JPH0664732U - Automatic intermittent power supply controller for electrostatic precipitator - Google Patents

Automatic intermittent power supply controller for electrostatic precipitator

Info

Publication number
JPH0664732U
JPH0664732U JP6869892U JP6869892U JPH0664732U JP H0664732 U JPH0664732 U JP H0664732U JP 6869892 U JP6869892 U JP 6869892U JP 6869892 U JP6869892 U JP 6869892U JP H0664732 U JPH0664732 U JP H0664732U
Authority
JP
Japan
Prior art keywords
electrostatic precipitator
turbidity
energized
power supply
level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6869892U
Other languages
Japanese (ja)
Inventor
志強 葉
春明 鄒
家賢 ▲葛▼
瑞進 張
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Industrial Technology Research Institute ITRI
Original Assignee
Industrial Technology Research Institute ITRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Industrial Technology Research Institute ITRI filed Critical Industrial Technology Research Institute ITRI
Priority to JP6869892U priority Critical patent/JPH0664732U/en
Publication of JPH0664732U publication Critical patent/JPH0664732U/en
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Electrical Variables (AREA)
  • Electrostatic Separation (AREA)

Abstract

(57)【要約】 【目的】 本考案の静電集塵装置の自動給電制御装置
は、該静電集塵装置に供給する直流電力の最適レベルに
つき、粉塵粒子の濁度検出と通電・非通電パラメータと
に基づいて決定をし、その間欠給電制御に係る人的労力
を軽減化すること、及び、その自動化を図ることを目的
とすること。 【構成】 交流電源に接続された整流手段によって発生
される直流電力により起動/給電される静電集塵装置の
構成において、該交流電源の通電・非通電期間を調整す
ることにより直流電力の大きさを制御する装置であっ
て、静電集塵装置を通って流れる粉塵粒子の濁度を検出
する濁度計と、静電集塵装置を通って流れる粉塵粒子で
検出された濁度レベルOPdに基づいて参照テーブルを
検索するCPU手段とを具備することを含む。
(57) [Abstract] [Objective] The automatic power supply control device for the electrostatic precipitator of the present invention is designed to detect turbidity of dust particles, turn on / off the electrification / non-conduction of the optimum level of DC power supplied to the electrostatic precipitator The purpose is to make a decision based on the energization parameter, reduce the human labor involved in the intermittent power supply control, and to automate the operation. In a configuration of an electrostatic precipitator that is activated / powered by DC power generated by rectifying means connected to an AC power supply, the magnitude of DC power is adjusted by adjusting the energized / de-energized period of the AC power supply. And a turbidity meter for detecting the turbidity of dust particles flowing through the electrostatic precipitator, and a turbidity level OPd detected by the dust particles flowing through the electrostatic precipitator. And CPU means for retrieving the lookup table based on.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は一般に静電集塵装置において使用するための自動間欠給電制御装置に 関する。 The present invention generally relates to an automatic intermittent power supply control device for use in an electrostatic precipitator.

【0002】[0002]

【従来の技術】[Prior art]

環境保護を目的として、排気ガスを発生する製造装置類には一般に静電集塵装 置を併設し、排気ガス中に含有される浮遊粉塵を捕集している。典型的なESP は相互に平行に配置された集塵板と集塵板の間に配置された放電線を含む。コロ ナ放電として公知のように、放電線によって放電された電子がESPを通過する 浮遊粉塵のイオン化を起こさせるように放電線へ直流電力が供給される。イオン 化した粉塵粒子は直流電力によって生成された電場によって吸引され、これによ って集塵板へ捕集される。 For the purpose of environmental protection, manufacturing equipment that generates exhaust gas is generally equipped with an electrostatic precipitator to collect suspended dust contained in the exhaust gas. A typical ESP includes a dust collecting plate arranged in parallel to each other and a discharge line arranged between the dust collecting plates. As is known as corona discharge, direct current power is supplied to the discharge line so that electrons discharged by the discharge line cause ionization of suspended dust passing through the ESP. The ionized dust particles are attracted by the electric field generated by the DC power, and are thus collected on the dust collecting plate.

【0003】 また、エネルギーの節減および高度な除塵効率を目的として、ESPへ供給す る直流電力はESPを通過する浮遊粉塵の濃度に従って変化させることがある。 すなわち、粉塵粒子の濃度が極めて高いことが検出された場合には直流電力は最 大限の大きさで供給され、粉塵粒子の流量が少ないことが検出された場合には直 流電力を減力することができる。Further, for the purpose of energy saving and high dust removal efficiency, the DC power supplied to the ESP may be changed according to the concentration of suspended dust passing through the ESP. That is, the direct current power is supplied at the maximum level when it is detected that the concentration of dust particles is extremely high, and the direct current power is reduced when it is detected that the flow rate of dust particles is low. be able to.

【0004】 図4は、従来例に係る静電集塵装置の間欠給電制御装置の構成図であり、図5 (a),(b),図6は、従来例に係るESP給電制御装置を説明する交流信号 波形図(その1,2)をそれぞれ示している。なお、図5(a)は交流電圧の信 号を示し、図5(b)は通電・非通電の対(C,P)=(5,1)に対応して交 流電圧を部的に割断した信号を示し、図6は通電・非通電の対(C,P)=(2 ,5)に対応して交流電圧を部分的に割断した別の信号を示す。FIG. 4 is a configuration diagram of an intermittent power supply control device of an electrostatic dust collector according to a conventional example, and FIGS. 5A, 5B and 6 show an ESP power supply control device according to a conventional example. The AC signal waveform diagrams (Nos. 1 and 2) to be described are respectively shown. Fig. 5 (a) shows the AC voltage signal, and Fig. 5 (b) shows the AC voltage partially corresponding to the energized / non-energized pair (C, P) = (5, 1). The cleaved signal is shown, and FIG. 6 shows another signal in which the AC voltage is partially cleaved corresponding to the energized / non-energized pair (C, P) = (2, 5).

【0005】 図4において、交流電力供給源10が周期Tを有し、一般的な工業用電力用途 ではT=1/60となる交流電圧V1 (t)を発生する主電力供給源として使用 され、その波形は図5(a)に示してある。サイリスタ回路20はサイリスタ起 動制御回路30と組み合わせて使用され、交流電圧V1 (t)における全正弦波 周期の通過または遮断を制御する。In FIG. 4, an AC power supply source 10 has a period T and is used as a main power supply source for generating an AC voltage V1 (t) of T = 1/60 in a general industrial power application. , Its waveform is shown in FIG. The thyristor circuit 20 is used in combination with the thyristor activation control circuit 30 to control passage or interruption of all sine wave cycles in the AC voltage V1 (t).

【0006】 通電周期は本論において、以後、交流電圧V1(t)における全正弦波周期の 第1の所定の数Cを含む1周期として、サイリスタ回路20を通過できるものと 定義する。また1回の通電周期の終端に続いてすぐに出現する非通電期間は交流 電圧V1 (t)における全正弦波周期の第2の所定の数Cを含む1周期として、 サイリスタ回路20によって遮断されるものと定義する。従って、1通電周期と それに続く1非通電期間はT1 +T2 の周期で交互に出現する。In the present discussion, the energization cycle will be defined as one cycle that can pass through the thyristor circuit 20 as one cycle including the first predetermined number C of all sinusoidal wave cycles in the AC voltage V1 (t). Further, the non-energization period that appears immediately after the end of one energization period is cut off by the thyristor circuit 20 as one period including the second predetermined number C of all sine wave periods in the AC voltage V1 (t). It is defined as one. Therefore, one energization period and the following one non-energization period alternately appear in the cycle of T1 + T2.

【0007】 図5(b)に図示した例では、(C,P)=(5,1)の場合、サイリスタ回 路V1 (t)における全正弦波周期を連続5回この回路を通って通過させ、これ に続く周期を6・Tの期間にわたって遮断する。図5(c)に図示した別の例で は、(C,P)=(2,5)の場合、サイリスタ回路20はV1 (t)にある連 続した2つの全正弦波周期をこの回路を通って通過させ、これに続く5周期を7 ・Tの期間にわたって遮断する。In the example shown in FIG. 5B, when (C, P) = (5,1), the entire sine wave period in the thyristor circuit V1 (t) is passed through this circuit five times in succession. Then, the subsequent cycle is cut off for a period of 6T. In another example, shown in FIG. 5 (c), if (C, P) = (2,5), the thyristor circuit 20 has two consecutive full sine wave cycles at V1 (t). Through and interrupt the following 5 cycles for a period of 7 · T.

【0008】 従ってV1(t)における全正弦波周期は昇圧トランス40を経由して間歇的 に整流回路50へ送出され、この回路を用いて平均電力V2 (t)に比例する直 流出力VDCを発生させる。基本的な電気の原理により、出力直流電圧はまたRC' にも比例するから、 Rc’=C/C+P が成立する。Rcが大きい場合は電力エネルギーが多く消費され、Rcが小さい 場合は電力エネルギーの消費が少ないことを表す。Therefore, the entire sine wave period at V1 (t) is intermittently sent to the rectifier circuit 50 via the step-up transformer 40, and this circuit is used to generate a direct current output VDC proportional to the average power V2 (t). generate. According to the basic principle of electricity, the output DC voltage is also proportional to RC ', so that Rc' = C / C + P holds. When Rc is large, a large amount of electric energy is consumed, and when Rc is small, a small amount of electric energy is consumed.

【0009】 従来技術によるESP給電制御装置での通電・非通電のパラメータの組(C, P)の選択は手動入力によってのみ行われる。いったん選択を行なうと、制御装 置は粉塵粒子の流量の変化に適応し得ない。ESPへ入力される直流電力レベル を変更する唯一の方法は別の新しい組(C,P)を手動的に入力することである 。よって、ESP操作員はESPのそばに待機し、粉塵粒子の流量を監視し、こ れによって粉塵除去処理の適切な制御を行なうための適切なパラメータの対(C ,P)を選択する必要がある。The selection of the energized / non-energized parameter set (C, P) in the ESP power feeding control device according to the related art is performed only by manual input. Once selected, the control device cannot adapt to changes in the dust particle flow rate. The only way to change the DC power level input to the ESP is to manually enter another new set (C, P). Therefore, the ESP operator must stand by the ESP, monitor the dust particle flow rate, and thereby select the appropriate pair of parameters (C, P) for proper control of the dust removal process. is there.

【0010】[0010]

【考案が解決しようとする課題】[Problems to be solved by the device]

従って本考案の第1の目的は粉塵粒子の流量に合わせてESP装置へ供給され る直流電力のレベルを制御する能力を有するESP給電制御装置を提供すること である。 Therefore, a first object of the present invention is to provide an ESP power feeding control device having the ability to control the level of DC power supplied to the ESP device according to the flow rate of dust particles.

【0011】[0011]

【課題を解決するための手段】[Means for Solving the Problems]

本考案の静電集塵装置の自動間欠給電制御装置は、図1〜3にその実施例を示 すように、交流電源に接続された整流手段によって発生される直流電力により起 動/給電される静電集塵装置の構成において、上記交流電源の通電・非通電期間 を調整することにより上記直流電力の大きさを制御する装置であって、(a)上 記静電集塵装置を通って流れる粉塵粒子の濁度を検出する濁度計と、(b)上記 静電集塵装置を通って流れる粉塵粒子で検出された濁度レベルOPdに基づいて 参照テーブルを検索するCPU手段とを具備し、上記参照テーブルが直流電力レ ベルを可変させる所定数の通電・非通電期間から構成され、上記CPU手段が上 記検出された濁度レベルOPd と初期濁度レベルOPs との間の差が所定の許容 範囲内となるような上記通電・非通電期間のひとつの値が見つかるまで、それぞ れが対応する濁度レベルOPdと初期濁度レベルOPs を相対させて直流電力の 最適レベルを検出することを特徴とする。 The automatic intermittent power supply control device for an electrostatic precipitator of the present invention is activated / powered by DC power generated by a rectifying means connected to an AC power supply, as shown in FIGS. In the configuration of the electrostatic precipitator according to the present invention, it is a device for controlling the magnitude of the direct current power by adjusting the energized / non-energized period of the alternating current power supply, which is (a) the electrostatic precipitator. A turbidimeter for detecting the turbidity of the dust particles flowing through, and (b) CPU means for searching a reference table based on the turbidity level OPd detected in the dust particles flowing through the electrostatic precipitator. The reference table comprises a predetermined number of energized / de-energized periods for varying the DC power level, and the CPU means provides the difference between the detected turbidity level OPd and the initial turbidity level OPs. Is within the specified tolerance range Until it finds one value of the energization and non-energization period, and detects the optimum level of the DC power by relatively turbidity level OPd initial turbidity level OPs which, respectively it corresponds.

【0012】 また、本考案の静電集塵装置の自動間欠給電制御装置において、上記通電・非 通電期間の参照テーブルが20の項目を含むことを特徴とする。 さらに、本考案の静電集塵装置の自動間欠給電制御装置は、上記検出された濁 度レベルOPd についての所定の許容範囲が−3≦OPd −OPs ≦0からなる ことを特徴とする。Further, in the automatic intermittent power supply control device for the electrostatic precipitator of the present invention, the reference table for the energized / non-energized period includes 20 items. Further, the automatic intermittent power supply control device for the electrostatic precipitator of the present invention is characterized in that the predetermined permissible range for the detected turbidity level OPd is -3≤OPd-OPs≤0.

【0013】 なお、本考案の静電集塵装置の自動間欠給電制御装置において、上記CPU手 段は上記最適な直流電力が発見された後、上記静電集塵装置を通って流れる粉塵 粒子の濁度の監視を継続し、検出された濁度レベルと初期設定の濁度レベルの間 に上記所定の許容範囲を逸脱するほどの差が検出された場合には、上記CPU手 段が再度上記通電・非通電期間の参照テーブルの検索を実行することを特徴とし 、上記目的を達成する。In the automatic intermittent power supply control device for the electrostatic precipitator of the present invention, the CPU means detects dust particles flowing through the electrostatic precipitator after the optimum DC power is found. When the turbidity is continuously monitored and a difference is detected between the detected turbidity level and the default turbidity level that deviates from the predetermined permissible range, the CPU means returns to the above The above-mentioned object is achieved, which is characterized in that a reference table for energized / non-energized periods is searched.

【0014】[0014]

【作用】[Action]

本考案の静電集塵装置の自動間欠給電制御装置によれば、濁度計及びCPU手 段が具備される。 According to the automatic intermittent power supply control device of the electrostatic precipitator of the present invention, the turbidity meter and the CPU means are provided.

【0015】 このため、静電集塵装置を通過する粉塵粒子について、検出された比濁レベル を所定の比濁レベルと実質的に等しくすることが可能となり、直流電力の最適レ ベルを決定することが可能となる。Therefore, it becomes possible to make the detected turbidity level of the dust particles passing through the electrostatic precipitator substantially equal to the predetermined turbidity level, and determine the optimum level of the DC power. It becomes possible.

【0016】 すなわち、ESP装置に装着された比濁計により、これを通過して流れる粉塵 粒子の濁度が検出され、その濁度レベルがCPUにより所定の濁度レベルと比較 され、これにしたがって該CPUでは、多数の所定の通電・非通電パラメータの 対を有する参照テーブルが検索される。That is, the turbidity meter attached to the ESP device detects the turbidity of the dust particles flowing therethrough, and the turbidity level is compared with a predetermined turbidity level by the CPU, and accordingly, the turbidity level is compared. The CPU searches a reference table having a large number of predetermined energization / de-energization parameter pairs.

【0017】 これにより、その検出された濁度レベルが所定範囲内に納まり得るようなひと つの通電・非通電パラメータを見出だすことが可能となる。このことで、従来例 に比べて静電集塵装置の間欠給電制御に係る人的労力が軽減化され、また、その 自動化が図られる。This makes it possible to find one energization / de-energization parameter such that the detected turbidity level can fall within a predetermined range. As a result, compared to the conventional example, the human labor involved in the intermittent power supply control of the electrostatic precipitator is reduced, and the automation thereof is achieved.

【0018】[0018]

【実施例】【Example】

次に、本考案の実施例について図を参照しながら説明をする。図1は本考案の 実施例に係るESP自動間欠給電制御装置の構成図であり、図2は、本考案の実 施例に係るESP自動給電制御装置のCPUの制御(メインルーチン)フローチ ャートである。 Next, an embodiment of the present invention will be described with reference to the drawings. 1 is a block diagram of an ESP automatic intermittent power supply control device according to an embodiment of the present invention, and FIG. 2 is a CPU control (main routine) flow chart of the ESP automatic power supply control device according to an embodiment of the present invention. is there.

【0019】 なお、本考案の実施例に係るESP自動給電制御装置のCPUの制御(サブル ーチン)フローチャートをそれぞれ示しいる。また、図1において、従来技術に 示したESP間欠給電制御装置の構成図に対して変更されていないブロックは同 一の参照番号が割り振られている。The control (subroutine) flow charts of the CPU of the ESP automatic power supply control device according to the embodiment of the present invention are shown respectively. Further, in FIG. 1, the same reference numerals are assigned to the blocks that are not changed in the block diagram of the ESP intermittent power supply control device shown in the prior art.

【0020】 すなわち、本考案の自動ESP間欠給電制御装置は図1において、CPU10 0およびESPの集塵板に装置された比濁計200を含む。比濁計200は任意 で光ビーム放射装置および光検出装置(どちらも図示していない)を含む装置で あって、ESPを通過して流れる粉塵粒子の濁度を検出するために使用される。That is, the automatic ESP intermittent power supply control device of the present invention includes the CPU 100 and the nephelometer 200 installed on the dust collecting plate of the ESP in FIG. The nephelometer 200 is a device that optionally includes a light beam emitting device and a light detecting device (neither shown), which is used to detect the turbidity of dust particles flowing through the ESP.

【0021】 光ビーム放射装置は光ビームを放射するために使用され、光ビームは粉塵粒子 の通路を経由して光検出装置へと流れ、これによって光検出装置を作動させてE SP内部の粉塵流量の検出濁度を表す電気信号OPd を発生させる。電気信号O Pd はCPUへフィードバックされる。粉塵粒子の濃度が高い場合、光検出装置 は薄暗い光ビームを検出し、これによって小さな電流を発生する。The light beam emitting device is used to emit a light beam, which flows through the path of the dust particles to the photodetector device, thereby actuating the photodetector device and causing dust inside the ESP. An electric signal OPd representing the detected turbidity of the flow rate is generated. The electric signal OPd is fed back to the CPU. When the concentration of dust particles is high, the photodetector detects a dim light beam, which produces a small current.

【0022】 また粉塵粒子の濃度が低い場合、光検出装置は明るい光ビームを検出するので これによって大きな電流を発生する。従って光検出装置によって生成された電流 の大きさは、粉塵流の不透明度を示すために用いられることができる。不透明度 を表現するために使用される単位は濁度と呼ばれ、大きな濁度値は粉塵粒子の流 れが多いことを示し、小さな濁度値は粉塵粒子の流れが少ないことを示す。Further, when the concentration of dust particles is low, the photodetector detects a bright light beam, and thus a large current is generated. Therefore, the magnitude of the current generated by the photodetector can be used to indicate the opacity of the dust stream. The unit used to express opacity is called turbidity, where a high turbidity value indicates a high flow of dust particles and a low turbidity value indicates a low flow of dust particles.

【0023】 自動ESP間欠給電制御装置の操作に入る前に、2つの所定の定数パラメータ OPs およびtR が手動操作によりCPU100へ入力される。ここで、OPs は粉塵流について所望する不透明度の所定の値、tR はESP内の粉塵流の残留 時間である。Before entering the operation of the automatic ESP intermittent power supply control device, two predetermined constant parameters OPs and tR are manually input to the CPU 100. Where OPs is a predetermined value of the desired opacity for the dust stream and tR is the residence time of the dust stream in the ESP.

【0024】 CPU100の機能は粉塵流で検出された不透明度OPd に対応する通電・非 通電の組の最適値を求めることである。最適な通電・非通電の組み合わせがいっ たん求まれば、これがサイリスタ制御回路40へ送出される。The function of the CPU 100 is to obtain the optimum value of the energized / non-energized group corresponding to the opacity OPd detected in the dust flow. When the optimum energized / non-energized combination is found, this is sent to the thyristor control circuit 40.

【0025】 CPU100によって実行されるプログラムの流れを図2の制御フローチャー トに示している。最適な通電・非通電の組み合わせを見つけるために、参照テー ブル検索法を用いて20組の所定の通電・非通電の組み合わせの中から検索する 。これは次の組み合わせを含む: (C0 ,P0 )=(5,1), (C1 ,P1 )=(4,1), (C2 ,P2 )=(3,1), (C3 ,P3 )=(5,2), (C4 ,P4 )=(2,1), (C5 ,P5 )=(4,2), (C6 ,P6 )=(5,3), (C7 ,P7 )=(3,2), (C8,P8)=(4,3), (C9 ,P9 )=(5,4), (C10,P10)=(2,2), (C11,P11)=(3,3), (C12,P12)=(4,4), (C13,P13)=(5,5), (C14,P14)=(2,3), (C15,P15)=(3,4), (C16,P16)=(4,5), (C17,P17)=(3,5), (C18,P18)=(2,4), (C19,P19)=(2,5). i<jの場合、通電・非通電の組み合わせ(Ci,Pi)は通電・非通電の組 み合わせ(Cj,Pj)よりも大きな直流電力をESPへ供給する。CPU10 0の出力通電・非通電の組み合わせは(Ccppt,Pcppt)で表され、ここで0≦ CPPT≦19である。The flow of the program executed by the CPU 100 is shown in the control flow chart of FIG. In order to find the optimal energized / de-energized combination, a reference table search method is used to search from 20 predetermined energized / de-energized combinations. This includes the following combinations: (C0, P0) = (5,1), (C1, P1) = (4,1), (C2, P2) = (3,1), (C3, P3) = (5,2), (C4, P4) = (2,1), (C5, P5) = (4,2), (C6, P6) = (5,3), (C7, P7) = (3 , 2), (C8, P8) = (4,3), (C9, P9) = (5,4), (C10, P10) = (2,2), (C11, P11) = (3,3) ), (C12, P12) = (4,4), (C13, P13) = (5,5), (C14, P14) = (2,3), (C15, P15) = (3,4), (C16, P16) = (4,5), (C17, P17) = (3,5), (C18, P18) = (2,4), (C19, P19) = (2,5). When i <j, the energized / non-energized combination (Ci, Pi) supplies more DC power to the ESP than the energized / non-energized combination (Cj, Pj). The output energization / non-energization combination of the CPU 100 is represented by (Ccppt, Pcppt), where 0 ≦ CPPT ≦ 19.

【0026】 プログラムの始めで、CPUはCPPT=0、すなわち(Ccppt,Pcppt)=(C 0 ,P0 )=(5,1)をサイリスタ制御回路30への出力として選択する。こ の通電・非通電率で作動される直流電力により、CPU100は濁度読み取り段 階を続けて実行し、この期間中にCPU100は2秒間隔で10回濁度計200 の出力を連続して読み取り、これによって10個の検出した濁度読み値を収集す る。10個の読み値データはこのあと平均されてOPd を得る。At the beginning of the program, the CPU selects CPPT = 0, ie (Ccppt, Pcppt) = (C 0, P 0) = (5,1), as the output to the thyristor control circuit 30. The CPU 100 continuously executes the turbidity reading stage by the DC power operated at this energization / de-energization rate, and during this period, the CPU 100 continuously outputs the output of the turbidity meter 200 10 times at intervals of 2 seconds. Read, thereby collecting 10 detected turbidity readings. The 10 readings are then averaged to obtain OPd.

【0027】 当該値OPdは初期値OPsと比較され、該値がOPd>OPsの場合、高濃度の 粉塵粒子がまだESP内に存在し、よってCPPT=0に対応する通電・非通電パラ メータの組み合わせは粉塵粒子の効果的な除去には充分な高さでないことを示す 。The value OPd is compared with the initial value OPs, and if the value OPd> OPs, high-concentration dust particles are still present in the ESP, so that the energized / de-energized parameter corresponding to CPPT = 0. The combination shows that it is not high enough for effective removal of dust particles.

【0028】 従って交流出力V1 (t)は部分的な割断(チョップ)なしに昇圧トランス4 0,整流回路50へ転送され、ESPに最大の直流電力が供給される。交流電力 の全転送は5ないし132秒にわたって継続される。この後、CPU100はプ ログラムの第1の段階へ復帰する。Therefore, the AC output V1 (t) is transferred to the step-up transformer 40 and the rectifier circuit 50 without partial cutting (chopping), and the maximum DC power is supplied to the ESP. The full transfer of AC power lasts for 5 to 132 seconds. After this, the CPU 100 returns to the first stage of the program.

【0029】 一方、値OPd <OPs の場合、低流量の粉塵粒子がESP内に存在し、また これによってCPPT=0に対応する通電・非通電期間に、必要以上の直流電力が作 動していることを示す。その結果、CPU100はCPPT=19を試行する、すな わち、(Ccppt,Pcppt)=(C19,P19)=(2,5)を用いて最小限の直流 電力を作動させる。On the other hand, in the case of the value OPd <OPs, the dust particles of low flow rate exist in the ESP, and this causes more DC power than necessary during the energized / de-energized period corresponding to CPPT = 0. Indicates that As a result, the CPU 100 tries CPPT = 19, that is, uses (Ccppt, Pcppt) = (C19, P19) = (2,5) to activate the minimum DC power.

【0030】 この通電・非通電パラメータの組み合わせを用いて、CPU100はもう一度 濁度計200の出力を2秒間隔で10回読み取り、これによって10個の濁度読 み値を収集する。10個の読み値データはこの後平均化されて新しいOPdを得 る。Using this combination of energized / non-energized parameters, the CPU 100 again reads the output of the turbidimeter 200 10 times at 2 second intervals, thereby collecting 10 turbidity readings. The 10 readings are then averaged to obtain a new OPd.

【0031】 新しいOPd はまた初期値OPs と比較される。OPd <OPs の場合、ES P内に極めて低い流量の粉塵粒子が存在することが示される。この場合、CPPT= 19に対応する通電・非通電期間がCPU100からサイリスタ起動制御回路3 0への出力として維持される。同時にCPU100は表示装置300上に(5, 2)を表示し、ESP操作員に情報を提供する。The new OPd is also compared with the initial value OPs. When OPd <OPs, it is shown that there is a very low flow rate of dust particles in the ESP. In this case, the energized / non-energized period corresponding to CPPT = 19 is maintained as an output from the CPU 100 to the thyristor start control circuit 30. At the same time, the CPU 100 displays (5, 2) on the display device 300 to provide the ESP operator with information.

【0032】 一方、値がOPd >OPs の場合、最適な通電・非通電パラメータの組み合わ せ(Ccppt,Pcppt)は係数CPPTが0から19の間のどこかに存在するはずであ ると示している。最適な通電・非通電パラメータの組み合わせを検出するための 制御(サブルーチン)フローチャートを図3に示している。On the other hand, when the value is OPd> OPs, it indicates that the optimum combination of energization / de-energization parameters (Ccppt, Pcppt) should exist somewhere between 0 and 19 in the coefficient CPPT. There is. FIG. 3 shows a control (subroutine) flowchart for detecting the optimum combination of energization / de-energization parameters.

【0033】 ここで、図3を参照すると、CPU100は新しい通電・非通電パラメータの 組み合わせ(Ccppt,Pcppt)を次の演算によって決定したCPPT値で試行する。 CPPT=TRUNC(TOPINDEX/2) なお、TRUNC(TOPINDEX/2) は算術演算で、括弧内の数字の加数部分を丸める ことによって整数値を生成している。またTOPINDEXは初期値を19とする整数値 で、これはCPPTの最低値である。従って、CPPT=9が選択され濁度読み取り段階 がもう一度実行されてOPs と比較される新しいOPd がまた得られる。Here, referring to FIG. 3, the CPU 100 tries a new combination of energization / de-energization parameters (Ccppt, Pcppt) with the CPPT value determined by the following calculation. CPPT = TRUNC (TOPINDEX / 2) TRUNC (TOPINDEX / 2) is an arithmetic operation that generates an integer value by rounding the addend part of the numbers in parentheses. TOPINDEX is an integer with an initial value of 19, which is the lowest CPPT value. Therefore, CPPT = 9 is selected and the turbidity reading step is performed again to obtain a new OPd which is compared to OPs.

【0034】 本考案の好適実施例において、OPd −OPs が−3から0の範囲内に存在す る場合、CPPTの現在値がCPU100からサイリスタ起動制御回路30へ送出さ れるべき最適な(Ccppt,Pcppt)指数として受け入れられる。In the preferred embodiment of the present invention, when OPd-OPs is in the range of -3 to 0, the current value of CPPT is optimum (Ccppt, Ccppt, which should be sent from the CPU 100 to the thyristor start control circuit 30). Pcppt) index is accepted.

【0035】 従って、OPd −OPs ≦−3の場合、最適な通電・非通電パラメータの組み 合わせ(Ccppt,Pcppt)は0から9までの間のどこかにCPPT係数が存在するは ずであることが解る。この場合、CPU100は算術演算,すなわち、 TOPINDEX=TOPINDEX−4 を実行し、TOPINDEXが19から15へ変更されるようになす。Therefore, in the case of OPd−OPs ≦ −3, the optimum combination of energization / de-energization parameters (Ccppt, Pcppt) is that the CPPT coefficient does not exist anywhere from 0 to 9. Understand. In this case, the CPU 100 executes an arithmetic operation, that is, TOPINDEX = TOPINDEX-4, and TOPINDEX is changed from 19 to 15.

【0036】 またこれによってCPPT=7が次の段階で得られる。CPU100は、−3≦O Pd −OPs ≦0が得られるようなひとつの係数値CPPTが見つかるまでこれらの 段階を反復して実行し、いったんCPPT値が見つかると、CPU100はサイリス タ起動制御回路30へ(Ccppt,Pcppt)値の送出を継続しまた表示装置200 上へCCPPTおよびPCPPTの値を表示する。Further, as a result, CPPT = 7 is obtained in the next step. The CPU 100 repeats these steps until it finds one coefficient value CPPT that gives -3≤OPd-OPs≤0, and once the CPPT value is found, the CPU 100 causes the thyristor activation control circuit 30 to operate. (Ccppt, Pcppt) values are continuously transmitted and the values of CCPPT and PCPPT are displayed on the display device 200.

【0037】 一方、OPd −OPs ≧0の場合、最適な通電・非通電パラメータの組み合わ せは(Ccppt,Pcppt)が11から18の間のどこかにCPPT係数が存在するはず であることが解る。この場合、CPU100は次の算術演算を実行する。On the other hand, when OPd−OPs ≧ 0, it is understood that the optimum combination of energization / de-energization parameters should have a CPPT coefficient somewhere between (Ccppt, Pcppt) 11 and 18. . In this case, the CPU 100 executes the following arithmetic operation.

【0038】 TOPINDEX=TOPINDEX+TRUNC (CPPT/2)+1 これでTOPINDEXが19から24へ変更されるようになし、またこれによってCP PT=12が次の段階で得られる。CPU100は、−3≦OPd −OPs ≦0が 得られるようなひとつの係数値CPPTが見つかるまで、これらの処理段階を反復実 行する。TOPINDEX = TOPINDEX + TRUNC (CPPT / 2) +1 This does not allow TOPINDEX to be changed from 19 to 24, and this also gives CP PT = 12 in the next step. The CPU 100 repeats these processing steps until it finds one coefficient value CPPT such that -3≤OPd-OPs≤0 is obtained.

【0039】 いったん最適なCPPT値が見つかると、CPU100はサイリスタ起動制御回路 30へ最適なCPPTに対応する(Ccppt,Ccppt)の送出を継続し、表示装置20 0上にCCPPTおよびPCPPTの値を表示する。Once the optimum CPPT value is found, the CPU 100 continues to send (Ccppt, Ccppt) corresponding to the optimum CPPT to the thyristor activation control circuit 30, and displays the values of CCPPT and PCPPT on the display device 200. To do.

【0040】 通電・非通電パラメータの組み合わせについて最適な係数値CPPTが見つかった 後、CPU100は粉塵流の濁度の監視を継続する。検出された濁度値OPd が −3≦OPd −OPs ≦0の許容範囲外に存在する場合、CPU100はプログ ラムを第一の段階から実行して別の最適な通電・非通電パラメータの組み合わせ を発見しようとする。After finding the optimum coefficient value CPPT for the combination of energized / de-energized parameters, the CPU 100 continues to monitor the turbidity of the dust stream. If the detected turbidity value OPd is outside the allowable range of -3≤OPd-OPs≤0, the CPU 100 executes the program from the first stage to select another optimum energization / non-energization parameter combination. Try to discover.

【0041】 本考案の典型的な好適実施例と共に以上に詳述したとおりであるが、本考案の 範囲は開示した好適実施例に限定されるべきものではないことは理解されたい。 むしろ以下に添付の請求の範囲に定めた範囲内に各種の変更および同様の構成 を含むものと意図している。請求の範囲はこれらの変更並びに同様の構成のすべ てを包含するべく最大限に広範囲に解釈されるべきものとする。Although detailed above with exemplary preferred embodiments of the present invention, it should be understood that the scope of the present invention should not be limited to the disclosed preferred embodiments. Rather, it is intended to include various modifications and similar arrangements within the scope of the appended claims. The claims should be read as broadly as possible to encompass all such modifications and similar arrangements.

【0042】[0042]

【考案の効果】[Effect of device]

以上、説明したように、本考案の静電集塵装置の自動間欠給電制御装置によれ ば、静電集塵装置を通って流れる粉塵粒子の濁度を検出する濁度計と、静電集塵 装置を通って流れる粉塵粒子で検出された濁度レベルOPdに基づいて参照テー ブルを検索するCPU手段とが具備される。 As described above, according to the automatic intermittent power supply control device of the electrostatic precipitator of the present invention, the turbidimeter for detecting the turbidity of the dust particles flowing through the electrostatic precipitator, and the electrostatic precipitator. CPU means for retrieving the reference table based on the turbidity level OPd detected in the dust particles flowing through the dust device.

【0043】 このため、静電集塵装置を通過する粉塵粒子について、検出された比濁レベル を所定の比濁レベルと実質的に等しくすることが可能となり、直流電力の最適レ ベルを決定することが可能となる。Therefore, it is possible to make the detected turbidity level of the dust particles passing through the electrostatic precipitator substantially equal to the predetermined turbidity level, and determine the optimum level of the DC power. It becomes possible.

【0044】 これにより、従来例に比べて静電集塵装置の間欠給電制御に係る人的労力が軽 減化され、また、その自動化が図られる。このことで、粉塵除去処理の合理化及 び当該装置の性能向上を図ることが可能となる。As a result, compared with the conventional example, the human labor involved in the intermittent power supply control of the electrostatic precipitator is reduced, and the automation thereof is achieved. This makes it possible to rationalize the dust removal process and improve the performance of the device.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の実施例に係るESP自動給電制御装置
の構成図である。
FIG. 1 is a configuration diagram of an ESP automatic power supply control device according to an embodiment of the present invention.

【図2】本考案の実施例に係るESP自動給電制御装置
のCPUの制御(メインルーチン)フローチャートであ
る。
FIG. 2 is a control (main routine) flowchart of the CPU of the ESP automatic power supply control device according to the embodiment of the present invention.

【図3】本考案の実施例に係るESP自動給電制御装置
のCPUの制御(サブルーチン)フローチャートであ
る。
FIG. 3 is a control (subroutine) flowchart of the CPU of the ESP automatic power supply control device according to the embodiment of the present invention.

【図4】従来例に係る静電集塵装置の間欠給電制御装置
の構成図である。
FIG. 4 is a configuration diagram of an intermittent power supply control device of an electrostatic dust collector according to a conventional example.

【図5】従来例に係るESP給電制御装置を説明する交
流信号波形図(その1)である。
FIG. 5 is an AC signal waveform diagram (No. 1) for explaining an ESP power feeding control device according to a conventional example.

【図6】従来例に係るESP給電制御装置を説明する交
流信号波形図(その2)である。
FIG. 6 is an AC signal waveform diagram (No. 2) for explaining an ESP power feeding control device according to a conventional example.

───────────────────────────────────────────────────── フロントページの続き (72)考案者 張 瑞進 台湾新竹県竹東鎮中興路四段195号64館 財団法人工業技術研究院内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor, Zhang Suin, No. 195, 4th Section, Zhongxing Road, Zhongxing Town, Hsinchu County, Taiwan 64th Building, National Institute of Advanced Industrial Science and Technology

Claims (4)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 交流電源に接続された整流手段によって
発生される直流電力により起動/給電される静電集塵装
置の構成において、上記交流電源の通電・非通電期間を
調整することにより上記直流電力の大きさを制御する装
置であって、 (a)上記静電集塵装置を通って流れる粉塵粒子の濁度
を検出する濁度計と、 (b)上記静電集塵装置を通って流れる粉塵粒子で検出
された濁度レベルOPdに基づいて参照テーブルを検索
するCPU手段とを具備し、 上記参照テーブルが直流電力レベルを可変させる所定数
の通電・非通電期間から構成され、 上記CPU手段が上記検出された濁度レベルOPd と初
期濁度レベルOPs との間の差が所定の許容範囲内とな
るような上記通電・非通電期間のひとつの値が見つかる
まで、それぞれが対応する濁度レベルOPdと初期濁度
レベルOPs とを相対させて直流電力の最適レベルを検
出することを特徴とする静電集塵装置の自動間欠給電制
御装置。
1. A structure of an electrostatic precipitator which is activated / powered by a DC power generated by a rectifying means connected to an AC power supply, wherein the DC power is adjusted by adjusting the energization / de-energization period of the AC power supply. A device for controlling the magnitude of electric power, comprising: (a) a turbidimeter for detecting the turbidity of dust particles flowing through the electrostatic precipitator; and (b) passing through the electrostatic precipitator. CPU means for retrieving a reference table based on the turbidity level OPd detected by flowing dust particles, the reference table comprising a predetermined number of energized / non-energized periods for varying the DC power level, Until the means finds one value of the energized / de-energized period such that the difference between the detected turbidity level OPd and the initial turbidity level OPs is within a predetermined allowable range, the corresponding turbidity is detected. Every time An automatic intermittent power supply control device for an electrostatic precipitator, characterized in that an optimum level of DC power is detected by making a level OPd and an initial turbidity level OPs face each other.
【請求項2】上記通電・非通電期間の参照テーブルが2
0の項目を含むことを特徴とする請求の範囲第1項に記
載の静電集塵装置の自動間欠給電制御装置。
2. The reference table for the energized / non-energized period is 2
The automatic intermittent power feeding control device for an electrostatic precipitator according to claim 1, characterized in that it includes 0 items.
【請求項3】上記検出された濁度レベルOPd について
の所定の許容範囲が−3≦OPd −OPs ≦0からなる
ことを特徴とする請求の範囲第1項に記載の静電集塵装
置の自動間欠給電制御装置。
3. The electrostatic precipitator according to claim 1, wherein the predetermined permissible range for the detected turbidity level OPd is -3≤OPd-OPs≤0. Automatic intermittent power supply control device.
【請求項4】上記CPU手段は上記最適な直流電力が発
見された後、上記静電集塵装置を通って流れる粉塵粒子
の濁度の監視を継続し、検出された濁度レベルと初期設
定の濁度レベルとの間に上記所定の許容範囲を逸脱する
ほどの差が検出された場合には、上記CPU手段が再度
上記通電・非通電期間の参照テーブルの検索を実行する
ことを特徴とする請求の範囲第1項に記載の静電集塵装
置の自動間欠給電制御装置。
4. The CPU means continues to monitor the turbidity of dust particles flowing through the electrostatic precipitator after the optimum DC power is found, and the detected turbidity level and initial setting. When a difference between the turbidity level and the turbidity level is detected that deviates from the predetermined allowable range, the CPU means again searches the reference table of the energized / non-energized period. An automatic intermittent power supply control device for an electrostatic precipitator according to claim 1.
JP6869892U 1992-10-01 1992-10-01 Automatic intermittent power supply controller for electrostatic precipitator Pending JPH0664732U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6869892U JPH0664732U (en) 1992-10-01 1992-10-01 Automatic intermittent power supply controller for electrostatic precipitator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6869892U JPH0664732U (en) 1992-10-01 1992-10-01 Automatic intermittent power supply controller for electrostatic precipitator

Publications (1)

Publication Number Publication Date
JPH0664732U true JPH0664732U (en) 1994-09-13

Family

ID=13381252

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6869892U Pending JPH0664732U (en) 1992-10-01 1992-10-01 Automatic intermittent power supply controller for electrostatic precipitator

Country Status (1)

Country Link
JP (1) JPH0664732U (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5879560A (en) * 1981-11-06 1983-05-13 Hitachi Plant Eng & Constr Co Ltd electrostatic precipitator
JPS5936559A (en) * 1982-08-26 1984-02-28 Mitsubishi Heavy Ind Ltd Controlling method of electrostatic precipitator
JPS61468A (en) * 1984-06-14 1986-01-06 Fuji Electric Co Ltd Intermittent charge controlling system of electric precipitator

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5879560A (en) * 1981-11-06 1983-05-13 Hitachi Plant Eng & Constr Co Ltd electrostatic precipitator
JPS5936559A (en) * 1982-08-26 1984-02-28 Mitsubishi Heavy Ind Ltd Controlling method of electrostatic precipitator
JPS61468A (en) * 1984-06-14 1986-01-06 Fuji Electric Co Ltd Intermittent charge controlling system of electric precipitator

Similar Documents

Publication Publication Date Title
JP4744719B2 (en) Method and apparatus for operating a gas discharge lamp
TW406039B (en) Power supply apparatus for plasma arc utilizing equipment
US7833322B2 (en) Air treatment apparatus having a voltage control device responsive to current sensing
KR950011993A (en) Operation control device of air conditioner and its control method
US5288309A (en) Flue gas conditioning agent demand control apparatus
EP1176855A3 (en) High pressure discharge lamp driving apparatus, luminaire and high pressure discharge lamp driving method
JPS61141949A (en) Method of controlling intermittent voltage supply to electrostatic dust collector
EP0701389A3 (en) Circuit for controlling the light intensity and the operating mode of discharge lamps
JP2014533607A (en) Method and apparatus for cleaning an electrostatic precipitator
EP0097161A4 (en) Detecting, measuring and applying back corona parameters on an electrostatic precipitator.
KR101084009B1 (en) Determination System and Determination Method of Air Purifier Filter Replacement by Measuring Motor Speed
US3469371A (en) Apparatus for controlling the removal of particle accumulations from the electrodes of an electric precipitator
CA2189878A1 (en) Flue gas conditioning system for intermittently energized precipitation
US5321274A (en) Automatic intermittent energization controller of electrostatic precipitator (ESP)
CN118301812A (en) Power line switching communication control mode and LED lamp control system
JP2002216995A (en) Static eliminator and high-voltage generating circuit assembled in this
KR20100005501A (en) System and method for judging the noninstalling of humidification filter of natural humidification air cleaner
CN111023210B (en) High-voltage power supply system of intelligent oil fume purifier and control method
RU2147468C1 (en) Method of automatic control over voltage of electric filter
CN116321608B (en) Intelligent illumination control method based on road detection
CN216351053U (en) Positive and negative ion generator fault diagnosis control circuit
KR101834721B1 (en) Electronic ballast-compatible led driving device and driving method therefor
CN220964671U (en) Power stable generating circuit, ion generating module and aldehyde removal odor eliminator
JPH06349433A (en) Ion source device
JPS60157151A (en) Vacuum exhaust controller

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02