JPH0768848B2 - Tunnel construction method - Google Patents
Tunnel construction methodInfo
- Publication number
- JPH0768848B2 JPH0768848B2 JP2331380A JP33138090A JPH0768848B2 JP H0768848 B2 JPH0768848 B2 JP H0768848B2 JP 2331380 A JP2331380 A JP 2331380A JP 33138090 A JP33138090 A JP 33138090A JP H0768848 B2 JPH0768848 B2 JP H0768848B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- ground
- outer circumference
- operation rod
- hardening material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】 a.産業上の利用分野 本発明は、トンネル堀削作業の作業能率の向上を図り得
るトンネルの構築工法に関する。TECHNICAL FIELD The present invention relates to a tunnel construction method capable of improving the work efficiency of tunnel excavation work.
b.従来の技術 トンネル工事に際しては本工事に先だって地盤の改良が
行なわれる。この場合、堀削作業の先立って、第5図及
び第6図のように、トンネル外周予定ラインLに沿って
削孔機の操作ロッドを操作し、トンネル外周予定ライン
L上に円柱状のパイル100を連続して成形している。こ
のパイル100は操作ロッドの先端から地盤硬化材を噴射
し、対象地盤の深さ方向に硬化材を含浸させて地盤を硬
化させたものである。次ぎに、堀削面を補強してから、
削孔機を前進させ、再びトンネル外周予定ラインLに沿
って操作ロッドを操作する。b. Conventional technology In the tunnel construction, the ground will be improved prior to this construction. In this case, prior to the excavation work, as shown in FIGS. 5 and 6, the operation rod of the drilling machine is operated along the tunnel outer circumference planned line L, and the column-shaped pile is formed on the tunnel outer circumference planned line L. 100 are continuously molded. This pile 100 is obtained by injecting a ground hardening material from the tip of an operation rod and impregnating the ground hardening material in the depth direction of the target ground to harden the ground. Next, after strengthening the excavated surface,
The boring machine is moved forward, and the operating rod is operated again along the planned line L for the outer circumference of the tunnel.
こうして第7図のように、柱状撹拌部によるパイル100
をトンネルの深さ方向に順次成形していく。そして、ト
ンネル外周予定Lの内側に突き出した部分101(斜線で
示す)を削り取り、トンネル内面にセメントを吹き付け
て、トンネル工事の基礎工事をする。関連する先行技術
として、特開平1-137094号公報、および特開平2-252891
号公報がある。Thus, as shown in FIG. 7, the pile 100 by the columnar stirring unit is
Are sequentially formed in the depth direction of the tunnel. Then, the portion 101 (indicated by diagonal lines) protruding to the inside of the tunnel outer circumference schedule L is scraped off, and cement is sprayed on the inner surface of the tunnel to form the foundation work of the tunnel construction. As related prior arts, JP-A 1-137094 and JP-A 2-252891
There is a gazette.
c.発明が解決しようとする課題 しかしながら、上記のような従来の工法では、トンネル
外周予定ラインLの内側に突き出したパイルを削り取る
必要があるため、作業能率の低下を来たしていた。ま
た、従来では、小径のパイルを連続して成形しているた
め、パイルの成形に長時間を要していた。c. Problem to be Solved by the Invention However, in the conventional construction method as described above, it is necessary to scrape off the pile protruding inside the tunnel outer peripheral planned line L, resulting in a decrease in work efficiency. Further, in the past, since small-diameter piles were continuously formed, it took a long time to form the piles.
本発明は上記課題を解決し、作業能率の向上を図り、か
つパイル成形時の泥水等を能率良く排出し得るトンネル
の構築工法を提供することを目的とする。SUMMARY OF THE INVENTION It is an object of the present invention to solve the above-mentioned problems, improve the work efficiency, and provide a tunnel construction method capable of efficiently discharging muddy water and the like during pile forming.
d.課題を解決するための手段 本発明は上記課題を解決するため、トンネル掘削対象地
盤のトンネル外周予定ラインに沿って所定間隔をおいて
地盤の深さ方向に削孔機の操作ロッドを操作し、操作ロ
ッド先端部に設けられた噴出部から地盤硬化材を噴射し
てトンネル外周予定ラインに沿って柱状撹拌部の連続壁
を形成し、これら柱状撹拌部の内側を掘削してトンネル
孔を形成するトンネルの構築工法であって、高圧ポンプ
を用いて地盤硬化材を上記操作ロッドに供給するととも
に、上記トンネル外周予定ラインに沿って所定間隔をお
いて、順次、上記削孔機の操作ロッドを上記トンネル外
周予定ラインの外側の所定角度の範囲内を回動操作し
て、大口径の略半円状の柱状撹拌部を形成し、これら各
柱状撹拌部の末端がトンネル外周予定ラインの内側に入
らないようにトンネル外周予定ラインの外側にのみ略半
円状の柱状撹拌部を形成し、トンネル外周予定ラインの
内側の地盤を掘削してトンネルを構築することにある。d. Means for Solving the Problems In order to solve the above problems, the present invention operates an operation rod of a boring machine in a depth direction of the ground at predetermined intervals along a tunnel outer circumference planned line of the ground to be excavated by the tunnel. Then, the ground hardening material is jetted from the jetting portion provided at the tip of the operating rod to form a continuous wall of the columnar stirring section along the tunnel outer peripheral planned line, and the inside of these columnar stirring sections is excavated to form the tunnel hole. A method for constructing a tunnel to be formed, in which a ground hardening material is supplied to the operation rod using a high-pressure pump, and the operation rod of the hole drilling machine is sequentially operated at predetermined intervals along the tunnel outer peripheral planned line. Is rotated within a range of a predetermined angle outside the planned tunnel outer circumference line to form a large-diameter, substantially semi-circular columnar stirring section, and the ends of these columnar stirrers correspond to the tunnel outer circumference planned line. Only to form a substantially semicircular columnar stirring portion on the outside of the tunnel periphery planned line not to enter on the side, is to build a tunnel drilled inside the ground of the tunnel periphery scheduled line.
また、本発明は上記課題を解決するため、上記削孔機の
操作ロッドに地盤硬化材の通路の他にエアーおよび泥水
を排出する通路を設け、この通路から柱状撹拌部成形時
の泥水等を排出することにある。Further, in order to solve the above problems, the present invention provides the operation rod of the boring machine with a passage for discharging air and muddy water in addition to the passage of the ground hardening material, and through this passage, the muddy water at the time of forming the columnar stirring portion is provided. It is to discharge.
e.作用 トンネル本工事に先だってトンネル掘削対象地盤のトン
ネル外周予定ラインの外側に削孔機の操作ロッドを所定
角度回動操作する。削孔機は操作ロッドを回転させて対
象地盤の深さ方向に進行させる。次に、操作ロッドを所
定角度の範囲だけ回動し噴出部から地盤硬化材を噴射さ
せ、操作ロッドをゆっくりと引き抜く。こうして、トン
ネル外周予定ラインの外側だけ略半円状の柱状撹拌部の
パイルを順次成形する。削孔機の操作ロッドに設けられ
ている地盤硬化材噴出孔と別に設けられた孔から、操作
ロッド操作時の泥水あるいはエアーを抜き、所望の形状
を有するパイルを成形する。e. Operation Tunnel Prior to this construction, the operation rod of the hole drilling machine is turned to a predetermined angle outside the planned tunnel outer circumference line of the ground to be excavated. The hole drilling machine rotates the operation rod to advance in the depth direction of the target ground. Next, the operation rod is rotated within a predetermined angle range to eject the ground hardening material from the ejection portion, and the operation rod is slowly pulled out. In this way, the pile of the columnar stirring portion having a substantially semicircular shape is sequentially formed only on the outer side of the tunnel outer peripheral planned line. Muddy water or air during operation of the operating rod is drained from a hole provided separately from the ground hardening material injection hole provided in the operating rod of the boring machine to form a pile having a desired shape.
f.実施例 以下本発明の一実施例を図面を参照しながら詳細に説明
する。f. Embodiment One embodiment of the present invention will be described in detail below with reference to the drawings.
第1図は本発明のをトンネル構築工法に用いる削孔機と
関連機器を示したものである。FIG. 1 shows a drilling machine and related equipment used in the tunnel construction method of the present invention.
第1図において、削孔機1は、自走式の基台2と、基台
2上に設けられたリフト3と、リフト3に載置された削
孔機本体4とで構成されている。削孔機本体4には超高
圧ポンプ5からセメントと混和剤からなる地盤硬化材が
圧送されるものである。超高圧ポンプ5にはセメントお
よび混和剤を混合するミキシングプラント6から地盤硬
化材が供給されるものである。In FIG. 1, a boring machine 1 is composed of a self-propelled base 2, a lift 3 provided on the base 2, and a boring machine body 4 mounted on the lift 3. . A ground hardening material composed of cement and an admixture is fed under pressure from an ultrahigh pressure pump 5 to the boring machine body 4. The ground hardening material is supplied to the ultra-high pressure pump 5 from a mixing plant 6 which mixes cement and an admixture.
7はミキシングプラント6に配給水を供給する給水タン
クである。削孔機1の後方には後述する操作ロッドから
排出された泥水8を汲み上げるサンドポンプ9が設けら
れ、このサンドポンプ9によって汲み上げられた泥水8
は泥水タンク10に溜められるものである。11は泥水タン
ク10に溜められた泥水8から水を除去する脱水処理機で
ある。脱水処理機11によって脱水された水は水中ポンプ
12によって中和処理タンク13に集められ中和されるもの
である。Reference numeral 7 is a water supply tank for supplying water to the mixing plant 6. A sand pump 9 for pumping muddy water 8 discharged from an operation rod described later is provided behind the drilling machine 1, and the muddy water 8 pumped by the sand pump 9 is provided.
Is stored in the muddy water tank 10. Reference numeral 11 is a dehydrator for removing water from the muddy water 8 stored in the muddy water tank 10. The water dehydrated by the dehydrator 11 is an underwater pump.
It is collected in the neutralization treatment tank 13 by 12 and neutralized.
第2図および第3図は削孔機本体4の操作ロッド14を示
したものである。2 and 3 show the operating rod 14 of the boring machine body 4.
操作ロッド14は角ロッドの内部に2本の孔15、16を設け
たもので、一方の孔15は地盤硬化材が圧送されて先端の
ノズル17から地盤硬化材を噴射するものである、他方の
孔16はノズル17位置から少し後方に下げて開口したもの
で、泥水あるいはエアーの通路として用いるものであ
る。操作ロッド14の先端には掘削用のチップ18を設けた
メタルクラウン19が装着されている。The operation rod 14 is provided with two holes 15 and 16 inside a square rod, and one hole 15 is one through which the ground hardening material is pumped and jets the ground hardening material from the nozzle 17 at the tip. The hole 16 is opened slightly downward from the position of the nozzle 17 and is used as a passage for muddy water or air. A metal crown 19 provided with a tip 18 for excavation is attached to the tip of the operation rod 14.
次に、上記装置を用いてトンネルを構築する工法につい
て第4図にしたがって説明する。20はトンネル外周予定
ライン、このトンネル外周予定ライン20に沿って削孔機
1の操作ロッド14を進行させて堀削する。この削孔は操
作ロッド14のノズル17からジェットにより水を噴射しな
がらチップ18を設けたメタルクラウン19の回転により行
う。次に、操作ロッド14を後退させながら一定角度の範
囲内を回動させて地盤硬化材を噴射する。地盤中にはト
ンネル外周予定ライン20の外側にのみ略半円状の柱状撹
拌部のパイル21a,21b,21c,…が成形される。そして、こ
のとき、地盤中に生じる泥水等は孔16からホース22を通
して外部に排出する。操作ロッド14の先端部にはメタル
クラウン19が設けられているので削孔した穴から固化す
る前の地盤硬化材が流出するのを防止する。次に、地盤
硬化材の注入が完了すると、孔16を塞ぎ、ノズル17から
さらに地盤硬化材を圧送して、削孔した孔の内部にある
エアー溜りを地盤中に吸収させる。そして操作ロッド14
の引き抜きと共にメタルクラウン19に代えて蓋(図示せ
ず)をして地盤硬化材の固化を待つ。一方、削孔機1は
順次、柱状撹拌部の成形を行う。そして、略半円状のパ
イル21a,21b,21c,…がトンネル外周予定ライン20の外側
に、一定深さ成形されると、パイル21a,21b,…が成形さ
れた部分まで、トンネルを掘りすすむ。トンネルを掘り
すすんだ部分の壁面を固めると、再びトンネル外周予定
ライン20の全周に、一定深さの略半円状のパイル21a,21
b,…を成形する。そして、パイル21a,21b,…が成形され
ると、成形部分まで堀り進む。外周予定ライン20の内側
には地盤硬化材が噴射されていないので、容易に堀削を
行なうことができる。Next, a method of constructing a tunnel using the above device will be described with reference to FIG. Reference numeral 20 is a tunnel outer peripheral planned line, and the operating rod 14 of the hole drilling machine 1 is advanced along this tunnel outer peripheral planned line 20 to excavate. This drilling is performed by rotating a metal crown 19 provided with a tip 18 while jetting water from a nozzle 17 of an operating rod 14 with a jet. Next, the operation hardening rod 14 is moved backward and rotated within a certain angle range to inject the ground hardening material. In the ground, piles 21a, 21b, 21c, ... Of substantially semicircular columnar stirring portions are formed only on the outer side of the tunnel outer peripheral planned line 20. At this time, muddy water or the like generated in the ground is discharged to the outside from the hole 16 through the hose 22. Since the metal crown 19 is provided at the tip of the operation rod 14, the ground hardening material before solidification is prevented from flowing out from the drilled hole. Next, when the injection of the ground hardening material is completed, the hole 16 is closed, and the ground hardening material is further pressure-fed from the nozzle 17 to absorb the air pool inside the drilled hole into the ground. And operating rod 14
And the lid (not shown) instead of the metal crown 19 is pulled out and the solidification of the ground hardening material is waited. On the other hand, the boring machine 1 sequentially forms the columnar stirring section. When the semi-circular piles 21a, 21b, 21c, ... Are formed outside the planned tunnel outer circumference line 20 to a certain depth, the tunnel is dug up to the portion where the piles 21a, 21b ,. . When the wall of the part where the tunnel is dug is hardened, the semicircular piles 21a, 21 of a certain depth are again formed on the entire circumference of the planned tunnel outer circumference line 20.
Mold b, ... Then, when the piles 21a, 21b, ... Are formed, the piles are dug up to the formed portion. Since the ground hardening material is not sprayed inside the planned outer circumference line 20, it is possible to easily carry out excavation.
g.発明の効果 以上述べたように、本発明によるトンネルの構築工法に
よれば、トンネル外周予定ラインに沿って所定間隔をお
いて順次、上記削孔機の操作ロッドを上記トンネル外周
予定ラインの外側の所定角度の範囲内を回動操作して、
大口径の略半円状の柱状撹拌部を形成トンネル外周予定
ラインに沿って所定間隔をおいて、順次、上記削孔機の
操作ロッドを上記トンネル外周予定ラインの外側の所定
角度の範囲内を回動操作して、大口径を略半円状の柱状
撹拌部を形成し、これら各柱状撹拌部の末端がトンネル
外周予定ラインの内側に入らないようにトンネル外周予
定ラインの外側にのみ略半円状の柱状撹拌部を形成した
ので、掘削部分には地盤硬化材が含浸していないことか
ら、掘削作業を容易に行うことができる。g. Effect of the Invention As described above, according to the tunnel construction method of the present invention, the operation rods of the boring machine are sequentially moved along the tunnel outer circumference planned line at predetermined intervals. Rotate within the range of a predetermined angle outside,
A large-diameter, substantially semi-circular columnar stirring section is formed at predetermined intervals along the tunnel outer circumference planned line, and the operation rods of the hole drilling machine are sequentially moved within a predetermined angle range outside the tunnel outer circumference planned line. By rotating the columnar stirrer with a large diameter to form a semi-circular shape, the columnar stirrer should be approximately half outside the tunnel outer circumference line so that the end of each columnar stirrer does not go inside the tunnel outer circumference line. Since the circular columnar stirring portion is formed, the excavated portion is not impregnated with the ground hardening material, so that excavation work can be easily performed.
また、高圧ポンプを用いて地盤硬化材を操作ロッドに供
給するので、大口径の略半円状の柱状撹拌部を形成でき
ることから、柱状撹拌部の数を減らして作業能率の向上
を図ることができる。また、削孔作業および柱状撹拌部
成形時の穴内に生じる泥水を地盤硬化材の通路と別の通
路を通して排出できるので、柱状撹拌部成形時の作業能
率の向上を図ることができる。さらに、地盤硬化材注入
によって内部に生じるエアー溜りを地盤中に吸収させる
ので、必要なパイル形状が得られることから所望強度を
保つことができる。Further, since the ground hardening material is supplied to the operation rod using a high-pressure pump, a large-diameter, substantially semicircular columnar stirring section can be formed. it can. In addition, muddy water generated in the holes during drilling work and forming the columnar stirring portion can be discharged through a passage different from the passage for the ground hardening material, so that work efficiency at the time of forming the columnar stirring portion can be improved. Furthermore, since the air pool generated inside by the injection of the ground hardening material is absorbed into the ground, the required pile shape can be obtained, and thus the desired strength can be maintained.
第1図ないし第4図は本発明によるトンネルの構築工法
の一実施例を示し、第1図は削孔機および関連機器を示
す概念図、第2図は削孔機の操作ロッドを示す縦断面
図、第3図は操作ロッドを示す斜視図、第4図はトンネ
ルの構築工法を示す概念図である。第5図ないし第7図
は従来のトンネル構築工法を示し、第5図は縦断面図、
第6図は横断面図、第7図は縦断面図である。 1……削孔機、4……削工機本体、5……超高圧ポン
プ、8……泥水、14……操作ロッド、15,16……孔、17
……ノズル、20……トンネル外周予定ライン、21a,21b,
21c……パイル。1 to 4 show an embodiment of a tunnel construction method according to the present invention. FIG. 1 is a conceptual diagram showing a drilling machine and related equipment, and FIG. 2 is a vertical section showing an operating rod of the drilling machine. Fig. 3 is a perspective view showing the operation rod, Fig. 4 is a conceptual view showing the tunnel construction method. 5 to 7 show a conventional tunnel construction method, and FIG. 5 is a longitudinal sectional view,
FIG. 6 is a horizontal sectional view, and FIG. 7 is a vertical sectional view. 1 ... Drilling machine, 4 ... Drilling machine body, 5 ... Ultra-high pressure pump, 8 ... Muddy water, 14 ... Operation rod, 15,16 ... Hole, 17
…… Nozzle, 20 …… Planned line around the tunnel, 21a, 21b,
21c …… Pile.
Claims (2)
ラインに沿って所定間隔をおいて地盤の深さ方向に削孔
機の操作ロッドを操作し、操作ロッド先端部に設けられ
た噴出部から地盤硬化材を噴射してトンネル外周予定ラ
インに沿って柱状撹拌部の連続壁を形成し、これら柱状
撹拌部の内側を掘削してトンネル孔を形成するトンネル
の構築工法であって、高圧ポンプを用いて地盤硬化材を
上記操作ロッドに供給するとともに、上記トンネル外周
予定ラインに沿って所定間隔をおいて、順次、上記削孔
機の操作ロッドを上記トンネル外周予定ラインの外側の
所定角度の範囲内を回動操作して、大口径の略半円状の
柱状撹拌部を形成し、これら各柱状撹拌部の末端がトン
ネル外周予定ラインの内側に入らないようにトンネル外
周予定ラインの外側にのみ略半円状の柱状撹拌部を形成
し、トンネル外周予定ラインの内側の地盤を掘削してト
ンネルを構築することを特徴とするトンネルの構築工
法。1. An operation rod of a hole drilling machine is operated in a depth direction of the ground at predetermined intervals along a planned tunnel outer circumference of the ground to be excavated by the tunnel, and the ground is ejected from a jet portion provided at the tip of the operation rod. A method of constructing a tunnel in which a hardening material is injected to form a continuous wall of columnar stirring parts along a planned line around the tunnel, and the inside of these columnar stirring parts is excavated to form a tunnel hole. While supplying the ground hardening material to the operation rod, the operation rods of the boring machine are sequentially arranged within a predetermined angle outside the tunnel outer circumference planned line at predetermined intervals along the tunnel outer circumference planned line. Rotate to form a large-diameter, roughly semi-circular columnar stirring section, and keep the ends of these columnar stirring sections outside the tunnel outer circumference planned line so that they do not enter inside the tunnel outer circumference planned line. Semicircular form a columnar stirring section, building construction method of a tunnel, characterized in that to build a tunnel drilled inside the ground of the tunnel periphery scheduled line only.
通路の他にエアーおよび泥水を排出する通路を設け、こ
の通路から柱状撹拌部成形時の泥水等を排出することを
特徴とする特許請求の範囲第(1)項に記載のトンネル
構築工法。2. The operation rod of the boring machine is provided with a passage for discharging air and muddy water in addition to the passage for the ground hardening material, and muddy water at the time of forming the columnar stirring portion is discharged from this passage. The tunnel construction method according to claim (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2331380A JPH0768848B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2331380A JPH0768848B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04198584A JPH04198584A (en) | 1992-07-17 |
| JPH0768848B2 true JPH0768848B2 (en) | 1995-07-26 |
Family
ID=18243042
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2331380A Expired - Fee Related JPH0768848B2 (en) | 1990-11-29 | 1990-11-29 | Tunnel construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0768848B2 (en) |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01137094A (en) * | 1987-11-24 | 1989-05-30 | Nit Co Ltd | Method of excavation construction of tunnel, etc. and injector used for said method of construction |
| JPH0776509B2 (en) * | 1989-03-28 | 1995-08-16 | 株式会社フジタ | Stabilization method of tunnel face |
-
1990
- 1990-11-29 JP JP2331380A patent/JPH0768848B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH04198584A (en) | 1992-07-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4679705B2 (en) | Equipment for constructing mechanically stirred air cement milk mixed pressure feeding method | |
| JPH09317373A (en) | Method of shaft construction | |
| JPH0768848B2 (en) | Tunnel construction method | |
| JP3626972B1 (en) | Jet stirring method and jet stirring device | |
| JP3547096B2 (en) | Fore pile construction method and drilling equipment used for it | |
| KR200261599Y1 (en) | Base improvement reinforcement system and device | |
| JP4633273B2 (en) | Earth retaining method and equipment | |
| JP3528986B2 (en) | Fore pile construction method | |
| JP3242373B2 (en) | Injection water flow hardening material injection method and its equipment. | |
| JP2006322190A (en) | Pile head processing method of cast-in-place concrete pile and concrete processing agent mixing device | |
| JP3944553B2 (en) | Construction method of underground hardened material | |
| JP3825896B2 (en) | Ground improvement body construction method and apparatus | |
| JP2695141B2 (en) | Lining hardened layer construction method | |
| JP2695143B2 (en) | Lining hardened layer construction method and injection equipment | |
| JP3237797B2 (en) | Excavation method for tunnels | |
| JP2006045867A (en) | Tunnel branch construction method and equipment | |
| JP2865653B1 (en) | Hardening material injection method in cohesive ground | |
| JP3455157B2 (en) | Shoring construction method | |
| JP3682194B2 (en) | Curing material mixing method and curing material mixing device | |
| JPH09228356A (en) | Construction method of improved wall | |
| JP2930939B1 (en) | Construction method of ground hardened layer by polymerization jet | |
| JP3678935B2 (en) | Consolidation pile construction method | |
| JPH0786223B2 (en) | Construction method of hollow hardened layer | |
| JPH05321511A (en) | Construction method for underground vessel in weak ground | |
| KR800000650B1 (en) | Method of forming continuous underground walls on weak footing |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080726 Year of fee payment: 13 |
|
| LAPS | Cancellation because of no payment of annual fees |