JPH071971B2 - Floor wiring construction method - Google Patents

Floor wiring construction method

Info

Publication number
JPH071971B2
JPH071971B2 JP1051544A JP5154489A JPH071971B2 JP H071971 B2 JPH071971 B2 JP H071971B2 JP 1051544 A JP1051544 A JP 1051544A JP 5154489 A JP5154489 A JP 5154489A JP H071971 B2 JPH071971 B2 JP H071971B2
Authority
JP
Japan
Prior art keywords
duct
wiring
floor
construction method
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1051544A
Other languages
Japanese (ja)
Other versions
JPH02231914A (en
Inventor
廣司 沖田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nihon Pit Co Ltd
Original Assignee
Nihon Pit Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nihon Pit Co Ltd filed Critical Nihon Pit Co Ltd
Priority to JP1051544A priority Critical patent/JPH071971B2/en
Publication of JPH02231914A publication Critical patent/JPH02231914A/en
Publication of JPH071971B2 publication Critical patent/JPH071971B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Details Of Indoor Wiring (AREA)
  • Installation Of Indoor Wiring (AREA)

Description

【発明の詳細な説明】 A.発明の目的 (1) 産業上の利用分野 本発明は床配線施工方法、特に、基礎構造体上に複数の
支持構造部材を相互に間隔をとって固定する工程、各支
持構造部材上に配線収納ダクトを載置し、またその配線
収納ダクト上に押え部材を載置する工程、配線収納ダク
トの長手方向両側方に在って各支持構造部材上に立設さ
れたナット部材に、押え部材に存する各押えボルトを螺
着して配線収納ダクトを各支持構造部材上に固定する工
程、基礎構造体上にコンクリート打設作業を行って床を
形成すると共にその床に配線収納ダクトをその上面を露
出させて埋設する工程、床面を配線収納ダクト上面と面
一に仕上げる工程、およびコンクリートが硬化した後押
え部材を取外す工程を用いる床配線施工方法の改良に関
する。
DETAILED DESCRIPTION OF THE INVENTION A. Objectives of the Invention (1) Field of Industrial Application The present invention relates to a floor wiring construction method, and more particularly, a step of fixing a plurality of supporting structural members on a foundation structure at intervals. , A step of placing the wiring accommodating duct on each supporting structure member and placing a holding member on the wiring accommodating duct, standing on each supporting structural member on both sides in the longitudinal direction of the wiring accommodating duct The step of fixing the wiring storage duct on each supporting structure member by screwing each pressing bolt existing in the pressing member to the formed nut member, performing the concrete placing work on the foundation structure to form the floor and Regarding improvement of a floor wiring construction method using a step of burying a wiring storage duct on the floor with its upper surface exposed, a step of finishing the floor surface flush with the upper surface of the wiring storage duct, and a step of removing a holding member after hardening of concrete .

(2) 従来の技術 この種床配線施工方法として、本出願人は、先に、特願
昭62-323495号明細書および図面に開示された方法を提
案している。
(2) Conventional Technology As the seed floor wiring construction method, the present applicant has previously proposed the method disclosed in the specification of Japanese Patent Application No. 62-323495 and the drawings.

(3) 発明が解決しようとする課題 前記のように配線収納ダクトを各支持構造部材に押え部
材を用いて固定する理由は、コンクリート打設作業中に
おける配線収納ダクトの浮上り、垂下がり、水平面内で
の位置ずれ等を防止することにあるが、床面の仕上げ作
業時には、各押えボルトが床面上に突出し、また押え部
材が配線収納ダクトから押えボルト側に突出しているの
で、各押えボルトおよび配線収納ダクト上端縁部間にお
いて床面の仕上げ作業性が悪いという問題がある。
(3) Problems to be Solved by the Invention As described above, the reason why the wiring storage duct is fixed to each support structure member by using the pressing member is that the wiring storage duct floats up, hangs down, or is level during the concrete pouring work. Although it is to prevent the position from being displaced within the interior, each presser bolt protrudes above the floor surface during the finishing work on the floor surface, and the presser member protrudes from the wiring storage duct toward the presser bolt side. There is a problem that the workability of finishing the floor surface is poor between the bolt and the upper edge of the wiring storage duct.

本発明は前記問題を解決し得る前記床配線施工方法を提
供することを目的とする。
An object of the present invention is to provide the floor wiring construction method capable of solving the above problems.

B.発明の構成 (1) 課題を解決するための手段 本発明は、基礎構造体上に複数の支持構造部材を相互に
間隔をとって固定する工程、各支持構造部材上に配線収
納ダクトを載置し、また該配線収納ダクト上に押え部材
を載置する工程、前記配線収納ダクトの長手方向両側方
に在って各支持構造部材上に立設されたナット部材に、
前記押え部材に存する各押えボルトを螺着して前記配線
収納ダクトを各支持構造部材上に固定する工程、前記基
礎構造体上にコンクリート打設作業を行って床を形成す
ると共に該床に前記配線収納ダクトをその上面を露出さ
せて埋設する工程、床面を前記配線収納ダクト上面と面
一に仕上げる工程、および前記コンクリートが硬化した
後前記押え部材を取外す工程を用いる床配線施工方法で
あって、各ナット部材上端部および前記配線収納ダクト
上端縁部間にて、前記床に埋設されて前記床面の一部を
構成する複数の床面構成体を、前記コンクリート打設作
業前に各ナット部材に保持させることを特徴とする。
B. Structure of the Invention (1) Means for Solving the Problems The present invention is a process of fixing a plurality of supporting structure members on a foundation structure at intervals, and a wiring accommodating duct on each supporting structure member. A step of placing and holding a pressing member on the wiring accommodating duct; on nut members standing on both sides in the longitudinal direction of the wiring accommodating duct and erected on each supporting structure member,
A step of screwing each holding bolt existing in the holding member to fix the wiring storage duct on each supporting structure member, concrete placing work is performed on the foundation structure to form a floor, and the floor is formed on the floor. A floor wiring construction method using a step of burying the wiring storage duct with its upper surface exposed, a step of finishing the floor surface flush with the upper surface of the wiring storage duct, and a step of removing the holding member after the concrete has hardened. Between each nut member upper end portion and the wiring storage duct upper end edge portion, a plurality of floor surface structures embedded in the floor and forming a part of the floor surface are provided before the concrete placing work. It is characterized in that it is held by a nut member.

(2) 作用 前記手法によれば、各押えボルトおよび配線収納ダクト
上端縁部間において、床面の一部が床面構成体より構成
されるので、その部分の仕上げ作業を行う必要がない。
(2) Operation According to the above-mentioned method, since a part of the floor surface is formed by the floor surface structure between each of the holding bolts and the upper edge portion of the wiring accommodating duct, it is not necessary to finish the portion.

(3) 実施例 第1,第2図に示す床配線構造において、H形鋼からなる
複数の縦梁11が相互に間隔をとって平行に配設され、ま
たそれら縦梁11と直交する方向に延びるようにH形鋼か
らなる複数の横梁12が相互に間隔をとって平行に配設さ
れる。各縦梁11および各横梁12上に、複数のデッキプレ
ート2が相互に連結して連続的に敷かれ、そのデッキプ
レート2上にコンクリートが打設されて床3が形成され
る。横梁12と平行に延びる配線収納ダクト4が、相隣る
両横梁12間にて床3に埋設され、そのダクト4の上面は
床面5と面一になっている。
(3) Example No. 1, the floor wiring structure shown in FIG. 2, a plurality of longitudinal beams 1 1 made of H-beams are arranged in parallel spaced from each other, also orthogonal their longitudinal beam 1 1 a plurality of cross beams 1 2 consisting of H-shaped steel so as to extend in a direction are disposed in parallel spaced from each other. Kakutatehari to 1 1 and Kakuyokohari 1 2 over a plurality of deck plate 2 is laid continuously interconnected, concrete is pouring the floor 3 is formed thereon deck plate 2. Cross beam 1 2 extend parallel wiring housing duct 4, is embedded in the floor 3 at phase Tonariru both lateral beams 1 2 between the upper surface of the duct 4 has a floor 5 and flush.

配線収納ダクト4は、上部が開口した略U字状のダクト
本体6と、そのダクト本体6の上部を開閉自在に閉鎖す
る蓋7とからなり、その蓋7は止め具8によりダクト本
体6に固定される。
The wiring accommodating duct 4 is composed of a substantially U-shaped duct body 6 having an open top and a lid 7 for opening and closing the top of the duct body 6, and the lid 7 is attached to the duct body 6 by a stopper 8. Fixed.

配線収納ダクト4において、ダクト本体6の底部に立設
された4つのセパレータ91〜94により、第2図左側から
右側に向けて順に、電源線を収納するための電源線通線
路101、電源線接続線路102、電話線通線路103、電話・
信号線接続線路104および信号線通線路105が画成され
る。電源線接続線路102は、電源線通線路101内に収納さ
れる電源線の接続や取出しを行なうためのものであり、
セパレータ91には電源線の授受を行なう通孔11が形成さ
れ、その通孔11にゴム製グロメット12が装着される。電
源線はそのグロメット12の薄肉部に切れ目を入れて通孔
11に挿通される。また電話・信号線接続線路104は、電
話線通線路103に収納された電話線および信号線通線路1
05に収納された信号線の接続や取出しを行なうためのも
のであり、セパレータ93,94の通孔には前記同様にグロ
メット12が設けられる。
In the wiring housing duct 4, by the four separators 91 to 93 4 provided upright on the bottom of the duct body 6, in this order toward the right side from the second left side of the drawing, the power line communication line 10 1 for housing the power line , Power line connection line 10 2 , telephone line communication line 10 3 , telephone
A signal line connection line 10 4 and a signal line through line 10 5 are defined. The power supply line connection line 10 2 is for connecting and extracting the power supply line housed in the power supply line communication line 10 1 .
The separator 9 1 through hole 11 for exchanging power line is formed, a rubber grommet 12 is attached to the through hole 11. Make a cut in the thin part of the grommet 12 for the power supply line
Inserted in 11. The telephone / signal line connecting line 10 4 is a telephone line and a signal line connecting line 1 stored in the telephone line connecting line 10 3.
0 5 is intended for connection or retrieve the stored signal lines, the through-hole of the separator 9 3, 9 4 grommet 12 is provided in the same manner as described above.

また各セパレータ91〜94の高さは、寸法公差を考慮して
蓋7との間に間隙を生じる程度に設定されている。各セ
パレータ91〜94の上端に弾性材料からなる緩衝部材13が
それぞれ取付けられ、これにより蓋7上の歩行等により
蓋7が撓んでセパレータ91〜94に衝突した際の衝突音の
発生が防止される。
The heights of the separators 9 1 to 9 4 are set so that a gap is formed between the separators 9 1 to 9 4 and the lid 7 in consideration of dimensional tolerance. A cushioning member 13 made of an elastic material is attached to the upper ends of the separators 9 1 to 9 4 , respectively, whereby the lid 7 bends due to walking on the lid 7 or the like, and a collision noise when the collision occurs with the separators 9 1 to 9 4 Occurrence is prevented.

配線収納ダクト4は、各縦梁11、各横梁12およびデッキ
プレート2から成る基礎構造体B上に固定された後、コ
ンクリート打設作業により床3に埋設されるものであ
り、次に配線収納ダクト4の固定構造について説明す
る。
Wire receiving duct 4, Kakutatehari 1 1, after being secured to the crossbeam 1 2 and the deck plate 2 from consisting basic structure on B, and which is embedded in the floor 3 by concrete設作industry, then The fixing structure of the wiring storage duct 4 will be described.

第3〜第6図において、配線収納ダクト4の敷設ルート
L(第3図)上に在る各縦梁11上に、配線収納ダクト4
の幅よりも広い間隔をとって一対の第1支持ボルト141
が立設される。各第1支持ボルト141の下端頭部には、
そのボルト141が回転し得るように取付金具15が取付け
られ、その取付金具15はデッキプレート2の非連結部を
通して縦梁11上に溶接により直接固着される。両第1支
持ボルト141に、逆チャンネル形第1ダクトホルダ161
両端部に存するナット17が螺合されており、したがって
第1ダクトホルダ161から突出する第1支持ボルト141
端の係合溝18に工具を係合してそのボルト141を回転さ
せれば、第1ダクトホルダ161を昇降させることができ
る。第1ダクトホルダ161の各ナット取付部よりも内側
には、上方からの螺合が可能なようにナット19が固着さ
れる。
In the third to sixth view, on each longitudinal beam 1 1 located on the laying route L of the wiring housing duct 4 (FIG. 3), the wiring housing duct 4
A pair of first support bolts 14 1 with a spacing wider than the width of
Is erected. At the lower end head of each first support bolt 14 1 ,
As the bolt 14 mounting bracket 15 so that one can rotate is attached, the mounting bracket 15 is fixed directly by welding on the longitudinal beam 1 1 through the non-connecting portion of the deck plate 2. Both first support bolts 14 1, and a nut 17 existing on both ends of the reverse channel shaped first duct holder 16 1 is screwed, thus the first support bolts 14 1 the tip of which projects from 1 first duct holder 16 By engaging a tool in the engaging groove 18 and rotating the bolt 14 1 thereof, the first duct holder 16 1 can be moved up and down. A nut 19 is fixed to the inside of each nut mounting portion of the first duct holder 16 1 so as to be screwed from above.

これら各第1支持ボルト141、取付金具15、第1ダクト
ホルダ161およびナット17は支持構造部材Sを構成す
る。
Each of the first support bolts 14 1, mounting bracket 15, the first duct holder 16 1 and the nut 17 constitute a support structure S.

第1,第2、第7〜第10図に示すように、相隣る両縦梁11
間において隣接する両横梁12間に、デッキプレート2上
を延びる一対の配線収納ダクト用支持部材20が相互に間
隔をとって架設される。
As shown in Figs. 1, 2 and 7 to 10, both vertical beams 1 1 adjacent to each other
Between adjacent Ryoyokohari 1 2 between the pair of wiring housing duct support member 20 extending over the deck plate 2 are bridged by spaced from each other.

第9,第10図に明示するように、各支持部材20は、両端部
をデッキプレート2の非連結部を通して両横梁12上に溶
接により直接固着される下部主材21と、その下部主材21
と平行に配設されて配線収納ダクト4を支持する上部主
材22と、上部および下部主材22,21間を複数箇所で連結
する一対の棒状脚材23とより構成される。図示例では、
下部主材21は、相互に間隔をとって平行に配置された一
対の長い鋼棒b1と、両鋼棒b1間に等間隔に溶接された複
数の短い鋼棒b2とよりなり、また上部主材22は、相互に
平行な一対の長い鋼棒b2を密接状態で溶接してなり、さ
らに脚材23は鋼棒をジグザグ状に成形したものであり、
各脚材23の各頂部tは、上部主材22の一方の鋼棒b3に溶
接され、また各谷部vは、下部主材21の一方の鋼棒b1
溶接される。
9, as best shown in FIG. 10, each support member 20 includes a lower main member 21 which is secured directly by welding on both crossbeam 1 2 the ends through the non-connecting portion of the deck plate 2, the lower main Material 21
It is composed of an upper main member 22 arranged in parallel with and supporting the wiring storage duct 4, and a pair of rod-like leg members 23 connecting the upper and lower main members 22, 21 at a plurality of points. In the example shown,
The lower main material 21 is composed of a pair of long steel rods b 1 arranged in parallel at a distance from each other, and a plurality of short steel rods b 2 welded at equal intervals between both steel rods b 1 . Further, the upper main material 22 is formed by welding a pair of long steel rods b 2 parallel to each other in a close state, and further, the leg member 23 is a zigzag shaped steel rod,
Each top portion t of each leg member 23 is welded to one steel rod b 3 of the upper main member 22 and each trough portion v is welded to one steel rod b 1 of the lower main member 21.

各支持部材20の上部主材22上において、配線収納ダクト
4の幅よりも広い間隔をとった位置に一対の第2支持ボ
ルト142がそれぞれ立設される。各第2支持ボルト142
下端部には、そのボルト142が回転し得るように前記と
同様の取付金具24が取付けられ、その取付金具24は上部
主材22に溶接により固着される。両第2支持ボルト142
に、逆チャンネル形第2ダクトホルダ162の両端部に存
するナット25が螺合されており、したがって第2支持ボ
ルト142先端の係合溝26に工具を係合して第2支持ボル
ト142を回転させれば第2ダクトホルダ162を昇降させる
ことができる。第2ダクトホルダ162の各ナット取付部
よりも内側には雌ねじ孔27が形成される。
On the upper main member 22 of each support member 20, a pair of second support bolts 14 2 are provided upright at positions spaced apart from the width of the wiring accommodating duct 4. Each the second lower end of the support bolt 14 2, the bolts 14 2 similar mounting bracket 24 and the like can be rotated is mounted, the mounting bracket 24 is fixed by welding to the upper main member 22. Both second support bolts 14 2
The nuts 25 present at both ends of the reverse channel type second duct holder 16 2 are screwed together, and therefore, the tool is engaged with the engaging groove 26 at the tip of the second support bolt 14 2 to allow the second support bolt 14 2 to be engaged. The second duct holder 16 2 can be moved up and down by rotating 2 . Female screw holes 27 are formed inside the nut mounting portions of the second duct holder 16 2 .

第2ダクトホルダ162と支持部材20の上部主材22との間
を通過させてデッキプレート2上方にはコンクリートの
ひび割れを防止するための金網28が展設される。
The deck plate 2 upward to pass between the upper main member 22 of the second duct holder 16 2 and the support member 20 is a wire mesh 28 exhibition settings to prevent cracking of the concrete.

前記のように配設された複数の第1,第2ダクトホルダ16
1,162上に配線収納ダクト4が載置される。
A plurality of first and second duct holders 16 arranged as described above
The wiring accommodating duct 4 is placed on 1 , 16 2 .

第5図に明示するように、ダクト本体6の両側壁外面下
部に、上方に臨んで開口する係合溝29が全長に亘って形
成されている。
As clearly shown in FIG. 5, engagement grooves 29, which open upward and face each other, are formed on the lower portions of the outer surfaces of both side walls of the duct body 6 over the entire length.

第1ダクトホルダ161において、各係合溝29に連結金具3
0の一端が係合され、その他端は、配線収納ダクト4の
長手方向両側方において第1ダクトホルダ161上に立設
されたナット部材31により固定される。即ち、ナット部
材31は下方へ突出する小径ねじ軸部32を有し、その小径
ねじ軸部32が連結金具30を貫通してナット19に螺着され
る。
In the first duct holder 16 1 , each of the engaging grooves 29 has a connecting fitting 3
One end of 0 is engaged, and the other end is fixed by nut members 31 standing on the first duct holder 16 1 on both sides in the longitudinal direction of the wiring accommodating duct 4. That is, the nut member 31 has a small-diameter screw shaft portion 32 protruding downward, and the small-diameter screw shaft portion 32 penetrates the connecting fitting 30 and is screwed to the nut 19.

ナット部材31は上向きに開口する雌ねじ孔33を有する。The nut member 31 has a female screw hole 33 that opens upward.

第7図に明示するように第2ダクトホルダ162において
は、連結金具30は、その他端側を貫通する小ねじ341
雌ねじ孔27に螺着することによって固定される。
As clearly shown in FIG. 7, in the second duct holder 16 2 , the connecting fitting 30 is fixed by screwing a small screw 34 1 penetrating the other end side into the female screw hole 27.

またダクト本体6の底壁は、第1,第2ダクトホルダ1
61,162にそれぞれ複数の小ねじ342により連結される。
In addition, the bottom wall of the duct body 6 is the first and second duct holders 1
6 1 and 16 2 are connected to each other by a plurality of machine screws 34 2 .

以上のように配線収納ダクト4を第1,第2ダクトホルダ
161,162上に連結した後、各第1,第2支持ボルト141,1
42を前記のように回転させて第1,第2ダクトホルダ1
61,162を介し配線収納ダクト4を昇降させ、これによ
り配線収納ダクト4の高さ位置が決定される。
As described above, the wiring storage duct 4 is attached to the first and second duct holders.
16 1 , 16 2 After connecting on top of each, first and second support bolts 14 1 , 1
Rotate 4 2 as described above to rotate the 1st and 2nd duct holders 1
The wiring accommodating duct 4 is moved up and down via 6 1 and 16 2 so that the height position of the wiring accommodating duct 4 is determined.

第5,第11,第12図に明示するように、各ナット部材31
に、塩化ビニル樹脂等の合成樹脂よりなる床面構成体35
が保持される。その床面構成体35は、略四角形の平板部
36と、その下面略中央部に突設された筒部37とを有し、
その筒部37がナット部材31の上部に嵌合固着され、また
平板部36の一側縁が配線収納ダクト4の上端縁部eに密
接する。平板部36に筒部37に連通するボルト挿通孔38が
形成される。
As clearly shown in FIGS. 5, 11, and 12, each nut member 31
The floor surface structure 35 made of synthetic resin such as vinyl chloride resin.
Is retained. The floor structure 35 is a substantially rectangular flat plate portion.
36, and a cylindrical portion 37 protrudingly provided in the substantially central portion of the lower surface thereof,
The tubular portion 37 is fitted and fixed to the upper portion of the nut member 31, and one side edge of the flat plate portion 36 comes into close contact with the upper end edge portion e of the wiring storage duct 4. A bolt insertion hole 38 communicating with the tubular portion 37 is formed in the flat plate portion 36.

第5図に明示するように、配線収納ダクト4の蓋7上面
は養生紙39で覆われ、さらに養生紙39の幅方向両端を押
さえるべく、蓋7の両端部に養生材40が装着される。養
生紙39は、蓋7上に飛散したコンクリートにより蓋7が
汚れるのを防止する機能を有し、また養生材40はコンク
リートをこて塗りする時の定規としての機能をも有す
る。
As clearly shown in FIG. 5, the upper surface of the lid 7 of the wiring accommodating duct 4 is covered with the curing paper 39, and the curing material 40 is attached to both ends of the lid 7 so as to press both ends of the curing paper 39 in the width direction. . The curing paper 39 has a function of preventing the lid 7 from being soiled by the concrete scattered on the lid 7, and the curing material 40 also has a function as a ruler when the concrete is troweled.

このように養生紙39および養生材40を配置した状態で、
配線収納ダクト4の上面には、押え部材41が載置され
る。押え部材41は、配線収納ダクト4の長手方向に延び
る複数、図示例では4本の角パイプ材42と、各角パイプ
材42にその上方から嵌合する多数のチャンネル材43とよ
りなる。各2本の角パイプ材42は、それぞれ配線収納ダ
クト4の幅方向両端寄りに配設され、またチャンネル材
43の両端部は配線収納ダクト4の両側方に突出してい
る。
With the curing paper 39 and the curing material 40 thus arranged,
A pressing member 41 is placed on the upper surface of the wiring accommodating duct 4. The holding member 41 includes a plurality of, in the illustrated example, four square pipe members 42 extending in the longitudinal direction of the wiring accommodating duct 4, and a large number of channel members 43 fitted to the square pipe members 42 from above. Each of the two square pipe members 42 is disposed near both ends of the wiring accommodating duct 4 in the width direction, and is also a channel member.
Both ends of 43 project to both sides of the wiring storage duct 4.

第1ダクトホルダ161において、チャンネル材43の両端
部を貫通する各押えボルト44が各ナット部材31に螺着さ
れ、これにより配線収納ダクト4が押え部材41を介して
第1ダクトホルダ161に押圧固定される。
In the first duct holder 16 1 , the holding bolts 44 penetrating both ends of the channel member 43 are screwed to the nut members 31, so that the wiring accommodating duct 4 is held in the first duct holder 16 1 via the holding member 41. It is pressed and fixed to.

第3,第4,第13図に明示するように、相隣る両縦梁11間に
おいて、両第2ダクトホルダ162を回避するように複数
の第1ダクトホルダ161が、相互に間隔をとって配線収
納ダクト4下面側に配設される。各第1ダクトホルダ16
1は、第1支持ボルト141に支持されていない点を除いて
前記と同一構成を有し、したがって連結金具30、ナット
部材31、床面構成体35等を有する。
As clearly shown in FIGS. 3, 4, and 13, a plurality of first duct holders 16 1 are mutually provided so as to avoid both second duct holders 16 2 between adjacent vertical beams 11 1. It is arranged on the lower surface side of the wiring accommodating duct 4 at intervals. Each first duct holder 16
1 has the same configuration except that is not supported by the first support bolts 14 1, thus having the connecting fitting 30, the nut member 31, the floor structure 35 or the like.

そして、前記同様に各チャンネル材43を貫通する各押え
ボルト44が各ナット部材31に螺着され、これにより配線
収納ダクト4が押え部材41に吊持固定される。
Then, similarly to the above, each holding bolt 44 penetrating each channel member 43 is screwed to each nut member 31, whereby the wiring housing duct 4 is suspended and fixed to the holding member 41.

上記のように配線収納ダクト4を押圧および吊持固定し
た状態にてデッキプレート2上にコンクリート打設作業
を行って床3を形成すると共に床3に配線収納ダクト4
を、その上面を露出させて埋設する。
As described above, the wiring storage duct 4 is pressed and suspended and fixed, and the concrete is placed on the deck plate 2 to form the floor 3, and the wiring storage duct 4 is formed on the floor 3.
Is buried with its upper surface exposed.

このコンクリート打設作業における配線収納ダクト4の
浮上り、垂下がり、水平面内での位置ずれ等は前記押え
部材41により防止される。
The pressing member 41 prevents the wiring accommodating duct 4 from rising, hanging down, and being displaced in the horizontal plane during the concrete placing work.

また各支持部材20において、上、下部主材22,21と各棒
状脚材23とにより多くのコンクリート流通口45が画成さ
れ、また各脚材23は棒状であってコンクリートの流れに
対する塞止め作用が少ないので、コンクリートの流れは
各支持部材20をスムーズに通過する。
Further, in each support member 20, a large number of concrete flow ports 45 are defined by the upper and lower main members 22 and 21 and each rod-shaped leg member 23, and each leg member 23 is rod-shaped and blocks the flow of concrete. Since the action is small, the concrete flow smoothly passes through each support member 20.

その後床面5を配線収納ダクト4上面と面一に仕上げる
ものであるが、各ナット部材31の上端部および配線収納
ダクト4の上端縁部e間における床面5の一部は、床3
に埋設された各床面構成体35の平板部36により構成され
るので、その部分の仕上げ作業を行う必要がない。
After that, the floor surface 5 is finished to be flush with the upper surface of the wiring storage duct 4. However, a part of the floor surface 5 between the upper end portion of each nut member 31 and the upper end edge e of the wiring storage duct 4 is the floor 3
Since it is constituted by the flat plate portion 36 of each floor surface structure 35 buried in, it is not necessary to perform the finishing work for that portion.

したがって、各押えボルト44が床面5上に突出し、また
各チャンネル材43が配線収納ダクト4から突出していて
も、それらが床面5の仕上げ作業性を妨げることがな
い。
Therefore, even if each holding bolt 44 projects above the floor surface 5 and each channel member 43 projects from the wiring storage duct 4, they do not interfere with the finishing workability of the floor surface 5.

前記コンクリートが硬化した後各押えボルト44を緩め、
押え部材41を配線収納ダクト4から取外す。
After the concrete has hardened, loosen each holding bolt 44,
The holding member 41 is removed from the wiring storage duct 4.

第14図に明示するように、各床面構成体35のボルト挿通
孔38には、ナット部材31の雌ねじ孔33に達する塩化ビニ
ル樹脂等の合成樹脂よりなる盲栓46が装着される。
As clearly shown in FIG. 14, a blind plug 46 made of synthetic resin such as vinyl chloride resin reaching the female screw hole 33 of the nut member 31 is attached to the bolt insertion hole 38 of each floor structure 35.

C.発明の効果 本発明によれば、各押えボルトおよび配線収納ダクト上
端縁部間における床面の一部に仕上げ作業を行なう必要
がなく、これにより床面の仕上げ作業能率を向上させ得
る前記床配線施工方法を提供することができる。
C. Effect of the Invention According to the present invention, it is not necessary to perform a finishing work on a part of the floor surface between each holding bolt and the upper edge of the wiring storage duct, and thus the finishing work efficiency of the floor surface can be improved. A floor wiring construction method can be provided.

【図面の簡単な説明】[Brief description of drawings]

第1,第2図は床配線構造を示し、第1図は平面図、第2
図は第1図II-II線断面図、第3〜第14図は床配線施工
方法における配線収納ダクトの固定構造を示し、第3図
は平面図、第4図は第3図IV-IV線断面図、第5図は第
3図V−V線断面図、第6図は第5図VI-VI線断面図、
第7図は第3図VII-VII線断面図、第8図は第7図VIII-
VIII線断面図、第9図は第3図IX-IX線断面図、第10図
は支持部材と第2支持ボルトとの関係を示す分解斜視
図、第11図は第5図の要部拡大図、第12図は第11図XII
矢視図、第13図は第3図XIII-XIII線断面図、第14図は
第11図に対応する要部拡大図である。 B……基礎構造体、S……支持構造部材、e……上端縁
部、3……床、4……配線収納ダクト、5……床面、31
……ナット部材、35……床面構成体、41……押え部材、
44……押えボルト
1 and 2 show a floor wiring structure, and FIG. 1 is a plan view and a second view.
Fig. 1 is a sectional view taken along line II-II of Fig. 1, Figs. 3 to 14 show a fixing structure of a wiring storage duct in a floor wiring construction method, Fig. 3 is a plan view, and Fig. 4 is Fig. 3 IV-IV. 5 is a sectional view taken along line V-V in FIG. 3, and FIG. 6 is a sectional view taken along line VI-VI in FIG.
FIG. 7 is a sectional view taken along line VII-VII of FIG. 3, and FIG. 8 is FIG.
Fig. 9 is a sectional view taken along line VIII, Fig. 9 is a sectional view taken along line IX-IX of Fig. 3, Fig. 10 is an exploded perspective view showing the relationship between the support member and the second support bolt, and Fig. 11 is an enlarged view of the main part of Fig. 5. Figure, Figure 12 is Figure 11 XII
FIG. 13 is a sectional view taken along the line XIII-XIII in FIG. 3, and FIG. 14 is an enlarged view of an essential part corresponding to FIG. B ... Foundation structure, S ... Support structural member, e ... Upper edge, 3 ... Floor, 4 ... Wiring storage duct, 5 ... Floor surface, 31
...... Nut member, 35 …… Floor surface structure, 41 …… Pressing member,
44 ...... Presser bolt

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】基礎構造体上に複数の支持構造部材を相互
に間隔をとって固定する工程、各支持構造部材上に配線
収納ダクトを載置し、また該配線収納ダクト上に押え部
材を載置する工程、前記配線収納ダクトの長手方向両側
方に在って各支持構造部材上に立設されたナット部材
に、前記押え部材に存する各押えボルトを螺着して前記
配線収納ダクトを各支持構造部材上に固定する工程、前
記基礎構造体上にコンクリート打設作業を行って床を形
成すると共に該床に前記配線収納ダクトをその上面を露
出させて埋設する工程、床面を前記配線収納ダクト上面
と面一に仕上げる工程、および前記コンクリートが硬化
した後前記押え部材を取外す工程を用いる床配線施工方
法であって、各ナット部材上端部および前記配線収納ダ
クト上端縁部間にて、前記床に埋設されて前記床面の一
部を構成する複数の床面構成体を、前記コンクリート打
設作業前に各ナット部材に保持させることを特徴とする
床配線施工方法。
1. A step of fixing a plurality of supporting structure members on a foundation structure at a distance from each other, a wiring accommodating duct is placed on each supporting structure member, and a pressing member is mounted on the wiring accommodating duct. The step of placing the wiring accommodating duct by screwing each holding bolt existing in the pressing member to a nut member standing on each supporting structure member on both sides in the longitudinal direction of the wiring accommodating duct. Fixing on each support structure member, concrete placing work on the foundation structure to form a floor and burying the wiring storage duct on the floor with its upper surface exposed, A floor wiring construction method using a step of finishing flush with an upper surface of the wiring storage duct, and a step of removing the pressing member after the concrete is hardened, wherein the upper end portion of each nut member and the upper end edge of the wiring storage duct are Floor wiring construction method characterized in that to hold a plurality of floor structure constituting a part of the floor surface is embedded in the floor, each nut member before the concreting work.
JP1051544A 1989-03-03 1989-03-03 Floor wiring construction method Expired - Lifetime JPH071971B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1051544A JPH071971B2 (en) 1989-03-03 1989-03-03 Floor wiring construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1051544A JPH071971B2 (en) 1989-03-03 1989-03-03 Floor wiring construction method

Publications (2)

Publication Number Publication Date
JPH02231914A JPH02231914A (en) 1990-09-13
JPH071971B2 true JPH071971B2 (en) 1995-01-11

Family

ID=12889966

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1051544A Expired - Lifetime JPH071971B2 (en) 1989-03-03 1989-03-03 Floor wiring construction method

Country Status (1)

Country Link
JP (1) JPH071971B2 (en)

Also Published As

Publication number Publication date
JPH02231914A (en) 1990-09-13

Similar Documents

Publication Publication Date Title
US4198176A (en) Concrete expansion joint forming structure
RU95108519A (en) WALL STRUCTURE FROM FOAM MATERIAL AND CONCRETE AND METHOD AND DEVICE FOR ITS MANUFACTURE
JPH071971B2 (en) Floor wiring construction method
JPH0732690Y2 (en) Support structure for wiring storage device in floor structure
CN218623281U (en) Formula of sinking aluminum mould board
CN214423570U (en) Prefabricated balcony slab
JP2005213852A (en) Foundation block for guardrail
JPH0249856A (en) Foundation form
JPH0865863A (en) Wiring duct support structure on the floor
JPH0593423A (en) Guide wall constructing pc slab and construction method of guide wall
JPS5922187Y2 (en) Support device for formwork construction
KR830002140B1 (en) Assembly method of building
JP2560054B2 (en) Floor wiring construction method and construction structure
JPH05187030A (en) Gravity-type retaining wall and manufacture thereof
JP3029055U (en) Building tool for building slab openings
JPS62220647A (en) Floor apparatus
JP2606810B2 (en) Floor support structure
JPH0539155Y2 (en)
CN2222754Y (en) Compound F-shape furred ceiling inserting and suspending device
JPS61146531U (en)
JPS6319477Y2 (en)
JPS6024759Y2 (en) Concrete block for retaining wall
JPS6058685U (en) drainage device
JPH0139777Y2 (en)
JPS5847086Y2 (en) Earth retention shoring device for excavated trenches