JPH062329A - Shoring and cut-off method by underground continuous wall - Google Patents
Shoring and cut-off method by underground continuous wallInfo
- Publication number
- JPH062329A JPH062329A JP4157867A JP15786792A JPH062329A JP H062329 A JPH062329 A JP H062329A JP 4157867 A JP4157867 A JP 4157867A JP 15786792 A JP15786792 A JP 15786792A JP H062329 A JPH062329 A JP H062329A
- Authority
- JP
- Japan
- Prior art keywords
- underground
- continuous wall
- underground continuous
- wall
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
(57)【要約】 (修正有)
【目的】 地下構造物における地中連続壁による山留
め、止水工法を提供する。
【構成】 この発明の地中連続壁による山留め、止水工
法は、深い部分にある不透水層4に達する地中連続壁1
をまず構築し、その内側、または外側に土圧、水圧に対
する抵抗力として必要な深さまで地中連続壁2,3を重
ねて構築する方法と、深い部分にある不透水層4に達す
る地中連続壁をまず構築し、次に、その内側または外側
に、地中連続壁と直角方向に一体化して土圧、水圧に対
する抵抗力として必要な深さまで地中連続壁2を構築
し、さらにその地中連続壁3と直角方向に一体化して同
じ深さまで地中連続壁を構築する方法である。
(57) [Summary] (Corrected) [Purpose] To provide a retaining method and a waterproofing method for underground structures using continuous underground walls. [Structure] The earth retaining and water stopping method of the underground continuous wall of the present invention is based on the underground continuous wall 1 reaching the impermeable layer 4 in the deep portion.
First, the method of building the underground continuous walls 2 and 3 on the inside or outside to the depth required as resistance to earth pressure and water pressure, and the underground to reach the impermeable layer 4 in the deep part. The continuous wall is first constructed, and then, inside or outside thereof, is integrated with the underground continuous wall at a right angle to the underground continuous wall 2 to a depth required as a resistance force against earth pressure and water pressure. This is a method in which the underground continuous wall 3 is integrated at right angles to construct the underground continuous wall to the same depth.
Description
【0001】[0001]
【産業上の利用分野】この発明はLNGや原油の地下タ
ンク、シールドトンネルの縦坑、その他の地下構造物に
おける地中連続壁による山留め、止水工法である。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is an underground tank for LNG or crude oil, a vertical shaft for shield tunnels, or a mountain retaining by a continuous underground wall in a subterranean structure or a waterproofing method.
【0002】[0002]
【発明が解決しようとする課題】地下構造物がどんどん
大型化しており、例えば、LNGの地下タンクの場合で
20年前に容量60,000KLだったものが、最近で
は容量200,000KLが建設されている。また、原
油の地下タンクは、容量350,000KLが建設され
ている。大型の地下構造物の場合、大きな土圧、水圧を
受けることから、ほとんどの場合地中連続壁による山留
め、止水工法が採用されている。The underground structure is becoming larger and larger. For example, in the case of an LNG underground tank, the capacity of 60,000 KL 20 years ago was recently constructed to be 200,000 KL. ing. The underground tank for crude oil has a capacity of 350,000 KL. In the case of large underground structures, large earth pressure and water pressure are applied. Therefore, in most cases, the earth retaining and water stopping methods using continuous underground walls are used.
【0003】地中連続壁は、地中に短冊型の鉄筋コンク
リートの壁を連続して造り、土圧、水圧に抵抗するとと
もに、その連続した壁で止水性を確保するものである。
一般に、地中連続壁の上部においては、土圧、水圧に対
する抵抗力が期待されるのに対して、下部は止水性のみ
が期待される。The continuous underground wall is a continuous strip-shaped reinforced concrete wall constructed in the ground to resist earth pressure and water pressure, and to secure water stopping performance by the continuous wall.
In general, the upper part of the underground wall is expected to have resistance to earth pressure and water pressure, whereas the lower part is expected to have only water stoppage.
【0004】掘削する機械の関係から、地中連続壁は一
定の壁厚で構築されるのが一般的であるが、地中連続壁
の上部および下部における機能を考えると、下部におい
ては薄い地中連続壁で十分であり、上部の土圧、水圧に
対して必要な厚い壁厚を下部まで同じ寸法でつくること
は不経済である。Due to the excavating machine, the continuous underground wall is generally constructed with a constant wall thickness, but considering the functions of the upper and lower portions of the continuous underground wall, the underground continuous wall is thin. A medium continuous wall is sufficient, and it is uneconomical to make the thick wall thickness necessary for earth pressure and water pressure in the upper part to the same size in the lower part.
【0005】この問題を解決するため、変断面地中連続
壁が開発されており、特開昭59−154217が当社
から出願されている。In order to solve this problem, an underground continuous wall with a variable cross section has been developed and Japanese Patent Application Laid-Open No. 59-154217 has been filed.
【0006】この工法は、鉄筋コンクリート製の一体構
造である変断面地中連続壁を構築するものであり、変断
面に地中を掘削した後、掘削形状に応じた鉄筋籠を建て
込み、コンクリートを打設する。この工法は、以下の問
題点がある。This method is for constructing an underground continuous wall with a variable cross section, which is an integrated structure made of reinforced concrete. To set. This construction method has the following problems.
【0007】すなわち断面変化部分で掘削面の肌落ちが
生じやすく、止水性の確保が難しい。That is, the skin of the excavated surface is liable to be removed at the portion where the cross section changes, and it is difficult to secure the waterproofness.
【0008】また掘削に長時間を要するため、孔壁の安
定確保が難しい。Further, since it takes a long time to excavate, it is difficult to secure a stable hole wall.
【0009】また壁厚の大きい掘削機械で上部を掘削し
た後、掘削機械を変え、壁厚の小さい下部を掘削するた
め、2種類の掘削機械が必要となる。In addition, after excavating the upper part with an excavating machine having a large wall thickness, the excavating machine is changed to excavate the lower part having a small wall thickness, so that two types of excavating machines are required.
【0010】さらに横方向の鉄筋をラップさせる場合
に、鉄筋籠の挿入が困難である。Further, when the reinforcing bars in the lateral direction are wrapped, it is difficult to insert the reinforcing bar cage.
【0011】この発明は前記問題点を解消すべく開発し
た工法である。The present invention is a method developed to solve the above problems.
【0012】[0012]
【課題を解決するための手段】この発明の地中連続壁に
よる山留め、止水工法は、深い部分にある不透水層に達
する地中連続壁をまず構築し、その内側、または外側に
土圧、水圧に対する抵抗力として必要な深さまで地中連
続壁を構築し、この作業を必要な壁厚が確保できるまで
繰り返す方法と、深い部分にある不透水層に達する地中
連続壁をまず構築し、次に、その内側または外側に、地
中連続壁と直角方向に一体化して土圧、水圧に対する抵
抗力として必要な深さまで地中連続壁を構築し、さらに
その地中連続壁と直角方向に一体化して同じ深さまで地
中連続壁を構築する方法である。According to the earth retaining and water stopping method of the underground continuous wall of the present invention, the underground continuous wall reaching the impermeable layer in the deep portion is first constructed, and the earth pressure is applied to the inside or outside of the underground continuous wall. The method of constructing a continuous underground wall to the depth required for resistance to water pressure and repeating this work until the required wall thickness is secured, and first constructing a continuous underground wall reaching the impermeable layer in the deep part. , Next, inside or outside, it is integrated with the underground continuous wall in the direction perpendicular to it to build the underground continuous wall to the depth required as resistance to earth pressure and water pressure, and in the direction perpendicular to the underground continuous wall. It is a method to build a continuous underground wall to the same depth.
【0013】[0013]
【実施例】1番目の発明は重ね方式地中接続壁であり、
深い部分にある不透水層4に達する地中連続壁1をまず
構築する。その内側、または外側に土圧、水圧に対する
抵抗力として必要な深さまで地中連続壁2を構築する。
この作業を必要な壁厚が確保できるまで繰り返す。また
地中連続壁1と2の間は必要に応じてグラウトする。さ
らに断熱性を良くするため連続壁2は例えばパーライト
を混入したコンクリート(パーライトコンクリート)の
ようにポーラスなコンクリートを打設してもよい。[First Embodiment] The first invention is a superposition type underground connection wall,
First, the underground continuous wall 1 reaching the impermeable layer 4 in the deep part is constructed. The underground continuous wall 2 is constructed inside or outside to a depth required as a resistance force against earth pressure and water pressure.
This process is repeated until the required wall thickness is secured. Also, grout between the underground continuous walls 1 and 2 as needed. Further, in order to improve the heat insulating property, the continuous wall 2 may be made of porous concrete such as concrete mixed with pearlite (perlite concrete).
【0014】2番目の発明は井桁方式地中連続壁であ
り、深い部分にある不透水層4に達する地中連続壁1を
まず構築する。次に、その内側または外側に、地中連続
壁1と直角方向に一体化して土圧、水圧に対する抵抗力
として必要な深さまで地中連続壁2を構築する。さら
に、地中連続壁2と直角方向に一体化して地中連続壁2
と同じ深さまで地中連続壁3を構築する。The second aspect of the present invention is a double girder underground continuous wall, and the underground continuous wall 1 reaching the impermeable layer 4 in the deep portion is first constructed. Next, the underground continuous wall 2 is integrated with the underground continuous wall 1 in the direction perpendicular to the inside or outside thereof, and the underground continuous wall 2 is constructed to a depth required as a resistance force against earth pressure and water pressure. Furthermore, the underground continuous wall 2 is integrated with the underground continuous wall 2 at a right angle.
The underground wall 3 is constructed to the same depth as.
【0015】その後、円筒形の山留めなど軸圧縮力が卓
越する場合には、土圧、水圧に対する抵抗力として必要
な深さまで井桁の内部を掘削しコンクリートに置き換え
る。After that, when the axial compressive force is predominant, such as a cylindrical mountain clasp, the inside of the girder is excavated and replaced with concrete to a depth required as resistance to earth pressure and water pressure.
【0016】また、必要に応じて1番目の発明のように
連続壁1と3の間の2で区切られた部分に上記の断熱を
目的として材料を打設する。If necessary, as in the first aspect of the invention, a material is placed in the area between the continuous walls 1 and 3 divided by 2 for the purpose of the heat insulation.
【0017】[0017]
【発明の効果】この発明は以上の構成からなり、同じ壁
厚の地中連続壁となるため掘削機械が一種類で済み、機
械の効率的な運用ができ、工事費の低減が図れる。EFFECTS OF THE INVENTION The present invention has the above-described structure. Since the underground wall has the same wall thickness, only one type of excavating machine is required, the machine can be operated efficiently, and the construction cost can be reduced.
【0018】また掘削の終了した部分から順次コンクリ
ートを打設していくため、孔壁の安定が確保しやすい。Further, since the concrete is sequentially placed from the portion where the excavation is completed, it is easy to ensure the stability of the hole wall.
【0019】また汎用の掘削機械が使用できるため、機
械の調達が容易であり、費用が安い。Since a general-purpose excavating machine can be used, it is easy to procure the machine and the cost is low.
【0020】また従来の地中連続壁と同様の止水性が確
保される。Further, the same waterproofness as the conventional continuous underground wall is secured.
【0021】さらに必要とされる山留の規模に応じて、
土圧、水圧に対する抵抗力として必要な深さまで、前記
重ね方式地中連続壁であれば地中連続壁の数をふやすこ
とにより、前記井桁方式地中連続壁であれば井桁の数を
増やすことにより容易に対応できる。Further, depending on the scale of the Yamadome required,
Increase the number of double girders in the double girder type underground continuous wall by increasing the number of underground continuous walls in the pile type continuous continuous wall to the depth required as resistance to earth pressure and water pressure. Can be handled more easily.
【図1】1番目の発明の実施例で(a) は横断面図、(b)
は一部縦断面図である。FIG. 1A is a cross-sectional view of the first embodiment of the invention, and FIG.
FIG. 4 is a partial vertical sectional view.
【図2】2番目の発明の実施例(a) は横断面図、(b) は
一部縦断面図である。2A and 2B are a horizontal sectional view and a partial vertical sectional view, respectively, of an embodiment (a) of the second invention.
1,2,3…地中連続壁、4…不透水層。 1,2,3 ... Continuous underground wall, 4 ... Impermeable layer.
Claims (2)
続壁をまず構築し、その内側、または外側に土圧に対す
る抵抗力として必要な深さまで地中連続壁を構築し、こ
の作業を必要な壁厚が確保できるまで繰り返すことを特
徴とする地中連続壁による山留め、止水工法。1. An underground continuous wall that reaches an impermeable layer in a deep portion is first constructed, and then an underground continuous wall is constructed inside or outside the soil to a depth required for resistance to earth pressure. A mountain retaining and water stopping method using a continuous underground wall, which is repeated until the required wall thickness is secured.
続壁をまず構築し、次に、その内側または外側に、地中
連続壁と直角方向に一体化して土圧、水圧に対する抵抗
力として必要な深さまで地中連続壁を構築し、さらにそ
の地中連続壁と直角方向に一体化して同じ深さまで地中
連続壁を構築することを特徴とする地中連続壁による山
留め、止水工法。2. The underground continuous wall reaching the impermeable layer in the deep portion is first constructed, and then, inside or outside thereof, integrated with the underground continuous wall in a direction perpendicular to the earth continuous wall, and resistance to earth pressure and water pressure. The underground continuous wall is built up to the required depth, and the underground continuous wall is integrated at right angles to the same depth to build the underground continuous wall to the same depth. Construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP04157867A JP3099521B2 (en) | 1992-06-17 | 1992-06-17 | Construction method of mountain retaining and water blocking wall with underground continuous wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP04157867A JP3099521B2 (en) | 1992-06-17 | 1992-06-17 | Construction method of mountain retaining and water blocking wall with underground continuous wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH062329A true JPH062329A (en) | 1994-01-11 |
| JP3099521B2 JP3099521B2 (en) | 2000-10-16 |
Family
ID=15659139
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP04157867A Expired - Fee Related JP3099521B2 (en) | 1992-06-17 | 1992-06-17 | Construction method of mountain retaining and water blocking wall with underground continuous wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3099521B2 (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2007046399A (en) * | 2005-08-12 | 2007-02-22 | Takenaka Komuten Co Ltd | Earth retaining wall of double structure, its construction method, and horizontal multi-spindle rotary soil improvement device |
| CN101914920A (en) * | 2010-08-11 | 2010-12-15 | 山西太钢不锈钢股份有限公司 | Well Drilling and Dewatering Construction Method for Protecting Groundwater Level of Adjacent Buildings |
| JP5537719B1 (en) * | 2013-09-02 | 2014-07-02 | 秀樹 中込 | Fluid porous concrete |
| JP2015229822A (en) * | 2014-06-03 | 2015-12-21 | 大成建設株式会社 | Earth retaining structure and method for constructing earth retaining structure |
-
1992
- 1992-06-17 JP JP04157867A patent/JP3099521B2/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2007046399A (en) * | 2005-08-12 | 2007-02-22 | Takenaka Komuten Co Ltd | Earth retaining wall of double structure, its construction method, and horizontal multi-spindle rotary soil improvement device |
| CN101914920A (en) * | 2010-08-11 | 2010-12-15 | 山西太钢不锈钢股份有限公司 | Well Drilling and Dewatering Construction Method for Protecting Groundwater Level of Adjacent Buildings |
| JP5537719B1 (en) * | 2013-09-02 | 2014-07-02 | 秀樹 中込 | Fluid porous concrete |
| WO2015030051A1 (en) * | 2013-09-02 | 2015-03-05 | NAKAGOMI Hideki | Porous concrete having fluidity |
| JP2015048282A (en) * | 2013-09-02 | 2015-03-16 | 秀樹 中込 | Fluid porous concrete |
| JP2015229822A (en) * | 2014-06-03 | 2015-12-21 | 大成建設株式会社 | Earth retaining structure and method for constructing earth retaining structure |
Also Published As
| Publication number | Publication date |
|---|---|
| JP3099521B2 (en) | 2000-10-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2000352296A (en) | Method o constructing passage just under underground structure | |
| JPH062329A (en) | Shoring and cut-off method by underground continuous wall | |
| JP6869862B2 (en) | Wall construction method and wall | |
| JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
| KR100779988B1 (en) | Construction method of small diameter pile | |
| KR970002571B1 (en) | Process for defensing earth with the arch shape blocking pile in basement construction | |
| JPH0613770B2 (en) | Method of constructing mountain retaining wall with parent pile | |
| KR20090016237A (en) | Earthen construction | |
| JPH09111754A (en) | Parent pile water stop wall construction method | |
| JPS6018769B2 (en) | Construction method of underground structure | |
| JPS62220616A (en) | Construction work for underground space | |
| JP2688101B2 (en) | Continuous underground wall | |
| JPS61186623A (en) | Method of building foundation of building | |
| JPS5869924A (en) | Construction of sheathing wall having upper part consisting of underground continuous wall and lower part of pillar-row pile | |
| JP2675858B2 (en) | Vertical shaft excavation method | |
| JP3608175B2 (en) | Yamadome method | |
| JPH03224999A (en) | Construction methods for large-section underground cavities and large-section tunnels | |
| JPH0598633A (en) | Steel underground continuous wall and construction method thereof | |
| JPH03206213A (en) | Construction method of earth support | |
| JPH11200361A (en) | Core material for earth retaining and wall surface member for earth retaining | |
| JPS61191716A (en) | Method of building sheathing wall in open excavating process | |
| JPS6243009B2 (en) | ||
| JPH04269210A (en) | Construction method of underground continuous wall | |
| JPS6020531B2 (en) | How to build a retaining wall | |
| JPS5826124A (en) | Construction of retaining wall for basement |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 19991116 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20000718 |
|
| LAPS | Cancellation because of no payment of annual fees |