JPH063881Y2 - Concrete formwork for concrete foundation construction - Google Patents

Concrete formwork for concrete foundation construction

Info

Publication number
JPH063881Y2
JPH063881Y2 JP12112187U JP12112187U JPH063881Y2 JP H063881 Y2 JPH063881 Y2 JP H063881Y2 JP 12112187 U JP12112187 U JP 12112187U JP 12112187 U JP12112187 U JP 12112187U JP H063881 Y2 JPH063881 Y2 JP H063881Y2
Authority
JP
Japan
Prior art keywords
concrete
foundation
formwork
mold
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP12112187U
Other languages
Japanese (ja)
Other versions
JPS6426461U (en
Inventor
努 本間
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP12112187U priority Critical patent/JPH063881Y2/en
Publication of JPS6426461U publication Critical patent/JPS6426461U/ja
Application granted granted Critical
Publication of JPH063881Y2 publication Critical patent/JPH063881Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Reinforcement Elements For Buildings (AREA)

Description

【考案の詳細な説明】 産業上の利用分野 この考案は、コンクリート基礎構築に使用されるコンク
リート型枠に関するものである。
TECHNICAL FIELD The present invention relates to a concrete formwork used for constructing a concrete foundation.

従来技術とその欠点 従来、コンクリート製基礎を構築するには、設置位置の
地均しを行った後、コンクリートで安定板を打設し、そ
の養生後、木板製又は金属板製の型枠を組み立て、その
型枠内に鉄筋などを組み入れて、生コンクリートを型枠
内に投入して基礎を形成し、その養生固化後に型枠の取
外しを行い、安定板の埋め戻しをしていた。
Conventional technology and its drawbacks Conventionally, in order to construct a concrete foundation, after leveling the installation position, a stable board is placed with concrete, and after curing, a wooden board or metal plate formwork is used. After assembling, incorporating reinforcing bars and the like into the mold, raw concrete was put into the mold to form a foundation, and after curing and solidification, the mold was removed and the stabilizer was backfilled.

上記のように、従来は、現場で、型枠組み立てを行い、
投入した生コンクリートの養生固化後に型枠取外しを行
う必要があったから、現場作業が非常に面倒であり、か
つ、多くの時間を要し、とくに現場作業時間に占める型
枠取扱い時間の割合は比較的多く、また、型枠の資材倉
庫などと現場との間の往復搬送にかかる運賃及び現場で
の仕掛にかかる工賃が高く付く欠点があった。
As mentioned above, conventionally, on-site formwork assembly,
Since it was necessary to remove the formwork after curing and solidifying the poured ready-mixed concrete, on-site work was very troublesome and required a lot of time, and the ratio of the formwork handling time to the on-site work time was compared. However, there is a drawback in that the fare required for round-trip transportation between the material warehouse of the formwork and the site and the labor cost required for the work in process on the site are high.

また、防災設備の緊急な建設が必要な場合や、山岳地帯
など地理的気候的条件の厳しい場所に建造物を構築する
場合は、可及的短期間の基礎構築が要請されるが、従来
の型枠を用いる工法では、どうしても工期の面において
上記要請に応えることは困難であった。
In addition, when urgent construction of disaster prevention facilities is required, or when constructing buildings in places with severe geographical and climatic conditions such as mountainous areas, it is required to build a foundation for the shortest possible time. It was difficult for the construction method using a formwork to meet the above requirements in terms of construction period.

解決しようとする技術課題 この考案は、上記の点に鑑み、鉄筋コンクリート製型枠
を工場で製造し、これを基礎構築現場に搬送・設置し、
これを基礎の補強部材の設置基準及び支持部材として使
用し、かつ、コンクリート投入後は養生固化によりその
型枠を基礎に一体に接合して基礎の一部とすることによ
りにより、現場における型枠組立て及び基礎コンクリー
ト打設後の型枠取外し作業を不要化して、運賃及び工賃
の低減、及び工期の著しい短縮を可能にしたコンクリー
ト基礎構築用コンクリート型枠を提供しようとするもの
である。
Technical problem to be solved In view of the above points, the present invention manufactures a reinforced concrete formwork in a factory, transports it to a foundation construction site, and installs it.
By using this as an installation standard and support member for the reinforcing member of the foundation, and after adding concrete, the mold is integrally joined to the foundation by curing and solidification to form a part of the foundation so that It is an object of the present invention to provide a concrete formwork for constructing a concrete foundation by eliminating the work of removing the formwork after the assembling and the placing of the foundation concrete, and reducing the freight and labor cost and the construction period significantly.

課題解決手段 上記の課題を解決するため、この考案では、第一に、型
枠を鉄筋コンクリートで角筒状又は円筒状に形成し、内
部に生コンクリートを投入して基礎を打設できるように
した。第二に、型枠の内壁面より内側に突出する補強用
リブを設けた。第三に、前記リブは使用時にコンクリー
ト基礎内に配設される鉄筋の被り厚さを設定するスペー
サを兼ねるようにした。
Means for Solving the Problems In order to solve the above-mentioned problems, in the present invention, firstly, a form is formed of reinforced concrete into a rectangular tube shape or a cylindrical shape, and ready-cast concrete can be poured into the interior of the formwork to make a foundation. . Secondly, a reinforcing rib protruding inward from the inner wall surface of the mold is provided. Thirdly, the ribs also serve as spacers for setting the covering thickness of the reinforcing bars arranged in the concrete foundation during use.

作用 上記型枠内周面に突設されたリブは、コンクリート壁の
引張り力に対して弱い欠点が排除され、投入されるコン
クリートに対する耐圧力を確保する。また、リブにより
型枠内に形成される基礎の鉄筋の被り厚さを容易かつ確
実に設定することができる。また、型枠内に投入した生
コンクリートが養成固化した場合は、前記型枠が基礎に
一体に接合し、これを補強する。
Action The rib projectingly provided on the inner peripheral surface of the mold eliminates a weak point against the tensile force of the concrete wall and secures the pressure resistance against the concrete to be poured. Further, the covering thickness of the reinforcing bar of the base formed in the mold by the ribs can be easily and surely set. Further, when the ready-mixed concrete put into the mold is cured and solidified, the mold is integrally joined to the foundation to reinforce it.

この考案の実施例 次に、この考案の実施例を、この考案に係る型枠を使用
してコンクリート基礎を構築する旋工例の工程順に沿っ
て、図面に基いて説明する。
Embodiment of the Invention Next, an embodiment of the invention will be described with reference to the drawings in the order of steps of a lathe example in which a concrete foundation is constructed using a mold according to the invention.

[第一工程](型枠製作) この考案に係る鉄筋コンクリート型枠は、まず、コンク
リート基礎構築の予備工程として、予め工場において製
作される。この型枠の製作方法は従来方法と同様であ
り、第1図に示すように、内外の金属板又は木板製の型
枠1,2を用いて、その型枠内に格子状に接合した補強
用鉄筋3をそれが型枠内の中央に位置するようにセット
したのち、型枠1,2内にコンクリートを流入充填させ
て養生し、固化後に型枠を取外して、第3図に示すよう
な鉄筋コンクリート型枠Aを製造する。
[First Step] (Form Making) The reinforced concrete form according to the present invention is first made in a factory in advance as a preliminary step for constructing a concrete foundation. The method of manufacturing this formwork is the same as the conventional method, and as shown in FIG. 1, the formwork 1 and 2 made of metal plates or wooden boards inside and outside are used to reinforce the formwork in a lattice shape. After setting the reinforcing bar 3 so that it is located in the center of the mold, concrete is poured into the molds 1 and 2 for curing, and after solidification, the mold is removed, and as shown in FIG. A reinforced concrete formwork A is manufactured.

型枠Aは基礎の外見に対する要望により、又は、基礎の
上に設けられる建造物の形状により、あるいは地中梁と
の接合位置により、多角筒状又は円筒状に成形される。
鉄筋3のコーナー部付近又は円筒形の型枠の場合は円筒
中心に関して対称位置に、上方に延びる吊り輪4を予め
接合しておき、コンクリート型枠製作後にその吊り輪4
を型枠Aから突出させてある。
The form A is formed into a polygonal cylindrical shape or a cylindrical shape depending on the appearance of the foundation, the shape of the building provided on the foundation, or the position of connection with the underground beam.
Near the corners of the reinforcing bars 3 or in the case of a cylindrical form, a suspension ring 4 extending upward is preliminarily joined at a symmetrical position with respect to the center of the cylinder, and the suspension ring 4 is produced after the concrete form is manufactured.
Are projected from the form A.

また、コンクリート型枠Aには、第2図に示すように、
その内壁面から突出し、上記鉄筋3の一部である横筋が
埋設されたリブ5が、型枠の高さ方向に適宜の間隔をも
って設けられている。このリブ5は、後述されるよう
に、第一には、型枠A自体の壁面に対して直角な方向の
力に対する強度を補強して、この型枠内に流入されるコ
ンクリートに対する耐圧力を確保すること、第二に、こ
の型枠内に設けられる基礎の鉄筋及びアンカーなどの被
り厚さ(型枠内に投入されるコンクリートが鉄筋などを
覆う厚さ)を決定すること、の二つの機能を果たすため
に設けられている。
Further, as shown in FIG. 2, the concrete form A is
Ribs 5 that project from the inner wall surface and in which the horizontal bars that are a part of the reinforcing bars 3 are embedded are provided at appropriate intervals in the height direction of the mold. As will be described later, the rib 5 firstly reinforces the strength against the force in the direction perpendicular to the wall surface of the mold A itself, and increases the pressure resistance against the concrete flowing into the mold. Secondly, to secure, and secondly, to determine the covering thickness of the reinforcing bars and anchors of the foundation provided in this formwork (the thickness of the concrete that is put into the formwork to cover the reinforcing bars). It is provided to perform the function.

[第二工程](型枠搬送・現場設置) コンクリート基礎を構築するときは、上記コンクリート
型枠Aを搬送装置により基礎建設現場まで搬送して、所
定位置に設置する。
[Second Step] (Form Transfer / Site Installation) When constructing a concrete foundation, the concrete form A is transferred to a foundation construction site by a transfer device and installed at a predetermined position.

型枠Aは上記のように吊り輪4を有するので、第3図に
示すように、各吊り輪4にワイヤロープ6などの先端に
固着したフック7を引っ掛け、そのロープを固定クレー
ン、車上クレーン、ヘリコプターなどで上げ下げして、
型枠を容易にトラックその他の搬送装置に積み卸しして
現場まで移送することができる。また、現場でも簡単に
所定位置に設置することができる。
Since the form A has the suspension wheels 4 as described above, as shown in FIG. 3, the hooks 7 fixed to the ends of the wire ropes 6 are hooked on each suspension wheel 4, and the ropes are fixed on the crane or on the vehicle. Raise and lower with a crane, helicopter, etc.,
The formwork can be easily loaded and unloaded on a truck or other transfer device and transferred to the site. Further, it can be easily installed at a predetermined position even on site.

基礎建設現場の所定位置に設置するには、その位置を必
要に応じて地均しをし、そこに型枠Aを所定の方向とレ
ベルを取って設置する。通常は、基礎の底部に鉄筋コン
クリート製安定板が設けられる。この場合は、第4図に
示すように、地均しをしたのち、型枠位置決め枠8を地
中に固定し、その型枠位置決め枠にコンクリート型枠A
を載せて正確な方向とレベルを設定し、型枠位置決め枠
8の周囲に安定板用鉄筋9及び型枠10を配設すること
となる。
In order to install at a predetermined position on the foundation construction site, the position is leveled if necessary, and the form A is installed at a predetermined direction and level there. Normally, a reinforced concrete stabilizer is provided at the bottom of the foundation. In this case, as shown in FIG. 4, after leveling the ground, the formwork positioning frame 8 is fixed in the ground, and the concrete formwork A is attached to the formwork positioning frame.
Then, the correct direction and level are set, and the stabilizer reinforcing bar 9 and the mold 10 are arranged around the mold positioning frame 8.

[第三工程](配筋・アンカー設置) 上記のようにして型枠Aの設置を終了した後は、第4図
及び第5図に示すように、この型枠A内に基礎補強用鉄
筋11及び建造物固定用アンカーボルト12を配設す
る。コンクリート型枠Aは成形後の変形率が少ないの
で、鉄筋11を型枠の内面に突設してあるリブ5に当接
することによりその被り厚さを容易に確保することがで
き、また、アンカー支持部材13を介してアンカー12
の型枠上端部内面からの距離を設定して、所要位置にお
いて固定することにより、アンカー設置位置を容易にか
つ、正確に決めることができる。吊り輪4はアンカー支
持部材の位置決めにも利用することができる。
[Third step] (Installation of rebar / anchor) After the installation of the form A is completed as described above, as shown in Figs. 4 and 5, the reinforcing bar for foundation reinforcement is placed in the form A. 11 and an anchor bolt 12 for fixing the building are arranged. Since the concrete form A has a low deformation rate after forming, the covering thickness can be easily secured by abutting the reinforcing bar 11 on the rib 5 protruding on the inner surface of the form, and the anchor Anchor 12 via support member 13
The anchor installation position can be easily and accurately determined by setting the distance from the inner surface of the upper end of the mold and fixing it at a required position. The suspension ring 4 can also be used for positioning the anchor support member.

[第四工程](コンクリート投入・養生) 上記のようにして、型枠A内への鉄筋11及びアンカー
ボルト12の設置を終了したならば、次に、型枠A内に
生コンクリートを投入し、充填する。基礎の下部に安定
板4を打設する場合は、最初に生コンクリートを型枠A
の周囲の型枠10内に投入して、その表面を均し、続い
て、型枠A内にコンクリートを投入してその底部から安
定板形成用空間に流下充填し、これに続いて投入される
生コンクリートを型枠A内に充填する。この場合、型枠
の内壁面に、流動するコンクリートの圧力が加わるが、
型枠は上記リブ5を有してコンクリート壁の弱点を排除
され、十分な耐圧力性を備えているので、型枠の壁部分
の厚みを比較的薄くしても強度的には問題がない。従っ
て、型枠の壁を薄くして型枠の総重量を軽くし、搬送負
荷の軽減を図ることが可能である。
[Fourth Step] (Concrete Filling / Curing) After the installation of the reinforcing bars 11 and the anchor bolts 12 in the form A is completed as described above, next, the concrete is placed in the form A. , Fill. When placing the stabilizer 4 on the lower part of the foundation, first mix ready-mixed concrete with form A
It is thrown into the mold 10 around and the surface is leveled. Then, concrete is thrown into the mold A to flow down and fill the space for forming the stabilizer from the bottom of the mold A. Fill the mold A with ready-mixed concrete. In this case, the pressure of flowing concrete is applied to the inner wall surface of the form,
Since the formwork has the ribs 5 to eliminate the weak points of the concrete wall and has sufficient pressure resistance, there is no problem in strength even if the wall part of the formwork is made relatively thin. . Therefore, it is possible to make the wall of the mold thin to reduce the total weight of the mold and reduce the transport load.

型枠A内に投入したコンクリートが固化すれば、アンカ
ー支持部材13を除去することにより、第6図に示すよ
うに、所望の基礎Bが完成する。安定板14を同時に成
形した場合は、必要ならば養生固化後に安定板形成用型
枠10を取外したのち、基礎の周囲を埋め戻して安定板
14を土砂で覆う。安定板形成用型枠を取外す必要がな
い場合あるいはその時間的余裕がない場合は、型枠Aへ
の生コンクリート投入を終了した時点で、原則として基
礎建設の旋工は完了である。
When the concrete put into the mold A is solidified, the anchor support member 13 is removed, and the desired foundation B is completed as shown in FIG. When the stabilizer 14 is molded at the same time, the stabilizer forming frame 10 is removed after curing and solidification if necessary, then the periphery of the foundation is backfilled and the stabilizer 14 is covered with earth and sand. If it is not necessary to remove the stabilizer forming frame or there is not enough time to do so, at the time when the injection of ready-mixed concrete into the form A is completed, the foundation construction is basically completed.

第6図は安定板14を同時に形成した基礎Bの完成状態
を示す斜視図であり、基礎の外周には型枠Aが一体に接
合され、基礎の上面にはアンカーボルト12が突出して
いる。従って、この基礎の上に、第7図に例示するよう
に、アンカーボルトとナットを用いて建造物Cを固定す
ることができる。
FIG. 6 is a perspective view showing a completed state of the foundation B on which the stabilizer 14 is simultaneously formed. The form A is integrally joined to the outer periphery of the foundation, and the anchor bolt 12 projects from the upper surface of the foundation. Therefore, the building C can be fixed on this foundation by using anchor bolts and nuts as illustrated in FIG. 7.

吊り輪4は、基礎完成後も、建造物のボルトナットによ
る締結終了時まで、建造物を直立状態に保つワイヤーな
どを通すために利用することもできる。
The suspension ring 4 can also be used for passing a wire or the like that keeps the building upright even after the foundation is completed and until the fastening of the building with the bolts and nuts is completed.

以上は、独立基礎の場合の例であるが、設置した基礎に
地中梁を容易に接続しうるような構造とすることもでき
る。すなわち、第8図に示すように、コンクリート型枠
A′の一つ又は複数の壁面の中間部又はコーナー部に凹
部15を設け、この基礎設置後に、コンクリート型枠
A′と同様にコンクリート型枠で形成した板状又はU字
形の地中梁成形用型枠16の端部を前記凹部15に嵌合
固定し、その型枠内に鉄筋17を組み、生コンクリート
を投入し、養生固化することにより、第9図に示すよう
に、簡単に地中梁Cを形成して、これを基礎Bに接合す
ることができる。接合部には補強鉄棒18等を埋設する
とがよい。建設現場の地理的条件が許すならば、別の場
所で成形した地中梁を移動して、その地中梁の端部を隣
接する基礎の凹部15に嵌合して連結することもでき
る。
The above is an example of an independent foundation, but it is also possible to have a structure in which an underground beam can be easily connected to the installed foundation. That is, as shown in FIG. 8, a concave portion 15 is provided at an intermediate portion or a corner portion of one or a plurality of wall surfaces of the concrete formwork A ', and after the foundation is installed, the concrete formwork A'is also provided. The end portion of the plate-shaped or U-shaped underground beam forming mold 16 formed in 1 is fitted and fixed in the recess 15, the reinforcing bar 17 is assembled in the mold, and ready-mixed concrete is added to cure and solidify. Thereby, as shown in FIG. 9, the underground beam C can be easily formed and joined to the foundation B. It is preferable to embed a reinforcing iron rod 18 or the like in the joint portion. If the geography of the construction site allows, the molded girder can be moved elsewhere to fit and connect the ends of the girder to the recess 15 in the adjacent foundation.

型枠Aの上記吊り輪4を型枠Aの角部至近において内壁
面に沿って上方に突出させれば、背の高い基礎柱を建設
する必要がある場合は、第10図に要部を示すように、
複数の型枠A,Aを積み重ねたときに、その吊り輪
4により上下型枠の相対移動を阻止して、安定した状態
でこの型枠内に生コンクリートを投入することができ、
他の保持手段を必要としない利点がある。
If it is necessary to construct a tall foundation column by projecting the suspension ring 4 of the form A upward along the inner wall surface in the vicinity of the corner of the form A, the main parts are shown in FIG. As shown
When a plurality of molds A 1 and A 2 are stacked, the suspension ring 4 prevents relative movement of the upper and lower molds, and ready-mixed concrete can be poured into the molds in a stable state.
There is the advantage that no other holding means is required.

この考案の効果 上述のように、この考案によれば、型枠を鉄筋コンクリ
ートで角筒状又は円筒状に形成し、内部に生コンクリー
トを投入して基礎を打設できるようにし、型枠の内壁面
より内側に突出する補強用リブを設け、前記リブは使用
時にコンクリート基礎内に配設される鉄筋の被り厚さを
設定するスペーサを兼ねるようにしたから、従来のよう
に、現場での型枠の組立てをする必要はなく、搬送設置
した型枠内に直ちに生コンクリートを投入し、その固化
後は型枠は基礎に一体に接合されて基礎の一部となり、
コンクリート養生固化後の型枠取外しが不要であるか
ら、現場作業が著しく簡略化され、工期が大幅に短縮さ
れるとともに、運賃及び工賃が著しく削減される。
As described above, according to the present invention, the mold is made of reinforced concrete in the shape of a rectangular tube or a cylinder, and ready-mixed concrete can be poured into the mold so that the foundation can be placed. Providing reinforcing ribs that project inward from the wall surface, the ribs also function as spacers that set the overburden thickness of the reinforcing bars that are placed in the concrete foundation when in use. It is not necessary to assemble the frame, immediately pouring ready-mixed concrete into the transferred and installed formwork, and after solidifying, the formwork is integrally joined to the foundation and becomes part of the foundation,
Since it is not necessary to remove the formwork after the curing and hardening of concrete, on-site work is remarkably simplified, the construction period is significantly shortened, and the freight rate and the labor cost are remarkably reduced.

また、至急に建設することが要請される防災設備などの
基礎構築や、山岳地帯など建設が季節的に制限される構
造物の基礎構築に有効適切である。
It is also effective and appropriate for the construction of foundations such as disaster prevention facilities, which are urgently required to be constructed, and for the construction of structures such as mountainous areas where construction is seasonally restricted.

【図面の簡単な説明】[Brief description of drawings]

図面は、この考案の実施例を説明するものであり、第1
図は鉄筋コンクリート型枠を製造する工程の一例を示す
斜視図、第2図はコンクリート型枠の一部の縦断面図、
第3図は完成したコンクリート型枠を移動する状態を示
す斜視図、第4図はコンクリート型枠を現場に設置する
様子を示す斜視図、第5図はコンクリート型枠を利用し
て基礎中に埋設する鉄筋及びアンカーの取付けをする状
態を示す斜視図、第6図は完成した基礎の斜視図、第7
図は基礎に建造物を取付けた例を示す要部斜視図、第8
図は地中梁と接続できるように改良した例を示す斜視
図、第9図は接合部の縦断面図、第10図は複数の型枠
を縦に連結する場合の例を示す一部正面断面図である。 1,2…型枠、 3…鉄筋、 4…吊り輪、 A…鉄筋コンクリート型枠、 5…リブ、 11…鉄筋、 12…アンカーボルトなど、 13…アンカー支持部材、 14…安定板、 B…基礎、 15…凹部、 16…地中梁成形型枠、 17…鉄筋、 C…地中梁。
The drawings illustrate an embodiment of this invention,
The figure is a perspective view showing an example of a process for manufacturing a reinforced concrete formwork, and Fig. 2 is a longitudinal sectional view of a part of the concrete formwork,
Fig. 3 is a perspective view showing a state where the completed concrete formwork is moved, Fig. 4 is a perspective view showing a state in which the concrete formwork is installed on the site, and Fig. 5 is a concrete formwork that is used in the foundation. FIG. 6 is a perspective view showing a state where the reinforcing bars and anchors to be embedded are attached, FIG. 6 is a perspective view of the completed foundation, and FIG.
The figure is a perspective view of the essential parts showing an example in which a building is attached to the foundation.
The figure is a perspective view showing an example improved to connect with an underground beam, Fig. 9 is a vertical sectional view of a joint, and Fig. 10 is a partial front view showing an example in which a plurality of molds are vertically connected. FIG. 1, 2 ... Formwork, 3 ... Reinforcing bar, 4 ... Suspension ring, A ... Reinforced concrete formwork, 5 ... Rib, 11 ... Reinforcing bar, 12 ... Anchor bolt, 13 ... Anchor support member, 14 ... Stabilizer plate, B ... Foundation , 15 ... Recessed portion, 16 ... Underground beam forming form, 17 ... Reinforcing bar, C ... Underground beam.

Claims (4)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】(イ)鉄筋コンクリートで角筒状又は円筒
状に形成され、内部に生コンクリートを投入して基礎を
構築するために使用されること、 (ロ)内壁面より内側に突出する補強用リブを有するこ
と、 (ハ)前記リブは使用時にコンクリート基礎内に配設さ
れる鉄筋の被り厚さを設定するスペーサを兼ねること、 を特徴とするコンクリート基礎構築用コンクリート型
枠。
1. (a) It is formed of reinforced concrete in the shape of a rectangular tube or a cylinder and is used for constructing a foundation by pouring ready-mixed concrete into it. (B) Reinforcement protruding inward from the inner wall surface. (C) The rib also serves as a spacer for setting the covering thickness of the reinforcing bar arranged in the concrete foundation during use, and the concrete formwork for constructing a concrete foundation.
【請求項2】外側面に凹み、地中梁成形用型枠の端部又
は地中梁の端部を嵌合するための凹部を有することを特
徴とする実用新案登録請求の範囲第1項に記載のコンク
リート基礎構築用コンクリート型枠。
2. A utility model registration claim according to claim 1, characterized in that it has a recess on the outer side and a recess for fitting the end of the underground beam forming mold or the end of the underground beam. Concrete formwork for concrete foundation construction described in.
【請求項3】鉄筋の一部が吊り輪を形成し、上端部の重
心に対して均等な複数の位置において、上方に突出され
ていることを特徴とする実用新案登録請求の範囲第1項
又は第2項に記載のコンクリート基礎構築用コンクリー
ト型枠。
3. A utility model registration claim according to claim 1, wherein a part of the reinforcing bar forms a suspension ring, and is projected upward at a plurality of positions which are even with respect to the center of gravity of the upper end. Alternatively, the concrete formwork for constructing a concrete foundation according to item 2.
【請求項4】吊り輪は内壁面延長上に配設され、上下重
ねられる型枠の位置決め具及びずれ防止具を兼ねること
を特徴とする実用新案登録請求の範囲第3項に記載のコ
ンクリート基礎構築用コンクリート型枠。
4. The concrete foundation according to claim 3, wherein the suspension ring is provided on the extension of the inner wall surface and serves as a positioning tool and a slip prevention tool for the vertically stacked molds. Concrete formwork for construction.
JP12112187U 1987-08-07 1987-08-07 Concrete formwork for concrete foundation construction Expired - Lifetime JPH063881Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12112187U JPH063881Y2 (en) 1987-08-07 1987-08-07 Concrete formwork for concrete foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12112187U JPH063881Y2 (en) 1987-08-07 1987-08-07 Concrete formwork for concrete foundation construction

Publications (2)

Publication Number Publication Date
JPS6426461U JPS6426461U (en) 1989-02-15
JPH063881Y2 true JPH063881Y2 (en) 1994-02-02

Family

ID=31367841

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12112187U Expired - Lifetime JPH063881Y2 (en) 1987-08-07 1987-08-07 Concrete formwork for concrete foundation construction

Country Status (1)

Country Link
JP (1) JPH063881Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2915746B2 (en) * 1993-06-08 1999-07-05 高伸建設 株式会社 Foundation formwork

Also Published As

Publication number Publication date
JPS6426461U (en) 1989-02-15

Similar Documents

Publication Publication Date Title
US7062885B1 (en) Foundation wall, construction kit and method
JPH08269911A (en) Concrete wall balustrade mounting structure
KR100787178B1 (en) Lightweight steel frame base plate and construction method
KR101036177B1 (en) Construction method of building structure using PPC composite method
JPH063881Y2 (en) Concrete formwork for concrete foundation construction
JP3671344B2 (en) Joint structure between foundation pile and column base and its construction method
JP2743961B2 (en) Concrete foundation method
JP2022175669A (en) How to build a slab foundation
EP0151626B1 (en) Procedure for making foundations for a structure, and intermediate piece for use in the procedure
JP2588990B2 (en) Concrete formwork
JPH11158813A (en) How to build a concrete pier
JPH11107293A (en) Foundation structure of building, foundation construction method, and block for foundation
JP2000160687A (en) Construction method of mixed structure and precast concrete column
JP3014987U (en) Reinforcement equipment for existing buildings
JP2709346B2 (en) Block for legal framework
JP3002026B2 (en) Structure of residential continuous foundation
JP3110341B2 (en) Construction formwork and method of fabric foundation or fence for housing
JPH0777596A (en) Large slab in nuclear facility and its construction method
JP2554382B2 (en) Dwelling
JP3629684B2 (en) Sound insulation wall foundation block
JP2869764B2 (en) Reservoir construction method
KR20100086374A (en) Sectional pier using precast coping and constructing method thereof
JP2002339380A (en) Retaining wall structure and its assembly and construction method
JPS6351212B2 (en)
JPH05222766A (en) Building method