retaining Wall |