JPH0744533U - Revetment reinforcement block - Google Patents
Revetment reinforcement blockInfo
- Publication number
- JPH0744533U JPH0744533U JP058850U JP5885093U JPH0744533U JP H0744533 U JPH0744533 U JP H0744533U JP 058850 U JP058850 U JP 058850U JP 5885093 U JP5885093 U JP 5885093U JP H0744533 U JPH0744533 U JP H0744533U
- Authority
- JP
- Japan
- Prior art keywords
- natural
- revetment
- outer peripheral
- flow
- river
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 11
- 239000004575 stone Substances 0.000 claims abstract description 58
- 239000000463 material Substances 0.000 claims abstract description 13
- 230000002093 peripheral effect Effects 0.000 claims abstract description 11
- 230000003014 reinforcing effect Effects 0.000 claims description 11
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 abstract description 5
- 229910052760 oxygen Inorganic materials 0.000 abstract description 5
- 239000001301 oxygen Substances 0.000 abstract description 5
- 238000012856 packing Methods 0.000 abstract description 5
- 238000004140 cleaning Methods 0.000 abstract description 4
- 230000002411 adverse Effects 0.000 abstract 1
- 230000006866 deterioration Effects 0.000 abstract 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 238000010276 construction Methods 0.000 description 5
- 238000003780 insertion Methods 0.000 description 5
- 230000037431 insertion Effects 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000007596 consolidation process Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 241000195493 Cryptophyta Species 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 235000015278 beef Nutrition 0.000 description 1
- 230000005587 bubbling Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 238000009991 scouring Methods 0.000 description 1
- 235000014102 seafood Nutrition 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/80—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in fisheries management
- Y02A40/81—Aquaculture, e.g. of fish
Landscapes
- Revetment (AREA)
- Artificial Fish Reefs (AREA)
Abstract
(57)【要約】
[目的] 従来の護岸補強は、経年使用による劣化の問
題があり、コンクリートを用いた場合には、河川の自浄
作用や生態系に好ましくない影響を与えることが知られ
るようになった。そこで本考案は、護岸強度を十分に確
保しつつ河川の自然作用に影響を及すことなく護岸面を
補強することを目的とする。
[構成] 隣接する自然石同士を連結手段を用いて相互
に連絡し、外周フレームを構成する一方、該外周フレー
ムによって囲まれた内側空間に間詰材を配する。かかる
構成によれば、それぞれの自然石材を単独で積み上げる
場合に較べ、ブロック全体の重量が増し、より強い流勢
に対しても十分対抗することが可能となる。また外周フ
レームが間詰材を保護するから、洪水氾濫時のように流
勢が極端に強い場合であっても間詰材の流出は最小限に
抑えられる。各自然石の間には隙間が生じるから、大気
中の酸素を河川に導入でき、自然に近い流れを作り上げ
て生物環境を保持する。
(57) [Summary] [Purpose] Conventional revetment reinforcement has the problem of deterioration over time, and it is known that when concrete is used, it adversely affects the self-cleaning action of rivers and the ecosystem. Became. Therefore, an object of the present invention is to reinforce the revetment surface without affecting the natural action of the river while sufficiently securing the revetment strength. [Structure] Adjacent natural stones are connected to each other using a connecting means to form an outer peripheral frame, while a filling material is arranged in an inner space surrounded by the outer peripheral frame. With such a configuration, the weight of the entire block is increased as compared with the case where each of the natural stone materials is piled up independently, and it becomes possible to sufficiently oppose a stronger flow force. Further, since the outer peripheral frame protects the packing material, the flow of the packing material can be minimized even when the flow force is extremely strong as in the case of flooding. Since a gap is created between each natural stone, oxygen in the atmosphere can be introduced into the river, creating a flow close to nature and maintaining the biological environment.
Description
【0001】[0001]
本考案は自然石を用いた護岸補強ブロックに係り、特に護岸の強度を向上させ るための補強技術に関する。 The present invention relates to a revetment reinforcement block using natural stone, and more particularly to a reinforcement technique for improving the strength of a revetment.
【0002】[0002]
河川等の水際に施す護岸施設には、堤防法面を保護するものや低水路の岸を保 護する各種のタイプがあり、護岸傾斜面には石張りやコンクリート張り等各種の 法覆を施すのが一般であり、図8および図9に示ように、法覆1の法先を抑える ため法留2および根固め3を設け、護岸の強度維持および水流調整を図る。 There are various types of revetment facilities that protect the dike slopes and shores of low-water canals at the waterfront of rivers, etc., and various slopes such as stone and concrete are applied to the revetment slopes. In general, as shown in FIGS. 8 and 9, in order to suppress the slope tip of the slope cover 1, a slope stay 2 and a root consolidation 3 are provided to maintain the strength of the revetment and adjust the water flow.
【0003】 従来、この法留2としては例えば図示したように杭4を打ち込み、或いは杭4 の間に自然石5を配するもの(石詰め)があり、また根固め3としてはいわゆる 木工沈床(3a)や牛わく(3b)を使用するものがあった。また近時は木工沈 床(3a)等の根固め3に代え、法面にコンクリートブロックを配し、或いは自 然石をコンクリート河床に埋設して根固めするケースも多い。この点は、低水路 の流勢を調整するための、いわゆる水制工事においても同様である。[0003] Conventionally, as the mooring 2, for example, there is one in which piles 4 are driven as shown in the figure or natural stones 5 are arranged between the piles 4 (stone filling). Some used (3a) or beef frame (3b). In recent years, in many cases, concrete blocks are placed on the slopes or natural stones are buried in concrete riverbeds instead of solidifying the groundwork 3 (a) to consolidate it. This point also applies to so-called flood control work for adjusting the flow of low-water canals.
【0004】[0004]
ところで、このような護岸の法先施工法は従来より以下のような問題が指摘さ れた。第一に、法留として伝統的に行われる石詰めは洪水時に杭4が破損し、各 石5が流勢で押し流される場合が少なくない。これは特に杭4が老朽化している 場合や、氾濫時の流勢が強い箇所で発生し易い問題である。 By the way, the following problems have been pointed out in the prior construction method for such seawalls. First of all, the stone packing, which is traditionally performed as hodome, often damages the piles 4 and causes each stone 5 to be swept away by flood force during a flood. This is a problem that tends to occur especially when the piles 4 are deteriorated or where the flow is strong during flooding.
【0005】 第二に、コンクリートを用いた根固めは、単純にコンクリートを打設するため 表面が平坦形状となるが、河川は単なる水路ではなく自然の自浄作用を営むもの であり、藻類や各種の魚介を育成する自然の循環系である。自然の自浄作用は、 淵のくぼみや小石の凹凸による水流の泡立ちにより空気中から酸素を導入するこ とによって達成されるが、平坦なコンクリート表面では河川流水が泡立つことも なく、流勢も単調となって酸素の取り入れや十分な撹拌作用が営まれず、河川の 自浄作用が弱められ、自然のバランスが歪められる。Secondly, in the case of root consolidation using concrete, the surface is flat because the concrete is simply placed, but the river is not just a waterway but a natural self-cleaning action, and it does not affect algae and various types of water. It is a natural circulatory system that nurtures seafood. The natural self-cleaning action is achieved by introducing oxygen from the air due to the bubbling of the water flow due to the depressions in the pool and the unevenness of the pebbles. As a result, the intake of oxygen and a sufficient stirring action are not performed, the self-cleaning action of the river is weakened, and the natural balance is distorted.
【0006】 そこで本考案の目的は、護岸の強度を十分に保証し、河川の自然作用に影響を 及すことのなく護岸面を補強する点にある。Therefore, an object of the present invention is to sufficiently assure the strength of the revetment and to reinforce the revetment surface without affecting the natural action of the river.
【0007】[0007]
前記目的を達成して課題を達成するため、本考案に係る護岸補強ブロックは、 隣接する自然石同士を連結手段を用いて相互に連絡し、外周フレームを構成する 一方、該外周フレームによって囲まれた内側空間に間詰材を配する。 In order to achieve the above object and to achieve the object, the seawall reinforcement block according to the present invention connects adjacent natural stones to each other by using connecting means to form an outer peripheral frame while being surrounded by the outer peripheral frame. Place the filling material in the inner space.
【0008】[0008]
本考案に係る補強ブロックは所定重量を有する自然石材を多数並列させ、これ にワイヤロープ等の索条手段を通して相互に連絡し、外周フレームを構成する。 各自然石材の形状は任意であり、また自然石が形成する外周フレームの形状は、 略三角形、略四角形、略六角形など、護岸法面に応じて適宜設計する。 In the reinforcing block according to the present invention, a large number of natural stones having a predetermined weight are juxtaposed and connected to each other through a rope means such as a wire rope to form an outer peripheral frame. The shape of each natural stone material is arbitrary, and the shape of the outer peripheral frame formed by the natural stone is appropriately designed according to the revetment slope, such as a substantially triangular shape, a substantially quadrangular shape, or a substantially hexagonal shape.
【0009】 かかる構成によれば、それぞれの自然石材を単独で積み上げる場合に較べ、ブ ロック全体の重量が増し、より強い流勢に対しても十分対抗することが可能とな る。フレーム内部に配する間詰材は連結を要しないから、施工面積当たりの作業 時間は大幅に短縮され、工事コストも格段に低減する。また外周フレーム全体が 間詰材を保護するから、洪水氾濫時のように流勢が極端に強い場合であっても間 詰材の流出は最小限に抑えられる。勿論、各自然石の間には隙間が生じるから、 大気中の酸素を河川に導入できるとともに、この隙間は河川流水を適度に撹拌し 自然に近い流れを作り上げて生物環境を維持する。According to such a configuration, the weight of the entire block is increased as compared with the case where each of the natural stone materials is piled up independently, and it is possible to sufficiently counter a stronger flow force. Since the filling material placed inside the frame does not need to be connected, the work time per construction area is greatly shortened, and the construction cost is significantly reduced. In addition, since the entire outer frame protects the packing material, even if the flow is extremely strong, such as during a flood, the outflow of packing material is minimized. Of course, a gap is created between each natural stone, so that oxygen in the atmosphere can be introduced into the river, and this gap appropriately agitates the river water to create a flow close to nature to maintain the biological environment.
【0010】[0010]
以下、添付図面に基づいて本考案の実施例を説明する。 図1,図2は、本考案に係る護岸補強ブロックの一例を示すものである。この 補強ブロック10は、複数の大型自然石11に小径の貫通孔12を穿設し、各貫 通孔12が一直線になるように自然石11を並べ、貫通孔12にワイヤロープ1 4を通して各自然石11の連結強度を高めてある。また、各自然石11は平面略 方形のブロックフレーム20を形成するよう、配列や大きさを揃えてある。 Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. 1 and 2 show an example of a seawall reinforcement block according to the present invention. In this reinforcing block 10, a plurality of large natural stones 11 are provided with small-diameter through holes 12, the natural stones 11 are arranged so that the through holes 12 are in a straight line, and the wire ropes 14 are passed through the through holes 12. The connection strength of the natural stone 11 is increased. The natural stones 11 are arranged and arranged in the same size so as to form a block frame 20 having a substantially rectangular shape in plan view.
【0011】 このブロックフレーム20は、自然石11を正方形状に並べて構成してなり、 貫通孔12にワイヤロープ14を挿通させるとともに、ワイヤロープ14の端部 を適当箇所に固定して全体を堅縛支持する。隅角部に位置する自然石11cは、 ワイヤロープ14を縦横に挿通させる必要があるため、図3に示すように縦横二 つの貫通孔12a,12bを供える。二つの貫通孔12a,12bは、同一平面 に穿設しても良く(図3b)、或いは上下二段に穿設しても良い(図3c)。The block frame 20 is formed by arranging natural stones 11 in a square shape. The wire rope 14 is inserted into the through hole 12 and the end portion of the wire rope 14 is fixed at an appropriate position to make the whole block rigid. Support tied up. The natural stone 11c located at the corner portion needs to have the wire rope 14 inserted vertically and horizontally, and therefore has two through holes 12a and 12b as shown in FIG. The two through holes 12a and 12b may be formed in the same plane (FIG. 3b) or may be formed in two upper and lower stages (FIG. 3c).
【0012】 このように構成したブロックフレーム20の内側空間Pには、適当な大きさを もった間詰用の自然石21を充填する。この自然石21は、ブロックフレーム2 0を構成する自然石11よりも小型のもので良く、また特にコンクリートで固定 する必要もない。ブロックフレーム20の全体重量と構造によって、河川の流勢 に抗することが出来るからである。The inner space P of the block frame 20 thus configured is filled with natural stones 21 for padding having an appropriate size. The natural stone 21 may be smaller than the natural stone 11 forming the block frame 20 and need not be fixed with concrete. This is because the overall weight and structure of the block frame 20 can withstand the flow of the river.
【0013】 ブロックフレーム20は、敷設箇所の面積に応じて複数配する。この場合、ワ イヤロープ14は、縦横それぞれ一本で賄っても構わない。また適当なブロック 単位でワイヤロープ14の長さを設定しても良い。最小の単位は1個のブロック フレーム20であり、貫通孔12を一巡させて適当箇所で固定するか、または縦 横それぞれの方向にワイヤーロープ14を挿通させ、両端部を固定する。ワイヤ ロープ14の固定に際しては、例えばクリップおよび座金を使用し、或いは端部 を固結びにして挿通孔12からの抜けを防止する。A plurality of block frames 20 are arranged according to the area of the installation site. In this case, one wire rope 14 may be provided for each length and width. Further, the length of the wire rope 14 may be set in an appropriate block unit. The minimum unit is one block frame 20, and the through hole 12 is looped around and fixed at an appropriate place, or the wire ropes 14 are inserted in the vertical and horizontal directions to fix both ends. When fixing the wire rope 14, for example, a clip and a washer are used, or the ends are fixedly tied to prevent the wire rope 14 from coming off the insertion hole 12.
【0014】 尚、自然石11の大きさは河川流量に応じて可変であるが、一般河川氾濫時の 流量からいって1〜5トンの重量をもつ河床自然石を用いるのが望ましい。また 連結させるべき自然石11の個数は、河川流量、配設箇所の河川形状、使用する 自然石11の大きさ等によって適宜設定できるが、通常の場合約5〜10個程度 である。自然石11は、とくにその形状を揃える必要はない。このため、隣合う 自然石11同士の間には一定の隙間が生ずるが、必要に応じて間詰め石を配して も良い。この間詰め石により、ブロックフレーム20の強度が増し、より強く流 勢や洗掘に抗して護岸を支えることが出来る。Although the size of the natural stone 11 can be changed according to the river flow rate, it is desirable to use the river bed natural stone having a weight of 1 to 5 tons in view of the flow rate at the time of flooding of a general river. The number of natural stones 11 to be connected can be appropriately set depending on the flow rate of the river, the shape of the river at the location where the natural stones 11 are used, the size of the natural stones 11 to be used, and the like, but is usually about 5 to 10 pieces. The natural stones 11 do not need to have the same shape. Therefore, a certain gap is created between the adjacent natural stones 11, but filling stones may be arranged if necessary. The padding stone during this time increases the strength of the block frame 20 and can more strongly support the revetment against the flow and scouring.
【0015】 当然であるが貫通孔12の形状は問わない。また孔12の穿設位置は、当該自 然石11の重心位置付近に設定するのが望ましい。石材に穿設する貫通孔の数は 一つに限定されない。より大きな石材を連結させる場合等、必要に応じて複数本 の貫通孔を穿設し、それに対応した本数の索条を用いることも可能である。また 石材形状を整える必要がある場合、少なくとも流勢に面する箇所(特に表面側) には適当な凹凸を設け、自然の流れを失わないようにさせるのが望ましい。Naturally, the shape of the through hole 12 does not matter. Further, it is desirable that the drilling position of the hole 12 is set near the center of gravity of the natural stone 11. The number of through holes formed in the stone material is not limited to one. When connecting larger stones, it is possible to form a plurality of through-holes and use the corresponding number of ropes if necessary. In addition, when it is necessary to arrange the stone shape, it is desirable that at least the part facing the flow force (especially the surface side) is provided with appropriate unevenness so that the natural flow is not lost.
【0016】 従って、かかる護岸補強ブロックによれば、自然石11を単独で積み上げる場 合に較べ、ブロックフレーム20を含む全体の重量が増し、強い流勢に対しても 護岸目的を十分に達成することが出来る。またブロックフレーム20によって囲 まれた空間に配する間詰用の自然石21は、とくに連結を要しないから、施工面 積当たりの作業時間は大幅に短縮され、工事コストも低減する。また外周フレー ム20の全体が自然石21を保護するから、洪水氾濫時のように流勢が極端に強 い場合であっても自然石21の流出は最小限に抑えられる。勿論、各自然石の間 には隙間が生じるから、大気中の酸素を河川に導入でき、この隙間は河川流水を 適度に撹拌し自然に近い流れを作り上げて生物環境を維持する。Therefore, according to such a seawall reinforcement block, the weight of the whole including the block frame 20 is increased as compared with the case where the natural stones 11 are stacked alone, and the seawall purpose is sufficiently achieved even with a strong flow. You can Moreover, since the natural stones 21 for padding arranged in the space surrounded by the block frame 20 do not particularly need to be connected, the working time per construction area is greatly shortened and the construction cost is also reduced. Further, since the entire outer frame 20 protects the natural stones 21, the outflow of the natural stones 21 can be minimized even when the flow is extremely strong as in the case of flooding. Of course, since gaps are created between each natural stone, oxygen in the atmosphere can be introduced into the river, and this gap allows the river water to be appropriately agitated to create a flow close to nature and maintain the biological environment.
【0017】 本考案に係る補強ブロックは、自然石を用いて外周フレームを構成するもので あるが、外周フレームの平面形状や連結のさせ方は前記実施例のものに限定され ない。例えばワイヤロープによる隣石同士の連絡は、図4に示すように挿通リン グ31を持ったアンカーボルト30を自然石11に固定し、このリング31にワ イヤロープ14を挿通することによって固定しても良い。アンカーボルト30の 固定は、例えば、自然石11に予め埋設穴を穿ち、この埋設穴にアンカーボルト 30の脚部を嵌挿し接着剤によって固定する。Although the reinforcing block according to the present invention constitutes the outer peripheral frame by using natural stone, the planar shape of the outer peripheral frame and the connecting method are not limited to those in the above-mentioned embodiment. For example, to connect adjacent stones with a wire rope, fix the anchor bolt 30 with the insertion ring 31 to the natural stone 11 by inserting the wire rope 14 into this ring 31, as shown in FIG. Is also good. The anchor bolts 30 are fixed by, for example, forming a buried hole in the natural stone 11 in advance, and inserting the leg portions of the anchor bolts 30 into the buried holes and fixing them with an adhesive.
【0018】 また、このようなアンカーボルト30を使用した場合は、ワイヤロープ14の 挿通が比較的自由となるので、図5に示すように、縦横方向にワイヤロープ14 を挿通させることも可能である。Further, when such an anchor bolt 30 is used, the wire rope 14 can be inserted relatively freely, so that the wire rope 14 can be inserted vertically and horizontally as shown in FIG. is there.
【0019】 尚、自然石11に挿通孔12を穿設する場合のワイヤロープ14の連絡である が、例えば図6に示すように、ワイヤロープ14を適当箇所(符号Qで表す)で 相互に固定しても良い。このような連結を行えば、隅角部に配する自然石を省略 することができる。図1、図3に示した隅角部の自然石11cは、十字クロスの 挿通孔12a,12bを要するため、穿設作業や配置作業が煩わしい場合もある が、挿通孔12の規格を統一することにより作業上の煩しさを軽減することが可 能となる。これは平面三角形状のブロックフレーム40を用いる場合も同様であ り、その概略を図7に例示する。同図において、符号Qの部分がワイヤーロープ 14の固定箇所である。The wire ropes 14 are connected to each other when the insertion holes 12 are formed in the natural stones 11. For example, as shown in FIG. 6, the wire ropes 14 are connected to each other at appropriate places (denoted by reference numeral Q). You may fix it. If such a connection is made, the natural stones placed in the corners can be omitted. The natural stones 11c at the corners shown in FIGS. 1 and 3 require the insertion holes 12a and 12b of the cross, so that the drilling work and the placement work may be troublesome, but the standards of the insertion hole 12 are unified. This will reduce the complexity of work. This is the same when the block frame 40 having a flat triangular shape is used, and its outline is illustrated in FIG. In the figure, the portion indicated by the reference sign Q is a fixed portion of the wire rope 14.
【0020】 本考案は、ブロックフレームの連結手段をワイヤーロープに限定されない。適 当素材の索条手段、金属または樹脂等の杆状部材など、十分な引張強度と可撓性 のある適当な部材を使用することが出来る。本考案に係るブロックは必ずしもコ ンクリート石材の使用を除外するものではないが、コンクリート使用の場合は石 灰成分など河川環境に対して好ましくない成分を滲み出させる可能性がある。し かし、自然石11であれば河川水に好ましくない成分を滲み出すことがなく、ま たコスト的にも有利である。In the present invention, the block frame connecting means is not limited to the wire rope. Appropriate members having sufficient tensile strength and flexibility such as a rope member made of a suitable material and a rod-shaped member made of metal or resin can be used. The block according to the present invention does not necessarily exclude the use of concrete stone, but when concrete is used, it may exude components that are not preferable to the river environment such as ash components. However, natural stone 11 does not exude undesirable components into river water and is advantageous in cost.
【0021】[0021]
以上説明したように本考案に係る護岸補強ブロックは、自然石を連結してブロ ックフレームを形成し、当該フレームの内側に間詰石を配するから、比較的容易 な作業によって非常に大きなブロック重量を獲得することが出来、従って護岸強 度を十分に確保しつつ、河川の自然作用に影響を及すことのなく護岸を補強する ことが出来る。 As described above, the revetment reinforcement block according to the present invention forms a block frame by connecting natural stones and disposes stuffing stones inside the frame. Therefore, it is possible to reinforce the revetment without affecting the natural action of the river while securing sufficient revetment strength.
【図1】本考案に係る補強ブロックの一例を示す平面図
である。FIG. 1 is a plan view showing an example of a reinforcing block according to the present invention.
【図2】図1に示す補強ブロックの側面断面図である。FIG. 2 is a side sectional view of the reinforcing block shown in FIG.
【図3】ブロックフレームを構成する自然石の一例を示
す図である。FIG. 3 is a diagram showing an example of natural stones constituting a block frame.
【図4】本考案に係る補強ブロックの第二の実施例を示
す平面図である。FIG. 4 is a plan view showing a second embodiment of the reinforcing block according to the present invention.
【図5】本考案に係る補強ブロックの第三の実施例を示
す平面図である。FIG. 5 is a plan view showing a third embodiment of the reinforcing block according to the present invention.
【図6】本考案に係る補強ブロックの第四の実施例を示
す平面図である。FIG. 6 is a plan view showing a fourth embodiment of the reinforcing block according to the present invention.
【図7】本考案に係る補強ブロックの第五の実施例を示
す平面図である。FIG. 7 is a plan view showing a fifth embodiment of the reinforcing block according to the present invention.
【図8】従来の護岸補強例を示す図である。FIG. 8 is a diagram showing a conventional example of seawall reinforcement.
【図9】従来の護岸補強の他の例を示す図である。FIG. 9 is a diagram showing another example of conventional seawall reinforcement.
10 補強ブロック 11,21 自然石 12 貫通孔 14 ワイヤロープ 20,40 ブロックフレーム 30 アンカーボルト 31 リング Q ワイヤーロープの結び目 10 Reinforcing block 11,21 Natural stone 12 Through hole 14 Wire rope 20,40 Block frame 30 Anchor bolt 31 Ring Q Knot of wire rope
Claims (1)
て、隣接する自然石同士を連結手段を用いて相互に連絡
し外周フレームを構成する一方、該外周フレームによっ
て囲まれた内側空間に間詰材を配することを特徴とする
護岸補強ブロック。1. A reinforcing block for arranging natural stones on a revetment, wherein adjacent natural stones are connected to each other using connecting means to form an outer peripheral frame, and an inner space surrounded by the outer peripheral frame is provided. A revetment reinforcement block that features a filling material.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1993058850U JP2587397Y2 (en) | 1993-10-04 | 1993-10-04 | Seawall reinforcement block |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1993058850U JP2587397Y2 (en) | 1993-10-04 | 1993-10-04 | Seawall reinforcement block |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0744533U true JPH0744533U (en) | 1995-11-21 |
| JP2587397Y2 JP2587397Y2 (en) | 1998-12-16 |
Family
ID=13096160
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1993058850U Expired - Lifetime JP2587397Y2 (en) | 1993-10-04 | 1993-10-04 | Seawall reinforcement block |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2587397Y2 (en) |
-
1993
- 1993-10-04 JP JP1993058850U patent/JP2587397Y2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2587397Y2 (en) | 1998-12-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6171569B2 (en) | Embankment reinforcement structure | |
| KR20190082131A (en) | Stone net structure | |
| JP3458275B2 (en) | Embankment stabilization method on soft ground | |
| KR100458928B1 (en) | Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid | |
| JP2002180438A (en) | Precast concrete armour units, revetment structure, and method of manufacturing precast concrete armour units | |
| JP2587397Y2 (en) | Seawall reinforcement block | |
| JP3427066B2 (en) | Manufacturing method for civil engineering blocks | |
| KR100699707B1 (en) | Gabion retaining wall reinforcement pins and retaining wall structure using the same | |
| JP4844787B2 (en) | Civil engineering block, civil engineering structure structure, civil engineering structure construction method, and civil engineering block manufacturing method | |
| JP3315977B1 (en) | Civil engineering block, civil engineering structure structure, method of constructing civil engineering structure structure, and method of manufacturing civil engineering block | |
| JP2003171920A (en) | Natural stone fixing unit and multiple nature type construction method using unit | |
| JP2001107336A (en) | Natural stone fixing sheet | |
| JP3547699B2 (en) | Seawall structure | |
| JPH09302641A (en) | Seabottom structure, and laying method thereof | |
| JPH011828A (en) | Top-shaped block for ground stabilization and its installation method | |
| JPH0653629U (en) | Revetment reinforcement block | |
| JP2005325514A (en) | Banking stabilizing construction method on soft ground | |
| JP2004060386A (en) | Natural stone fixing unit and multi-natural type construction method using the unit | |
| KR200327420Y1 (en) | Structure for fixing stone-net bag for wash preventing of rivers bank | |
| JPH10266161A (en) | Mat member and execution method thereof | |
| JP3479214B2 (en) | Units for civil engineering structures | |
| JP3502895B2 (en) | Landfill method | |
| JP3431905B2 (en) | Improved soil structure of sandy soil layer and improvement method | |
| JP2840061B2 (en) | Natural stone wire mesh for ecosystem protection | |
| KR200253330Y1 (en) | Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19980818 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R323113 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081016 Year of fee payment: 10 |
|
| EXPY | Cancellation because of completion of term |