JPH06200626A - Jacking-up method for building - Google Patents
Jacking-up method for buildingInfo
- Publication number
- JPH06200626A JPH06200626A JP154093A JP154093A JPH06200626A JP H06200626 A JPH06200626 A JP H06200626A JP 154093 A JP154093 A JP 154093A JP 154093 A JP154093 A JP 154093A JP H06200626 A JPH06200626 A JP H06200626A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- jack
- pillar
- ground
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
(57)【要約】 (修正有)
【目的】 タワークレーン、大型のブーム式コンクリー
トポンプ車を使用しないで高層建物の地上躯体を施工す
る。
【構成】 所定位置の地中に形成された縦孔に柱3を挿
入し、その柱3をジャッキアップ可能に支持し、地表G
Lより突出する柱3に屋上階の床及び最上階のスラブ1
0、スラブ梁10A、壁11、床12並びに梁13等を
取り付けた後は、一階の高さ分だけジャッキアップして
柱3に壁、床及び梁等を取り付ける手順を繰り返す。
(57) [Summary] (Correction) [Purpose] To construct the ground frame of a high-rise building without using a tower crane or a large boom concrete pump truck. [Structure] A pillar 3 is inserted into a vertical hole formed in the ground at a predetermined position, and the pillar 3 is supported so that it can be jacked up.
On the pillar 3 protruding from L, the floor on the rooftop floor and the slab 1 on the top floor
After attaching 0, the slab beam 10A, the wall 11, the floor 12, the beam 13, etc., the procedure of jacking up by the height of the first floor and attaching the wall, floor, beam, etc. to the pillar 3 is repeated.
Description
【0001】[0001]
【産業上の利用分野】本発明は、先に施工した屋上階を
ジャッキアッブしながら一階より最上階まで順次施工す
る建物のジャッキアップ工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a jack-up construction method for a building, which is sequentially constructed from the first floor to the uppermost floor while jacking up the roof floor constructed earlier.
【0002】[0002]
【従来の技術】一般に高層建物の躯体のうち地上部分の
施工法としては、地上階(以下1Fと略称する)より屋
上階(以下RFと略称する)まで順に施工する方法とR
Fを先に施工しRFをジャッキアップしながら1Fから
最上階(以下R−1Fと略称する)まで順次施工する方
法に大別される。後者の特殊例としてRFのみの構造物
の場合にRFを地上で組み立てて、一気にジャッキアッ
プし柱を取り付ける工法も知られている。2. Description of the Related Art Generally, as a method of constructing the above-ground portion of the frame of a high-rise building, a method of sequentially constructing from a ground floor (abbreviated as 1F below) to a roof floor (abbreviated as RF hereinafter) and R
The method is roughly divided into a method in which F is applied first and RF is jacked up, and the steps from 1F to the top floor (hereinafter abbreviated as R-1F) are sequentially performed. As a special case of the latter, there is also known a method of assembling RF on the ground in the case of a structure having only RF, jacking up at once and attaching a pillar.
【0003】[0003]
【発明が解決しようとする課題】しかし、上記施工法の
うち、前者はRFにタワークレーンと呼ばれる揚重機を
設置して柱、梁や床等の材料を揚重する必要があり、作
業場所が高所になるほど効率が低下しかつ危険度が増大
する問題があり、後者では各階毎に柱、梁や床等の材料
の揚重が必要で、またRFのジャッキアップの反力を受
けるために各階の補強する必要があるという問題があ
る。また両者に共通して、分割されて搬入した柱を各階
に施工に従って順次接続する必要があること、床のコン
クリート打設のため大型のコンクリート車が必要である
こと、さらに柱建て込みから梁架設、梁架設から床パネ
ル設置更に床パネル設置から床コンクリート打設という
手順を繰り返すため、たいていの場合RFの揚重機の能
力によって施工スピードが支配されるという問題もあ
る。However, of the above construction methods, the former requires a hoisting machine called a tower crane to be installed in the RF to hoist materials such as columns, beams, and floors, and the working place is There is a problem that the efficiency decreases and the risk increases as the height rises. In the latter, it is necessary to lift the material such as columns, beams and floors for each floor, and to receive the reaction force of RF jack-up. There is a problem that it is necessary to reinforce each floor. In addition, common to both, it is necessary to connect the columns that have been divided and carried in to each floor sequentially according to the construction, that a large concrete car is required for placing concrete on the floor, and further from the pillar erection to beam erection Since the steps of beam erection, floor panel installation, floor panel installation and floor concrete placement are repeated, there is a problem that the construction speed is controlled by the ability of the RF lifting machine in most cases.
【0004】本発明は、揚重機及びコンクリートポンプ
車を必要とせず、かつ高所作業のない安全な建物のジャ
ッキアップ工法を堤供することを目的とする。An object of the present invention is to provide a safe jack-up construction method for a building that does not require a lifting machine and a concrete pump truck and does not require work at height.
【0005】[0005]
【課題を解決するための手段】本発明によれば、先に施
工した屋上階をジャッキアッブしながら一階より最上階
まで順次施工する建物のジャッキアップ工法において、
所定位置の地中に形成された縦孔に柱を挿入し、その柱
をジャッキアップ可能に支持し、地表より突出する柱に
屋上階の床及び最上階のスラブ、壁、床並びに梁等を取
り付けた後は、一階の高さ分だけジャッキアップして柱
にスラブ、壁、床及び梁等を取り付ける手順を繰り返す
ことを特徴とする。According to the present invention, there is provided a jack-up method for a building in which construction is performed sequentially from the first floor to the top floor while jacking up the roof floor constructed earlier.
A pillar is inserted into a vertical hole formed in the ground at a predetermined position, the pillar is supported so that it can be jacked up, and the floor protruding from the surface of the floor and the slabs, walls, floors, beams on the rooftop floor, etc. After mounting, it is characterized by repeating the procedure of jacking up by the height of the first floor and attaching slabs, walls, floors, beams, etc. to columns.
【0006】[0006]
【作用効果の説明】上記のように構成された建物のジャ
ッキアップ工法は、各階の組立を地上で行うことができ
高所作業がなくなり、コンクリートポンプ車が不要とな
り、揚重機は地上の移動式クレーンで十分であり、かつ
重量の重い壁材もクレーンが設置場所まで接近できるの
でクレーンは小型でよく、柱のジャッキアップは地上で
行い、かつ柱を直接持ち上げるため床の補強を必要とし
ない。また柱は一本の連続柱としたので階毎に柱を接続
することなく、作業は連続に行わせることができる。[Explanation of action and effect] In the jack-up method of the building configured as above, the assembly of each floor can be done on the ground, the work at height is eliminated, the concrete pump truck is not required, and the lifting machine is a mobile type on the ground. Cranes are sufficient, and even heavy wall materials allow the cranes to approach the installation site, so the cranes can be small in size, the pillars are jacked up on the ground, and the pillars are lifted directly without the need for floor reinforcement. Also, since the pillars are one continuous pillar, the work can be performed continuously without connecting the pillars for each floor.
【0007】[0007]
【実施例】本発明の実施例につき図1から図15までを
参照して説明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to FIGS.
【0008】まず地表GLを整地して(図1)から所定
位置例えば建物の四隅にジャッキの基礎1を形成するコ
ンクリートを打設(図2)し、次にジャッキの基礎1の
所定位置に縦孔2を穿設して鋼管2Aを打設する(図
3)。この鋼管2Aは柱3の格納ビットとして使用する
ものであり、この場合建屋の地表高さと基礎部分の高さ
とを加えた長さを有している。建物の柱3は全階に通ず
る一本の連続柱として形成されていて、地表よりほぼ1
Fの高さ分だけ突出するようにして鋼管2Aに挿入さ
れ、ジャッキ4は基礎1に形成されたピット1Aに据え
付けられる(図4)。この状態で柱3の頂部3AにRF
床8とR−1Fスラブ10、RF−1壁11、RF−1
床12及びRF−1梁13がそれぞれ取り付けられると
ともに柱3の外側面にジャッキブラケット5がボルト及
びナットを介して取り外し可能に取り付けられる(図
5)。次にジャッキブラケット5の底面部をジャッキ4
で押し上げRF−1の躯体を上昇させる。1階分上昇し
た位置で仮受けブラケット6を柱3の内側面にボルト及
びナットを介して取り外し可能に取り付け、ジャッキ4
を縮小させても躯体が下降しないようにしておく(図
6)。ジャッキ4を縮小させ躯体の重量を仮受けブラケ
ット6で支持される状態にしてジャッキブラケット5を
取り外し、仮受けブラケット6の反対側の柱3の外側面
にジャッキブラケット5を付け変える(図7)。新位置
に付け変えられたジャッキブラケット5を僅かにジャッ
キアップして仮受けブラケット6を地表GLより隔離し
ておいて取り外した後ジャッキダウンさせ、躯体重量を
ジャッキブラケット5に受け持たせる。この状態でRF
−2壁21、RF−2床22及びRF−2梁23がそれ
ぞれ取り付けられRF−2の躯体工事が終了する(図
8)。次にジャッキブラケット5の底面部をジャッキ4
で押し上げ躯体を上昇させ(図9)、1階分上昇した位
置で仮受けブラケット6を柱3の内側面に取り付け(図
10)、ジャッキ4を縮小させ躯体の重量を仮受けブラ
ケット6により支持される状態にしてジャッキブラケッ
ト5を取り外し、仮受けブラケット6の反対側の柱3の
外側面に付け変え、新位置に付け変えられたジャッキブ
ラケット5を僅かにジャッキアップして仮受けブラケッ
ト6を地表GLより隔離しておいて取り外した後ジャッ
キダウンさせ、躯体重量をジャッキブラケット5に受け
持たせる。この状態でRF−3壁31、RF−3床32
及びRF−3梁33がそれぞれ取り付けられてRF−3
の躯体工事が終了する(図11)。このようにして、図
9から図11に至る手順を繰り返して図12に示すよう
に、1F壁91、1F床92及び必要ならば1F梁93
がそれぞれ取り付けられて1Fの躯体工事が終了し、図
13に示すように鋼管2A内にコンクリートが打設され
柱3が固着される。最後に図14に示すように柱3より
ジャッキブラケット5を取り外し、更にジャッキ4を撤
去したあとをコンクリートの中詰めをして躯体工事が完
成する。First, the ground surface GL is leveled (FIG. 1), and then concrete for forming the foundation 1 of the jack is placed at predetermined positions, for example, at the four corners of the building (FIG. 2), and then vertically at predetermined positions of the foundation 1 of the jack. The hole 2 is bored and the steel pipe 2A is driven (FIG. 3). The steel pipe 2A is used as a storage bit for the pillar 3, and in this case, has a length that is the sum of the height of the ground surface of the building and the height of the foundation portion. The pillar 3 of the building is formed as one continuous pillar that leads to all floors, and it is almost 1 from the ground surface.
The jack 4 is inserted into the steel pipe 2A so as to project by the height of F, and the jack 4 is installed in the pit 1A formed in the foundation 1 (FIG. 4). In this state, RF is applied to the top 3A of the pillar 3.
Floor 8 and R-1F slab 10, RF-1 wall 11, RF-1
The floor 12 and the RF-1 beam 13 are attached, respectively, and the jack bracket 5 is detachably attached to the outer surface of the column 3 via bolts and nuts (FIG. 5). Next, attach the bottom of the jack bracket 5 to the jack 4
Push up with to raise the body of RF-1. The temporary support bracket 6 is detachably attached to the inner surface of the pillar 3 via the bolts and nuts at the position raised by one floor, and the jack 4 is attached.
Make sure that the skeleton does not descend even if it is contracted (Fig. 6). The jack 4 is reduced so that the weight of the skeleton is supported by the temporary receiving bracket 6, the jack bracket 5 is removed, and the jack bracket 5 is attached to the outer surface of the column 3 on the opposite side of the temporary receiving bracket 6 (FIG. 7). . The jack bracket 5 relocated to the new position is slightly jacked up, the temporary receiving bracket 6 is isolated from the ground surface GL, removed, and then jacked down so that the weight of the body is carried by the jack bracket 5. RF in this state
-2 wall 21, RF-2 floor 22 and RF-2 beam 23 are attached, respectively, and the RF-2 frame construction is completed (Fig. 8). Next, attach the bottom of the jack bracket 5 to the jack 4
Push up to raise the skeleton (Fig. 9) and attach the temporary receiving bracket 6 to the inner surface of the pillar 3 at the position raised by one floor (Fig. 10), and reduce the jack 4 to support the weight of the skeleton by the temporary receiving bracket 6. State, the jack bracket 5 is removed, the jack bracket 5 is attached to the outer surface of the column 3 on the opposite side of the temporary support bracket 6, and the jack bracket 5 relocated to the new position is slightly jacked up to remove the temporary support bracket 6. After separating it from the ground surface GL and removing it, it is jacked down, and the weight of the body is carried by the jack bracket 5. In this state, the RF-3 wall 31 and the RF-3 floor 32
And RF-3 beam 33 are attached respectively to RF-3
The skeleton construction is completed (Fig. 11). In this way, the procedure from FIG. 9 to FIG. 11 is repeated, and as shown in FIG. 12, the 1F wall 91, the 1F floor 92 and the 1F beam 93 if necessary.
Are attached to complete the 1F frame work, and concrete is placed in the steel pipe 2A to fix the pillars 3 as shown in FIG. Finally, as shown in FIG. 14, the jack bracket 5 is removed from the pillar 3, and after the jack 4 is removed, the concrete is filled and the skeleton construction is completed.
【0009】以上説明に供した図によれば、柱3は建物
の四隅に建てられているが、建物が大形になればそれ以
外の適宜な箇所に増設して差し支えなく、その場合でも
適宜な箇所に増設した柱に対してそれぞれジャッキ4が
対応することはいうまでもない。According to the drawings provided above, the pillars 3 are built in the four corners of the building. However, if the building becomes large, it may be installed in any other suitable place, and even in that case, it is appropriate. It goes without saying that the jacks 4 correspond to the pillars added at various places.
【0010】[0010]
【発明の効果】本発明による建物のジャッキアップ工法
によれば、従来工法のようなタワークレーン、大型のブ
ーム式コンクリートポンプ車は不必要であり、かつ危険
な高所作業がなく安全であるという効果がある。According to the jacking-up method for a building according to the present invention, the tower crane and the large boom type concrete pump truck as in the conventional method are unnecessary, and there is no dangerous work at a high place and it is safe. effective.
【図1】建物の建設予定地の整地状態を示す図。FIG. 1 is a view showing a leveled state of a planned construction site of a building.
【図2】ジャッキ基礎を示す図。FIG. 2 is a diagram showing a jack foundation.
【図3】縦孔に鋼管を打設した状態を示す図。FIG. 3 is a view showing a state in which a steel pipe is placed in a vertical hole.
【図4】柱を鋼管に挿入しジャッキを据え付けた状態
図。FIG. 4 is a state diagram in which a pillar is inserted into a steel pipe and a jack is installed.
【図5】最上階の工事施工を説明する図。FIG. 5 is a diagram illustrating construction work on the top floor.
【図6】最初にジャッキアップした状態を示す図。FIG. 6 is a diagram showing a state where the jack-up is first performed.
【図7】ジャッキブラケットを付け変えた状態図。FIG. 7 is a state view in which the jack bracket is replaced.
【図8】次の階の工事施工を説明する図。FIG. 8 is a diagram for explaining the construction work on the next floor.
【図9】二番目にジャッキアップした状態を示す図。FIG. 9 is a view showing a second jacked-up state.
【図10】仮受けブラケットの取り付けを説明する図。FIG. 10 is a view for explaining the attachment of the temporary receiving bracket.
【図11】更なる次の階の工事施工を説明する図。FIG. 11 is a diagram for explaining construction work on a further next floor.
【図12】全階の工事施工を説明する図。FIG. 12 is a diagram illustrating construction work on all floors.
【図13】鋼管内にコンクリート打設した状態図。FIG. 13 is a state diagram in which concrete is placed in a steel pipe.
【図14】工事施工完成図。[Figure 14] Construction completion drawing.
1・・・ジャッキの基礎 1A・・・ピット 1F・・・地上階 2・・・縦孔 2A・・・鋼管 3・・・柱 4・・・ジャッキ 5・・・ジャッキブラケット 6・・・仮受けブラケット 8・・・RF床 10・・・R−1Fスラブ 10A・・・R−1F梁 11・・・R−1F壁 12・・・R−1F床 13・・・R−1F梁 21・・・R−2F壁 22・・・R−2F床 23・・・R−2F梁 31・・・R−3F壁 32・・・R−3F床 33・・・R−3F梁 91・・・地上階の壁 92・・・地上階の床 93・・・地上階の梁 GL・・・地表 RF・・・屋上階 RF−1・・・最上階 RF−2・・・最上階の下の階 RF−3・・・最上階の下の更に下の階 1 ... basic of jack 1A ... pit 1F ... ground floor 2 ... vertical hole 2A ... steel pipe 3 ... pillar 4 ... jack 5 ... jack bracket 6 ... tentative Receiving bracket 8 ... RF floor 10 ... R-1F slab 10A ... R-1F beam 11 ... R-1F wall 12 ... R-1F floor 13 ... R-1F beam 21. ..R-2F wall 22 ... R-2F floor 23 ... R-2F beam 31 ... R-3F wall 32 ... R-3F floor 33 ... R-3F beam 91 ... Ground floor wall 92 ... Ground floor 93 ... Ground floor GL ... Ground RF ... Rooftop RF-1 ... Top floor RF-2 ... Below top floor Floor RF-3 ... Floor below the top floor
Claims (1)
ブしながら一階より最上階まで順次施工する建物のジャ
ッキアップ工法において、所定位置の地中に形成された
縦孔に柱を挿入し、その柱をジャッキアップ可能に支持
し、地表より突出する柱に屋上階の床及び最上階のスラ
ブ、壁、床並びに梁等を取り付けた後は、一階の高さ分
だけジャッキアップして柱にスラブ、壁、床及び梁等を
取り付ける手順を繰り返すことを特徴とする建物のジャ
ッキアップ工法。1. A jack-up construction method for a building in which construction is performed sequentially from the first floor to the top floor while jacking up the roof floor constructed earlier, by inserting a pillar into a vertical hole formed in the ground at a predetermined position, and Supports pillars so that they can be jacked up, and after attaching the roof floor floor and slabs on the top floor, walls, floors, and beams to the pillars protruding from the ground, jack up only the height of the first floor to form pillars. A jack-up method for buildings, characterized by repeating the steps of attaching slabs, walls, floors, beams, etc.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP154093A JPH06200626A (en) | 1993-01-08 | 1993-01-08 | Jacking-up method for building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP154093A JPH06200626A (en) | 1993-01-08 | 1993-01-08 | Jacking-up method for building |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH06200626A true JPH06200626A (en) | 1994-07-19 |
Family
ID=11504362
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP154093A Pending JPH06200626A (en) | 1993-01-08 | 1993-01-08 | Jacking-up method for building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH06200626A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109898664A (en) * | 2019-02-02 | 2019-06-18 | 高继良 | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure |
-
1993
- 1993-01-08 JP JP154093A patent/JPH06200626A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109898664A (en) * | 2019-02-02 | 2019-06-18 | 高继良 | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10829927B2 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
| JPH1061193A (en) | Method of building steel frame structure and device therefor | |
| JPH06200626A (en) | Jacking-up method for building | |
| JPH04161566A (en) | Constructing apparatus for large space building | |
| GB2055130A (en) | Method of raising buildings | |
| JPH08270081A (en) | Construction method of frame structure | |
| JP2696486B2 (en) | Building construction method | |
| JPH0932120A (en) | Method of construction of structure | |
| JP2946372B2 (en) | Construction method of structure | |
| JPH04161565A (en) | Construction of large space building | |
| JPH08218628A (en) | Construction of roof for cylindrical structure | |
| JP2751988B2 (en) | Building construction equipment | |
| JPH06101348A (en) | How to build a tower | |
| JP3263504B2 (en) | Construction method of tower structure | |
| JP2761528B2 (en) | How to build structures | |
| JPH03235838A (en) | Lift up method of construction using temporary pillar | |
| JP3416759B2 (en) | Underground structure frame building equipment | |
| JP3002054U (en) | Tower crane with multiple main columns as tower mast | |
| JPH0874278A (en) | Construction method for large underground space | |
| JP2761526B2 (en) | How to build structures | |
| JPH06101280A (en) | Erection method | |
| JP3060333B2 (en) | Construction method of building frame | |
| JPH0485427A (en) | Composite building construction of medium-high-building and low building | |
| JPS63147037A (en) | Building construction method | |
| JPH0874279A (en) | Construction method for large underground space |