JPH07293003A - Construction method of slab formwork - Google Patents

Construction method of slab formwork

Info

Publication number
JPH07293003A
JPH07293003A JP6106197A JP10619794A JPH07293003A JP H07293003 A JPH07293003 A JP H07293003A JP 6106197 A JP6106197 A JP 6106197A JP 10619794 A JP10619794 A JP 10619794A JP H07293003 A JPH07293003 A JP H07293003A
Authority
JP
Japan
Prior art keywords
formwork
work
slab
constructing
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6106197A
Other languages
Japanese (ja)
Other versions
JP3014918B2 (en
JPH07293003A5 (en
Inventor
Daisaku Nishimoto
大策 西本
Tetsuo Suda
哲生 須田
Michio Ishida
陸夫 石田
Hiroaki Kamiyoshi
弘明 神吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dow Kakoh KK
Original Assignee
Dow Kakoh KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dow Kakoh KK filed Critical Dow Kakoh KK
Priority to JP6106197A priority Critical patent/JP3014918B2/en
Publication of JPH07293003A publication Critical patent/JPH07293003A/en
Publication of JPH07293003A5 publication Critical patent/JPH07293003A5/ja
Application granted granted Critical
Publication of JP3014918B2 publication Critical patent/JP3014918B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】 【構成】 鉄筋コンクリートスラブを構築するための型
枠の建込みにおいて、発泡プラスチック板を支保工と
し、その支保工の上に型枠を設置することを特徴とする
スラブ型枠の施工方法。 【効果】 本発明のスラブ型枠の施工方法によって、支
保工の設置作業が軽量化され、組み立ても容易となる、
支保工の解体が容易となり、使用機材の搬出が軽量化さ
れる、また支保工の設置高さが低い場合でもスラブ型枠
の建て込みが可能となる、などのこれまでになかった新
規な効果が発生する。
(57) [Summary] [Structure] A slab formwork characterized by using foamed plastic plates as the support and installing the formwork on the support when building the formwork for constructing reinforced concrete slabs. Construction method. [Effect] By the method of constructing a slab formwork of the present invention, the installation work of the supporting work is reduced in weight and the assembly is facilitated.
New effects that have never existed, such as supporting work can be dismantled easily, the weight of equipment used can be carried out lightly, and slab formwork can be built even when the installation height of the supporting work is low. Occurs.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄筋コンクリート構造
物等のスラブ(水平な平板部分)を構築するにあたって
のスラブ型枠の施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a slab formwork for constructing a slab (horizontal flat plate portion) such as a reinforced concrete structure.

【0002】[0002]

【従来の技術】従来、集合住宅等の鉄筋コンクリート構
造物においてスラブ型枠を形成する際、型枠を支える支
保工として、まずスラブ下の作業床上にパイプサポート
を組み立て、その上に大引と呼ばれる梁とこれと直角に
鋼管等の根太を配置した後、その上に型枠を敷設する方
法、あるいは、軽量支持梁に直接または根太を介して型
枠を敷設する方法が行われている。
2. Description of the Related Art Conventionally, when forming a slab formwork in a reinforced concrete structure such as an apartment house, as a supporting work for supporting the formwork, first, a pipe support is assembled on a work floor under the slab, and it is called Daihiki. A method of laying a beam and a joist such as a steel pipe at right angles to the beam and then laying a form on it, or a method of laying the form on the lightweight support beam directly or through the joist is used.

【0003】この支保工は、型枠を所定の位置に保持す
るための必須不可欠な機材であり、従来から、支えるコ
ンクリートの重量や目的に応じて、それぞれに適した各
種の鋼管、緊結金具等が使用されている。このようにし
て組み立てられた支保工の上に型枠を張り、更に鉄筋を
配置した後、コンクリートの打設が行なわれる。打設さ
れたコンクリートの硬化後は、一般には型枠および支保
工が撤去されるが、特開平3−208944号公報に記
載されている型枠兼用の断熱板を用いた場合には、支保
工のみが撤去される。
This supporting work is an indispensable equipment for holding the formwork at a predetermined position, and conventionally, various steel pipes, binding fittings, etc. suitable for the weight and purpose of the concrete to be supported are used. Is used. The formwork is stretched on the support work assembled in this way, and the reinforcing bars are arranged, and then concrete is poured. After the cast concrete is hardened, the formwork and the support work are generally removed. However, when the heat insulating plate also used as the formwork described in JP-A-3-208944 is used, the support work is performed. Only will be removed.

【0004】これらの支保工や型枠の撤去作業は、広い
空間がある場合には比較的容易であるが、1階床やピッ
トの場合には、通常床下換気口やマンホール等のコンク
リートの打設後に残る開口部はこれらの機材を搬出する
のに十分な大きさがない場合が多く、予め別途に設けて
おいた開口部から型枠と共に支保工として用いた機材等
を搬出し、その後開口部を塞ぐという方法がとられてい
る。
The support work and the work of removing the formwork are relatively easy when there is a large space, but in the case of the first floor or the pit, the concrete is usually placed under the floor ventilation opening or manhole. In many cases, the openings left behind are not large enough to carry out these equipment, and the equipment used for supporting work together with the formwork is carried out from the openings that were separately provided in advance, and then the openings The method of blocking is taken.

【0005】[0005]

【発明が解決しようとする課題】従来の支保工を用いる
型枠の敷設方法では、例えば、床下の低い建築物の床、
水処理設備等の排水、湧水ピットの構築、施工、あるい
は逆打ち工法で構築する場合等、スラブ型枠を形成する
ための支保工を設置する空間高さが低い場合は、パイプ
サポート等が立てられないとか、あるいは、支保工をな
んとか設置してもスラブ型枠解体時に狭い空間内で作業
を行なわなければならず機材を搬出するのが極めてた困
難である等、の問題があった。また、スラブ型枠の設
置、撤去に関するこうした作業はそのほとんどが人手に
よってなされ、機械化の余地が少なく、特に従来から使
用されているパイプサポートおよび鋼管等は重量が重い
ため、搬入、設置、解体、搬出の作業が重労働であり、
極めて困難な作業となる等の問題点があった。
In the conventional method of laying a formwork using the support work, for example, the floor of a building with a low floor,
If the space height for installing the support for forming the slab formwork is low, such as when draining water treatment facilities, building or constructing a spring pit, or constructing by the reverse construction method, pipe support, etc. There was a problem that it could not be stood up or that it was extremely difficult to carry out the equipment because the work had to be carried out in a narrow space when the slab formwork was dismantled even if some support work was installed. In addition, most of these work related to installation and removal of slab formwork is done manually, there is little room for mechanization, and since the pipe supports and steel pipes that have been conventionally used are heavy in weight, carrying in, installation, dismantling, The work of carrying out is heavy labor,
There were problems such as extremely difficult work.

【0006】本発明の目的は、作業の軽減、設置条件の
制約の緩和が図られる画期的なスラブ型枠の施工方法を
提案することである。
An object of the present invention is to propose an epoch-making method for constructing a slab formwork, which can reduce the work and alleviate the restrictions on the installation conditions.

【0007】[0007]

【課題を解決するための手段】本発明者らは、前記した
問題点を解決べく鋭意検討を重ねていたところ、支保工
として、発泡プラスチック板のパネルと発泡プラスチッ
ク板のスペーサーを用い、これらパネルとスペーサーと
を特定の配置で形成し、結合することによって、支える
コンクリートの重量に起因する垂直荷重による座屈(バ
ックリング)がなく、支保工として十分機能しうること
を見いだし、従来の支保工とは根本的に異なる画期的な
スラブ型枠の施工方法を完成するに至った。
Means for Solving the Problems The inventors of the present invention have made extensive studies to solve the above-mentioned problems, and as a supporting work, a panel made of a foamed plastic plate and a spacer made of a foamed plastic plate are used. It was found that by forming and connecting the spacer and the spacer in a specific arrangement, there is no buckling (back ring) due to vertical load due to the weight of the concrete to be supported, and it can function sufficiently as a supporting work. We have completed a radically different slab formwork construction method.

【0008】すなわち、前記した課題を解決するための
本発明のスラブ型枠の施工方法は、以下のとおりであ
る。 1.鉄筋コンクリートスラブを構築するための型枠の建
込みにおいて、発泡プラスチック板を支保工とし、その
支保工の上に型枠を設置することを特徴とするスラブ型
枠の施工方法。 2.鉄筋コンクリートスラブを構築するための型枠の建
込みにおいて、発泡プラスチック板の複数枚のパネル
(1)を、パネル(1)の幅方向を作業床(4)に垂直
に立てた状態で、間隔をおいて配置するとともに、パネ
ル(1)どうしの間に、発泡プラスチック板のスペーサ
ー(2)を配置した後、パネル(1)とスペーサー
(2)とを連結、固定して、型枠(3)を支える支保工
とし、その支保工の上に型枠を設置することを特徴とす
るスラブ型枠の施工方法。
That is, the method of constructing the slab formwork of the present invention for solving the above-mentioned problems is as follows. 1. A method of constructing a slab formwork, characterized in that, when building a formwork for constructing a reinforced concrete slab, a foam plastic plate is used as the support work and the formwork is installed on the support work. 2. When constructing a formwork for constructing a reinforced concrete slab, a plurality of panels (1) of foamed plastic plates are set up with the width direction of the panels (1) standing vertically on the work floor (4). After placing the spacers (2) of foamed plastic plates between the panels (1), the panels (1) and the spacers (2) are connected and fixed, and the form (3) is placed. A method of constructing a slab formwork, which comprises supporting work for supporting the slab, and installing the formwork on the supporting work.

【0009】以下、本発明を詳細に説明する。本発明の
方法が適用される例については、鉄筋コンクリート構造
物の居室などが設置される比較的広い空間の上に構築す
るスラブの場合に適用されるのは勿論であるが、床下の
低い建築物の床や、水処理設備等の排水、湧水ピット等
の比較的狭い空間の上に構築するスラブの場合に、特に
好適である。また、最近、新設建物の地下工事につい
て、場所打ち杭工事を利用して構真柱および作業床を先
行設置し、土を上階から掘削しながら柱、梁、床、壁部
材のコンクリートを逆打ちする工法が採用されている
が、本発明の方法は、これら逆打ち工法にも好適であ
る。
The present invention will be described in detail below. Regarding the example to which the method of the present invention is applied, it is needless to say that the method is applied to the case of a slab constructed on a relatively wide space where a living room of a reinforced concrete structure is installed, but a building under the floor is low. It is particularly suitable for a slab constructed on a relatively narrow space such as a floor, drainage of a water treatment facility or a spring pit. In addition, recently, for the underground construction of a new building, by using cast-in-place pile construction, the structure columns and work floors were installed in advance, and while excavating the soil from the upper floor, the concrete of columns, beams, floors, and wall members was reversed. Although the striking method is adopted, the method of the present invention is also suitable for these reverse striking methods.

【0010】本発明は、前述したように、従来のサポー
ト、大引、根太の組合せに代わり、作業面に垂直に立て
た発泡プラスチック板の複数枚のパネルを、同じく発泡
プラスチック板を用いた複数枚のスペーサーで固定した
形状のもので型枠(3)を支持する新規な施工方法であ
る。本発明に用いる複数枚のパネルは、機材として最も
軽量である発泡プラスチック板を用いるものであるが、
この発泡プラスチック板の補強がさらに必要な場合は、
この発泡プラスチック板に他の材料を積層したり、また
他の部材で補強したりすることができる。好ましいパネ
ルは、ポリスチレン系の発泡プラスチック板であり、特
に好ましいのは、押し出し発泡ポリスチレン板である。
ポリスチレン系の発泡プラスチック板は、圧縮強さ、曲
げ強さ、曲げ弾性等の点で適当な物性を有しており、他
の部材で補強する必要もなく、単に厚みをコントロール
するだけでそのまま採用することができることが判っ
た。
As described above, the present invention replaces the conventional combination of the support, the Daihiki, and the joist, with a plurality of panels of foamed plastic plates standing upright on the work surface, and a plurality of panels using the same foamed plastic plates. This is a new construction method in which the form (3) is supported with a shape fixed by a spacer. The plurality of panels used in the present invention uses the lightest foam plastic plate as the equipment,
If you need further reinforcement of this foam plastic plate,
Other materials can be laminated on the foamed plastic plate, or can be reinforced with other members. A preferred panel is a polystyrene-based foamed plastic plate, and particularly preferred is an extruded expanded polystyrene plate.
The polystyrene foam plastic plate has suitable physical properties in terms of compressive strength, bending strength, bending elasticity, etc., and it is not necessary to reinforce with other members, and it is adopted as it is by simply controlling the thickness. It turns out that you can do it.

【0011】本発明に用いる複数枚のパネルの厚みは、
薄くてもまた厚過ぎても充分な効果が得られない。好ま
しいのは、厚みが50〜200mmのパネルである。支
えるコンクリートの重量や工事の状況によって施工管理
者が最適な厚みのものを選定することができる。
The thickness of the plurality of panels used in the present invention is
Even if it is thin or too thick, sufficient effect cannot be obtained. Preferred is a panel with a thickness of 50-200 mm. The construction manager can select the optimum thickness depending on the weight of the concrete to be supported and the construction conditions.

【0012】施工にあたっては、複数枚のパネルは、図
1に示すように、パネルの幅方向を作業床に対して垂直
に立てた状態で、互いに平行に間隔をおいて配置され
る。パネルの間隔(ピッチ)は、図1、2に示す実施例
では、6尺(1820mm)で6ツ割となっているが、
必ずしもこのピッチに限定されるものではない。支える
コンクリートの重量、さらに工事の状況等によってパネ
ルの間隔(ピッチ)を自由に選定することができる。
In the construction, the plurality of panels are arranged in parallel with each other at intervals with the width direction of the panels standing upright with respect to the work floor, as shown in FIG. In the embodiment shown in FIGS. 1 and 2, the panel interval (pitch) is 6 scales (1820 mm), which is 60%.
The pitch is not necessarily limited to this. The spacing (pitch) of panels can be freely selected depending on the weight of concrete to be supported and the construction conditions.

【0013】本発明に用いるパネルは、上記した厚みを
有ししかもその表面(図1のA)が平らになっているた
め、型枠の継手部分が1枚のパネルの上で出会うことに
なる。そのため、従来の円形断面を有する根太では、2
本の根太を継手部分の下に当てがうかあるいは桟木を用
いて継手部分を仮止めする必要があったが、このような
手間のかかる作業は必要がない。
Since the panel used in the present invention has the above-mentioned thickness and its surface (A in FIG. 1) is flat, the joint portion of the formwork meets on one panel. . Therefore, with a joist with a conventional circular cross section, 2
It was necessary to put the joists of the book under the joint part or to temporarily fix the joint part by using a crosspiece, but such troublesome work is not necessary.

【0014】また、本発明では、上記発泡プラスチック
板のパネルの間にスペーサーを配置することが必要であ
る。このスペーサーは一種の転び止めであり、パネルの
横倒れおよびバックリングを防止することができる。こ
のスペーサーは、図1、2に示すように、パネルどうし
の間に、パネルの面とスペーサーの端面とがぴったり接
触するように配置される。接触する面積が大きい方がス
ペーサーとしての機能をより発揮することができる。ス
ペーサーの厚みは、パネルと同様、一般に50〜200
mmのものを用いるが、必ずしも特定するものではな
い。また、スペーサーの高さは、図1ではパネルの幅と
同等の寸法となっているが、これも必ずしも同等でなく
てもよい。
Further, in the present invention, it is necessary to dispose a spacer between the panels of the foamed plastic plate. This spacer is a kind of anti-roll, and can prevent the panel from falling sideways and buckling. As shown in FIGS. 1 and 2, the spacers are arranged between the panels so that the surfaces of the panels and the end surfaces of the spacers are in close contact with each other. The larger the contact area, the more the function as a spacer can be exhibited. The thickness of the spacer is generally 50 to 200, like the panel.
Although the value of mm is used, it is not necessarily specified. Further, the height of the spacer has the same dimension as the width of the panel in FIG. 1, but it does not necessarily have to be the same.

【0015】また、これらの複数のパネルとスペーサー
は、両面テープ、粘着テープあるいは緊結金具等の簡便
な接着手段によって互いに固定される。更に、図1にお
いてパネル(1)のB面に凹部(図示せず)を形成して
おけば、パネル(1)とスペーサー(2)とは嵌合する
ことになるから、特別な緊結手段を必要としない。この
ような簡便な接着手段で互いに強固に固定できるのは、
軽量であってしかも大きな平らな表面を有する発泡プラ
スチック板特有の特徴である。
The plurality of panels and the spacer are fixed to each other by a simple adhesive means such as a double-sided tape, an adhesive tape or a binding metal fitting. Further, in FIG. 1, if a recess (not shown) is formed on the surface B of the panel (1), the panel (1) and the spacer (2) will be fitted together, so that a special fastening means is required. do not need. What can be firmly fixed to each other with such a simple adhesive means is
This is a unique feature of a foamed plastic plate that is lightweight and has a large flat surface.

【0016】次いで、このようにして組み立てられた支
保工の上にスラブ型枠が配置される。従来の支保工の場
合と同様、型枠の種類を問わずどのような型枠でも用い
ることができるが、本発明の効果をさらに発揮させるた
めには、特開平3−208944号公報に記載されてい
る型枠兼用の断熱板を採用することが好ましい。この型
枠兼用の断熱板は、発泡ポリスチレン板からなる断熱板
の片面にプラスチックフィルムを貼着積層させてなる型
枠兼用断熱板である。貼着積層されるプラスチックフィ
ルムとしては、ポリエステルフィルム、ポリエチレンフ
ィルム等がある。
Next, the slab formwork is placed on the support work thus assembled. Similar to the case of the conventional supporting work, any form can be used regardless of the type of form, but in order to further exert the effect of the present invention, it is described in JP-A-3-208944. It is preferable to use a heat insulating plate that also serves as a mold. This heat insulating plate that also serves as a mold is a heat insulating plate that also serves as a mold and is formed by sticking and laminating a plastic film on one surface of a heat insulating plate made of expanded polystyrene plate. Examples of the plastic film to be stuck and laminated include a polyester film and a polyethylene film.

【0017】[0017]

【実施例】以下に、図面を参照しながら、本発明の1実
施例について、具体的に説明をする。この実施例は、空
間高さの比較的低い鉄筋コンクリートの1階床下に適用
した例である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be specifically described below with reference to the drawings. This example is an example applied to the lower floor of reinforced concrete with a relatively low space height.

【0018】厚み100mmの押出し発泡ポリスチレン
板を、支保工の高さに合わせた幅と施工現場に適合した
長さに切断して、パネル(1)を複数枚作製した。これ
ら複数枚のパネル(1)を、図1に示すように、作業床
(4)上に、パネル(1)の幅方向が作業床(4)に対
して垂直になるように立て、そして等間隔に配置した。
一方、パネル(1)と同じ幅をもつ発泡プラスチック板
をパネルどうしの間隔に合わせて切断したしたものを、
スペーサー(2)としてパネルの面Bに対して直角に介
在させて並べた。
An extruded expanded polystyrene plate having a thickness of 100 mm was cut into a width adapted to the height of the supporting work and a length adapted to the construction site to prepare a plurality of panels (1). These plural panels (1) are erected on the work floor (4) so that the width direction of the panel (1) is perpendicular to the work floor (4) as shown in FIG. 1, and so on. It was arranged at intervals.
On the other hand, a foamed plastic plate having the same width as the panel (1) was cut at the intervals between the panels,
The spacers (2) were arranged at right angles to the surface B of the panel.

【0019】以上のパネル(1)とスペーサー(2)の
相互配置を上部から見たのが図2であり、パネル(1)
とスペーサー(2)が碁盤目状に配置されていることが
わかる。
FIG. 2 shows the mutual arrangement of the panel (1) and the spacer (2) as seen from above, and the panel (1)
It can be seen that and the spacers (2) are arranged in a grid pattern.

【0020】パネル(1)の厚みとパネル(1)どうし
のピッチ(間隔)、スペーサー(2)どうしのピッチ
(間隔)は、型枠(3)上に打設されるコンクリートの
重量を支えるに充分となるように設定した。パネル
(1)とスペーサー(2)とは、パネル(1)の横倒れ
およびバックリングを完全に防止するため、両面テー
プ、粘着テープあるいは緊結金具等を用いて互いに固定
された。
The thickness of the panel (1), the pitch (spacing) between the panels (1) and the pitch (spacing) between the spacers (2) depend on the weight of the concrete cast on the form (3). It was set to be sufficient. The panel (1) and the spacer (2) were fixed to each other using a double-sided tape, an adhesive tape, a binding metal fitting or the like in order to completely prevent the panel (1) from falling over and buckling.

【0021】このようにして構築された発泡プラスチッ
ク板の支保工の上に、型枠(3)を水平に張った。図2
に示すように、型枠(3)の長手方向がパネル(1)に
対して直角になるように配置し、また型枠(3)の継ぎ
手部分はパネル(1)およびスペーサー(2)の上で出
会うように、スペーサー(2)の寸法およびピッチで調
整した。型枠(3)として、発泡ポリスチレン板からな
る断熱板の下面にプラスチックフィルムを貼着積層した
型枠兼用の断熱板(長さ1820mm、幅910mm、
厚み30mm)を用いた。
The formwork (3) was stretched horizontally on the support of the foamed plastic plate thus constructed. Figure 2
As shown in Fig. 3, the form (3) is arranged so that the longitudinal direction of the form (3) is perpendicular to the panel (1), and the joint part of the form (3) is above the panel (1) and the spacer (2). Was adjusted by the size and pitch of the spacer (2). As the mold (3), a heat insulating plate (1820 mm in length, 910 mm in width, which also serves as a mold) in which a plastic film is stuck and laminated on the lower surface of a heat insulating plate made of expanded polystyrene plate,
A thickness of 30 mm) was used.

【0022】次いで、型枠(3)の上に配筋し、コンク
リートを打設した。コンクリートの硬化後、パネル
(1)およびスペーサー(2)を撤去した。パネル
(1)とスペーサー(2)とが主として粘着テープで固
定されているので、その解体作業は、金具で固定された
パイプサポート等に比べて極めて容易であり、搬出も容
易であった。
Then, reinforcement was placed on the formwork (3) and concrete was poured. After hardening of the concrete, the panel (1) and the spacer (2) were removed. Since the panel (1) and the spacer (2) are mainly fixed by the adhesive tape, the dismantling work is extremely easy as compared with the pipe support fixed by the metal fittings and the carrying out is easy.

【0023】実施例では、型枠(3)として特開平3−
208944号公報に開示された型枠兼用断熱ボードを
使用したため、型枠工事と断熱材敷設とが同時に行なわ
れると共に、支保工解体時に型枠の撤去および搬出作業
を省略することができた。この実施例からも、支保工の
高さが低いために従来のパイプサポートが入れにくい場
合でも、パネル(1)とスペーサー(2)の寸法によっ
て支保工の高さを自由に調節することができることが判
る。
In the embodiment, the form (3) is disclosed in
Since the heat insulating board that also serves as the form disclosed in Japanese Patent No. 208944 is used, the form work and the laying of the heat insulating material can be performed at the same time, and the work of removing and carrying out the form can be omitted at the time of dismantling the support work. Also from this embodiment, even when it is difficult to insert the conventional pipe support due to the low height of the supporting work, the height of the supporting work can be freely adjusted by the dimensions of the panel (1) and the spacer (2). I understand.

【0024】[0024]

【発明の効果】本発明の効果を箇条書きすると以下の通
りである。 1.支保工の設置作業が軽量化され、組み立ても容易と
なる。すなわち、鋼管、緊結金具等で構成される従来の
支保工と比較して発泡プラスチック板は軽量であり、ま
た組み立てるに際しても刃物で簡単に自由に切断可能で
あり、粘着テープ等を用いて簡便に固定でき、組み立て
ることができる等、極めて容易である。 2.支保工の解体が容易となり、使用機材の搬出が軽量
化される。粘着テープ等で固定された発泡プラスチック
板の解体は極めて容易である。また再使用しない場合は
取り壊してそのまま廃棄してもよい。搬出が軽量である
点は設置時と同じである。 3.支保工の設置高さが低い場合でも、スラブ型枠の建
て込みが可能となる。支保工の高さが低くて従来のパイ
プサポートでは入らない場合でも、パネル(1)とスペ
ーサー(2)の寸法によって支保工の高さを自由に調節
出来る。また解体、搬出が容易なことも設置高さの制約
を緩和するものである。
The effects of the present invention are listed as follows. 1. The installation work of the supporting work is lightened and the assembly is easy. That is, the foamed plastic plate is lighter than the conventional support structure composed of steel pipes, binding metal fittings, etc., and it can be easily cut freely with a blade when assembling, and it is easy to use adhesive tape etc. It is extremely easy to fix and to assemble. 2. It will be easier to dismantle the shoring work, and the equipment used will be lighter to carry out. Disassembling the foamed plastic plate fixed with an adhesive tape or the like is extremely easy. If it is not reused, it may be destroyed and discarded as it is. The point that the carry-out is lightweight is the same as the time of installation. 3. The slab formwork can be built even if the installation height of the support work is low. Even if the height of the supporting work is too low to fit in the conventional pipe support, the height of the supporting work can be freely adjusted by the dimensions of the panel (1) and the spacer (2). Also, the ease of dismantling and carrying out eases restrictions on the installation height.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の施工方法によるスラブ型枠の一例を示
す斜視図である。
FIG. 1 is a perspective view showing an example of a slab formwork according to a construction method of the present invention.

【図2】本発明の施工方法によるスラブ型枠の一例を示
す平面図である。
FIG. 2 is a plan view showing an example of a slab formwork according to the construction method of the present invention.

【符号の説明】[Explanation of symbols]

1.パネル 2.スペーサー 3.型枠 4.作業床 1. Panel 2. Spacer 3. Formwork 4. Work floor

フロントページの続き (72)発明者 神吉 弘明 東京都港区芝浦1丁目2番1号 ダウ化工 株式会社内Front Page Continuation (72) Inventor Hiroaki Kamiyoshi 1-2-1 Shibaura, Minato-ku, Tokyo Dow Kako Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋コンクリートスラブを構築するため
の型枠の建込みにおいて、発泡プラスチック板を支保工
とし、その支保工の上に型枠を設置することを特徴とす
るスラブ型枠の施工方法。
1. A method of constructing a slab formwork, characterized in that, in building a formwork for constructing a reinforced concrete slab, a foam plastic plate is used as a support work, and the formwork is installed on the support work.
【請求項2】 鉄筋コンクリートスラブを構築するため
の型枠の建込みにおいて、発泡プラスチック板の複数枚
のパネル(1)を、パネル(1)の幅方向を作業床
(4)に垂直に立てた状態で、間隔をおいて配置すると
ともに、パネル(1)どうしの間に、発泡プラスチック
板のスペーサー(2)を配置した後、パネル(1)とス
ペーサー(2)とを連結、固定して、型枠(3)を支え
る支保工とし、その支保工の上に型枠を設置することを
特徴とするスラブ型枠の施工方法。
2. In building a formwork for constructing a reinforced concrete slab, a plurality of panels (1) of foamed plastic plates are erected vertically in the width direction of the panels (1) on a work floor (4). In this state, while arranging with a space between them, after arranging the spacer (2) of the foamed plastic plate between the panels (1), the panel (1) and the spacer (2) are connected and fixed, A method for constructing a slab formwork, characterized in that the formwork (3) is supported and the formwork is installed on the supportwork.
JP6106197A 1994-04-22 1994-04-22 Construction method of slab formwork Expired - Lifetime JP3014918B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6106197A JP3014918B2 (en) 1994-04-22 1994-04-22 Construction method of slab formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6106197A JP3014918B2 (en) 1994-04-22 1994-04-22 Construction method of slab formwork

Publications (3)

Publication Number Publication Date
JPH07293003A true JPH07293003A (en) 1995-11-07
JPH07293003A5 JPH07293003A5 (en) 1999-04-20
JP3014918B2 JP3014918B2 (en) 2000-02-28

Family

ID=14427456

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6106197A Expired - Lifetime JP3014918B2 (en) 1994-04-22 1994-04-22 Construction method of slab formwork

Country Status (1)

Country Link
JP (1) JP3014918B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015137499A (en) * 2014-01-23 2015-07-30 鹿島建設株式会社 Method of constructing reinforcement slab
JP2015137500A (en) * 2014-01-23 2015-07-30 鹿島建設株式会社 Reinforcement slab construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015137499A (en) * 2014-01-23 2015-07-30 鹿島建設株式会社 Method of constructing reinforcement slab
JP2015137500A (en) * 2014-01-23 2015-07-30 鹿島建設株式会社 Reinforcement slab construction method

Also Published As

Publication number Publication date
JP3014918B2 (en) 2000-02-28

Similar Documents

Publication Publication Date Title
US6434900B1 (en) Prefabricated concrete wall system
US20090151298A1 (en) Method of Making Monolithic Concrete Structures
US3678638A (en) Building construction of modular units with settable material therebetween
US7219474B2 (en) Load bearing building panel
US20050086904A1 (en) Method and apparatus for forming cast wall panels
JP3014918B2 (en) Construction method of slab formwork
JP2000234410A (en) Driving formwork and slab construction method using the same
US4660349A (en) Method of erecting a building using preconstructed modular units
JP7350502B2 (en) Detached houses and their construction methods
KR100389535B1 (en) subway open cut structure water proofing method and panel thereby
CN217460884U (en) Structure of floating window
JP7749786B1 (en) Detached house and construction method thereof
JP3233938U (en) Precast board and the lowest floor structure using the precast board
AU2004203867B2 (en) A building system
JPH06248741A (en) Double floor construction method
JP4152328B2 (en) Wall type reinforced concrete structure
JP3001210U (en) Insulation board that also serves as a formwork for floor slab construction
RU2013505C1 (en) Floor
JPH02304150A (en) Floor construction method
JP2720776B2 (en) Construction method of pigeon hut
JPH04117040U (en) Building foundation structure
JP2001254465A (en) Insulation method of wall, heat insulation wall and disposable formwork panel for wall
IL124209A (en) Construction method
AU2002234421B2 (en) A load bearing building panel
JPH1018307A (en) Solid foundation and its construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19991130

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111217

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111217

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141217

Year of fee payment: 15

EXPY Cancellation because of completion of term