JPH0619924A - Production scheduling device - Google Patents
Production scheduling deviceInfo
- Publication number
- JPH0619924A JPH0619924A JP17783792A JP17783792A JPH0619924A JP H0619924 A JPH0619924 A JP H0619924A JP 17783792 A JP17783792 A JP 17783792A JP 17783792 A JP17783792 A JP 17783792A JP H0619924 A JPH0619924 A JP H0619924A
- Authority
- JP
- Japan
- Prior art keywords
- order
- list
- orders
- load
- graph
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 84
- 238000000034 method Methods 0.000 claims description 19
- 238000000605 extraction Methods 0.000 claims description 13
- 230000001186 cumulative effect Effects 0.000 claims description 4
- 238000010586 diagram Methods 0.000 description 12
- 230000004913 activation Effects 0.000 description 3
- 238000013500 data storage Methods 0.000 description 3
- 230000003213 activating effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011165 process development Methods 0.000 description 1
- 238000013517 stratification Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Multi-Process Working Machines And Systems (AREA)
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は生産スケジューリング装
置に関し、特に、指定したオーダの製造日程を変更する
ことによって受注したオーダの製造日程で決まる工程の
負荷を調整する生産スケジューリング装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production scheduling apparatus, and more particularly to a production scheduling apparatus for adjusting a process load determined by a manufacturing schedule of an ordered order by changing a manufacturing schedule of a designated order.
【0002】[0002]
【従来の技術】従来の生産スケジューリング装置は、負
荷を調整する際に、全オーダに関するオーダ情報と製造
日程情報との一覧から生産スケジューリング装置操作者
が選んだオーダのオーダ名を指定することにより、製造
日程を変更すべきオーダを特定していた。2. Description of the Related Art A conventional production scheduling apparatus, when adjusting a load, specifies an order name of an order selected by a production scheduling apparatus operator from a list of order information and manufacturing schedule information regarding all orders. The order for which the manufacturing schedule should be changed was specified.
【0003】[0003]
【発明が解決しようとする課題】上述した従来の生産ス
ケジューリング装置は、負荷を調整する際に、山積グラ
フを見ただけでは、山積グラフの負荷の棒の各各の部分
がどのオーダによる負荷であるかが直接読み取ることが
できず、全オーダに関するオーダ情報と製造日程情報と
の一覧から製造日程を変更すべきオーダを選び、生産ス
ケジューリング装置操作者がオーダ名をいちいち入力指
定する操作が必要であり、また製造日程を変更しようと
するオーダに対応する負荷の把握が困難であるという欠
点があった。In the conventional production scheduling apparatus described above, when the load is adjusted, by simply looking at the pile graph, each part of the load bar of the pile graph shows the load by which order. It is not possible to directly read whether there is any, and it is necessary for the operator of the production scheduling device to input and specify the order name one by one from the list of order information and manufacturing schedule information for all orders, for which the manufacturing schedule should be changed. However, there is a drawback that it is difficult to grasp the load corresponding to the order in which the manufacturing schedule is changed.
【0004】[0004]
【課題を解決するための手段】本発明の生産スケジュー
リング装置は、オーダ名,顧客名,製品名,注文数およ
び要求納期などの項目で構成される複数のオーダ情報を
格納する手段と;各各の前記製品についての、製造工程
の順序,各各の前記製造工程のリードタイムおよび各各
の前記製造工程に掛かる1注文当りの基準負荷に関する
製品情報を格納する手段と;前記オーダ情報と前記製品
情報とをもとに、全オーダについて各各の前記製造工程
の開始日時と終了日時との項目で構成される製造日程情
報を決める工程展開の手段と;前記全オーダについての
前記製造日程情報を格納する手段と;前記オーダ情報と
前記製品情報と前記製造日程情報とをもとに、指定され
た前記製造工程について、指定された複数のオーダの累
積負荷を一定期間毎に算出する無制限負荷山積手段と;
前記製造工程の能力を格納する手段と;前記累積負荷と
指定された前記製造工程に関する前記製造工程能力とを
格納する山積グラフデータ格納手段と;表やグラフを表
示する表・グラフ表示手段と;前記山積グラフデータを
グラフ形式の山積グラフとして前記表・グラフ表示手段
に描画する手段と;前記山積グラフの指定された一部分
の負荷に対応する全てのオーダのリストを作成する抽出
オーダリスト作成手段と;前記抽出オーダリストを格納
する手段と;前記抽出オーダリストを表形式の抽出オー
ダ一覧表として前記表・グラフ表示手段に描画する手段
とを備える。また、本発明の生産スケジューリング装置
は、前記抽出オーダ一覧表の指定された一部分に対応す
る全ての選択されたオーダのリストを作成する手段と;
前記選択オーダリストを格納する手段と;前記選択オー
ダリストに対応する負荷を前記山積グラフに重ねて描画
する手段とを備える。さらに、本発明の生産スケジュー
リング装置は、 前記抽出オーダ一覧表の指定された一
部分に対応する全ての選択されたオーダのリストを作成
する手段と;前記選択オーダリストを格納する手段と;
指定されたオーダに適用する製造日程変更指示を格納す
る手段と;前記選択オーダリストの中の前記全オーダに
ついて前記製造日程変更指示に基づき前記オーダ情報お
よび前記製造日程情報を変更する手段とを備える。A production scheduling apparatus according to the present invention comprises means for storing a plurality of order information composed of items such as order name, customer name, product name, number of orders and requested delivery date; Means for storing the manufacturing process order, the lead time of each manufacturing process, and the reference load per order required for each manufacturing process of each of the products; and the order information and the product. Means for developing process schedule information including the start date and time and end date and time of each manufacturing process for all orders based on the information; and the production schedule information for all orders. Means for storing; based on the order information, the product information, and the manufacturing schedule information, the accumulated load of a plurality of designated orders for a specified manufacturing process for a certain period. And unlimited load piling means for calculating a;
Means for storing the capacity of the manufacturing process; mountain graph data storage means for storing the cumulative load and the manufacturing process capacity for the designated manufacturing process; table / graph display means for displaying a table or a graph; Means for drawing the mountain graph data as a mountain graph in the form of a graph on the table / graph display means; and an extraction order list creating means for creating a list of all orders corresponding to a load of a specified part of the mountain graph. Means for storing the extracted order list; and means for drawing the extracted order list on the table / graph display means as a table-formatted extracted order list. The production scheduling apparatus of the present invention further comprises means for creating a list of all selected orders corresponding to a specified part of the extracted order list.
And means for storing the selected order list; and means for drawing the load corresponding to the selected order list on the mountain graph. Furthermore, the production scheduling apparatus of the present invention includes means for creating a list of all selected orders corresponding to a specified part of the extracted order list, and means for storing the selected order list;
Means for storing a manufacturing schedule change instruction applied to a specified order; and means for changing the order information and the manufacturing schedule information based on the manufacturing schedule change instruction for all the orders in the selected order list .
【0005】[0005]
【実施例】次に、本発明の実施例について図面を参照し
て説明する。図1は本発明の一実施例を示すブロック図
である。図1を参照すると、この実施例の生産スケジュ
ーリング装置において、オーダ情報格納手段1は、オー
ダ名,顧客名,製品名,注文数および要求納期などの項
目で構成される複数のオーダ情報aを格納する。製品情
報格納手段2は、各各の製品についての製造工程の順序
と、各各の製造工程のリードタイムと、各各の製造工程
に掛かる1注文当りの基準負荷とに関する製品情報bを
格納する。工程展開手段3は、オーダ情報aと製品情報
bとをもとに全オーダについて各各の工程の開始日時と
終了日時との項目で構成される製造日程情報cを決め
る。製造日程情報格納手段4は、全オーダについての製
造日程情報cを格納する。無制限負荷山積手段5は、オ
ーダ情報aと製品情報bと製造日程情報cとをもとに、
指定された工程について、指定された複数のオーダの累
積負荷dを一定期間毎に算出する無制限負荷山積を行
う。工程能力格納手段6は、各各の工程能力eを格納す
る。山積グラフデータ格納手段7は、指定された工程に
関する累積負荷dと工程能力eとからなる山積グラフデ
ータfを格納する。山積グラフ描画手段8は、山積グラ
フデータfをグラフ形式の山積グラフgとして表・グラ
フ表示手段9に描画する。抽出オーダリスト作成手段1
0は、山積グラフgの指定された一部分の負荷に対応す
る全てのオーダを集めた抽出オーダリストhを作成す
る。抽出オーダリスト格納手段11は、抽出オーダリス
トhを格納する。抽出オーダ一覧表描画手段12は、抽
出オーダリストhを表形式の抽出オーダ一覧表iとして
表・グラフ表示手段9に描画する。選択オーダリスト作
成手段13は、抽出オーダ一覧表iの指定された一部分
に対応する全ての選択されたオーダを集めた選択オーダ
リストjを作成する。選択オーダリスト格納手段14
は、選択オーダリストjを格納する。選択オーダリスト
負荷描画手段15は、選択オーダリストjに対応する負
荷を山積グラフgに重ねて表・グラフ表示手段9に描画
する。製造日程変更指示格納手段16は、指定されたオ
ーダに適用する製造日程変更指示kを格納する。製造日
程情報変更手段17は、選択オーダリストjの中の全オ
ーダについて製造日程変更指示kに基づきオーダ情報a
および製造日程情報cを変更する。Embodiments of the present invention will now be described with reference to the drawings. FIG. 1 is a block diagram showing an embodiment of the present invention. Referring to FIG. 1, in the production scheduling apparatus of this embodiment, the order information storage means 1 stores a plurality of order information a including items such as order name, customer name, product name, number of orders and requested delivery date. To do. The product information storage means 2 stores the product information b regarding the order of the manufacturing process for each product, the lead time of each manufacturing process, and the reference load per order required for each manufacturing process. . Based on the order information a and the product information b, the process developing means 3 determines manufacturing schedule information c including items of start date and time and end date and time of each process for all orders. The manufacturing schedule information storage means 4 stores manufacturing schedule information c for all orders. The unlimited load pile-up means 5 is based on the order information a, the product information b, and the manufacturing schedule information c.
For the designated process, unlimited load pile-up for calculating the cumulative loads d of a plurality of designated orders at regular intervals is performed. The process capability storage means 6 stores each process capability e. The mountain graph data storage unit 7 stores the mountain graph data f including the accumulated load d and the process capability e regarding the designated process. The mountain graph drawing means 8 draws the mountain graph data f as a mountain graph g in a graph format on the table / graph display means 9. Extraction order list creation means 1
0 creates an extracted order list h in which all orders corresponding to the load of a specified part of the mountainous graph g are collected. The extraction order list storage means 11 stores the extraction order list h. The extraction order list drawing means 12 draws the extraction order list h on the table / graph display means 9 as a table-format extraction order list i. The selected order list creating means 13 creates a selected order list j in which all the selected orders corresponding to a specified part of the extracted order list i are collected. Selected order list storage means 14
Stores the selected order list j. The selected order list load drawing means 15 superimposes the load corresponding to the selected order list j on the mountain graph g and draws it on the table / graph display means 9. The manufacturing schedule change instruction storage means 16 stores the manufacturing schedule change instruction k applied to the designated order. The manufacturing schedule information changing unit 17 orders all the orders in the selected order list j based on the manufacturing schedule change instruction k.
And the manufacturing schedule information c is changed.
【0006】図2は、この実施例で扱う山積グラフgの
例をマウス付のディスプレイ等の表示装置を使用してグ
ラフの一部を指示しオーダを抽出する方法の例を示す図
である。図2において、Tは山積グラフの表題、A1 は
グラフ横軸、A2 はグラフ縦軸、G1 ,G2 およびG3
は層別グラフ棒、P1 はマウスボタンを押した位置、P
2 はマウスボタンを離した位置、C1 はマウスカーソ
ル、C2 は切り出しカーソル、B1 は抽出オーダ一覧表
示起動用ボタン、B2 は山積グラフ表示終了用ボタンで
ある。山積グラフ表題Tはグラフの種類を示す。グラフ
横軸A1 は4月の週毎に負荷積みをしていることを示
す。グラフ縦軸A2 は負荷積の単位が数量であることと
0から100までのグラフ高さとを示す。層別グラフ棒
G1 ,G2 およびG3 は負荷積対象工程の負荷を3つの
品種の負荷に層別集計した高さを持つ。マウスボタンを
位置P1 で押し、そのまま位置P2 まで動かして離すま
での間、P1 とP2 とを2対角とする長方形の形をした
切り出しカーソルC2 が表示され、切り出しカーソルC
2 で完全に囲むことにより一覧抽出対象として指定され
た層別グラフ棒G2 の枠は太線表示がされる。処理起動
ボタンB1 を押すと、一覧抽出対象について抽出オーダ
一覧表示が起動される。FIG. 2 is a diagram showing an example of a method of extracting an order by instructing a part of the graph using a display device such as a display with a mouse, as an example of the mountain graph g handled in this embodiment. In FIG. 2, T is the title of the pile graph, A 1 is the horizontal axis of the graph, A 2 is the vertical axis of the graph, G 1 , G 2 and G 3
Is a stratified graph bar, P 1 is the position where the mouse button is pressed, P
2 is a position where the mouse button is released, C 1 is a mouse cursor, C 2 is a cutout cursor, B 1 is a button for starting the extraction order list display, and B 2 is a button for ending the piled-up graph display. The pile graph title T indicates the type of graph. The horizontal axis A 1 of the graph indicates that loading is carried out every week in April. The vertical axis A 2 of the graph indicates that the unit of the load product is the quantity and the graph height from 0 to 100. The stratified graph bars G 1 , G 2 and G 3 have heights obtained by stratifying the loads of the load product target process into the loads of the three types. Until the mouse button is pressed at the position P 1 and moved to the position P 2 and released, a cutout cursor C 2 in the shape of a rectangle having P 1 and P 2 on two diagonals is displayed, and the cutout cursor C is displayed.
Been stratification graph bar G 2 frames specified as a list extraction target by completely surrounded by 2 is the thick lines. When the process start button B 1 is pressed, the extraction order list display for the list extraction target is started.
【0007】図3は、この実施例で扱う抽出オーダ一覧
の例をマウス付のディスプレイ等の表示装置を使用して
一覧の一部を指示しオーダを選択する方法の例を示す図
である。図3において、F1 ,F2 ,F3 ,F4 ,F5
およびF6 はオーダ情報の属性データ用欄、F7 は選択
用欄、B3 は負荷表示機能起動用ボタン、B4 は製造日
程変更機能起動用ボタン、Sは選択状態表示記号であ
る。オーダ情報の属性データ用欄F1 ,F2 ,F3 ,F
4 ,F5 およびF6 は、山積グラフで指定されたオーダ
について属性データを1行1オーダの形式で表示する。
マウスで選択用欄F7 を指示するとその行のオーダを選
択したことになり、その後選択状態表示記号Sが現れ
る。負荷表示機能起動用ボタンB3 を押すと、選択した
オーダリストに対応する山積グラフの負荷の部分が強調
表示される。製造日程変更機能起動用ボタンB4 は、製
造日程変更についてパラメータ指定と実行を行うウィン
ドウを起動する。FIG. 3 is a diagram showing an example of a method of selecting an order by instructing a part of the list using a display device such as a display with a mouse, as an example of the list of extracted orders handled in this embodiment. In FIG. 3, F 1 , F 2 , F 3 , F 4 , F 5
Further, F 6 is an attribute data column of order information, F 7 is a selection column, B 3 is a load display function activation button, B 4 is a manufacturing schedule change function activation button, and S is a selection state display symbol. Order information attribute data fields F 1 , F 2 , F 3 , F
4 , F 5 and F 6 display the attribute data in the form of one order per line for the order specified in the mountain chart.
When the selection field F 7 is pointed with the mouse, it means that the order of that line is selected, and then the selection state display symbol S appears. When the load display function activating button B 3 is pressed, the load portion of the mountain graph corresponding to the selected order list is highlighted. Production rescheduling function activation button B 4 activates the window for execution and parameters specified for the manufacturing schedule changes.
【0008】図4は、この実施例で扱う抽出オーダ一覧
で選択したオーダに対応する負荷を重ねて描画した山積
グラフgを示す図である。図4において、G1 ,G2 ,
G21,G3 ,G4 ,G5 およびG6 は層別グラフ棒であ
る。層別グラフ棒G21は抽出オーダ一覧表で選択したオ
ーダの負荷に対応する。FIG. 4 is a diagram showing a mountain graph g in which the loads corresponding to the orders selected in the extracted order list handled in this embodiment are superimposed and drawn. In FIG. 4, G 1 , G 2 ,
G 21 , G 3 , G 4 , G 5 and G 6 are stratified graph bars. The stratified graph bar G 21 corresponds to the load of the order selected in the extracted order list.
【0009】図5は、この実施例で扱う製造日程変更指
示のデータ例をマウス付のディスプレイ等の表示装置を
使用したときの入力画面を示す図である。図5におい
て、文字列Dは製造日程変更指示、ボタンB6 は製造日
程変更実行ボタン、ボタンB7は製造日程変更中止ボタ
ンである。文字列Dは、「オーダの製造着手日を4日あ
とにずらす」という製造日程変更の内容を表す。ボタン
B6 をマウスで指示すると、抽出オーダ一覧で選択され
たオーダについて、文字列Dで指示された製造日程変更
をすることが製造日程情報変更手段に伝達される。FIG. 5 is a diagram showing an input screen when a display device such as a display with a mouse is used as a data example of a manufacturing schedule change instruction handled in this embodiment. In FIG. 5, a character string D is a manufacturing schedule change instruction, a button B 6 is a manufacturing schedule change execution button, and a button B 7 is a manufacturing schedule change stop button. The character string D represents the content of the manufacturing schedule change of "shifting the manufacturing start date of the order to four days later". When the button B 6 is designated with the mouse, the manufacturing schedule information changing means is informed that the manufacturing schedule information designated by the character string D will be changed for the order selected in the extracted order list.
【0010】図6は、この実施例で扱う製造日程変更指
示後の山積グラフを示す図である。図6において、
G1 ,G2 ’,G3 ,G4 ,G5 ’およびG6 は層別グ
ラフ棒である。図4の層別グラフ棒G2 およびG5 が、
製造日程変更指示後、層別グラフ棒G2 ’およびG5 ’
となっている。FIG. 6 is a diagram showing a stack graph after the manufacturing schedule change instruction is handled in this embodiment. In FIG.
G 1 , G 2 ' , G 3 , G 4 , G 5 ' and G 6 are stratified graph bars. The stratified graph bars G 2 and G 5 in FIG.
After instructing to change the manufacturing schedule, the graph bars G 2 ' and G 5 ' by layer
Has become.
【0011】[0011]
【発明の効果】以上説明したように、本発明によれば、
負荷を調整する際に、山積グラフの負荷の棒の指定され
た部分がどのオーダの負荷であるかが一覧で直接読み取
れるため負荷とオーダの関係が容易に把握でき、その一
覧表の行を指定することにより製造日程変更しようとす
るオーダを複数指定できるのでオーダをオーダ名で指定
する手間が省け、指定したオーダが負荷としてどの割合
であるかが明示できることにより製造日程変更の負荷に
ついての影響が製造日程を変更する前に容易に把握でき
る。As described above, according to the present invention,
When adjusting the load, it is possible to directly read in the list which order is the load of the specified portion of the load bar in the mountain chart, so it is easy to understand the relationship between the load and the order, and specify the row in the list. By doing so, you can specify multiple orders for which you want to change the manufacturing schedule, so you can save the trouble of specifying the order by the order name, and by clearly indicating what proportion of the specified order is the load, the effect on the load of the manufacturing schedule change is affected. It is easy to understand before changing the manufacturing schedule.
【図1】本発明の一実施例を示すブロック図である。FIG. 1 is a block diagram showing an embodiment of the present invention.
【図2】この実施例で扱う山積グラフの例とグラフの一
部を指示してオーダを抽出する方法の例を示す図であ
る。FIG. 2 is a diagram showing an example of a mountain graph used in this embodiment and an example of a method of instructing a part of the graph to extract an order.
【図3】この実施例で扱う抽出オーダ一覧の例と一覧の
一部を指示してオーダを選択する方法の例を示す図であ
る。FIG. 3 is a diagram showing an example of a list of extracted orders handled in this embodiment and an example of a method of instructing a part of the list and selecting an order.
【図4】この実施例で扱う抽出オーダ一覧の例と一覧の
一部を指示してオーダを選択する方法の例を示す図であ
る。FIG. 4 is a diagram showing an example of a list of extracted orders handled in this embodiment and an example of a method of instructing a part of the list to select an order.
【図5】この実施例で扱う製造日程変更指示のデータ例
とその入力画面を示す図である。FIG. 5 is a diagram showing a data example of a manufacturing schedule change instruction handled in this embodiment and an input screen thereof.
【図6】この実施例で扱う製造日程変更指示後の山積グ
ラフを示す図である。FIG. 6 is a diagram showing a stack graph after a manufacturing schedule change instruction in this embodiment.
1 オーダ情報格納手段 2 製品情報格納手段 3 工程展開手段 4 製造日程情報格納手段 5 無制限負荷山積手段 6 工程能力格納手段 7 山積グラフデータ格納手段 8 山積グラフ描画手段 9 表・グラフ表示手段 10 抽出オーダリスト作成手段 11 抽出オーダリスト格納手段 12 抽出オーダ一覧表描画手段 13 選択オーダリスト作成手段 14 選択オーダリスト格納手段 15 選択オーダリスト負荷描画手段 16 製造日程変更指示格納手段 17 製造日程情報変更手段 a オーダ情報 b 製品情報 c 製造日程情報 d 累積負荷 e 工程能力 f 山積グラフデータ g 山積グラフ h 抽出オーダリスト i 抽出オーダ一覧表 j 選択オーダリスト k 製造日程変更指示 1 order information storage means 2 product information storage means 3 process development means 4 manufacturing schedule information storage means 5 unlimited load pile means 6 process capacity storage means 7 pile graph data storage means 8 pile graph drawing means 9 table / graph display means 10 extraction order List creating means 11 Extracted order list storing means 12 Extracted order list drawing means 13 Selected order list creating means 14 Selected order list storing means 15 Selected order list load drawing means 16 Manufacturing schedule change instruction storing means 17 Manufacturing schedule information changing means a Order Information b Product information c Manufacturing schedule information d Cumulative load e Process capability f Mountaineering graph data g Mountaineering graph h Extracted order list i Extracted order list j Selected order list k Manufacturing schedule change instruction
Claims (3)
要求納期などの項目で構成される複数のオーダ情報を格
納する手段と;各各の前記製品についての、製造工程の
順序,各各の前記製造工程のリードタイムおよび各各の
前記製造工程に掛かる1注文当りの基準負荷に関する製
品情報を格納する手段と;前記オーダ情報と前記製品情
報とをもとに、全オーダについて各各の前記製造工程の
開始日時と終了日時との項目で構成される製造日程情報
を決める工程展開の手段と;前記全オーダについての前
記製造日程情報を格納する手段と;前記オーダ情報と前
記製品情報と前記製造日程情報とをもとに、指定された
前記製造工程について、指定された複数のオーダの累積
負荷を一定期間毎に算出する無制限負荷山積手段と;前
記製造工程の能力を格納する手段と;前記累積負荷と指
定された前記製造工程に関する前記製造工程能力とを格
納する山積グラフデータ格納手段と;表やグラフを表示
する表・グラフ表示手段と;前記山積グラフデータをグ
ラフ形式の山積グラフとして前記表・グラフ表示手段に
描画する手段と;前記山積グラフの指定された一部分の
負荷に対応する全てのオーダのリストを作成する抽出オ
ーダリスト作成手段と;前記抽出オーダリストを格納す
る手段と;前記抽出オーダリストを表形式の抽出オーダ
一覧表として前記表・グラフ表示手段に描画する手段
と;を備えることを特徴とする生産スケジューリング装
置。1. A means for storing a plurality of order information composed of items such as an order name, a customer name, a product name, the number of orders, and a required delivery date; Means for storing product information relating to the lead time of each manufacturing process and a reference load per order required for each manufacturing process; and for each order based on the order information and the product information. Means for developing process schedule information that includes items such as start date and time and end date and time of the manufacturing process; means for storing the production schedule information for all orders; the order information and the product information An unlimited load pile-up means for calculating a cumulative load of a plurality of designated orders for each designated period based on the manufacturing schedule information and the manufacturing schedule information; Means for storing; mountainous graph data storing means for storing the accumulated load and the manufacturing process capability for the designated manufacturing process; table / graph displaying means for displaying a table or a graph; and graphing the mountainous graph data Means for drawing on the table / graph display means as a mountain chart in the form; extraction order list creating means for creating a list of all orders corresponding to the load of a specified part of the mountain chart; and the extracted order list. A production scheduling apparatus comprising: a means for storing; and a means for drawing the extracted order list as a table-type extracted order list on the table / graph display means.
に対応する全ての選択されたオーダのリストを作成する
手段と;前記選択オーダリストを格納する手段と;前記
選択オーダリストに対応する負荷を前記山積グラフに重
ねて描画する手段と;を備えることを特徴とする請求項
1記載の生産スケジューリング装置。2. A means for creating a list of all selected orders corresponding to a specified part of the extracted order list; a means for storing the selected order list; and a load corresponding to the selected order list. 2. The production scheduling device according to claim 1, further comprising:
に対応する全ての選択されたオーダのリストを作成する
手段と;前記選択オーダリストを格納する手段と;指定
されたオーダに適用する製造日程変更指示を格納する手
段と;前記選択オーダリストの中の前記全オーダについ
て前記製造日程変更指示に基づき前記オーダ情報および
前記製造日程情報を変更する手段と;を備えること特徴
とする請求項1記載の生産スケジューリング装置。3. A means for creating a list of all selected orders corresponding to a specified part of the list of extracted orders; a means for storing the selected order list; a manufacturing applied to the specified order. 3. A means for storing a schedule change instruction; a means for changing the order information and the production schedule information based on the production schedule change instruction for all the orders in the selected order list. The production scheduling device described.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17783792A JP3039142B2 (en) | 1992-07-06 | 1992-07-06 | Production scheduling device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17783792A JP3039142B2 (en) | 1992-07-06 | 1992-07-06 | Production scheduling device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0619924A true JPH0619924A (en) | 1994-01-28 |
| JP3039142B2 JP3039142B2 (en) | 2000-05-08 |
Family
ID=16037987
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP17783792A Expired - Lifetime JP3039142B2 (en) | 1992-07-06 | 1992-07-06 | Production scheduling device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3039142B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0896028A (en) * | 1994-09-21 | 1996-04-12 | Nec Corp | Production schedule generating device |
| US6957190B1 (en) | 1997-09-24 | 2005-10-18 | Canon Kabushiki Kaisha | Parts management information system and parts management method, and storage medium |
-
1992
- 1992-07-06 JP JP17783792A patent/JP3039142B2/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0896028A (en) * | 1994-09-21 | 1996-04-12 | Nec Corp | Production schedule generating device |
| US6957190B1 (en) | 1997-09-24 | 2005-10-18 | Canon Kabushiki Kaisha | Parts management information system and parts management method, and storage medium |
Also Published As
| Publication number | Publication date |
|---|---|
| JP3039142B2 (en) | 2000-05-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7334195B2 (en) | System and process for presenting search results in a histogram/cluster format | |
| US5862381A (en) | Visualization tool for graphically displaying trace data | |
| US6057839A (en) | Visualization tool for graphically displaying trace data produced by a parallel processing computer | |
| US5023851A (en) | Method for presenting electronic calendar information in an interactive information handling system | |
| US7565608B2 (en) | Animation on object user interface | |
| US6380953B1 (en) | Method of display scrolling along a timebase and an apparatus for performing the method | |
| DE69521258T2 (en) | System for creating interactive software applications | |
| JP2525124B2 (en) | Apparatus and method for visually generating a trace data graphical display | |
| US6546558B1 (en) | Visual scenario editor for editing links between presentation screens in a multi-media application | |
| US10467782B2 (en) | Interactive hierarchical bar chart | |
| US10809904B2 (en) | Interactive time range selector | |
| JPS62224562A (en) | Display device for process control data | |
| JP3039142B2 (en) | Production scheduling device | |
| JP2000352528A (en) | How to display the trend graph | |
| JP2001243487A (en) | Image editing apparatus, image editing method, and medium storing computer-readable program | |
| JP2003099022A (en) | Multi-point measurement data display device, multi-point measurement data display method, and multi-point measurement data display program | |
| CN116483355A (en) | UI interactive assembly type main interface design method for quickly setting up form function of enterprise management operating system | |
| CN114594936A (en) | Page design method, device, storage medium and computer equipment | |
| JP2000010701A (en) | Operation menu setting method in graphical user interface | |
| US12353675B1 (en) | Data analysis platform with animation for rendering graphical representations of data | |
| JPH01266602A (en) | Generating method for production process schedule | |
| JPS5850039A (en) | List output method | |
| JP2007122530A (en) | Unit information processing apparatus, unit information processing method, and unit information processing program | |
| CN118536959A (en) | Project time display method and device, computer equipment and storage medium | |
| JPH08212189A (en) | Time series data editing device and editing method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|