JPH0734143U - Scaffolding hanging - Google Patents

Scaffolding hanging

Info

Publication number
JPH0734143U
JPH0734143U JP7118893U JP7118893U JPH0734143U JP H0734143 U JPH0734143 U JP H0734143U JP 7118893 U JP7118893 U JP 7118893U JP 7118893 U JP7118893 U JP 7118893U JP H0734143 U JPH0734143 U JP H0734143U
Authority
JP
Japan
Prior art keywords
chain
scaffold
support
main body
scaffolding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7118893U
Other languages
Japanese (ja)
Other versions
JP2538491Y2 (en
Inventor
勝清 下村
Original Assignee
柏原塗研工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 柏原塗研工業株式会社 filed Critical 柏原塗研工業株式会社
Priority to JP1993071188U priority Critical patent/JP2538491Y2/en
Publication of JPH0734143U publication Critical patent/JPH0734143U/en
Application granted granted Critical
Publication of JP2538491Y2 publication Critical patent/JP2538491Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

(57)【要約】 (修正有) 【目的】 吊り足場を支持する吊り支点間隔を自由に設
定することができ、吊り足場の取付けが容易で、安全な
足場吊り具を提供する。 【構成】 梁材等の被吊り下げ材に作業用足場を吊り下
げるための足場吊り具であって、被吊り下げ材に装着さ
れる本体支持具1と、本体支持具に装着され、チェーン
連結部が設けられたチェーン支持具と、チェーン支持具
に一端が連結された複数本のチェーン3と、チェーンの
他端に連結され、足場を保持する足場保持具を有し、本
体支持具が、被吊り下げ材に取着されるコ字状部材11
にチェーン支持具を保持するクランプ部材12を一体的
に設けた支持具で形成され、チェーン支持具が、少なく
とも両端部にそれぞれチェーンの一端を連結する連結孔
を有する棒体で形成されている構成よりなる。
(57) [Summary] (Correction) [Purpose] To provide a safe scaffold suspender that allows the suspension fulcrums supporting the suspension scaffold to be set at any intervals, facilitates mounting of the suspension scaffold, and is easy to install. [Structure] A scaffolding suspending tool for suspending a work scaffolding on a suspended material such as a beam, and a main body support 1 mounted on the suspended material and a chain connection mounted on the main body supporter. A chain support provided with a portion, a plurality of chains 3 one end of which is connected to the chain support, and a scaffold holder that is connected to the other end of the chain and holds a scaffold, and the main body support is U-shaped member 11 attached to a suspended material
A support member integrally provided with a clamp member 12 for holding the chain support member, and the chain support member is formed of a rod having at least both end portions each having a connecting hole for connecting one end of the chain. Consists of.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、足場吊り具に係り、より詳細には、仮設建築現場等において、鉄鋼 梁材等の被吊り下げ材に作業用足場を吊り下げるための足場吊り具に関する。 The present invention relates to a scaffold suspender, and more particularly to a scaffold suspender for suspending a working scaffold on a suspended material such as a steel beam or the like at a temporary construction site or the like.

【0002】[0002]

【従来の技術】[Prior art]

一般に、架台などの構築物の建設、メンテナンス作業においては、足場が必要 であり、特に架台の床裏面の作業や架台上部の配管設置作業等の作業には吊り足 場が必要になる。そして、吊り足場を設置する場合、次のような手法が採られて いる。すなわち、 架台の梁又はブレースに吊りチェーンを巻き付け、該吊りチェーンに吊り足 場を取り付ける(図6a参照)。 鉄鋼構造物の梁のフランジにチェーン吊り金具を支持具として吊りチェーン を取り付け、吊り足場を支持する(図6b参照)。 等の手法が採られている。 Generally, a scaffold is required for construction and maintenance work of a structure such as a pedestal, and especially for work such as work on the underside of the pedestal and piping installation work on the pedestal. The following methods are used to install suspended scaffolds. That is, the suspension chain is wound around the beam or brace of the frame, and the suspension scaffold is attached to the suspension chain (see FIG. 6a). Attach the suspension chain to the beam flange of the steel structure using the chain suspension metal fixture as a support to support the suspension scaffold (see Fig. 6b). Etc. are adopted.

【0003】 ところで、この種の吊り足場を設置する場合、(a)作業対象物の吊れる場所 から吊る方法が採られたり、あるいは(b)架台梁上に鋼材を仮置きし、その鋼 材に吊りチェーンを取り付けることにより、吊り足場を支持する方法が取られて いる。そして、前者(a)の方法は、後者(b)の方法のように仮置きされた鋼 材によって作業が妨げられないという利点を有し、後者(b)の方法は架台梁は 鉄骨構造物の間隔が広い場合でも吊り足場の吊り支点間隔を必要な間隔にするこ とができるという利点を有する。By the way, when installing a suspension scaffold of this type, (a) a method of suspending from the place where the work object is suspended, or (b) a steel material is temporarily placed on a trestle beam and the steel material is suspended. The method of supporting the suspension scaffolding is adopted by attaching the suspension chain to the. And, the former method (a) has an advantage that the work is not hindered by the temporarily placed steel material unlike the latter method (b), and the latter method (b) is not applicable to the steel frame structure. This has the advantage that the spacing between the suspension fulcrums of the suspension scaffolding can be set to the required spacing even when the spacing is wide.

【0004】[0004]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかし、上述したような従来の各方法によって吊り足場を吊る場合、次のよう な課題がある。すなわち、 前者(a)の方法による場合には、吊り足場を支持する重要部分である吊り 支点を必要な間隔で設置することができないので、吊り支点間隔が広くなって、 必要な足場の強度を確保できなくなるおそれがあり、構築物の建設やメンテナン ス作業上の安全性確保の上で充分ではない。 後者(b)の方法による場合には、例えば架台上に床材を取り付けるときに 仮置きされた鋼材が作業の邪魔になる等、構築物の建設やメンテナンス作業を妨 げ、作業に悪影響を及ぼす。 等の課題がある。 However, when suspending the suspension scaffold by each of the conventional methods described above, there are the following problems. In other words, in the case of the former method (a), it is not possible to install the suspension fulcrums, which are the important parts that support the suspension scaffold, at the required intervals, so the spacing between the suspension fulcrums becomes wider and the required strength of the scaffold is obtained. There is a risk that it will not be possible to secure it, and it is not sufficient to ensure safety in the construction and maintenance work of the structure. In the case of the latter method (b), for example, when temporarily installing a floor material on a pedestal, the temporarily placed steel material interferes with the work, which hinders the construction and maintenance work of the structure and adversely affects the work. There are issues such as.

【0005】 本考案は、上述した問題に対処して創案したものであって、その目的とすると ころは、吊り足場を支持する吊り支点間隔を自由に設定することができ、吊り足 場の取付けが容易で、安全な足場吊り具を提供することにある。The present invention has been made in view of the above-mentioned problems, and an object thereof is to freely set a suspension fulcrum interval for supporting a suspension scaffold and to mount the suspension scaffold. To provide an easy and safe scaffolding hanger.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

そして、上記目的を達成するための手段としての本考案の足場吊り具は、梁材 等の被吊り下げ材に作業用足場を吊り下げるための足場吊り具であって、前記被 吊り下げ材に装着される本体支持具と、該本体支持具に装着され、チェーン連結 部が設けられたチェーン支持具と、該チェーン支持具に一端が連結された複数本 のチェーンと、該チェーンの他端に連結され、前記足場を保持する足場保持具を 有し、前記本体支持具が、前記被吊り下げ材に取着されるコ字状部材に前記チェ ーン支持具を保持するクランプ部材を一体的に設けた支持具で形成され、前記チ ェーン支持具が、少なくとも両端部にそれぞれ前記チェーンの一端を連結する連 結孔を有する棒体で形成されている構成よりなる。 The scaffold suspender of the present invention as a means for achieving the above object is a scaffold suspender for suspending a work scaffold on a suspended material such as a beam, and The main body support to be attached, the chain support attached to the main body support and provided with a chain connecting portion, a plurality of chains having one end connected to the chain support, and the other end of the chain A scaffold holder that is connected and holds the scaffold, and the main body support is integrally formed with a clamp member that holds the chain support on a U-shaped member that is attached to the suspended material. The chain support is formed of a rod having at least both ends each having a connecting hole for connecting one end of the chain.

【0007】 また、本考案の他の足場吊り具は、上記考案において、チェーン支持具が、本 体支持具にて把持されるパイプ材に水平フラットバーを挿通するとともに、該パ イプ材の下面に垂直フラットバーを固着し、前記水平フラットバーの両端部およ び垂直フラットバーの下端部にそれぞれチェーンの一端を連結する連結孔が形成 された棒体である構成よりなる。更に、本考案の足場吊り具は、上記の足場吊り 具において、足場保持具が、チェーンの他端を連結するコ字状部材と、足場を保 持するクランプ部材とが一体的に設けられている構成としている。Further, another scaffold suspender of the present invention is the scaffold suspender according to the above-mentioned invention, wherein the chain support inserts the horizontal flat bar into the pipe material gripped by the main body support, and the lower surface of the pipe material. A vertical flat bar is fixedly attached to the vertical flat bar, and a connecting hole for connecting one end of the chain is formed at both ends of the horizontal flat bar and at the lower end of the vertical flat bar. Furthermore, the scaffolding suspension of the present invention is the scaffolding suspension as described above, wherein the scaffolding retainer is integrally provided with a U-shaped member for connecting the other end of the chain and a clamp member for holding the scaffolding. It has a structure.

【0008】[0008]

【作用】[Action]

本考案の足場吊り具は、本体支持具にチェーン支持具を装着して、該チェーン 支持具に複数本のチェーンを介して足場保持具を取付け、前記本体支持具を梁材 等に装着し、足場保持具にて足場を保持することにより、梁材等に本体支持具、 チェーン支持具、複数本のチェーン及び足場保持具にて足場が吊り下げられるよ うに作用する。また、本体支持具は、梁材等を構成する被取り付け材に固定され るコ字状部材と、チェーン支持具を保持するクランプ部材とが一体的に設けられ ているので、被取り付け材に本体支持具を容易に取付けることができる。更に、 チェーン支持具は、少なくとも両端部にそれぞれ前記チェーンの一端を連結する 連結孔を有する棒体で形成されているので安定状態で足場を取り付けることがで きる。 The scaffold suspending device of the present invention is such that a chain support is attached to the main body support, the scaffold holder is attached to the chain support via a plurality of chains, and the main body support is attached to a beam member, By holding the scaffolding with the scaffolding retainer, the scaffolding is hung on the beam or the like by the main body supporter, the chain supporter, the plurality of chains and the scaffolding retainer. Further, the main body support is integrally provided with a U-shaped member that is fixed to a material to be attached that constitutes a beam or the like, and a clamp member that holds the chain support, so that the main body support is attached to the material to be attached. The support can be easily installed. Further, since the chain support is formed of a rod body having a connecting hole for connecting one end of the chain to at least both ends, the scaffold can be attached in a stable state.

【0009】 また、本体支持具にて把持されるパイプ材に水平フラットバーを挿通するとと もに、パイプ材の下面に垂直フラットバーを固着して、水平フラットバーの両端 部及び垂直フラットバーの下端部にそれぞれチェーンの一端を連結する連結孔が 形成される構成とした場合は、左右及び中央の三点に複数本のチェーンの一端を 連結することができる。更にまた、足場保持具として、チェーンの他端を連結す るコ字状部材と、足場を保持するクランプ部材とが一体的に設けられた構成のも のを用いた場合は、いっそう足場に容易に取付けることができる。Further, the horizontal flat bar is inserted into the pipe material gripped by the main body support, and the vertical flat bar is fixed to the lower surface of the pipe material so that both end portions of the horizontal flat bar and the vertical flat bar are fixed. When the connecting holes for connecting one end of each chain are formed at the lower end portion, one end of a plurality of chains can be connected to the left, right, and center three points. Furthermore, when a scaffold holder having a U-shaped member that connects the other ends of the chains and a clamp member that holds the scaffold is integrally provided, the scaffold holder is easier to use. Can be installed on.

【0010】[0010]

【実施例】【Example】

以下、図面を参照しながら、本考案を具体化した実施例について説明する。こ こに、図1〜図5は、本考案の一実施例を示し、図1は全体図、図2は図1の要 部拡大図、図3は本体支持具の斜視図、図4はチェーン支持具の平面図、正面図 及び側面図、図5は足場保持具の斜視図である。 Embodiments embodying the present invention will be described below with reference to the drawings. 1 to 5 show an embodiment of the present invention, FIG. 1 is an overall view, FIG. 2 is an enlarged view of a main part of FIG. 1, FIG. 3 is a perspective view of a main body support, and FIG. FIG. 5 is a plan view, a front view and a side view of the chain support, and FIG. 5 is a perspective view of the scaffold holder.

【0011】 本実施例の足場吊り具は、鉄鋼梁材等の被吊り下げ材に作業用足場を吊り下げ るための足場吊り具であって、概略すると、本体支持具1と、該本体支持具1に 装着されたチェーン支持具2と、該チェーン支持具2に一端が連結された複数本 のチェーン3、3・・・と、該複数本のチェーン3、3・・・の他端が連結され た複数の足場保持具4とから構成され、梁材をなすH形鋼梁5に本体支持具1を 装着し、足場保持具4にて足場用鋼管6を保持することにより、H形鋼梁5に足 場用鋼管6を吊り下げるようにしている。The scaffold suspender of the present embodiment is a scaffold suspender for suspending a work scaffold on a suspended material such as a steel beam, and is roughly composed of a main body support 1 and the main body support. The chain support 2 attached to the tool 1, the plurality of chains 3, 3 ... One end of which is connected to the chain support 2, and the other ends of the plurality of chains 3, 3 ,. An H-shaped steel beam 5 composed of a plurality of scaffold holders 4 connected to each other is attached to the main body support 1 and the scaffold holder 4 holds the steel pipe 6 for scaffolding. The steel pipe 6 for scaffolding is hung on the steel beam 5.

【0012】 本体支持具1は、梁材に固定(取着)されるコ字状部材11と、チェーン支持 具2を保持するクランプ部材12とが溶接にて一体的に固着されている。コ字状 部材11には該コ字状部材11を梁材に固定する先端に押し付け部材14が設け られたボルト部材13が螺着され、ボルト部材13を締め付けることで押し付け 部材14とコ字状部材11の下辺部との間で梁材を挟持固定する。クランプ部材 12は、コ字状部材11に固着された固定部材15に可動部材16が支軸17に て揺動可能に軸支され、可動部材17の先端部にボルト支持金具18が設けられ 、固定部材15の先端部にナット金具19が支軸20にて揺動可能に軸支され、 ボルト支持金具18に挿通されたボルト21をナット金具19に螺着することに より、固定部材15と可動部材16との間でチェーン支持具2を挟持して保持す る。In the main body supporting member 1, a U-shaped member 11 fixed (attached) to the beam member and a clamp member 12 holding the chain supporting member 2 are integrally fixed by welding. A bolt member 13 having a pressing member 14 at the tip for fixing the U-shaped member 11 to the beam is screwed to the U-shaped member 11, and by tightening the bolt member 13, the pressing member 14 and the U-shaped member 11 The beam member is clamped and fixed between the lower side portion of the member 11. The clamp member 12 includes a fixed member 15 fixed to the U-shaped member 11, a movable member 16 pivotably supported by a support shaft 17, and a bolt support metal fitting 18 provided at the tip of the movable member 17. A nut fitting 19 is pivotally supported by a support shaft 20 at the tip of the fixing member 15, and a bolt 21 inserted into the bolt supporting fitting 18 is screwed into the nut fitting 19 to thereby fix the fixing member 15 to the fixing member 15. The chain support 2 is held between the movable member 16 and the movable support 16.

【0013】 チェーン支持具2は、四角パイプ材23内に水平フラットバー24、24が挿 通されて溶接にて固着されるとともに、パイプ材23の下面に垂直フラットバー 25が溶接にて固着され、水平フラットバー24、24の両端部及び垂直フラッ トバー25の下端部にそれぞれチェーン3の一端を連結するシャックルピン28 等を通す連結孔26、27が形成されている。ここで、パイプ材23としては鋼 製の50mm角の四角パイプを、フラットバー24、25は鋼製の38mm×1 2mmの板材を用いている。しかし、任意の大きさのものを使用することができ る。In the chain support 2, the horizontal flat bars 24, 24 are inserted into the square pipe material 23 and fixed by welding, and the vertical flat bar 25 is fixed by welding on the lower surface of the pipe material 23. Connection holes 26, 27 are formed at both ends of the horizontal flat bars 24, 24 and at the lower end of the vertical flat bar 25, respectively, through which a shackle pin 28 for connecting one end of the chain 3 is inserted. Here, as the pipe material 23, a square pipe made of steel of 50 mm square is used, and as the flat bars 24 and 25, a plate material of 38 mm × 12 mm made of steel is used. However, any size can be used.

【0014】 足場保持具4は、チェーン3の他端を連結するコ字状部材30と、足場用鋼管 6を保持するクランプ部材31とが溶接にて固着されて一体的に設けられている 。また、コ字状部材30には、チェーン3の他端を連結するシャックルピン33 等を通す連結孔32が形成されている。クランプ部材31は、コ字状部材30に 固着された固定部材34の両端部に爪部材35、36が支軸37、38にて揺動 可能に軸支され、爪部材35、36にボルト部材39を挿通してナット部材40 にて締め付けることにより、爪部材35、36間で足場用鋼管6を挟持して保持 する。The scaffolding holder 4 is integrally provided with a U-shaped member 30 that connects the other ends of the chains 3 and a clamp member 31 that holds the steel pipe 6 for scaffolding, fixed by welding. Further, the U-shaped member 30 is formed with a connection hole 32 through which a shackle pin 33 for connecting the other end of the chain 3 and the like is inserted. In the clamp member 31, claw members 35 and 36 are swingably supported by support shafts 37 and 38 at both ends of a fixing member 34 fixed to the U-shaped member 30, and the claw members 35 and 36 are bolted. By inserting 39 and tightening with a nut member 40, the steel pipe 6 for scaffolding is clamped and held between the claw members 35 and 36.

【0015】 次に、本実施例の足場吊り具を使用してH形鋼梁5に足場用鋼管6を吊り下げ る場合について説明すると、H形鋼梁5の下フランジ部5aの両端部にそれぞれ 本体支持具1のコ字状部材11を嵌め込んだ後、ボルト部材13を締め付けて押 し付け部材14とコ字状部材11の下辺部との間でH形鋼梁5の下フランジ部5 aを挟んで固定することにより、H形鋼梁5の下フランジ部5aの両端部に本体 支持具1、1をそれぞれ装着する。そして、該本体支持具1、1の各クランプ部 材12の固定部材15と可動部材16との間にチェーン支持具2の四角パイプ材 24の両端部を挿通した後、ボルト部材21を締め付けることにより可動部材1 6を揺動させながらチェーン支持具2の四角パイプ材24を固定部材15と可動 部材16との間に挟持して固定する。Next, the case of suspending the steel pipe 6 for scaffolding on the H-shaped steel beam 5 using the scaffolding suspending tool of this embodiment will be described. At both ends of the lower flange portion 5 a of the H-shaped steel beam 5. After the U-shaped member 11 of the main body support 1 is fitted, the bolt member 13 is tightened to press the lower member of the H-shaped steel beam 5 between the pressing member 14 and the lower side of the U-shaped member 11. The main body supporting members 1 and 1 are attached to both ends of the lower flange portion 5a of the H-shaped steel beam 5 by sandwiching and fixing 5a. Then, after inserting both ends of the square pipe material 24 of the chain support tool 2 between the fixed member 15 and the movable member 16 of each clamp member 12 of the main body support tool 1, 1, the bolt member 21 is tightened. Thus, the square pipe member 24 of the chain support 2 is clamped and fixed between the fixed member 15 and the movable member 16 while swinging the movable member 16.

【0016】 このチェーン支持具2の水平フラットバー24及び垂直フラットバー25の連 結孔26、27にシャックルピン28等で複数本のチェーン3、3・・・の一端 を連結する。ここで、複数本のチェーン3、3・・・は、足場用鋼管6の長さや 強度に応じて吊り支点(足場保持具4で支持する点)の間隔(図1の距離イ)を 設定して、設定した間隔及び全体的な強度を得るのに必要な本数及び長さを選択 することになるが、吊り支点の間隔は1500mm以内が望ましい。そして、チ ェーン3、3・・・の他端に足場保持具4のコ字状部材30をシャックルピン3 3等で連結し、該足場保持具4のクランプ部材31の爪部材35、36間に足場 用鋼管6を挿通した後、ボルト部材30を締め付けて爪部材35、36間で足場 用鋼管6を挟持して保持する。One end of a plurality of chains 3, 3, ... Is connected to the connecting holes 26, 27 of the horizontal flat bar 24 and the vertical flat bar 25 of the chain support tool 2 by a shackle pin 28 or the like. Here, for the plurality of chains 3, 3, ..., an interval (distance a in FIG. 1) between suspension fulcrums (points supported by the scaffolding holder 4) is set according to the length and strength of the scaffolding steel pipe 6. Therefore, the number and length required to obtain the set spacing and overall strength are selected, but the spacing between the suspension fulcrums is preferably 1500 mm or less. The U-shaped member 30 of the scaffolding holder 4 is connected to the other ends of the chains 3, 3, ... With the shackle pin 33 or the like, and between the claw members 35, 36 of the clamp member 31 of the scaffolding holder 4. After the scaffolding steel pipe 6 is inserted through the bolt, the bolt member 30 is tightened to hold the scaffolding steel pipe 6 between the claw members 35 and 36.

【0017】 これにより、本体支持具1、および本体支持具1に固定されたチェーン支持具 2は、H形鋼梁5の下フランジ部5aの任意の位置に取付け固定できて、H形鋼 梁5の上に床材を取付ける場合にも作業の邪魔になることがなくなり、また、斜 め方向からの力が加わって固定されて外れることがなく、チェーン3をシャック ルピン28、33等でチェーン支持具2及び足場保持具4に連結されているので 、チェーン3の長さ調整が可能になり、更に、足場保持具4は足場の親子パイプ や根太パイプの任意の位置に固定して必要な吊り支点間隔を確保するように作用 する。Accordingly, the main body support tool 1 and the chain support tool 2 fixed to the main body support tool 1 can be attached and fixed to an arbitrary position of the lower flange portion 5 a of the H-shaped steel beam 5, and the H-shaped steel beam can be fixed. Even when mounting the floor material on top of No. 5, it does not interfere with the work, and the chain 3 does not come off due to the force applied from the tilting direction. Since it is connected to the support tool 2 and the scaffolding holder 4, the length of the chain 3 can be adjusted. Furthermore, the scaffolding holder 4 can be fixed at any position of the parent-child pipe and joist pipe of the scaffold. It acts to secure the spacing between suspension fulcrums.

【0018】 なお、本考案は、上述した実施例に限定されるものではなく、本考案の要旨を 変更しない範囲内で変形実施できる構成を含むものである。また、上記実施例の 足場吊り具を用いてH形鋼梁5に足場用鋼管6を吊り下げる手順は上記の説明の 手順に限られるものではない。It should be noted that the present invention is not limited to the above-described embodiments, but includes configurations that can be modified and implemented within the scope of the present invention. Further, the procedure for suspending the scaffolding steel pipe 6 on the H-shaped steel beam 5 using the scaffold suspender of the above-described embodiment is not limited to the procedure described above.

【0019】[0019]

【考案の効果】[Effect of device]

以上の説明より明らかなように、本考案の足場吊り具によれば、本体支持具に チェーン支持具を装着して、該チェーン支持具に複数本のチェーンを介して足場 保持具を取付け、本体支持具を梁材等に装着し、足場保持具にて足場を保持して 梁材等に足場を吊り下げることができ、足場の吊り支点間隔を自由に設定するこ とができて必要な吊り支点間隔を確保することができ、且つ吊り支点間隔を広く することができ、足場の強度及び安全性を確保向上することができるとともに、 作業性を損うことがなく、しかも足場吊り具自体の構造も簡単で、コストも廉価 で、施工も容易になるという効果を有する。 As is clear from the above description, according to the scaffold suspender of the present invention, the chain support is attached to the main body support, and the scaffold holding tool is attached to the chain support via the plurality of chains. The support can be attached to the beam, etc., and the scaffold holder can hold the scaffold and suspend the scaffold on the beam, etc. The fulcrum spacing can be secured, the suspension fulcrum spacing can be widened, the strength and safety of the scaffolding can be secured and improved, workability is not impaired, and the scaffolding lifting device itself The structure is simple, the cost is low, and the construction is easy.

【0020】 また、本体支持具をH形鋼材からなる梁材のフランジ部に固定されるコ字状部 材と、チェーン支持具を保持するクランプ部材とを一体的に設けられているので 、梁材等を構成するH形鋼材のフランジ部に本体支持具を容易に取付けることが できるという効果を有する。更に、チェーン支持具は本体支持具にて把持される パイプ材に水平フラットバーを挿通するとともに、パイプ材の下面に垂直フラッ トバーを固着して、水平フラットバーの両端部及び垂直フラットバーの下端部に それぞれチェーンの一端を連結する連結孔が形成された構成の場合は、左右及び 中央の三点で複数本のチェーンの一端を連結することができ、チェーン支持具の 連結部にかかる力を分散できて強度が向上するという効果を有する。更にまた、 足場保持具として、チェーンの他端を連結するコ字状部材と、足場を保持するク ランプ部材とが一体的に設けられた構成とした場合は、足場を容易に保持するこ とができるという効果を有する。Further, since the main body supporting member is integrally provided with a U-shaped member for fixing the flange member of the beam member made of H-shaped steel and a clamp member for holding the chain supporting member, This has the effect that the main body support can be easily attached to the flange portion of the H-shaped steel material forming the material and the like. In addition, the chain support is inserted by the horizontal flat bar into the pipe material held by the main body support, and the vertical flat bar is fixed to the lower surface of the pipe material to secure both ends of the horizontal flat bar and the lower end of the vertical flat bar. In the case of a structure in which a connecting hole for connecting one end of each chain is formed in each part, one end of multiple chains can be connected at three points on the left and right and in the center, and the force applied to the connecting part of the chain support tool It has the effect that it can be dispersed and the strength is improved. Furthermore, when the scaffold holder is configured to integrally include a U-shaped member that connects the other ends of the chains and a clump member that holds the scaffold, the scaffold can be easily held. It has the effect that

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の一実施例の全体図である。FIG. 1 is an overall view of an embodiment of the present invention.

【図2】図1の要部拡大図である。FIG. 2 is an enlarged view of a main part of FIG.

【図3】本体支持具の斜視図である。FIG. 3 is a perspective view of a main body support tool.

【図4】チェーン支持具の平面図、正面図及び側面図で
ある。
FIG. 4 is a plan view, a front view and a side view of a chain support.

【図5】足場保持具の斜視図である。FIG. 5 is a perspective view of a scaffolding holder.

【図6】足場保持方法の従来例の説明図である。FIG. 6 is an explanatory diagram of a conventional example of a scaffold holding method.

【符号の説明】[Explanation of symbols]

1・・・本体支持具、2・・・チェーン支持具、3・・
・チェーン、4・・・足場保持具、5・・・H形鋼梁、
5a・・・フランジ部、6・・・足場用鋼管、11・・
・コ字状部材、12・・・クランプ部材、23・・・四
角パイプ材、24・・・水平フラットバー、25・・・
垂直フラットバー、30・・・コ字状部材、31・・・
クランプ部材
1 ... main body support, 2 ... chain support, 3 ...
・ Chain, 4 ・ ・ ・ Scaffold holder, 5 ・ ・ ・ H-shaped steel beam,
5a ... Flange part, 6 ... Scaffolding steel pipe, 11 ...
-U-shaped member, 12 ... Clamping member, 23 ... Square pipe material, 24 ... Horizontal flat bar, 25 ...
Vertical flat bar, 30 ... U-shaped member, 31 ...
Clamp member

Claims (3)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 梁材等の被吊り下げ材に作業用足場を吊
り下げるための足場吊り具であって、前記被吊り下げ材
に装着される本体支持具と、該本体支持具に装着され、
チェーン連結部が設けられたチェーン支持具と、該チェ
ーン支持具に一端が連結された複数本のチェーンと、該
チェーンの他端に連結され、前記足場を保持する足場保
持具を有し、前記本体支持具が、前記被吊り下げ材に取
着されるコ字状部材に前記チェーン支持具を保持するク
ランプ部材を一体的に設けた支持具で形成され、前記チ
ェーン支持具が、少なくとも両端部にそれぞれ前記チェ
ーンの一端を連結する連結孔を有する棒体で形成されて
いることを特徴とする足場吊り具。
1. A scaffolding suspending tool for suspending a work scaffold on a suspended material such as a beam, the main body supporting tool attached to the suspended material, and the main body supporting tool. ,
A chain support provided with a chain connecting part, a plurality of chains having one end connected to the chain support, and a scaffold holder connected to the other end of the chain for holding the scaffold, The main body support is formed by a support in which a clamp member for holding the chain support is integrally provided on a U-shaped member attached to the suspended material, and the chain support is at least at both ends. A scaffold suspender characterized by being formed of a rod body having a connection hole for connecting one end of each of the chains.
【請求項2】 チェーン支持具が、本体支持具にて把持
されるパイプ材に水平フラットバーを挿通するととも
に、該パイプ材の下面に垂直フラットバーを固着し、前
記水平フラットバーの両端部および垂直フラットバーの
下端部にそれぞれチェーンの一端を連結する連結孔が形
成された棒体である請求項1に記載の足場吊り具。
2. A chain supporting tool inserts a horizontal flat bar into a pipe material gripped by a main body supporting tool, and a vertical flat bar is fixed to a lower surface of the pipe material, and both end portions of the horizontal flat bar and The scaffolding suspension according to claim 1, wherein the vertical flat bar is a rod body in which a connecting hole for connecting one end of the chain is formed at a lower end portion of the vertical flat bar.
【請求項3】 足場保持具が、チェーンの他端を連結す
るコ字状部材と、足場を保持するクランプ部材とが一体
的に設けられている請求項1に記載の足場吊り具。
3. The scaffold suspender according to claim 1, wherein the scaffold holder is integrally provided with a U-shaped member that connects the other ends of the chains and a clamp member that holds the scaffold.
JP1993071188U 1993-12-03 1993-12-03 Scaffolding hanger Expired - Lifetime JP2538491Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1993071188U JP2538491Y2 (en) 1993-12-03 1993-12-03 Scaffolding hanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1993071188U JP2538491Y2 (en) 1993-12-03 1993-12-03 Scaffolding hanger

Publications (2)

Publication Number Publication Date
JPH0734143U true JPH0734143U (en) 1995-06-23
JP2538491Y2 JP2538491Y2 (en) 1997-06-18

Family

ID=13453442

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1993071188U Expired - Lifetime JP2538491Y2 (en) 1993-12-03 1993-12-03 Scaffolding hanger

Country Status (1)

Country Link
JP (1) JP2538491Y2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6026534U (en) * 1983-07-28 1985-02-22 株式会社 国元商会 Hanging device for temporary construction
JPS60194036U (en) * 1984-06-01 1985-12-24 株式会社竹中工務店 suspended scaffolding

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6026534U (en) * 1983-07-28 1985-02-22 株式会社 国元商会 Hanging device for temporary construction
JPS60194036U (en) * 1984-06-01 1985-12-24 株式会社竹中工務店 suspended scaffolding

Also Published As

Publication number Publication date
JP2538491Y2 (en) 1997-06-18

Similar Documents

Publication Publication Date Title
US6557807B1 (en) Rotatable pipe and conduit hanger
JP2009108473A (en) Hanging scaffold erection method for elevated structure
WO1992004516A1 (en) Improved clamp and mounting arrangement
JPH0734143U (en) Scaffolding hanging
CN215519223U (en) I-shaped beam hanging hanger
JP2893171B2 (en) Safety net hanging equipment for building construction and equipment with safety net for building construction
JP2561410Y2 (en) Horizontal swing grip metal fitting for temporary beam, and temporary beam for slab construction provided with the metal fitting
JPS636138Y2 (en)
JP3578813B2 (en) Hanging equipment
JP2549261Y2 (en) Switch breaker lifting tool for construction
CN220976300U (en) Steel construction installation hangs hoist
CN218541439U (en) Suspension type operation platform
CN218467043U (en) Suspension type operation platform is used in girder steel welding
JPH067183Y2 (en) Support device
JP2000047617A (en) Device housing planer advertisement support
CN213626571U (en) Installation component and box type truss suspension type operation platform
CN214575060U (en) Shockproof and anti-falling ceiling mounting structure
JPH09202584A (en) Suspension tool for roof panel and suspension method for roof panel
JP3010736U (en) Hanging equipment for beams and girders
JPS6245456Y2 (en)
JP7409780B2 (en) Hanging equipment for hanging scaffolds and hanging scaffolding
JP3069424U (en) Scaffolding hanging brackets that can simultaneously suspend both the suspended under the bridge girder and the two-stage scaffold between the bridge girder
JP2019196671A (en) Hanging jig for column strut
JPH0547225U (en) Safety net suspension device for construction
JP3038482U (en) Hanger for grid member of system ceiling

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term