JPH0612048Y2 - Anchor bolt installation device - Google Patents
Anchor bolt installation deviceInfo
- Publication number
- JPH0612048Y2 JPH0612048Y2 JP1987094444U JP9444487U JPH0612048Y2 JP H0612048 Y2 JPH0612048 Y2 JP H0612048Y2 JP 1987094444 U JP1987094444 U JP 1987094444U JP 9444487 U JP9444487 U JP 9444487U JP H0612048 Y2 JPH0612048 Y2 JP H0612048Y2
- Authority
- JP
- Japan
- Prior art keywords
- anchor bolt
- anchor
- installation device
- plate
- connecting member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Foundations (AREA)
Description
【考案の詳細な説明】 〔産業上の利用分野〕 本考案は鉄骨構造建物における露出形固定用柱脚に使用
するアンカーボルトの据付装置に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to an anchor bolt installation device used for an exposed fixing column base in a steel structure building.
鉄骨構造建物の精度は,最下階柱の位置精度によって大
きく左右され,その柱は基礎構造部分の精度に大きな影
響を受ける。工場において製作された鉄骨部材は許容誤
差範囲内で納入されるのが一般的であるから,工事現場
における鉄骨建方の誤差は,アンカーボルトの精度の影
響がそのまま現われる場合が多い。従って鉄骨建方の良
否は,一に上記アンカーボルトの精度にかかっており,
正確な位置決めを行なう必要がある。このため,例えば
鉄骨工事技術指針・同解説(昭和54年4月25日 日
本建築学会発行)第625頁に記載のようにアンカーボ
ルトを鋼製のフレーム若しくは保持具によって保持し,
コンクリートの打設による衝撃や流れによる圧力によっ
て移動しないようにするアンカーボルト据付装置を使用
するのが通常である。The accuracy of a steel structure building is greatly affected by the positional accuracy of the lowest floor pillar, and that pillar is greatly affected by the accuracy of the substructure. Since steel members manufactured in factories are generally delivered within the permissible error range, the error in the steel frame construction at the construction site often directly reflects the accuracy of the anchor bolts. Therefore, the quality of the steel frame construction depends on the accuracy of the anchor bolts.
Accurate positioning is required. Therefore, for example, the anchor bolt is held by a steel frame or holder as described on page 625 of Steel Frame Construction Technical Guide / Commentary (Published by the Architectural Institute of Japan on April 25, 1979).
It is common to use anchor bolt installation devices that prevent movement due to impact from concrete placement and pressure from the flow.
第6図は従来のアンカーボルトの据付装置の一例を示す
要部正面図である。同図において1はフレームであり,
例えば等辺山形鋼によって角枠状に構成すると共に,上
部に上部形板2を,下端部から若干の高さの位置に下部
形板3を各々固着し,上部形板2および下部形板3に設
けた保持穴(図示せず)にアンカーボル4を保持するよ
うに構成する。なおアンカーボルト4の上下方向の位置
決めは,例えば角片状の定着板5を介してナット6によ
り下部形板3を挟着する手段によって行なう。上記の構
成により,予め打設した捨てコンクリート7上の所定の
位置にフレーム1を載置し,ドリルアンカー9を打込ん
で固定した後,鎖線にて示すような基礎8をコンクリー
ト打設により形成するのである。FIG. 6 is a front view of essential parts showing an example of a conventional anchor bolt installation device. In the figure, 1 is a frame,
For example, an equilateral angle steel is used to form a square frame shape, and an upper shape plate 2 is fixed to the upper part and a lower shape plate 3 is fixed to a position slightly higher than the lower end part. The anchor bolt 4 is configured to be retained in a retaining hole (not shown) provided. The positioning of the anchor bolt 4 in the vertical direction is performed, for example, by means of sandwiching the lower shaped plate 3 with a nut 6 via a square plate-shaped fixing plate 5. With the above-described structure, the frame 1 is placed at a predetermined position on the cast concrete 7 that has been placed in advance, the drill anchor 9 is driven and fixed, and then the foundation 8 as shown by the chain line is formed by concrete placing. To do.
上記従来の据付装置を構成するフレーム1は,予め工場
において製作した後,建方現場に運搬するのが通常であ
るが,下記のような問題点がある。The frame 1 constituting the above-mentioned conventional installation device is usually manufactured in advance in a factory and then transported to a construction site, but there are the following problems.
(1)フレーム1には運搬途中およびコンクリート打設時
の外力による変形を防止し,その形状,寸法を維持する
ための鋼性が要求されるから,通常アンカーボルト4の
直径より比較的大なる幅寸法の構成部材が使用される。
例えば第6図に示す等辺山形鋼からなる直立部材が必要
となり,これらの垂直部材の林立が障害となって基礎コ
ンクリート8中に埋設される水平方向の鉄筋との干渉頻
度が高く,鉄筋配設位置の変更若しくは地中の鉄筋コン
クリートばりの設計変更等を要する。(1) Since the frame 1 is required to be steel to prevent deformation due to external force during transportation and during concrete placement, and to maintain its shape and size, it is usually larger than the diameter of the anchor bolt 4. Width sized components are used.
For example, an upright member made of equilateral angle steel shown in Fig. 6 is required, and the forest of these vertical members becomes an obstacle, and the frequency of interference with the horizontal reinforcing bars embedded in the basic concrete 8 is high, and the reinforcing bars are arranged. It is necessary to change the position or change the design of reinforced concrete beams in the ground.
(2)フレーム1に突出部分が多いため,工場から現場ま
での運搬途中において,フレーム1相互の重合,衝突等
によって変形を生じ,アンカーボルト4を基礎8中に高
精度で埋設することが困難である。(2) Since the frame 1 has many protruding parts, it is difficult to embed the anchor bolt 4 in the foundation 8 with high precision during the transportation from the factory to the site due to the mutual deformation and collision of the frames 1. Is.
(3)フレーム1は一般に溶接接合で組立製作されるた
め,建方現場におけるアンカーボルト4の水平方向若し
くは垂直方向の位置調整を行なうことができない。(3) Since the frame 1 is generally assembled by welding, it is impossible to adjust the position of the anchor bolt 4 in the horizontal or vertical direction at the construction site.
フレーム1を捨てコンクリート7上に固定するにはドリ
ルアンカー9等の固定部材を必要とし,特殊工具および
煩雑な作業が必要である。A fixing member such as a drill anchor 9 is required to discard the frame 1 on the concrete 7, and a special tool and complicated work are required.
本考案は上記従来技術に存在する問題点を解消し,容易
かつ高精度でアンカーボルトを据付け得るアンカーボル
トの据付装置を提供することを目的とする。SUMMARY OF THE INVENTION An object of the present invention is to solve the problems existing in the above-mentioned prior art and to provide an anchor bolt installation device capable of easily and highly accurately installing an anchor bolt.
上記問題点を解決するために,本考案において捨てコン
クリート上に,複数個の直立する支持部材を有しかつ上
端面が実質的に水平面を形成するアンカーフレームを設
け,アンカーボルト用穴を有する一対の上部形板と下部
形板とが前記アンカーボルト用穴と同芯的に設けられた
中空管状の連結部材によりかつこの連結部材の上下端を
閉塞するように一体的に接合形成されてなる保持具が前
記アンカーフレーム上に載置固着されており,前記保持
具を構成する上部形板,連結部材および下部形板を貫通
してアンカーボルトが設けられていると共に,アンカー
ボルトの下端部をナットを介して前記下部形板およびこ
の下部形板に密着する定着板に固定する,という技術的
手段を採用したのである。In order to solve the above-mentioned problems, in the present invention, a pair of anchor frames having a plurality of upright supporting members and an upper end surface of which substantially forms a horizontal plane is provided on abandoned concrete, and a pair of holes for anchor bolts is provided. A holding member in which the upper shaped plate and the lower shaped plate are integrally joined by a hollow tubular connecting member that is provided concentrically with the anchor bolt hole and that closes the upper and lower ends of the connecting member. The tool is placed and fixed on the anchor frame, and an anchor bolt is provided so as to penetrate through the upper plate, the connecting member and the lower plate that form the holder, and the lower end of the anchor bolt is a nut. The technical means of fixing to the lower shaped plate and the fixing plate which is in close contact with the lower shaped plate via the above is adopted.
上記の構成により,保持具によってアンカーボルトを正
確に位置決めした状態で基礎コンクリート中に埋設する
ことができるのである。With the above configuration, the anchor bolts can be embedded in the concrete foundation while being accurately positioned by the holder.
第1図および第2図は各々本考案の実施例を示す要部正
面図および一部断面平面図であり,同一部分は前記第6
図と同一の参照符号にて示す。両図において,10は連
結部材であり,貫通穴を有する中空パイプによって形成
し,上部形板2および下部形板3と両端部において例え
ば溶接接合により一体的に固着し,保持具11を形成す
る。なお連結部材10の内径寸法は,アンカーボルト4
に螺合するナット6の外形寸法より大に形成すると共
に,上部形板2および下部形板3には所定寸法のピッチ
で配設固着する。次に上部形板2および下部形板3に前
記所定寸法のピッチで設けた挿通穴(図示せず)を介し
てアンカーボルト4を保持する。アンカーボルト4を定
着板5およびナット6により,下部形板3を挟着するこ
とによって位置決めする手段は,前記第6図に示すもの
と同様である。次に捨てコンクリート7に例えば等辺山
形鋼からなる固定部材12を予め埋設し,支持板13お
よび支持部材14からなるアンカーフレーム15を載置
固着する。支持部材14は,例えば前記連結部材10と
同様の4本の中空パイプからなり,下端部を支持板13
と溶接接合すると共に,上端面を実質的に水平面を形成
するように構成する。上記の構成により,アンカーボル
ト4を挿通保持した保持具11をアンカーフレーム15
上に載置して,両者を例えば溶接接合により固着した
後,コンクリートを打設すれば,アンカーボルト4を保
持具11およびアンカーフレーム15と共に,基礎8中
に埋設することができる。1 and 2 are a front view and a partial sectional plan view of an essential part showing an embodiment of the present invention, respectively.
The same reference numerals as in the figure are used. In both figures, 10 is a connecting member, which is formed by a hollow pipe having a through hole, and is integrally fixed to the upper shaped plate 2 and the lower shaped plate 3 at both ends by, for example, welding to form a holder 11. . The inner diameter of the connecting member 10 is the anchor bolt 4
The nut 6 is formed to have a larger outer size than that of the nut 6 to be screwed into the upper shape plate 2 and is fixed to the lower shape plate 3 at a predetermined pitch. Next, the anchor bolt 4 is held through the insertion holes (not shown) formed in the upper shaped plate 2 and the lower shaped plate 3 at the pitches of the predetermined dimension. The means for positioning the anchor bolt 4 by sandwiching the lower shaped plate 3 with the fixing plate 5 and the nut 6 is the same as that shown in FIG. Next, a fixing member 12 made of equilateral angle steel, for example, is embedded in the discarded concrete 7 in advance, and an anchor frame 15 made of a supporting plate 13 and a supporting member 14 is placed and fixed. The supporting member 14 is composed of, for example, four hollow pipes similar to the connecting member 10, and the lower end portion thereof is supported by the supporting plate 13.
And the upper end surface are formed so as to form a substantially horizontal surface. With the above configuration, the holder 11 having the anchor bolt 4 inserted and held therein is attached to the anchor frame 15
The anchor bolt 4 can be embedded in the foundation 8 together with the holder 11 and the anchor frame 15 by placing it on top and fixing them by welding, for example, and then placing concrete.
なお上記のようにして基礎8中に埋設されたアンカーボ
ルト4は,基礎8を構成するコンクリートとは少なくと
も連結部材10が外周を包囲する部分においては全く接
触しない。すなわち,連結部材10の上下端は,上部形
板2および下部形板3によって閉塞された状態でコンク
リートが打設されるから,連結部材10の内部にはコン
クリートが侵入しないためである。従って柱脚を据付け
てナット6aを締付けた状態においては,アンカーボル
ト4に発生する応力は各部分において略均等である。こ
のため柱脚の固定度を確保するために付与した初期張力
が,経年的にもまた外力の作用によっても低減すること
がない。なお上部形板2の上方において基礎8中に埋設
されるアンカーボルト4の外周に,例えば薄肉パイプ
(金属製であっても非金属製であってもよい)若しくは
可撓性材料からなるテープ等を装着して,基礎8と不拘
束状態を形成すれば,上記作用を更に増大させ得る。The anchor bolt 4 embedded in the foundation 8 as described above does not contact the concrete forming the foundation 8 at least at the portion where the connecting member 10 surrounds the outer periphery. That is, since the concrete is poured in the upper and lower ends of the connecting member 10 in a state of being closed by the upper shaped plate 2 and the lower shaped plate 3, concrete does not enter the inside of the connecting member 10. Therefore, when the column base is installed and the nut 6a is tightened, the stress generated in the anchor bolt 4 is substantially equal in each part. For this reason, the initial tension applied to secure the fixedness of the column base does not decrease over time or due to the action of external force. On the outer periphery of the anchor bolt 4 embedded in the foundation 8 above the upper shaped plate 2, for example, a thin pipe (may be made of metal or non-metal) or a tape made of a flexible material or the like. By mounting and forming an unrestrained state with the foundation 8, the above action can be further increased.
第3図および第4図は各々本考案の他の実施例を示す要
部正面図および同平面図であり,同一部分は前記第1図
および第2図に示す実施例と同一の参照符号で示す。両
図において捨てコンクリート7に例えば等辺山形鋼から
なる4本の支持部材14aを突設すると共に,支持部材
14aの上端部に例えば等辺山形鋼からなる2本の水平
支持部材14bを,それらの上面が実質的に水平面を形
成するようにボルト17を介して固着し,アンカーフレ
ーム15を構成する。なお支持部材14aには上下方向
に延びる長穴16を穿設して,ボルト17を貫通可能と
する。このように構成することにより,水平支持部材1
4bを上下に移動可能とすることができ,上面のレベル
出し,ならびに第1図および第2図に示すアンカーボル
ト4の上下方向の位置調整が可能である。FIGS. 3 and 4 are a front view and a plan view of a main part of another embodiment of the present invention, respectively, and the same portions are designated by the same reference numerals as those of the embodiments shown in FIGS. 1 and 2. Show. In both figures, four supporting members 14a made of, for example, equilateral angle steel are projected on the discarded concrete 7, and two horizontal supporting members 14b made of, for example, equilateral angle steel are provided at the upper end of the support member 14a. Are fixed via bolts 17 so as to form a substantially horizontal surface, and constitute the anchor frame 15. A long hole 16 extending in the vertical direction is bored in the support member 14a so that the bolt 17 can penetrate therethrough. With this configuration, the horizontal support member 1
4b can be moved up and down, and the leveling of the upper surface and the vertical position adjustment of the anchor bolt 4 shown in FIGS. 1 and 2 are possible.
次に第5図は本考案の更に他の実施例を示す要部平面図
であり,同一部分は前記第1図〜第4図と同一の参照符
号で示す。同図において,下部形板3および水平支持部
材14bに各々直交するように長穴18,19を設けて
ボルト20を貫通可能とする。このように構成すること
により,下部形板3を水平面内において移動可能とし得
るから,下部形板3に設けた挿通穴4aに挿通保持する
アンカーボルト(図示せず)の水平面内における位置調
整が可能である。Next, FIG. 5 is a plan view of an essential part showing still another embodiment of the present invention, in which the same parts are designated by the same reference numerals as those in FIGS. In the figure, elongated holes 18 and 19 are provided in the lower shaped plate 3 and the horizontal support member 14b so as to be orthogonal to each other so that the bolt 20 can pass therethrough. With this configuration, the lower shaped plate 3 can be moved in the horizontal plane, so that the position adjustment of the anchor bolt (not shown) inserted and held in the insertion hole 4a provided in the lower shaped plate 3 in the horizontal plane can be performed. It is possible.
本実施例においては,保持具を溶接接合によって構成し
た例を示したが,ボルト・ナット接合によって構成して
もよく,両者を併用してもよい。また保持具を構成する
連結部材の数量は4本に限定せず,アンカーボルトの配
設本数その他を勘案して適宜選定することができる。更
に保持具およびアンカーフレームの構成部材が等辺山形
鋼である例を示したが,これに限定せず他の形鋼,管
材,棒材,その他の構造用部材の使用が可能であると共
に,これらの併用も当然に可能である。なお捨てコンク
リートに突設する支持部材は,コンクリート打設後,コ
ンクリート未凝固の間に所定位置に挿し込む手段を採用
してもよい。また保持具を構成する連結部材は,横断面
が円形以外の中空パイプによって形成してもよいことは
当然である。In this embodiment, an example in which the holder is constructed by welding is shown, but it may be constructed by bolt-nut joining, or both may be used together. Further, the number of connecting members constituting the holder is not limited to four, and can be appropriately selected in consideration of the number of anchor bolts to be arranged and the like. Furthermore, the example in which the holding member and the component of the anchor frame are equilateral angle steel is shown, but the present invention is not limited to this, and other shaped steels, pipes, rods, and other structural members can be used. Of course, the combination of is also possible. In addition, as the support member projecting on the discarded concrete, a means for inserting the concrete at a predetermined position after the concrete is cast and before the concrete is not solidified may be adopted. Further, it goes without saying that the connecting member constituting the holder may be formed by a hollow pipe whose cross section is not circular.
本考案は以上記述のような構成および作用であるから,
下記の効果を期待できる。Since the present invention has the structure and operation as described above,
The following effects can be expected.
(1)保持具を構成する中空管状の連結部材中にアンカー
ボルトが収容保持されるため,従来のフレームによる障
害がなくなり,装置全体の構造が簡単になり,基礎コン
クリート中に配設される水平方向の鉄筋との干渉が殆ど
無くなる。(1) Since the anchor bolt is housed and held in the hollow tubular connecting member that constitutes the holder, the conventional frame does not obstruct the structure, the structure of the entire device is simplified, and the horizontal structure is placed in the concrete foundation. Almost no interference with the direction rebar.
(2)連結部材の上下端部が閉塞された状態でコンクリー
ト打設が行われるから,基礎を構成するコンクリートは
連結部材中のアンカーボルトの外周とは全く接触しな
い。従って据付後においてアンカーボルトに発生する応
力は各部位に均等に作用し,初期張力は経年的にもまた
外力によっても低減せず安定した状態を継続する。(2) Since concrete is cast with the upper and lower ends of the connecting member closed, the concrete that constitutes the foundation does not contact the outer circumference of the anchor bolt in the connecting member at all. Therefore, after installation, the stress generated in the anchor bolts acts evenly on each part, and the initial tension does not decrease over time or due to external force and remains stable.
(3)工場において予め所定寸法に加工した構成部材のみ
を製作して建方現場において組立てることができるた
め,運搬作業が極めて容易となる。(3) Only the components that have been machined to the predetermined size in the factory can be manufactured and assembled at the construction site, so the transportation work becomes extremely easy.
(4)構成部材相互の接合手段の全部もしくは一部をボル
ト・ナット接合とすることができ,建方現場におけるア
ンカーボルトの位置調整が可能であり,アンカーボルト
の位置決め精度が大幅に向上する。(4) Bolts and nuts can be used to join all or part of the joining means between the constituent members, and the position of the anchor bolt can be adjusted at the construction site, greatly improving the positioning accuracy of the anchor bolt.
(5)アンカーフレームの設置が極めて容易であるため,
従来技術において必要としていた特殊工具の使用若しく
は煩雑な作業が全く不要となり,工程を大幅に短縮し得
る。(5) Since the installation of the anchor frame is extremely easy,
The use of special tools or complicated work required in the prior art is completely eliminated, and the process can be greatly shortened.
第1図および第2図は各々本考案の実施例を示す要部正
面図および一部断面平面図,第3図および第4図は各々
本考案の他の実施例を示す要部正面図および同平面図,
第5図は本考案の更に他の実施例を示す要部平面図,第
6図は従来のアンカーボルトの据付装置の一例を示す要
部正面図である。 2:上部形板,3:下部形板,4:アンカーボルト,1
0:連結部材,14,14a:支持部材,14b:水平
支持部材。1 and 2 are a front view and a partial sectional plan view of an essential part showing an embodiment of the present invention, and FIGS. 3 and 4 are front views of an essential part showing another embodiment of the present invention, respectively. Same plan,
FIG. 5 is a plan view of a main part showing still another embodiment of the present invention, and FIG. 6 is a front view of the main part showing an example of a conventional anchor bolt installation device. 2: Upper shape plate, 3: Lower shape plate, 4: Anchor bolt, 1
0: connection member, 14, 14a: support member, 14b: horizontal support member.
フロントページの続き (72)考案者 北野 隆司 福岡県北九州市若松区北浜1丁目9番1号 日立金属株式会社若松工場内 (72)考案者 岩田 満信 東京都江東区東陽4丁目1番13号 日立金 属機材株式会社内 (72)考案者 山本 紀明 北海道札幌市中央区北2条西4丁目1番地 日立金属機材株式会社札幌営業所内 (56)参考文献 実開 昭57−12444(JP,U) 実開 昭60−8305(JP,U) 特公 昭52−31085(JP,B2)Front page continued (72) Takashi Kitano, Takashi Kitano, 1-9-1, Kitahama, Wakamatsu-ku, Kitakyushu, Fukuoka Inside the Wakamatsu Factory, Hitachi Metals, Ltd. (72) Mitsunobu Iwata 4-1-1, Toyo, Koto-ku, Tokyo Hitachi Metals & Equipment Co., Ltd. (72) Noriaki Yamamoto Inventor Noriaki Nishi 4-chome, Chuo-ku, Sapporo-shi, Hokkaido, Hitachi Metals & Equipment Co., Ltd. Sapporo Sales Office (56) References: 57-12444 (JP, U) ) Actual development Sho 60-8305 (JP, U) Japanese Patent Sho 52-31085 (JP, B2)
Claims (6)
支持部材を有しかつ上端面が実質的に水平面を形成する
アンカーフレームを設け,アンカーボルト用穴を有する
一対の上部形板と下部形板とが前記アンカーボルト用穴
と同芯的に設けられた中空管状の連結部材によりかつこ
の連結部材の上下端を閉塞するように一体的に接合形成
されてなる保持具が前記アンカーフレーム上に載置固着
されており,前記保持具を構成する上部形板,連結部材
および下部形板を貫通してアンカーボルトが設けられて
いると共に,アンカーボルトの下端部をナットを介して
前記下部形板およびこの下部形板に密着する定着板に固
定したことを特徴とするアンカーボルトの据付装置。1. A pair of upper shape plate and lower shape having an anchor frame having a plurality of upright supporting members and an upper end surface of which substantially forms a horizontal surface on abandoned concrete, and having an anchor bolt hole. A retainer is integrally formed on the anchor frame by a plate-shaped hollow tubular connecting member concentrically provided with the anchor bolt hole and integrally formed so as to close the upper and lower ends of the connecting member. An anchor bolt is mounted and fixed, and an anchor bolt is provided so as to penetrate through the upper shaped plate, the connecting member and the lower shaped plate which constitute the holder, and the lower end of the anchor bolt is attached to the lower shaped plate through a nut. An anchor bolt installation device characterized in that it is fixed to a fixing plate that is in close contact with the lower shaped plate.
形成され,かつ開口を介してアンカーボルトの下端部お
よびナットが前記支持部材に挿入されている実用新案登
録請求の範囲第1項記載のアンカーボルトの据付装置。2. The utility model registration claim 1 in which the support member is formed in a hollow tubular shape having an opening at the top, and the lower end of the anchor bolt and the nut are inserted into the support member through the opening. Anchor bolt installation device.
おり,かつそれらの上端部に複数個の水平支持部材が固
着されている実用新案登録請求の範囲第1項記載のアン
カーボルトの据付装置。3. An anchor bolt installation device according to claim 1, wherein the support members are provided in a projecting manner on abandoned concrete, and a plurality of horizontal support members are fixed to their upper end portions. .
ットで接合した実用新案登録請求の範囲第3項記載のア
ンカーボルトの据付装置。4. An anchor bolt installation device according to claim 3, wherein the anchor frame and the holder are joined by bolts and nuts.
た実用新案登録請求の範囲第1項ないし第3項何れかに
記載のアンカーボルトの据付装置。5. An anchor bolt installation device according to any one of claims 1 to 3, wherein the anchor frame and the holder are welded and joined together.
接接合した実用新案登録請求の範囲第1項ないし第5項
何れかに記載のアンカーボルトの据付装置。6. An anchor bolt installation device according to any one of claims 1 to 5, wherein the upper profile plate and the lower profile plate and the connecting member are joined by welding.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1987094444U JPH0612048Y2 (en) | 1987-06-19 | 1987-06-19 | Anchor bolt installation device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1987094444U JPH0612048Y2 (en) | 1987-06-19 | 1987-06-19 | Anchor bolt installation device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS64647U JPS64647U (en) | 1989-01-05 |
| JPH0612048Y2 true JPH0612048Y2 (en) | 1994-03-30 |
Family
ID=30957914
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1987094444U Expired - Lifetime JPH0612048Y2 (en) | 1987-06-19 | 1987-06-19 | Anchor bolt installation device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0612048Y2 (en) |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2538179C2 (en) * | 1975-08-27 | 1986-05-28 | Bayer Ag, 5090 Leverkusen | 3-alkoxy-benzo-1,2,4-triazines, process for their preparation and their use as fungicides |
| JPS5712444U (en) * | 1980-06-20 | 1982-01-22 |
-
1987
- 1987-06-19 JP JP1987094444U patent/JPH0612048Y2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS64647U (en) | 1989-01-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5505033A (en) | Column base structure and connection arrangement | |
| JP3628417B2 (en) | Construction column construction method and guide pipe used for it | |
| JP2555111B2 (en) | Anchor bolt fixing device | |
| JP3175586B2 (en) | Column and pile connection method | |
| JPH0612048Y2 (en) | Anchor bolt installation device | |
| JP2943812B2 (en) | Pillar structure | |
| JP4884117B2 (en) | Column and steel pipe pile positioning device and positioning method | |
| JPH10311047A (en) | Method and apparatus for positioning a pillar when installing a plug-in type pillar | |
| JPH0581403U (en) | Joint structure of reinforced concrete columns and steel beams | |
| JPH0629233Y2 (en) | Anchor bolt installation device | |
| JPH09268573A (en) | Column and pile joining member | |
| JP2000240207A (en) | Installation of void member of hollow slab | |
| JPH066861B2 (en) | Construction method of Kumashindai | |
| JP2630623B2 (en) | Anchor bolt installation method and anchor bolt support device used for it | |
| JPH09177366A (en) | Joining structure of steel frame reinforced concrete column and seismic isolation device and joining method | |
| JP7274992B2 (en) | Anchor bolt fixture and anchor frame | |
| JPH0657971B2 (en) | Building frame | |
| JPH0452378A (en) | Construction method and device for setting anchor bolt for steel frame pole | |
| JPH0598704A (en) | Beam-column joint structure | |
| JP2000226938A (en) | Seismic retrofitting method for existing structures | |
| JP3489825B2 (en) | A joining device having a pair of diaphragms for joining a reinforced concrete column and a horizontal steel beam | |
| JP4120734B2 (en) | Column base structure of steel structure | |
| GB2225597A (en) | A column base structure | |
| JP2001107555A (en) | Scaffold for steel column | |
| JPH0790928A (en) | SRC pillar construction method |