JPH0711238Y2 - Scaffolding chains - Google Patents
Scaffolding chainsInfo
- Publication number
- JPH0711238Y2 JPH0711238Y2 JP1988151635U JP15163588U JPH0711238Y2 JP H0711238 Y2 JPH0711238 Y2 JP H0711238Y2 JP 1988151635 U JP1988151635 U JP 1988151635U JP 15163588 U JP15163588 U JP 15163588U JP H0711238 Y2 JPH0711238 Y2 JP H0711238Y2
- Authority
- JP
- Japan
- Prior art keywords
- chain
- operation frame
- chains
- scaffold
- turnbuckle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000000725 suspension Substances 0.000 claims description 5
- 238000010276 construction Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Description
【考案の詳細な説明】 〔産業上の利用分野〕 この考案は、建築工事現場等において使用する足場の吊
りチェーンに関するものである。[Detailed Description of the Invention] [Industrial field of application] The present invention relates to a suspension chain for a scaffold used at a construction site or the like.
従来より使用されている足場の吊りチェーンを第4図に
示す、この足場の吊りチェーン50は、多数のチェーンリ
ングがつなぎ合わされて構成され、両端にフック51、52
を有するものである。Fig. 4 shows a suspension chain of a scaffold that has been conventionally used. This suspension chain of a scaffold 50 is configured by connecting a number of chain rings, and hooks 51, 52 are provided at both ends.
Is to have.
上記チェーン50を使用して足場を吊る際には、構築物A
に設けられた吊手Bの挿通孔にチェーン50の一端を挿入
してループ53を形成し、一方のフック51をチェーン50の
上部に位置するチェーンリングに引っ掛け、チェーン50
の他端を引き上げ、ループ54を形成して、他方のフック
52をチェーン50に下部に位置するチェーンリングに引っ
掛ける。When suspending the scaffold using the above chain 50, the structure A
The one end of the chain 50 is inserted into the insertion hole of the lifting hand B provided in the above to form a loop 53, and one hook 51 is hooked on the chain ring located above the chain 50 to
Pull up the other end of the
Hook 52 to chain 50 on the lower chainring.
多数の吊手Dに上記のようにチェーン50を吊り下げ、各
チェーン50のループ54に縦パイプCを挿通する。このよ
うに支持された縦パイプCを複数列平行に設け、それら
の縦パイプC間に複数の横パイプDを掛け渡し、各縦パ
イプCと横パイプDの交差部をパイプクランプで連結し
て、複数の横パイプD上に足場Eを渡す。As described above, the chain 50 is hung on a large number of hanging hands D, and the vertical pipes C are inserted into the loops 54 of each chain 50. The vertical pipes C supported in this way are provided in parallel in a plurality of columns, a plurality of horizontal pipes D are laid between the vertical pipes C, and the intersections of the vertical pipes C and the horizontal pipes D are connected by pipe clamps. , Pass the scaffold E over a plurality of lateral pipes D.
〔考案が解決しようとする課題〕 しかしながら、上記のように足場Eを吊るすと、足場E
を支持する縦パイプCの歪みや、各チェーン50の寸法誤
差のため、各チェーン50が均等に緊張せず、緩んだ状態
となるものもあり、このような状態では、足場Eががた
つくほか、緊張しているチェーン50に計算外の大きな荷
重が作用し、安全性に問題が生じる場合があった。[Problems to be solved by the invention] However, if the scaffold E is suspended as described above, the scaffold E
Due to the distortion of the vertical pipe C that supports the and the dimensional error of each chain 50, each chain 50 may not be evenly tensioned and may be in a loose state. In such a state, the scaffold E rattles, There was a case where a large uncalculated load acted on the tensioned chain 50, which caused a safety problem.
上記チェーン50では、フック51またはフック52を他のチ
ェーンリングに掛け替えることにより各チェーン50の緊
張状態を調整することはできるが、チェーンリング一個
の長さを単位として調整することしかできず、全てのチ
ェーン50を均等に緊張させることができなかった。ま
た、フックの掛け替えに手間取ることもあった。In the above chain 50, the tension state of each chain 50 can be adjusted by replacing the hook 51 or the hook 52 with another chain ring, but only the length of one chain ring can be adjusted as a unit, It was not possible to tension all chains 50 equally. Also, it took time to change the hooks.
そこで、この考案は、長さの微調整が容易にできる足場
の吊りチェーンを提供することを課題とする。Then, this invention makes it a subject to provide the suspension chain of a scaffold which can make fine adjustment of length easily.
上記の課題を解決するため、この考案は、多数のチェー
ンリングがつなぎ合わされ、両端にフックを有するチェ
ーン本体を分割して複数の分割チェーンを形成し、それ
らの分割チェーン同士を操作枠と、その操作枠の一端に
ねじ込まれたねじ棒と、操作枠の他端に回転自在に支持
された連結軸とから成るターンバックルで連結した構成
を採用したのである。In order to solve the above-mentioned problems, the present invention has a structure in which a large number of chain rings are connected to each other and a chain main body having hooks at both ends is divided to form a plurality of divided chains. A structure is adopted in which a turnbuckle including a screw rod screwed into one end of the operation frame and a connection shaft rotatably supported at the other end of the operation frame is connected.
チェーン本体の両端に設けたフックをそれぞれチェーン
リングに引っ掛けてループを形成し、それらのループに
より構築物に足場を吊り下げる。Hooks provided at both ends of the chain body are hooked on the chain rings to form loops, and the loops suspend the scaffolding on the structure.
足場を吊る各チェーンの緊張状態を調整する際には、タ
ーンバックルの操作枠を回転させる。操作枠とねじ棒と
の相対的な移動により、チェーン本体の長さが連続的に
変化する。To adjust the tension of each chain that suspends the scaffold, rotate the operation frame of the turnbuckle. The length of the chain body continuously changes due to the relative movement of the operation frame and the screw rod.
以下、この考案の実施例を添付図面に基づいて説明す
る。An embodiment of the present invention will be described below with reference to the accompanying drawings.
第1図に示すように、多数のチェーンリングがつなぎ合
わされたチェーン本体1の両端には、それぞれフック
2、3が設けられている。上記チェーン本体1は二分割
され、一対の分割チェーン4、5が形成されており、そ
の一対の分割チェーン4、5は、ターンバックル6によ
り連結されている。As shown in FIG. 1, hooks 2 and 3 are provided at both ends of a chain body 1 in which a large number of chain rings are connected. The chain body 1 is divided into two to form a pair of divided chains 4 and 5, and the pair of divided chains 4 and 5 are connected by a turnbuckle 6.
上記ターンバックル6は、第2図に示すように、操作枠
7と、その操作枠7の一端にねじ込まれたねじ棒8と、
操作枠7の他端に回転自在に支持された連結軸9とから
成る。ねじ棒8のねじ部の長さは、チェーンリング一個
分程度の長さとなっている。The turnbuckle 6 is, as shown in FIG. 2, an operation frame 7, a screw rod 8 screwed into one end of the operation frame 7,
It comprises a connecting shaft 9 rotatably supported at the other end of the operation frame 7. The length of the threaded portion of the threaded rod 8 is about the length of one chain ring.
上記のようなチェーンにより足場を吊る際には、第4図
に示した従来例とは同様に、一方のフック2を使用して
構築物にチェーンを吊った後、第3図に示すように、チ
ェーンの下端を引き上げてループ10を形成し、他方のフ
ック3をチェーンの下部に位置するチェーンリングに引
っ掛け、ループ10に縦パイプCを挿通する。このように
支持された縦パイプCを複数列平行に設け、それらの縦
パイプC間に複数の横パイプDを掛け渡し、各縦パイプ
Cと横パイプDの交差部をパイプクランプで連結して、
複数の横パイプD上に足場Eを渡す。When suspending the scaffolding by the chain as described above, as in the conventional example shown in FIG. 4, after suspending the chain on the structure using one hook 2, as shown in FIG. The lower end of the chain is pulled up to form the loop 10, the other hook 3 is hooked on the chain ring located at the lower part of the chain, and the vertical pipe C is inserted through the loop 10. The vertical pipes C supported in this way are provided in parallel in a plurality of columns, a plurality of horizontal pipes D are laid between the vertical pipes C, and the intersections of the vertical pipes C and the horizontal pipes D are connected by pipe clamps. ,
The scaffold E is passed over the plurality of horizontal pipes D.
足場Eを吊る各チェーンの緊張状態を調整する際には、
ターンバックル6の操作枠7を回転させる。操作枠7と
ねじ棒8との相対的な移動により、チェーン本体1の長
さが連続的に変化する。When adjusting the tension of each chain that suspends the scaffold E,
The operation frame 7 of the turnbuckle 6 is rotated. The length of the chain body 1 is continuously changed by the relative movement of the operation frame 7 and the screw rod 8.
連結軸9が操作枠7に回転自在に支持されているため、
操作枠7の回転に伴ってチェーン本体1が捩じれること
はない。Since the connecting shaft 9 is rotatably supported by the operation frame 7,
The chain body 1 is not twisted with the rotation of the operation frame 7.
また、図示のものでは、チェーン本体1に設けたターン
バックル6は一個だけであるが、複数設けてもよい。Further, in the illustrated example, the number of the turnbuckle 6 provided on the chain body 1 is only one, but a plurality of the turnbuckles 6 may be provided.
この考案によれば、以上のように、分割されたチェーン
同士を操作枠と、その操作枠の一端にねじ込まれたねじ
棒と、操作枠の他端に回転自在に支持された連結軸とか
ら成るターンバックルで連結したので、足場を吊る各チ
ェーンの緊張状態を調整する際、ターンバックルの操作
枠を回転させることにより、長さの微調整を容易に行う
ことができる。According to this invention, as described above, the divided chains are composed of the operation frame, the screw rod screwed into one end of the operation frame, and the connecting shaft rotatably supported at the other end of the operation frame. Since they are connected by the turnbuckle, the length of the chains can be easily adjusted by rotating the operation frame of the turnbuckle when adjusting the tension state of each chain that suspends the scaffold.
従って、足場を吊る全てのチェーンを均等に緊張させる
ことができ、安全性が向上する。Therefore, all chains that suspend the scaffold can be evenly tensioned, and safety is improved.
また、連結軸が操作枠に回転自在に支持されているた
め、操作枠の回転に伴ってチェーン本体が捩じれること
がない。Further, since the connecting shaft is rotatably supported by the operation frame, the chain body is not twisted as the operation frame rotates.
第1図は本考案の実施例を示す一部省略側面図、第2図
は同上のターンバックルを示す断面図、第3図は同上の
使用状態を示す図、第4図は従来例の使用状態を示す図
である。 1……チェーン本体、2、3……フック、4、5……分
割チェーン、6……ターンバックル、7……操作枠、8
……ねじ棒、9……連結軸。FIG. 1 is a partially omitted side view showing an embodiment of the present invention, FIG. 2 is a sectional view showing a turnbuckle of the same, FIG. 3 is a view showing a usage state of the same, and FIG. It is a figure which shows a state. 1 ... Chain body, 2,3 ... Hook, 4,5 ... Split chain, 6 ... Turnbuckle, 7 ... Operating frame, 8
…… Screw rod, 9 …… Coupling shaft.
Claims (1)
両端にフックを有するチェーン本体を分割して複数の分
割チェーンを形成し、それらの分割チェーン同士を操作
枠と、その操作枠の一端にねじ込まれたねじ棒と、操作
枠の他端に回転自在に支持された連結軸とから成るター
ンバックルで連結した足場の吊りチェーン。1. A number of chain rings are connected together,
Divide the chain body that has hooks at both ends to form multiple split chains, and connect these split chains to the operation frame, the screw rod screwed into one end of the operation frame, and the other end of the operation frame. A suspension chain of scaffolds connected by a turnbuckle consisting of a connecting shaft supported by.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1988151635U JPH0711238Y2 (en) | 1988-11-21 | 1988-11-21 | Scaffolding chains |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1988151635U JPH0711238Y2 (en) | 1988-11-21 | 1988-11-21 | Scaffolding chains |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0271746U JPH0271746U (en) | 1990-05-31 |
| JPH0711238Y2 true JPH0711238Y2 (en) | 1995-03-15 |
Family
ID=31425850
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1988151635U Expired - Lifetime JPH0711238Y2 (en) | 1988-11-21 | 1988-11-21 | Scaffolding chains |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0711238Y2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5564398B2 (en) * | 2010-10-26 | 2014-07-30 | 健介 清水 | Chain misalignment prevention device |
| JP5114605B1 (en) * | 2012-07-02 | 2013-01-09 | 株式会社Osk | Single pipe hanging bracket |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5167646A (en) * | 1974-12-07 | 1976-06-11 | Nagamasa Uchida |
-
1988
- 1988-11-21 JP JP1988151635U patent/JPH0711238Y2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0271746U (en) | 1990-05-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207469103U (en) | A kind of building bridge pier anchor ear and its escape way steel pipe frame structure | |
| CN203878961U (en) | Attached automatic lifting multilayer construction platform | |
| US3763617A (en) | Tieback apparatus | |
| CN219453079U (en) | An adaptive tightening device for air sampling pipeline installation | |
| CN217079667U (en) | Elevator shaft and daylighting are handled well and are hung mould structure | |
| CN211846845U (en) | Stable form I-steel hoist | |
| JP2001123656A (en) | Chain slack remover | |
| CN208961375U (en) | Strengthen the pipeline tensioning device | |
| CN208749069U (en) | An adjustable spreader for hanging basket | |
| CN222922762U (en) | A pile foundation steel cage hanger | |
| CN222348472U (en) | A gypsum board hanger | |
| CN216918274U (en) | PC wallboard hoist and mount reinforcing apparatus | |
| SU709781A1 (en) | Hanging scaffolds | |
| JPH1181654A (en) | Scaffolding board suspendedscaffold and its temporary installation method | |
| CN224244402U (en) | Scaffold folding net hanging device | |
| CN218091988U (en) | Formwork fixing device for construction engineering | |
| CN217536721U (en) | Connecting structure is assembled with support to cast-in-place construction of bridge | |
| CN214575490U (en) | Diagonal tension door type scaffold | |
| CN221700871U (en) | Adjustable linear lifting appliance for vertical prefabrication of arch ribs | |
| CN119218877B (en) | Hoisting transportation equipment convenient for angle adjustment | |
| RU2078020C1 (en) | Boom variable ratio load sheave-block | |
| CN223689354U (en) | Building construction building net | |
| CN214170001U (en) | Safety protection system for disassembling and assembling external scaffold | |
| CN219416396U (en) | Electronic hanging scale capable of hanging steel pipe | |
| CN212151392U (en) | Equipment hoisting machine constructs for building site |